CN102478597A - Intelligent monitoring device for high-voltage cable of power transmission tower - Google Patents

Intelligent monitoring device for high-voltage cable of power transmission tower Download PDF

Info

Publication number
CN102478597A
CN102478597A CN2010105556595A CN201010555659A CN102478597A CN 102478597 A CN102478597 A CN 102478597A CN 2010105556595 A CN2010105556595 A CN 2010105556595A CN 201010555659 A CN201010555659 A CN 201010555659A CN 102478597 A CN102478597 A CN 102478597A
Authority
CN
China
Prior art keywords
data acquisition
monitoring device
current transformer
intelligent monitoring
voltage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105556595A
Other languages
Chinese (zh)
Inventor
赵延华
杨春雷
杨波
王增军
王爱华
杨学杰
孙晓彬
于景岳
王风伟
韩进新
张宝光
韩其会
李川川
钱冰
路新波
李宋林
孙庆国
丁宁
汪奇
李思毛
陈文栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical Zibo Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN2010105556595A priority Critical patent/CN102478597A/en
Publication of CN102478597A publication Critical patent/CN102478597A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to an intelligent monitoring device for a high-voltage cable of a power transmission tower. The intelligent monitoring device comprises an iron tower and a secondary coil arranged on the iron tower and is characterized by also comprising a voltage current transformer, a connecting wire and a data acquisition and transmission device, wherein one end of the voltage current transformer is connected with the secondary coil and the other end of the voltage current transformer is connected with the data acquisition and transmission device through the connecting wire; and the data acquisition and transmission device is arranged on the iron tower. According to the invention, the working difficulty is reduced. Two persons need to perform acquisition on the working rod in the past and one person can perform computer operation at background at present, so that the operator can perform multipoint acquisition analysis, acquisition is optimized, labor and time are saved, threat caused by operation induced voltage is reduced, reliability of data acquisition is guaranteed, and safe and reliable operation is realized. Compared with the traditional measurement, the invention has the advantages that: no difficulty exists in operation measurement; the process management and the labor intensity of workers are reduced; and safety production is indirectly guaranteed.

