CN102493363B - Quick construction method for segment No.0 of continuous beam - Google Patents
Quick construction method for segment No.0 of continuous beam Download PDFInfo
- Publication number
- CN102493363B CN102493363B CN201110411902.0A CN201110411902A CN102493363B CN 102493363 B CN102493363 B CN 102493363B CN 201110411902 A CN201110411902 A CN 201110411902A CN 102493363 B CN102493363 B CN 102493363B
- Authority
- CN
- China
- Prior art keywords
- block
- pier
- formwork
- main pier
- hoisting platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域 technical field
本发明涉及大跨径连续梁桥施工方法,具体涉及连续梁0号块快速施工方法。 The invention relates to a construction method for a long-span continuous girder bridge, in particular to a rapid construction method for No. 0 block of the continuous girder.
背景技术 Background technique
大跨径连续梁桥一般选用悬臂浇筑法施工,主要分四个部分进行,分别为墩顶梁段0号块、挂篮对称悬臂浇筑部分、边跨直线段和边跨及中跨合龙段,其中0号块施工在连续梁悬臂浇筑法施工是一个非常重要的阶段。 Long-span continuous girder bridges are generally constructed using the cantilever pouring method, which is mainly divided into four parts, namely, the No. 0 block of the top beam section of the pier, the symmetrical cantilever pouring part of the hanging basket, the straight line section of the side span, and the closing section of the side span and the middle span. Among them, the construction of No. 0 block is a very important stage in the construction of continuous beam cantilever pouring method.
目前,常规的连续梁0号块施工方法是在墩身浇筑完毕后安装0号块支撑体系,然后在支撑体系上拼装0号块钢筋模板,最后浇筑混凝土。由此可见,传统的施工法,0号块模板、钢筋、预应力管道等的安装须在墩身施工完成后按步进行,工期比较长,在工期紧张的情况下不能满足施工需要。 At present, the conventional continuous beam No. 0 block construction method is to install the No. 0 block support system after the pier body is poured, then assemble the No. 0 block steel formwork on the support system, and finally pour concrete. It can be seen that the traditional construction method, the installation of No. 0 block formwork, steel bars, prestressed pipes, etc. must be carried out step by step after the construction of the pier body is completed, the construction period is relatively long, and it cannot meet the construction needs under the tight construction period.
发明内容 Contents of the invention
本发明所要解决的技术问题是解决连续梁0号块施工工期比较长的问题。 The technical problem to be solved by the invention is to solve the problem that the construction period of the No. 0 block of the continuous beam is relatively long.
为了解决上述技术问题,本发明所采用的技术方案是提供一种连续梁0号块快速施工方法,包括以下步骤: In order to solve the above technical problems, the technical solution adopted in the present invention is to provide a rapid construction method for No. 0 block of continuous beam, comprising the following steps:
A10、在主墩的墩位旁顺桥向施工拼装基础,所述拼装基础用于拼装0号块钢筋模板整体吊装平台; A10, build the assembled foundation along the bridge direction beside the pier position of the main pier, and the assembled foundation is used to assemble the overall hoisting platform of No. 0 block reinforced formwork;
A20、在主墩施工的同时,在所述拼装基础上同步并行施工0号块钢筋模板整体吊装平台,且0号块钢筋模板整体吊装平台在主墩施工完成前完成; A20, while the main pier is being constructed, the No. 0 block reinforced formwork integral hoisting platform is constructed synchronously and in parallel on the assembled basis, and the No. 0 block reinforced formwork integral hoisting platform is completed before the construction of the main pier is completed;
A30、吊装0号块钢筋模板整体吊装平台至主墩墩顶,进行0号块主梁混凝土浇筑以及梁体的张拉压浆施工。 A30. Hoist the No. 0 block reinforced formwork and hoist the platform to the top of the main pier as a whole, and carry out the concrete pouring of the No. 0 block main beam and the tension and grouting construction of the beam body.
