CN102434005A - Precast beam unit construction technology - Google Patents
Precast beam unit construction technology Download PDFInfo
- Publication number
- CN102434005A CN102434005A CN2011104117665A CN201110411766A CN102434005A CN 102434005 A CN102434005 A CN 102434005A CN 2011104117665 A CN2011104117665 A CN 2011104117665A CN 201110411766 A CN201110411766 A CN 201110411766A CN 102434005 A CN102434005 A CN 102434005A
- Authority
- CN
- China
- Prior art keywords
- precast beam
- beam unit
- precast
- housing
- stirrup
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
The invention provides a precast beam unit construction technology, with which the precast can be made in advance, and the time for one-piece casting on a construction site can be greatly saved, a beam shell can be a light and thin precast unit which can be served as a formwork, can be directly used as a ribbed formwork, and can be produced in large scale at a factory, the beam shell is concreted after being transported to the construction site to be assembled, and then forms a combined structural unit. The construction speed is fast, and the formwork is free from being supported on site. Building-in reinforcement stirrup in the beam shell can ensure the structural stability of the whole precast beam unit during the transportation and the like, which is suitable for second casting on site, and the reinforcement stirrup still can play its original role after the beam shell is installed in a building and the construction is completed.
Description
Technical field
The present invention relates to a kind of construction technology of prefabricated units of building, be specifically related to a kind of precast beam unit construction technology that is used for building.
Background technology
At present, building adopts reinforced concrete structure mostly, post, beam.Connected node globality between wall and the plate is strong, has good shock resistance.But the building of reinforced concrete structure needs on-the-spot reinforcing bar and the concreting arranged, needs the construction of a large amount of workmans and device context.In addition, before the concreting, need set up template; Need to wait for the regular hour after building, treating that concrete reaches after the enough intensity could stripping, just can adhere to construction equipments such as scaffold.
Prefabricated units can centralized production, and overall package is carried out at the scene of transporting to again, has saved the time of solidifying of poured in place concrete, improves construction speed, and can reduce field worker and amount of equipment, saves cost.Normally used precast beam unit waters and builds up an integral body, and the scene transported to again is connected with other structural element.Such precast beam unit and other structural element jointing place intensity are lower, and the whole shock resistance of building is relatively poor.
The inventor has proposed a kind of follow-on precast beam unit through studying for a long period of time, and this member adopts semi-closed structure, and internal fixation has reinforcing bar, can have good seismic resistance through all the other the structural element monobloc casts with building of building at scene.
Summary of the invention
The object of the present invention is to provide a kind of precast beam unit construction technology, adopt a concrete prefabricated semiclosed hollow housing and an on-the-spot structural element monobloc cast that has reinforcing bar, take into account prefabricated and advantages antidetonation two aspects.
For achieving the above object, technical scheme of the present invention is: a kind of precast beam unit construction technology, may further comprise the steps,
The first step is made precast beam unit in batches at manufacturing field;
Said precast beam comprises beam housing and stirrup, and said beam housing is semiclosed housing, and said stirrup is imbedded in the beam housing, and said stirrup not inlet part protrudes in the opening surface of beam housing;
In second step, precast beam unit is transported to the job site;
The 3rd step is with the precast beam unit location and installation;
The 4th step, main muscle is installed in precast beam unit, be connected with main muscle with the reinforcing bar of the structural element of precast beam unit joint;
In the 5th step, in the beam housing, carry out the concrete spouting construction.
When adopting technique scheme, the beam housing be can the double as template frivolous prefabricated component, can directly use as non-dismantling formwork, can be by plant layout production, transport to on-site consolidation concreting more later on, form the fabricated structure member.Speed of application soon, does not need on-the-spot supporting template.In the beam housing, bury stirrup underground and can guarantee the structural stability of whole precast beam unit in processes such as transportation, be fit to on-the-spot secondary and build, after installation and construction finished in building, described stirrup was still brought into play its due effect.
Further, stirrup is provided with the sealing outer ring in the said first step.
Further, the cross section of said beam housing is " U " shape, and said sealing outer ring is square.
Further, comprise through connecting the plural precast beam unit that draw-in groove connects in the 3rd step.
Description of drawings
Below in conjunction with the accompanying drawing and the specific embodiment the present invention is done further detailed explanation:
Fig. 1 is the sketch map of a kind of precast beam unit construction technology of the present invention embodiment.
The specific embodiment
As shown in Figure 1, a kind of precast beam unit construction technology of the present invention may further comprise the steps,
The first step is made precast beam unit in batches at manufacturing field;
Said precast beam comprises beam housing 1 and stirrup 2, and said beam housing 1 is semiclosed housing, and said stirrup 2 is imbedded in the beam housing 1, and said stirrup 2 not inlet part protrudes in the opening surface of beam housing 1;
In second step, precast beam unit is transported to the job site;
The 3rd step is with the precast beam unit location and installation;
The 4th step, main muscle is installed in precast beam unit, be connected with main muscle with the reinforcing bar of the structural element of precast beam unit joint;
In the 5th step, in beam housing 1, carry out the concrete spouting construction.
