CN102412447A - Intelligent ion grounding system - Google Patents
Intelligent ion grounding system Download PDFInfo
- Publication number
- CN102412447A CN102412447A CN201010292266XA CN201010292266A CN102412447A CN 102412447 A CN102412447 A CN 102412447A CN 201010292266X A CN201010292266X A CN 201010292266XA CN 201010292266 A CN201010292266 A CN 201010292266A CN 102412447 A CN102412447 A CN 102412447A
- Authority
- CN
- China
- Prior art keywords
- ion
- grounding electrode
- intelligent
- soil
- built
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention provides an intelligent ion grounding system which consists of an ion grounding electrode (1), an infusion tube (2), a horizontal grounding electrode (3), an intelligent ion supplier (6), an ion storage unit (4) and a liquid adding cover (5), wherein, the front-end ion grounding electrode (1) is provided with a built-in efficient ion agent, and can continuously release ions to soil through exchange holes around the electrode body after the ion grounding electrode is buried underground; the intelligent liquid supply system (6) can intelligently set time and flow rate through a built-in computer chip and can quantitatively and regularly inject the ion agent in the ion storage unit (4) into the front-end ion grounding electrode (1) through the infusion tube (2) so as to timely supplement the ion agent in the front-end ion grounding electrode (1), thus preventing problems caused by ion loss; and the liquid adding cover (5) is arranged at the top of the ion storage unit (4), and the ion agent can be added after the liquid adding cover (5) is opened.
Description
Technical field
The present invention relates to a kind of intelligent ion earthing system, refer specifically to the intelligent ion earthing system of the leachability problem of a kind of corrosivity that can effectively solve soil resistivity height, ion and ion.
Background technology
One, on large stretch of area cement flooring, humidity is generally lower, greatly between 5%-10%; In addition, on hillside, it is main that soil property is generally the yellow mud burning into sand; In dry season, soil resistivity is about 250 Europe rice according to " soil resistivity reference table " yellow mud in " DL/T 621-1997 "; Dauk is about 80-1000 Europe rice.If be interpreted as that here both are comprehensive, then be appreciated that 300-500 Europe rice.For the purpose of ensureing, this gets median, and promptly setting soil resistivity is that 400 Europe rice are done as Parameter Calculation.
Two, designing requirement
According to the requirement of equipment, the local network designing requirement is 1 Europe.
Three, Traditional calculating methods and need material
Suppose that designing requirement is 0.1 Europe, we design by traditional method so:
With reference to the method in " DL/T 621-1997 ", compound earth mat computing formula:
For the purpose of image, we suppose that the earth mat that designs is foursquare earth mat, a S=L so
2
L is the foursquare length of side, and the formula that substitution is above-mentioned then has formula of reduction to be:
According to above-mentioned designing requirement, R=0.1 Europe; Again according to setting ρ=500 in the environmental assessment
Europe rice.In above-mentioned two data substitution formula (2), obtain
Promptly by traditional design, in environment like this, design the earth mat in one 0.1 Europe, the construction area that needs is 200 * 200m.In view of this, reach so requirement, be huge on dropping into, unpractiaca.
And mention in " electric resistance of soil counting rate meter " in " DL/T 621-1997 ", saliferous or alkali are in soil, soil resistivity is about 1/30~1/10 of native soil resistivity.This is a kind of thinking of design, but salt pair metal earth electrode has very strong corrosivity, therefore, can not use as the material that earth mat is built.Any way is arranged so, promptly increase the composition of soil intermediate ion, avoided corrosion again to earth mat?
Though ion grounding electrode can solve above technical problem,, the ion grounding electrode result of use can not be lasting; Generally about half a year, when running into the rainy day, or under the situation of Groundwater Flow; Ion component can little by little run off, when ion component spreads apart, and after having run off; Soil resistivity returns to original state, thereby the grounding resistance of earth mat has very big lifting, and equipment is caused very big harm.
Summary of the invention:
In order to solve the problem that exists in the above technology, the present invention has made following technical solution.
A kind of intelligent ion earthing system; Form by ion grounding electrode 1, woven hose 2, the horizontal grounding utmost point 3, intelligent ion supply 6, ion storage device 4, liquid feeding lid 5, can solve soil resistivity height, the corrosivity of ion and the leachability problem of ion well.Do further to introduce in the face of high-effect ionic supply grounding system down.