在上述方法中,所述0号块钢筋模板整体吊装平台包括由多根横向分配梁和纵向分配梁组成的框架式结构以及设置在所述框架式结构上的0号块底模板和左、右侧模板,步骤A20包括以下步骤: In the above method, the overall hoisting platform of No. 0 block reinforced formwork includes a frame structure composed of multiple transverse distribution beams and longitudinal distribution beams, and the No. 0 block bottom formwork and left and right Side formwork, step A20 comprises the following steps:
A201、在主墩的主墩承台上施工墩身和0号块支撑体系,所述0号块支撑体系由设置在墩身周围的四根钢管柱以及连接系和附臂组成,每根钢管柱分别利用与附臂与墩身上的预埋件连接,且横桥向设置的两根钢管柱之间通过连接系连接; A201. Construct the pier body and No. 0 block support system on the main pier cap of the main pier. The No. 0 block support system is composed of four steel pipe columns arranged around the pier body, connecting systems and attached arms. Each steel pipe The columns are respectively connected with the embedded parts of the attached arm and the pier body, and the two steel pipe columns arranged in the direction of the transverse bridge are connected by a connection system;
A202、在所述拼装基础上同步并行施工0号块浇注模的吊装平台,在所述吊装平台上安装底模板、侧模板,并进行钢筋整体绑扎和预应力管道安装; A202, synchronously constructing the hoisting platform of the No. 0 block pouring mold on the basis of the assembly, installing the bottom formwork and side formwork on the hoisting platform, and performing the overall binding of steel bars and the installation of prestressed pipelines;
步骤A202早于步骤A201施工完成。 Step A202 is completed earlier than step A201.
在上述方法中,在步骤A30中,0号块钢筋模板整体吊装平台吊装利用两台起重机分两步吊装就位,首先起吊至墩顶上方,当位于主梁设计位置上空20cm时, 将两台起重机的大臂锁死,然后在各钢管柱上分别设置手拉倒链,通过手拉倒链对0号块钢筋模板整体吊装平台进行就位调整,当与钢管柱之间的位置正确后,再将0号块钢筋模板整体吊装平台下落到位进行测量,并调整标高、中线,合格后松钩。 In the above method, in step A30, two cranes are used to hoist the overall hoisting platform of the No. 0 reinforced formwork into place in two steps. First, it is hoisted above the top of the pier. The big arm of the crane is locked, and then the hand-pull chains are respectively set on each steel pipe column, and the overall hoisting platform of the No. The overall hoisting platform of the No. 0 steel bar formwork falls in place for measurement, and the elevation and center line are adjusted, and the hook is released after passing the test.
在上述方法中,在步骤A10中,在主墩的墩位旁顺桥向施工两排至少四个拼装基础,且在每个拼装基础的顶面上分别点焊第一、第二楔块,第一、第二楔块顺桥向布置,相邻的两列拼装基础上中,靠近主墩的拼装基础上的第一楔块靠近主墩,第二楔块远离主墩;远离主墩的拼装基础上的第一楔块远离主墩,第二楔块靠近主墩,第一楔块的高度低于第二楔块,二者顶面之间形成的坡度与连续梁0号块的底面倾斜角度相同,在步骤A20中,第一、第二楔块的顶面与0号块钢筋模板整体吊装平台满焊连接。 In the above method, in step A10, two rows of at least four assembled foundations are constructed along the bridge direction next to the pier position of the main pier, and the first and second wedges are respectively spot-welded on the top surface of each assembled foundation, The first and second wedges are arranged along the direction of the bridge. Among the two adjacent assembled foundations, the first wedge on the assembled foundation close to the main pier is close to the main pier, and the second wedge is far away from the main pier; The first wedge on the assembled foundation is far away from the main pier, the second wedge is close to the main pier, the height of the first wedge is lower than that of the second wedge, and the slope formed between the two top surfaces is the same as the bottom surface of No. 0 block of the continuous beam The inclination angles are the same, and in step A20, the top surfaces of the first and second wedges are fully welded to the overall hoisting platform of the No. 0 steel bar formwork.
在上述方法中,所述拼装基础共有六个,相邻的两列用于拼装0号块钢筋模板整体吊装平台,另外一列作为备用。 In the above method, there are six assembled foundations, the two adjacent columns are used for assembling the overall hoisting platform of No. 0 block steel formwork, and the other column is used as a spare.