Description

Transmission tower high-tension cable intelligent monitoring device
Technical field
The present invention relates to a kind of transmission tower high-tension cable intelligent monitoring device.
Background technology
The acquisition method of present feeder cable line terminal ground voltage and electric current, main manual work is stepped on tower and is utilized pincerlike meter to measure.Because urbanization and samll cities and towns' construction are quickened; Terminals, ground connection case increase sharply on the shaft tower of the use of cable line and mixed frame; Acquisition method monitoring according to cable operating standard voltage and current will receive shaft tower and cable bare wire to mix the influence of electric parameters such as frame on the one hand, receives the influence of specialty point and operation on the other hand again; In reality because the operation; Particularly circuit close on, with other circuit of tower and different specialty; During a plurality of working groups operations; Acquisition method every the circuit in monitoring collection point that needs feeder cable line terminal secondary ground voltage and electric current lacks safe information technology control etc. owing to do not have information source collection and control.
Especially the current remote circuit of high-voltage cable does not have the information source of a feeder cable line terminal secondary ground voltage and electric current, particularly increases day by day and mixes frame cable line terminals, and as the annex of cable line etc., realizes that intelligent control monitors.
It is many to mix frame cable line branch earth point, relates to how tame needs of work such as power supply unit, Subscriber Unit transmission tower cable terminal secondary grounding monitor has been adopted the collecting work of mutual voltage and electric current, the more comprehensive monitor message of needs.
Prison voltage and current monitoring technology requires on the power transmission and distribution cable line cable terminal secondary extension bar tower according to waiting, the requirement of whole service monitoring standard; From safety, the reliable and accurate coefficient balance of data acquisition, key personnel's rod-rising tower measuring method of promoting now is to choose first method.Normally make an inspection tour the monitoring periods arrangement according to operating standard.Run unit is according to cable and fixed cable terminal group number and the shaft tower contrast of the charged work ticket row of circuit, and it is different that the operating personnel relates to specialty; The work permit order is dual; The staff fulfils the work permit formality, handles work ticket, explains safety practice and dangerous point; The operating personnel arrives work ticket institute column position, and the operating personnel needs the safety custody measure.Begin to step on bar and carry out work, belong to work high above the ground from technical the saying of operating environment; Since circuit with equipment and user's branch line more, add on shaft tower collection voltage and current etc., operating condition belongs to high-risk status; Operation and monitoring two people are on bar and work on the spot.The personnel that work on the whole bar need work high above the ground; And, need to carry out on the bar 4 two identical mutual voltages and electric current time monitoring collection and repeat work.
Existing employed survey instrument mainly comprises pincerlike meter, record sheet etc., and electric pressure is high more, and the induced voltage of survey crew and live wire is also outstanding more, and is also high more to person induction.And shaft tower is high more, and the ground connection case of cable just requires high more, does not allow during personnel's operation to measure; Sometimes meet the hardships rain and dew, shaft tower body portion or adhere to frosting etc., the needed Measuring Time of operation is just longer.Measure on the operation process king-rod with bar under personnel labor intensity high, cause muscular fatigue to cause danger easily.Cable professional particularly, shaft tower on operation, accidents such as falling object from high altitude very easily take place; Because the monitoring of transmission tower cable terminal secondary has adopted the acquisition method time of mutual voltage and electric current long, active section can not get protection, and the field intensity of other induction instrument aratus is higher can't to mask, and influences surveying work progress and accuracy.
Summary of the invention
According to above deficiency of the prior art, the technical matters that the present invention will solve is: provide a kind of and can overcome above-mentioned defective, reduce task difficulty, the transmission tower high-tension cable intelligent monitoring device of raising labour efficiency.
The technical solution adopted for the present invention to solve the technical problems is: a kind of transmission tower high-tension cable intelligent monitoring device; Comprise iron tower and be installed in the secondary line on the iron tower; It is characterized in that: also comprise voltage current transformer, connecting line and data acquisition emitter; Voltage current transformer one end is connected with secondary line, and an end is connected with the data acquisition emitter through connecting line, and the data acquisition emitter is arranged on the iron tower.
Described data acquisition emitter comprises data acquisition unit, single-chip microcomputer and wireless launcher; Voltage current transformer connects data acquisition unit through data line; Data acquisition unit connects the input end of single-chip microcomputer, and the output terminal of single-chip microcomputer connects wireless launcher.
Described wireless launcher is the gsm wireless emitter.
Voltage and current on the voltage current transformer induction secondary line; Induction current is sent to data acquisition unit through connecting line; Data acquisition unit converts induction current into digital signal and sends single-chip microcomputer to; Single-chip microcomputer sends the data to wireless launcher after through analytical calculation, and wireless launcher sends signal to supporting with it receiving terminal, accomplishes monitoring.
The beneficial effect that the present invention had is:
Reduced task difficulty.Collection needs 2 people on the former operation bar, needs 1 people to get final product through computer operation on the backstage now, personnel's ability multiple spot collection analysis; Accomplish the optimization collection, realize laborsaving, save time, reduce to threaten because of the operation induced voltage; Guaranteed that data acquisition is reliable, accomplished safe and reliable operation.
Compare with traditional measurement, operational measure of the present invention does not have difficulty, has reduced staff's process management and labour intensity, has guaranteed safety in production indirectly.Survey crew reduces to 1 people's consistency operation by 2~3 people on the bar, and measurement can be in real time and 24 hour records; Subtract few 100% minute of time, improved efficiency.
Description of drawings
Fig. 1 is a structural representation of the present invention.
Fig. 2 is a data acquisition emitter theory diagram.
Among the figure: 1, iron tower; 2, secondary line; 3, voltage current transformer; 4, connecting line; 5, data acquisition emitter;
Embodiment
Below in conjunction with accompanying drawing embodiments of the invention are done and to be further described:
Like Fig. 1~shown in Figure 2: a kind of transmission tower high-tension cable intelligent monitoring device; Comprise iron tower 1 and be installed in the secondary line 2 on the iron tower; Also comprise voltage current transformer 3, connecting line 4 and data acquisition emitter 5; Voltage current transformer 3 one ends are connected with secondary line 4, and an end is connected with data acquisition emitter 5 through connecting line 4, and data acquisition emitter 5 is arranged on the iron tower 1.
Described data acquisition emitter 5 comprises data acquisition unit, single-chip microcomputer and wireless launcher; Voltage current transformer connects data acquisition unit through data line; Data acquisition unit connects the input end of single-chip microcomputer, and the output terminal of single-chip microcomputer connects wireless launcher.
Described wireless launcher is the gsm wireless emitter.
Voltage and electric current on the voltage current transformer 3 induction secondary lines 2; Induction current is sent to data acquisition unit through connecting line 4; Data acquisition unit converts induction current into digital signal and sends single-chip microcomputer to; Single-chip microcomputer sends the data to wireless launcher after through analytical calculation, and wireless launcher sends signal to supporting with it receiving terminal, accomplishes monitoring.

Claims (3)

1. transmission tower high-tension cable intelligent monitoring device; Comprise iron tower and be installed in the secondary line on the iron tower; It is characterized in that: also comprise voltage current transformer, connecting line and data acquisition emitter; Voltage current transformer one end is connected with secondary line, and an end is connected with the data acquisition emitter through connecting line, and the data acquisition emitter is arranged on the iron tower.
2. transmission tower high-tension cable intelligent monitoring device according to claim 1; It is characterized in that: described data acquisition emitter comprises data acquisition unit, single-chip microcomputer and wireless launcher; Voltage current transformer connects data acquisition unit through data line; Data acquisition unit connects the input end of single-chip microcomputer, and the output terminal of single-chip microcomputer connects wireless launcher.
3. transmission tower high-tension cable intelligent monitoring device according to claim 2 is characterized in that: described wireless launcher is the gsm wireless emitter.
CN2010105556595A 2010-11-23 2010-11-23 Intelligent monitoring device for high-voltage cable of power transmission tower Pending CN102478597A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105556595A CN102478597A (en) 2010-11-23 2010-11-23 Intelligent monitoring device for high-voltage cable of power transmission tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105556595A CN102478597A (en) 2010-11-23 2010-11-23 Intelligent monitoring device for high-voltage cable of power transmission tower

Publications (1)

Publication Number Publication Date
CN102478597A true CN102478597A (en) 2012-05-30

Family

ID=46091308

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105556595A Pending CN102478597A (en) 2010-11-23 2010-11-23 Intelligent monitoring device for high-voltage cable of power transmission tower

Country Status (1)

Country Link
CN (1) CN102478597A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107831701A (en) * 2017-11-17 2018-03-23 广西电网有限责任公司防城港供电局 A kind of positioning of lightning fault and identifying system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1987500A (en) * 2006-12-21 2007-06-27 三峡大学 On-line monitoring system method for overhead line by potential method
CN101464488A (en) * 2009-01-16 2009-06-24 上海慧东电气设备有限公司 On-line monitoring system for high voltage cable
CN201903571U (en) * 2010-11-23 2011-07-20 山东电力集团公司淄博供电公司 Intelligent monitor device of transmission tower high-voltage cable

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1987500A (en) * 2006-12-21 2007-06-27 三峡大学 On-line monitoring system method for overhead line by potential method
CN101464488A (en) * 2009-01-16 2009-06-24 上海慧东电气设备有限公司 On-line monitoring system for high voltage cable
CN201903571U (en) * 2010-11-23 2011-07-20 山东电力集团公司淄博供电公司 Intelligent monitor device of transmission tower high-voltage cable

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107831701A (en) * 2017-11-17 2018-03-23 广西电网有限责任公司防城港供电局 A kind of positioning of lightning fault and identifying system
CN107831701B (en) * 2017-11-17 2020-05-05 广西电网有限责任公司防城港供电局 Lightning stroke fault positioning and identifying system

Similar Documents

Publication Publication Date Title
CN103874122B (en) Special transformer terminals network signal acquisition system and acquisition method
CN204536448U (en) A kind of high voltage supply leakage conductor wireless monitoring device
CN105807158A (en) Electric power parameter online monitoring system and monitoring control method for power grid connection points and switches
CN110912273A (en) Distribution network ground fault analysis management system
CN210438843U (en) Electric potential monitoring system
CN103389437A (en) Device and method for monitoring shielding current of secondary control cable of transformer substation in real time
CN202957659U (en) Line loss actual measurement and positioning system based on high voltage electric energy meter
CN108318732B (en) On-line monitoring device and method for grounding current of transformer core
CN201903571U (en) Intelligent monitor device of transmission tower high-voltage cable
CN102478597A (en) Intelligent monitoring device for high-voltage cable of power transmission tower
CN113206544A (en) Power grid GIC monitoring device based on transformer high-voltage incoming and outgoing lines
CN208571705U (en) A kind of 500kV substation fault recording teletransmission data monitoring system
CN203502504U (en) Electric power circuit line loss real time monitoring system based on internet of things
CN212693878U (en) Detection system of large-scale comprehensive grounding system
CN209372282U (en) A kind of acquisition of real-time stress and remote supervision system suitable for ocean engineering experiment
CN204203355U (en) Floating roof tank floating plate connects wire on-Line Monitor Device
CN208985350U (en) Lightning protection monitoring early-warning system based on NB-IOT transmission mode
CN203376430U (en) Substation secondary control cable shielding current real-time monitoring device
CN109708797A (en) A kind of acquisition of real-time stress and remote supervision system suitable for ocean engineering experiment
CN202600948U (en) Wireless data acquisition device in energy consumption monitoring system
CN207488353U (en) A kind of current conversion station earthing pole enters ground cable current monitoring system
CN104006793A (en) Sag real-time monitoring device
CN208155470U (en) Temperature of oil in transformer detection device and system
CN204203337U (en) A kind of system of carrying out ground potential difference monitoring
CN105021908A (en) Intelligent high voltage test system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POWER CORPORATION

Effective date: 20130802

Owner name: ZIBO POWER SUPPLY COMPANY OF SHANDONG ELECTRIC POW

Effective date: 20130802

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 100031 Xicheng District, Chang'an Avenue, No. 86,

Applicant after: State Grid Corporation of China

Applicant after: STATE GRID ZIBO POWER SUPPLY COMPANY OF SHANDONG PROVINCE

Address before: 100031 Xicheng District, Chang'an Avenue, No. 86,

Applicant before: State Grid Corporation of China

Applicant before: Zibo Power Supply Company of Shandong Electric Power Corp.

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 255032 ZIBO, SHANDONG PROVINCE TO: 100031 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20130802

Address after: 100031 Xicheng District, Chang'an Avenue, No. 86,

Applicant after: State Grid Corporation of China

Applicant after: Zibo Power Supply Company of Shandong Electric Power Corp.

Address before: 255032 No. 61 West Village Road, Zhangdian District, Shandong, Zibo

Applicant before: Zibo Power Supply Company of Shandong Electric Power Corp.

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120530