Front end ion grounding electrode 1 is built-in ionic agent efficiently, imbed underground after, through the exchange hole around the polar body,, thereby improve the conductive structure of soil to soil release of ionic continuously, reduce soil resistivity, thereby reduce the earth resistance of earth mat.
Intelligence liquid-supplying system 6 is by built-in computer chip, intelligent setting-up time; Flow, and through a woven hose 2, with the ionic agent in the ion reservoir 4; Regularly; Be injected into quantitatively in the front end ion grounding electrode 1, thereby the ionic agent in the front end ion grounding electrode 1 is in time replenished, avoid the variety of problems that runs off and bring because of ion.
Intelligence ion earthing system has following characteristics:
● according to actual conditions, can set whenever at regular intervals, fixedly forward end is injected ionic agent, exempts from artificial trouble of adding.
● band LED shows, the parameter intelligent setting is directly perceived simple.
● simple to operate, output state need not be regulated and can meet automatically
● the minimum time in a day can be set to second or minute
● according to the difference of capacity, but 2-5 is non-maintaining at most, keeps earth resistance constant.
● when ionic agent is exhausted, safeguard simply, the ionic agent in the ion storage device is finished using, and only need open top cover, with its fill it up with then can, simple and convenient, 10 clocks can be accomplished maintenance.Can use 2-5 again, its cost is less than transforming 1/10 of earth mat again.
Beneficial effect of the present invention has been to solve well soil resistivity height, the corrosivity of ion and the leachability problem of ion, has prolonged the useful life of intelligent grounding system, has practiced thrift cost.
Description of drawings:
Below in conjunction with accompanying drawing the present invention is further described.
Figure (1) is a fundamental diagram of the present invention.
Embodiment:
The front end ion grounding electrode is built-in ionic agent efficiently, imbed underground after, through the exchange hole around the polar body; To soil release of ionic continuously, by built-in computer chip, intelligent setting-up time; Flow, and through a woven hose, with the ionic agent in the ion reservoir; Regularly, be injected into quantitatively in the front end ion grounding electrode, thereby the ionic agent in the front end ion grounding electrode is in time replenished.
Claims (3)
1. an intelligent ion earthing system is made up of ion grounding electrode, woven hose, the horizontal grounding utmost point, intelligent ion supply, ion storage device, liquid feeding lid, it is characterized in that solving soil resistivity height, the corrosivity of ion and the leachability problem of ion.
2. by the described a kind of intelligent ion earthing of claim 1 system; It is characterized in that the front end ion grounding electrode built-in ionic agent efficiently, imbed underground after, through the exchange hole around the polar body; To soil release of ionic continuously; Thereby improve the conductive structure of soil, reduce soil resistivity, thereby reduce the earth resistance of earth mat.
3. by the described a kind of intelligent ion earthing of claim 1 system, it is characterized in that intelligent liquid-supplying system, is by built-in computer chip; The intelligence setting-up time, flow, and through a woven hose; With the ionic agent in the ion reservoir, regularly, be injected into quantitatively in the front end ion grounding electrode; Thereby the ionic agent in the front end ion grounding electrode is in time replenished, avoid the variety of problems that runs off and bring because of ion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010292266XA CN102412447A (en) | 2010-09-26 | 2010-09-26 | Intelligent ion grounding system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010292266XA CN102412447A (en) | 2010-09-26 | 2010-09-26 | Intelligent ion grounding system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102412447A true CN102412447A (en) | 2012-04-11 |
Family
ID=45914382
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201010292266XA Pending CN102412447A (en) | 2010-09-26 | 2010-09-26 | Intelligent ion grounding system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102412447A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105071061A (en) * | 2015-09-08 | 2015-11-18 | 国家电网公司 | Lightning protection grounding system of power distribution transformer area |