本发明的有益效果为: The beneficial effects of the present invention are:
(1)、在施工主墩承台、墩身时开始拼装0号块钢筋模板整体吊装平台、安装模板和绑扎钢筋,与主墩主体施工不冲突,即将0号块施工的开始时间提前,缩短了施工工期; (1) During the construction of the main pier cap and pier body, start to assemble the overall hoisting platform of the No. 0 block steel formwork, install the formwork and bind the steel bars, so as not to conflict with the main body construction of the main pier. The start time of the No. 0 block construction will be shortened construction period;
(2)、实现了“变高空为陆地”、“变散扎为整体”,由于连续梁0号块的模板、钢筋、预应力等工作已在吊装平台上完成,吊装到位后,可以很快浇筑混凝土,从而可以最大限度地压缩工期; (2) Realized "changing high altitudes into land" and "changing scattered into a whole". Since the formwork, steel bars, and prestressing work of the continuous beam No. 0 block have been completed on the hoisting platform, after hoisting in place, it can be quickly Pouring concrete, so that the construction period can be compressed to the greatest extent;
(3)、临时支架投入量少,节约了成本,提高了经济效益。 (3) The investment of temporary supports is small, which saves costs and improves economic benefits.
附图说明 Description of drawings
图1是本发明中0号块钢筋模板整体吊装平台吊装前的施工现场布置图; Fig. 1 is the construction site layout diagram before hoisting of No. 0 block reinforced formwork overall hoisting platform in the present invention;
图2是本发明在施工中的横桥向视图; Fig. 2 is the transverse bridge direction view of the present invention in construction;
图3是本发明在施工中的顺桥向视图; Fig. 3 is the view along the bridge of the present invention in construction;
图4是本发明中0号块钢筋模板整体吊装平台的框架式结构示意图。 Fig. 4 is a schematic diagram of the frame structure of the overall hoisting platform of the No. 0 block steel formwork in the present invention.
具体实施方式 Detailed ways
下面结合附图对本发明作出详细的说明。为了便于描述,以下实施例中以顺桥向方向为前后方向,以横桥向方向为左、右方向。 The present invention will be described in detail below in conjunction with the accompanying drawings. For ease of description, in the following embodiments, the direction along the bridge is used as the front-rear direction, and the direction across the bridge is used as the left and right directions.
本发明提供的连续梁0号块快速施工方法,包括以下步骤: The continuous beam No. 0 block rapid construction method provided by the present invention comprises the following steps:
A10、如图1所示,在主墩4的墩位旁施工六个拼装基础21、22、23、24、25和26,上述六个拼装基础顺桥向呈两排布置,且在每个拼装基础的顶面上分别点焊第一、第二楔块51、52,第一、第二楔块51、52顺桥向布置,拼装基础21、22以及25、26上的第一楔块51靠近主墩4,第二楔块52远离主墩4;拼装基础23、24上的第一楔块51远离主墩4,第二楔块52靠近主墩4,第一楔块51的高度低于第二楔块52,二者顶面之间形成的坡度与连续梁0号块的底面倾斜角度相同。
A10. As shown in Figure 1, six assembled
相临的两列共四个拼装基础用于拼装0号块钢筋模板整体吊装平台,另外一列共两个拼装基础作为备用,例如,拼装基础21、22、23、24用于拼装0号块钢筋模板整体吊装平台,拼装基础25、26备用;或者拼装基础23、24、25、26用于拼装0号块钢筋模板整体吊装平台,拼装基础21、22备用。
The two adjacent columns with a total of four assembly foundations are used to assemble the overall hoisting platform of the No. 0 steel bar formwork, and the other column has a total of two assembly foundations as spares. For example, the
A20、在施工主墩4的同时,在上述拼装基础上同步并行施工0号块钢筋模板整体吊装平台,且0号块钢筋模板整体吊装平台在主墩施工完成前完成。 A20. At the same time as the main pier 4 is being constructed, on the basis of the above assembly, the integral hoisting platform of the No. 0 steel formwork is constructed in parallel, and the overall hoisting platform of the No. 0 steel formwork is completed before the construction of the main pier is completed.