The cross section of above-mentioned hoop beam housing is " U " shape, and said stirrup is provided with square sealing outer ring.
During use, in advance that this precast beam unit is concentrated prefabricated, form a semiclosed housing that has stirrup 2.Wherein stirrup 2 plays and supports and the effect of antitorque tension after 1 moulding of beam housing.When transporting, lifting, build, play the effect of brace summer housing 1.But whole beam housing 1 also double as beam forms uses, and need not to take mould and form removal, also need not the metope maintenance.Directly beam housing 1 is connected with on-the-spot construction member and fixes, concreting in beam housing 1 again, obtain with the construction member of building for example: post, plate etc. connects into " precast beam " of an integral body, has overcome the relatively poor weakness of traditional precast beam shock resistance.
Above-described only is preferred implementation of the present invention; Should be understood that; For a person skilled in the art, not breaking away under the prerequisite of the present invention, can also make some distortion and improvement; These also should be regarded as protection scope of the present invention, and these can not influence effect and practical applicability that the present invention implements.
Claims (4)
1. a precast beam unit construction technology is characterized in that, may further comprise the steps,
The first step is made precast beam unit in batches at manufacturing field;
Said precast beam comprises beam housing and stirrup, and said beam housing is semiclosed housing, and said stirrup is imbedded in the beam housing, and said stirrup not inlet part protrudes in the opening surface of beam housing;
In second step, precast beam unit is transported to the job site;
The 3rd step is with the precast beam unit location and installation;
The 4th step, main muscle is installed in precast beam unit, be connected with main muscle with the reinforcing bar of the structural element of precast beam unit joint;
In the 5th step, in the beam housing, carry out the concrete spouting construction.
2. a kind of precast beam unit construction technology according to claim 1 is characterized in that, stirrup is provided with the sealing outer ring in the said first step.
3. a kind of precast beam unit construction technology according to claim 2 is characterized in that, the cross section of said beam housing is " U " shape, and said sealing outer ring is square.
4. a kind of precast beam unit construction technology according to claim 3 is characterized in that, comprises through connecting the plural precast beam unit that draw-in groove connects in the 3rd step.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011104117665A CN102434005A (en) | 2011-12-12 | 2011-12-12 | Precast beam unit construction technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011104117665A CN102434005A (en) | 2011-12-12 | 2011-12-12 | Precast beam unit construction technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102434005A true CN102434005A (en) | 2012-05-02 |
Family
ID=45982333
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011104117665A Pending CN102434005A (en) | 2011-12-12 | 2011-12-12 | Precast beam unit construction technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102434005A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105019599A (en) * | 2015-08-04 | 2015-11-04 | 万保金 | Disassembly-free precast concrete beam insulation template |
CN107386528A (en) * | 2017-08-07 | 2017-11-24 | 重庆交通大学 | Method for making the template free of demolition of beams of concrete and making beams of concrete |
CN109403497A (en) * | 2018-12-17 | 2019-03-01 | 杭州曼京科技有限公司 | A kind of skyscraper shock insulation damping device |
CN109403498A (en) * | 2018-12-17 | 2019-03-01 | 杭州曼京科技有限公司 | A kind of skyscraper earthquake isolation recovery device |
CN110886235A (en) * | 2019-12-21 | 2020-03-17 | 烟台仁晟工程设备有限公司 | Bridge construction method |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2406000Y (en) * | 1999-12-22 | 2000-11-15 | 吴方伯 | Overlapped mould for building |
CN2633992Y (en) * | 2003-09-09 | 2004-08-18 | 吴方伯 | Steel bar concrete prefabricated member for compound girder |
CN201050113Y (en) * | 2007-04-27 | 2008-04-23 | 刘泳霞 | Light aggregate reinforcing steel bar concrete energy-saving domestic architecture structure system |
CN201050128Y (en) * | 2007-03-05 | 2008-04-23 | 刘泳霞 | Cast in-situ light aggregate reinforcing steel concrete composite floor slab |
CN101298796A (en) * | 2008-03-31 | 2008-11-05 | 姚攀峰 | Self-bearing type preprocessing component, self-bearing type preprocessing concrete structure and construction method thereof |
CN101429803A (en) * | 2008-12-05 | 2009-05-13 | 重庆大学 | Construction column used for masonry structure and its production method and special precast segment |