CN109066250A (en) * | 2018-08-14 | 2018-12-21 | 中国铁建电气化局集团北方工程有限公司 | Mountain area high roadbed, high soil resistivity high-speed railway traction substation are grounded engineering method |
CN110277661A (en) * | 2019-05-13 | 2019-09-24 | 张昱 | Without the lightning protection construction method of the sustainable maintenance of secondary digging groove |
CN111082234A (en) * | 2019-12-11 | 2020-04-28 | 国网河南省电力公司电力科学研究院 | Permeation type grounding device |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101604794A (en) * | 2009-07-08 | 2009-12-16 | 无锡市格林电工装备有限公司 | Anti-corrosion type energy-storage ionic earthing array |
CN101728661A (en) * | 2008-10-21 | 2010-06-09 | 吕良 | Monitoring low-resistance module grounding device |
-
2010
- 2010-09-26 CN CN201010292266XA patent/CN102412447A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101728661A (en) * | 2008-10-21 | 2010-06-09 | 吕良 | Monitoring low-resistance module grounding device |
CN101604794A (en) * | 2009-07-08 | 2009-12-16 | 无锡市格林电工装备有限公司 | Anti-corrosion type energy-storage ionic earthing array |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105071061A (en) * | 2015-09-08 | 2015-11-18 | 国家电网公司 | Lightning protection grounding system of power distribution transformer area |
CN109066250A (en) * | 2018-08-14 | 2018-12-21 | 中国铁建电气化局集团北方工程有限公司 | Mountain area high roadbed, high soil resistivity high-speed railway traction substation are grounded engineering method |
CN109066250B (en) * | 2018-08-14 | 2019-11-19 | 中国铁建电气化局集团北方工程有限公司 | Mountain area high roadbed, high soil resistivity high-speed railway traction substation are grounded engineering method |
CN110277661A (en) * | 2019-05-13 | 2019-09-24 | 张昱 | Without the lightning protection construction method of the sustainable maintenance of secondary digging groove |
CN111082234A (en) * | 2019-12-11 | 2020-04-28 | 国网河南省电力公司电力科学研究院 | Permeation type grounding device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102412447A (en) | Intelligent ion grounding system | |
CN204335482U (en) | A kind of farmland intelligent irrigation system | |
CN103262727A (en) | Manufacturing method of tail slag field reclamation returning-to-farmland isolation layer | |
CN203167544U (en) | Isolated layer for reclamation returning of tail slag field with toxic heavy metals | |
CN205005637U (en) | A irrigation equipment under membrane for M type rectangular pieces of land in a field | |
Jenkins | Sustainable water management analysis of the Selwyn catchment using nested adaptive systems | |
CN209314231U (en) | A kind of erosion zone revegetation water conservation layer | |
CN209546513U (en) | A kind of massif irrigation robot control system(RCS) for hills area | |
Wunderlich et al. | Quantifying water storage capacity in, and dry season water yield from Bofedales, Andean Wetlands | |
Fang | Groundwater Salinity Simulation of a Subsurface Reservoir in Taiwan | |
Jiao et al. | Validation and application of a two-dimensional model to simulate soil salt transport under mulched drip irrigation | |
CN205425259U (en) | Novel solar airconditioning device | |
Vajja et al. | Ground Water Recharge Estimation Using Water Table Fluctuation Method And By GIS Applications | |
Abitew et al. | Simulating wind erosion in rangeland catchments using the APEX model | |
CN204010131U (en) | Old and useless battery intelligence retracting device | |
Verbunt et al. | The assessment of the impact of water management for energy production on the hydrological modelling of the Alpine Rhine catchment | |
Cey et al. | Quantifying depression-focused recharge in a seasonally frozen, semi-arid landscape | |
Decker et al. | Modelling Snow-Melt Floods over high-Mountain Areas of Norway using Statkraft's Hydrological Forecasting Toolbox (Shyft) | |
Bierkens et al. | Modelling water use in global hydrological models: review, challenges and directions | |
Sciance et al. | Temporal changes in extent and duration of flooding in the Ganges-Brahmaputra Delta, Bangladesh | |
Lange et al. | Water resources assessment in dry catchments by hydrological modelling adopted to limited data availability: River Anas, India | |
Gulbin et al. | Accounting for wetlands loss in a changing climate in the estimation of long-term flood risks of Devils Lake, North Dakota | |
Milewski et al. | Remote Sensing Solutions for Continuous Rainfall Runoff Modeling | |
CN201966333U (en) | Electrolytic ion type grounding module | |
Piccolroaz et al. | On the use of distributed microgravity observations to inform hydrological models |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120411 |