如图4所示,0号块钢筋模板整体吊装平台包括由四根平行布置的横向分配梁9和6根平行布置的纵向分配梁8组成的框架式结构以及设置在所述框架式结构上的0号块底模板13和左、右侧模板10(参见图2、图3),横向分配梁9与纵向分配梁8之间分别通过多根连接杆14形成稳固结构。
As shown in Figure 4, the overall hoisting platform for No. 0 block reinforced formwork includes a frame structure composed of four
步骤A20的详细步骤如下: The detailed steps of step A20 are as follows:
A201、在主墩4的主墩承台42上浇注墩身41,同时在主墩承台42上拼装0号块支撑体系,0号块支撑体系由设置在墩身41周围的四根钢管柱2以及连接系11和附臂6组成,每根钢管柱2分别利用与附臂6与墩身41上的预埋件连接,且横桥向设置的两根钢管柱2之间通过连接系11连接。
A201. Pour the
A202、在拼装基础上21、22、23、24同步并行施工0号块钢筋模板整体吊装平台,首先将多根横向分配梁9和纵向分配梁8在第一、第二楔块51、52上拼装组成的框架式结构,第一、第二楔块51、52与横向分配梁9满焊连接,然后在框架式结构的左、右两侧分别焊接第一、第二吊装梁15、16,第一、第二吊装梁15、16之间通过吊装梁连接系17连接;
A202. On the basis of assembly, 21, 22, 23, and 24 simultaneously construct the overall hoisting platform of the No. 0 steel bar formwork in parallel. First, a plurality of
之后,在框架式结构上安装底模板13和左、右侧模板10,并进行钢筋整体绑扎和预应力管道安装。
Afterwards, install the bottom template 13 and the left and
步骤A202应早于步骤A201施工完成。 Step A202 should be completed earlier than step A201.
A30、检查0号块钢筋模板整体吊装平台合格后,用两台大吨位起重机3将其吊装至0号块支撑体系上,由于第一、第二楔块51、52与拼装基础为点焊连接,而与0号块钢筋模板整体吊装平台为满焊连接,因此,第一、第二楔块51、52会在起重机的牵拉作用下与拼装基础分离,与0号块钢筋模板整体吊装平台成为一体上升。
A30. After checking that the overall hoisting platform of the No. 0 steel formwork is qualified, use two large-
0号块钢筋模板整体吊装平台吊装利用两台起重机分两步吊装就位,首先起吊至墩顶上方,当位于主梁7设计位置上空20cm时, 将两台起重机的大臂锁死,然后在四根钢管柱2 上分别设置手拉倒链,通过手拉倒链对0号块钢筋模板整体吊装平台进行就位调整,当与钢管柱2之间的位置正确后,再将0号块钢筋模板整体吊装平台下落到位进行测量,并调整标高、中线,合格后松钩。
The overall hoisting platform of No. 0 reinforced formwork is hoisted by two cranes in two steps. First, it is hoisted above the top of the pier. When it is 20cm above the design position of the main beam 7, lock the booms of the two cranes, and then The four
整个吊装过程中要时刻注意观察0号块支撑体系以及吊机支腿的支撑情况,尤其是第二步吊装时,要求整个过程保持水平,并保持缓慢同步,时刻观察0号块钢筋模板整体吊装平台上的水平尺读数并及时调整其水平度。 During the whole hoisting process, pay attention to observe the support system of block 0 and the support of the crane legs, especially in the second step of hoisting, it is required to keep the whole process level and keep slow and synchronous, and observe the overall hoisting of the steel formwork of block 0 at all times Read the level on the platform and adjust its level in time.
0号块钢筋模板整体吊装平台精确调整定位后,进行0号块主梁7混凝土浇筑以及0号块梁体的张拉压浆施工。 After the overall hoisting platform of block 0 reinforced formwork is precisely adjusted and positioned, the concrete pouring of the main beam 7 of block 0 and the tension and grouting construction of the beam body of block 0 are carried out.
上述方法中,拼装0号块支撑体系时,应控制好钢管柱2的垂直度并与墩身附臂6进行可靠连接。
In the above method, when assembling the No. 0 block support system, the verticality of the
0号块钢筋模板整体吊装平台拼装时,应保证测量放线精准,第一、第二楔块51、52的顶面与横向分配梁9之间焊接牢固。
When assembling the overall hoisting platform of the No. 0 steel bar formwork, it should be ensured that the measurement and setting-out are accurate, and the top surfaces of the first and
当然,本发明不拘泥于上述形式,拼装基础、0号块支撑体系以及0号块钢筋模板整体吊装平台的施工可以根据桥梁墩台施工进度适时调整,但是必须保证0号块钢筋模板整体吊装平台在主墩施工完成前完成,从而最大限度地压缩工期。 Of course, the present invention is not limited to the above-mentioned forms, the construction of the assembled foundation, the No. 0 block support system, and the No. 0 block steel formwork overall hoisting platform can be adjusted in due course according to the construction progress of the bridge pier abutment, but the overall hoisting platform of the No. 0 block steel formwork must be ensured. It is completed before the construction of the main pier is completed, so as to minimize the construction period.