CN201972393U (en) * | 2010-11-19 | 2011-09-14 | 清华大学建筑设计研究院 | Dismantling-free precast reinforced concrete template with crossed holes inside |
CN102235093A (en) * | 2010-04-22 | 2011-11-09 | 上海市第七建筑有限公司 | Construction method for cast-in-situ connecting joint of prefabricated member |
-
2011
- 2011-12-12 CN CN2011104117665A patent/CN102434005A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2406000Y (en) * | 1999-12-22 | 2000-11-15 | 吴方伯 | Overlapped mould for building |
CN2633992Y (en) * | 2003-09-09 | 2004-08-18 | 吴方伯 | Steel bar concrete prefabricated member for compound girder |
CN201050128Y (en) * | 2007-03-05 | 2008-04-23 | 刘泳霞 | Cast in-situ light aggregate reinforcing steel concrete composite floor slab |
CN201050113Y (en) * | 2007-04-27 | 2008-04-23 | 刘泳霞 | Light aggregate reinforcing steel bar concrete energy-saving domestic architecture structure system |
CN101298796A (en) * | 2008-03-31 | 2008-11-05 | 姚攀峰 | Self-bearing type preprocessing component, self-bearing type preprocessing concrete structure and construction method thereof |
CN101429803A (en) * | 2008-12-05 | 2009-05-13 | 重庆大学 | Construction column used for masonry structure and its production method and special precast segment |
CN102235093A (en) * | 2010-04-22 | 2011-11-09 | 上海市第七建筑有限公司 | Construction method for cast-in-situ connecting joint of prefabricated member |
CN201972393U (en) * | 2010-11-19 | 2011-09-14 | 清华大学建筑设计研究院 | Dismantling-free precast reinforced concrete template with crossed holes inside |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105019599A (en) * | 2015-08-04 | 2015-11-04 | 万保金 | Disassembly-free precast concrete beam insulation template |
CN107386528A (en) * | 2017-08-07 | 2017-11-24 | 重庆交通大学 | Method for making the template free of demolition of beams of concrete and making beams of concrete |
CN109403497A (en) * | 2018-12-17 | 2019-03-01 | 杭州曼京科技有限公司 | A kind of skyscraper shock insulation damping device |
CN109403498A (en) * | 2018-12-17 | 2019-03-01 | 杭州曼京科技有限公司 | A kind of skyscraper earthquake isolation recovery device |
CN110886235A (en) * | 2019-12-21 | 2020-03-17 | 烟台仁晟工程设备有限公司 | Bridge construction method |
CN110886235B (en) * | 2019-12-21 | 2021-07-06 | 烟台仁晟工程设备有限公司 | Bridge construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109577534B (en) | Tool-based hanging die assembly type composite floor slab and construction method | |
CN103088844B (en) | Reinforced concrete inspection well whole prefabricated hoisting construction method | |
CN110847044B (en) | Semi-prefabricated assembled bent cap construction method | |
CN104895092B (en) | The method that a kind of interim lattice column of inner support is used as permanent structure post | |
CN103410317A (en) | Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part | |
CN103015719B (en) | Integral casting process for reinforced concrete wastewater tank of pre-drilling engineering | |
CN105908777A (en) | Comprehensive pipe gallery sliding mold and application method thereof | |
CN105064555A (en) | Structural wallboard for superimposed decorative layer and insulating layer and construction method | |
CN206267422U (en) | A kind of assembly concrete superposed column | |
CN102434005A (en) | Precast beam unit construction technology | |
CN104963289A (en) | Integral one-time pouring construction method of large-volume concrete for special-shaped pier stud | |
CN103556819B (en) | A kind of construction method of reserved constructional column hole on beam slab | |
CN106113230B (en) | The non-type prefabricated for bench, template system and its construction method can be had enough to meet the need | |
CN105525753A (en) | Method and structure for simultaneously constructing constructional column and main body structure | |
BR102015027603A2 (en) | Method for installing a hollow concrete tower made of more than one segment and hollow concrete tower | |
KR100924701B1 (en) | Construction method for Utility-pipe conduit | |
CN104727552A (en) | Construction method for reserving water feed pipe grooves in prefabricated shear wall | |
KR20230090300A (en) | A twin wall structure using a PC panel and method for manufacturing of it | |
CN108582465A (en) | After pour canopy, precast reinforced concrete frame beam and after pour canopy manufacturing method | |
CN202945741U (en) | Non-vibrating concrete column of steel tube | |
CN203022222U (en) | Wholly-cast ring beam of brick-concrete building support | |
CN104947853B (en) | A kind of Inner standpipe formula cast-in-situ reinforced concrete column and construction method | |
CN203947381U (en) | A kind of steel concrete chain type plate | |
CN209907420U (en) | Wet joint structure among bridge pier, bearing platform and pile foundation | |
KR102268423B1 (en) | Precaste Bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20120502 |