本发明不局限于上述最佳实施方式,任何人应该得知在本发明的启示下作出的结构变化,凡是与本发明具有相同或相近的技术方案,均落入本发明的保护范围之内。 The present invention is not limited to the above-mentioned best implementation mode, and anyone should know that any structural changes made under the inspiration of the present invention, and any technical solutions that are identical or similar to the present invention, all fall within the protection scope of the present invention.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110411902.0A CN102493363B (en) | 2011-12-12 | 2011-12-12 | Quick construction method for segment No.0 of continuous beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110411902.0A CN102493363B (en) | 2011-12-12 | 2011-12-12 | Quick construction method for segment No.0 of continuous beam |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102493363A CN102493363A (en) | 2012-06-13 |
| CN102493363B true CN102493363B (en) | 2014-04-16 |
Family
ID=46185219
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201110411902.0A Expired - Fee Related CN102493363B (en) | 2011-12-12 | 2011-12-12 | Quick construction method for segment No.0 of continuous beam |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102493363B (en) |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103132463B (en) * | 2013-03-12 | 2015-06-24 | 中国建筑第六工程局有限公司 | Movable hanger operating platform and manufacturing, installing, using and removing methods thereof |
| CN104264592B (en) * | 2014-10-14 | 2016-08-24 | 中国水利水电第四工程局有限公司 | A kind of continuous beam construction method |
| CN110230259B (en) * | 2018-08-21 | 2021-05-28 | 中铁十八局集团有限公司 | Bridge cantilever casting pier top beam section and rapid construction method thereof |
| CN111042000A (en) * | 2020-01-16 | 2020-04-21 | 中建七局安装工程有限公司 | Temporary supporting method for continuous beam construction of support pier |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004218316A (en) * | 2003-01-16 | 2004-08-05 | Ps Mitsubishi Construction Co Ltd | Construction method for capital part and installing work vehicle |
| JP2007132077A (en) * | 2005-11-10 | 2007-05-31 | Yokogawa Bridge Corp | Construction method of rigid-frame bridge with angle brace member, and rigid-frame bridge with angle brace member |
| CN201169750Y (en) * | 2008-03-28 | 2008-12-24 | 中铁十三局集团有限公司 | Moving platform for bridging |
| CN101586330A (en) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | Receding construction method of cradle of continuous girder bridge made of prestressing concrete |
| JP2009299418A (en) * | 2008-06-17 | 2009-12-24 | Kajima Corp | Retreating and removing method and retreating device for travelling work vehicle for cantilever construction |
| CN201567533U (en) * | 2009-09-28 | 2010-09-01 | 中交二公局第六工程有限公司 | Assembly and disassembly-type bracket for cast-in-place of continuous beam |
| CN102051859A (en) * | 2010-12-14 | 2011-05-11 | 中铁大桥局集团第二工程有限公司 | Synchronous and fast construction method and device for cantilever-cast continuous girder No.0 block and lower structure |
-
2011
- 2011-12-12 CN CN201110411902.0A patent/CN102493363B/en not_active Expired - Fee Related
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2004218316A (en) * | 2003-01-16 | 2004-08-05 | Ps Mitsubishi Construction Co Ltd | Construction method for capital part and installing work vehicle |
| JP2007132077A (en) * | 2005-11-10 | 2007-05-31 | Yokogawa Bridge Corp | Construction method of rigid-frame bridge with angle brace member, and rigid-frame bridge with angle brace member |
| CN201169750Y (en) * | 2008-03-28 | 2008-12-24 | 中铁十三局集团有限公司 | Moving platform for bridging |
| CN101586330A (en) * | 2008-05-22 | 2009-11-25 | 中铁十一局集团第一工程有限公司 | Receding construction method of cradle of continuous girder bridge made of prestressing concrete |
| JP2009299418A (en) * | 2008-06-17 | 2009-12-24 | Kajima Corp | Retreating and removing method and retreating device for travelling work vehicle for cantilever construction |
| CN201567533U (en) * | 2009-09-28 | 2010-09-01 | 中交二公局第六工程有限公司 | Assembly and disassembly-type bracket for cast-in-place of continuous beam |
| CN102051859A (en) * | 2010-12-14 | 2011-05-11 | 中铁大桥局集团第二工程有限公司 | Synchronous and fast construction method and device for cantilever-cast continuous girder No.0 block and lower structure |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102493363A (en) | 2012-06-13 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN100503977C (en) | Tower column of cable-stayed bridge and its construction method | |
| CN101781879B (en) | Construction method of single-pylon cable-stayed bridge without dorsal cables | |
| CN102493360B (en) | Reinforced concrete arch bridge construction method | |
| CN105839536B (en) | A kind of construction method of Cable-stayed Bridge Pylon | |
| CN108914785B (en) | Construction method of hanging basket cantilever pouring for a multi-chamber corrugated steel web continuous girder bridge | |
| CN101117795A (en) | Installation method of single section of steel box basket arch | |
| CN204849607U (en) | A continuous beam string basket pre -compaction device for bridge construction | |
| CN106522102A (en) | Side span construction support, rigid frame bridge side span and rigid frame bridge | |
| CN112554077B (en) | Construction system and method of steel tube concrete assembled truss composite beam | |
| CN107190647A (en) | A kind of alignment control apparatus and method suitable for the special-shaped tower of steel construction | |
| CN111794119A (en) | Temporary support system and hoisting method for basket type steel box tied arch | |
| CN113550230A (en) | A kind of prefabricated construction and control method of double-cable plane steel cable-stayed bridge with special-shaped arch tower | |
| CN110847039A (en) | Full cantilever installation method of segmental precast concrete box girder | |
| CN114790693B (en) | Construction method of large-span river-crossing steel truss bridge structure | |
| CN115387234A (en) | Template system of lower beam of ultrahigh rhombic tower pier and construction method | |
| CN104314013A (en) | Double suspension arm construction method of ultra-asymmetry combined beam | |
| CN116065492A (en) | A construction method of cable-stayed support system for Y-shaped bridge piers | |
| CN109881587B (en) | Integral installation method of beam support on main tower in strong wind environment | |
| CN114606870A (en) | Integral dismantling method for hoop-method bent cap supporting system | |
| CN102493363A (en) | Quick construction method for segment No.0 of continuous beam | |
| CN109722981A (en) | A kind of landscaping walking-bridge and its construction method of installation using Sarasota structure | |
| CN115162165B (en) | Construction method for closing middle tower column of highway-railway dual-purpose river-crossing A-type cable-stayed bridge | |
| CN204643604U (en) | Door-shaped hanging bracket waterborne | |
| CN116005605A (en) | A prefabricated component support system and setting method for berthing at a wharf | |
| CN115387233A (en) | Construction method for large-span and large-volume bent cap of transition pier of composite beam cable-stayed bridge |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| ASS | Succession or assignment of patent right |
Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD. Effective date: 20150217 Owner name: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU Free format text: FORMER OWNER: NO.1 ENGINEERING CO., LTD., ZHONGTIE BRIDGE BUREAU GROUP GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU Effective date: 20150217 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 430074 WUHAN, HUBEI PROVINCE TO: 430050 WUHAN, HUBEI PROVINCE |
|
| TR01 | Transfer of patent right |
Effective date of registration: 20150217 Address after: 430050 Hanyang Road, Hanyang District, Hubei, No. 38, No. Patentee after: CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd. Patentee after: 1ST ENGINEERING CO., LTD. OF CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd. Address before: 430074 Hubei province Wuhan Dongxin East Lake New Technology Development Zone Road SBI Venture Street No. 6 Building 12 layer Patentee before: CHINA RAILWAY MAJOR BRIDGE ENGINEERING Co.,Ltd. Patentee before: 1ST ENGINEERING CO., LTD. OF CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd. Patentee before: CHINA RAILWAY MAJOR BRIDGE ENGINEERING GROUP Co.,Ltd. |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140416 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |