CN102407567B - Production pedestal for quickly prefabricating T-shaped beam - Google Patents
Production pedestal for quickly prefabricating T-shaped beam Download PDFInfo
- Publication number
- CN102407567B CN102407567B CN 201110337792 CN201110337792A CN102407567B CN 102407567 B CN102407567 B CN 102407567B CN 201110337792 CN201110337792 CN 201110337792 CN 201110337792 A CN201110337792 A CN 201110337792A CN 102407567 B CN102407567 B CN 102407567B
- Authority
- CN
- China
- Prior art keywords
- track foundation
- load area
- heavy
- light
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Foundations (AREA)
Abstract
本发明公开了一种快速预制T型梁生产台座,包括重载区轨道基础,置于重载区轨道基础纵向长度方向的轻载区轨道基础,置于重载区轨道基础和轻载区轨道基础内的钢轨联结预埋件,安装于钢轨联结预埋件上的钢轨,置于重载区轨道基础混凝土内且外露的T型梁外侧模预埋件,铺设于重载区轨道基础和轻载区轨道基础下的灰土垫层。可以在轻载区轨道基础上完成钢筋绑扎、模板安装等工序,在重载区轨道基础上完成混凝土浇筑、拆模、张拉、养护等工序,重载区轨道基础和轻载区轨道基础分别设计、各司其职,结构简单、设计合理,适应快速预制T型梁,结构整体性强,整体工程量小且适应范围广。
The invention discloses a rapid prefabricated T-beam production pedestal, which comprises a heavy-load area track foundation, a light-load area track foundation placed in the longitudinal direction of the heavy-load area track foundation, and a light-load area track foundation placed on the heavy-load area track foundation and light-load area track Rail connection embedded parts in the foundation, rails installed on the rail connection embedded parts, placed in the heavy-duty area track foundation concrete and exposed T-beam outer formwork embedded parts, laid on the heavy-duty area track foundation and light Lime-soil cushion under the track foundation in the loading area. It can complete the steel bar binding, formwork installation and other processes on the track foundation of the light load area, and complete the concrete pouring, form removal, tensioning, maintenance and other processes on the track foundation of the heavy load area. The track foundation of the heavy load area and the track foundation of the light load area are respectively Design, perform their own duties, simple structure, reasonable design, suitable for rapid prefabricated T-beams, strong structural integrity, small overall engineering volume and wide application range.
Description
技术领域technical field
本发明涉及一种桥梁预制生产设施,尤其涉及一种快速预制T型梁生产台座。The invention relates to a bridge prefabricated production facility, in particular to a rapid prefabricated T-beam production platform.
背景技术Background technique
普速铁路和重载铁路桥梁将规模采用自重轻、体积小、造价低、便于运输和架设的T型简支梁,从技术、运输、工期和造价等角度考虑,“现场制梁场场内制造、线上轮轨运梁车为主线下轮胎运梁车为辅运梁、边铺边架与先架后铺相结合架梁”是铁路T型梁建造主要模式。Normal-speed railway and heavy-duty railway bridges will adopt T-shaped simply supported beams with light weight, small size, low cost, and easy transportation and erection. From the perspectives of technology, transportation, construction period and cost, etc. Manufacturing, on-line wheel-rail beam transport vehicles as the main line, offline tire beam transport vehicles as auxiliary beam transport, side-laying and side-frame beam erection combined with first erection and then laying" are the main modes of railway T-beam construction.
随着铁路建设的发展规范和相关政策法规的日臻完善,T型梁预制场标准化、规范化、精细化规划与设计,进一步提高土地利用率和降低土建投资,实现预制场的标准化建场和工厂化、机械化、信息化、专业化生产,是建设、设计和施工单位共同关注的问题。T型梁生产台座是制梁区内为T型梁生产提供平台的混凝土结构物,在预制场土建结构中制梁台座的使用率最高,T型梁预制场建造的核心之一是T型梁预制台座的布置和设计。With the development of railway construction norms and the improvement of relevant policies and regulations, the standardization, standardization, and refined planning and design of T-beam prefabrication yards will further improve land utilization and reduce civil investment, and realize the standardized construction and industrialization of prefabrication yards. , mechanization, informatization, and specialized production are issues of common concern to construction, design, and construction units. T-beam production pedestal is a concrete structure that provides a platform for T-beam production in the beam area. The beam-making pedestal has the highest utilization rate in the civil structure of the precast yard. One of the cores of T-beam precast yard construction is T-beam Layout and design of prefabricated pedestals.
现有技术中,工厂制梁和现场制梁一直采用固定式T型梁生产台座生产,即在同一T型梁生产台座上完成钢筋绑扎、模板安装、混凝土浇筑、拆模、张拉到移出台座等所有工序,在环境、工效、工费、工时上存在较多问题。In the prior art, factory-made beams and on-site beams have been produced with fixed T-beam production pedestals, that is, steel bar binding, formwork installation, concrete pouring, formwork removal, tensioning, and removal of pedestals are completed on the same T-shaped beam production pedestal. There are many problems in the environment, work efficiency, labor cost and working hours in all processes.
发明内容Contents of the invention
本发明的目的是提供一种结构简单合理、钢筋混凝土和其他材料用量小、易于施工且施工周期短、整体结构刚度满足规范要求的快速预制T型梁生产台座。The purpose of the present invention is to provide a rapid prefabricated T-beam production platform with simple and reasonable structure, small amount of reinforced concrete and other materials, easy construction, short construction period, and overall structural rigidity meeting the specification requirements.
本发明是通过以下技术方案实现的:The present invention is achieved through the following technical solutions:
本发明的快速预制T型梁生产台座,包括重载区轨道基础、轻载区轨道基础;The rapid prefabricated T-beam production base of the present invention includes a track foundation in a heavy-load area and a track foundation in a light-load area;
所述重载区轨道基础的上平面为长方形,其长大于或等于预制T型梁的长度,其宽大于预制T型梁的顶板宽度;The upper plane of the track foundation in the heavy-duty area is rectangular, its length is greater than or equal to the length of the prefabricated T-beam, and its width is greater than the width of the top plate of the prefabricated T-beam;
所述轻载区轨道基础位于所述重载区轨道基础的纵向长度方向的顶端,其上平面为长方形,其长大于或等于预制T型梁的长度;The track foundation of the light-load area is located at the top of the longitudinal direction of the track foundation of the heavy-load area, and its upper plane is rectangular, and its length is greater than or equal to the length of the prefabricated T-beam;
所述重载区轨道基础和所述轻载区轨道基础分别设有两排钢轨联结预埋件,所述钢轨联结预埋件上安装有钢轨,所述重载区轨道基础上的钢轨与所述轻载区轨道基础上的钢轨连续对接;The track foundation in the heavy-load area and the track foundation in the light-load area are respectively provided with two rows of rail connecting embedded parts, and rails are installed on the rail connecting embedded parts, and the rails on the track foundation in the heavy-load area are connected to the rails in the heavy-load area. The continuous butt joint of rails on the track foundation in the light load area;
所述重载区轨道基础上设有T型梁外侧模预埋件,所述T型梁外侧模预埋件设于两排钢轨联结预埋件的外侧;The track foundation in the heavy-duty area is provided with a T-beam outer mold embedded part, and the T-shaped beam outer mold embedded part is arranged on the outside of the two rows of rail connecting embedded parts;
所述重载区轨道基础和轻载区轨道基础下铺设有灰土垫层。A lime-soil cushion is laid under the track foundation of the heavy-load area and the track foundation of the light-load area.
由上述本发明提供的技术方案可以看出,本发明所述的快速预制T型梁生产台座,由于设置了重载区轨道基础和轻载区轨道基础,并通过钢轨予以连接,可以在轻载区轨道基础上完成钢筋绑扎、模板安装等工序,在重载区轨道基础上完成混凝土浇筑、拆模、张拉、养护等工序,重载区轨道基础和轻载区轨道基础各司其职,互不冲突,充分利用场地和提高工效,形成自动化快速预制T型梁;区分了重载区轨道基础和轻载区轨道基础,可以分别按重载荷载和轻载荷载控制轨道基础的结构设计,并根据计算结果采用不同的基础截面形式和地基处理形式,保证结构强度、刚度和控制不均匀沉降同时可充分减少钢筋混凝土用量;钢轨置于重载区轨道基础和轻载区轨道基础的钢轨联结预埋件之上,可重复周转利用钢轨,提高经济性。设计合理、结构简单、安全可靠、适应性强,可实现自动化快速预制T型梁。It can be seen from the above-mentioned technical scheme provided by the present invention that the rapid prefabricated T-beam production pedestal of the present invention can be used under light load due to the arrangement of the track foundation in the heavy-load area and the track foundation in the light-load area, which are connected by rails. On the basis of the track in the heavy-load area, complete the processes of steel bar binding and formwork installation, and on the basis of the track in the heavy-load area, complete the procedures of concrete pouring, form removal, tensioning, and maintenance. The track foundation in the heavy-load area and the track foundation in the light-load area perform their respective duties It does not conflict with each other, makes full use of the site and improves work efficiency, and forms an automatic and rapid prefabricated T-beam; distinguishes the track foundation in the heavy-load area and the track foundation in the light-load area, and can control the structural design of the track foundation according to the heavy load and light load respectively. And according to the calculation results, different foundation section forms and foundation treatment forms are adopted to ensure the structural strength, rigidity and control uneven settlement while fully reducing the amount of reinforced concrete; the rails are placed in the rail connection of the track foundation in the heavy-load area and the track foundation in the light-load area On top of the embedded parts, the rails can be reused to improve economy. The design is reasonable, the structure is simple, safe and reliable, and the adaptability is strong, which can realize automatic and rapid prefabrication of T-beams.
附图说明Description of drawings
图1为本发明快速预制T型梁生产台座的具体实施例的平面布置示意图;Fig. 1 is the plane layout schematic diagram of the specific embodiment of fast prefabricated T-beam production pedestal of the present invention;
图2为本发明的具体实施例中重载区轨道基础平面结构示意图;Fig. 2 is a schematic diagram of the plane structure of the heavy-duty zone track foundation in a specific embodiment of the present invention;
图3为本发明的具体实施例中重载区轨道基础立面结构示意图;Fig. 3 is a schematic diagram of the facade structure of the track foundation in the heavy-duty area in a specific embodiment of the present invention;
图4为本发明的具体实施例中重载区轨道基础A-A断面结构示意图;Fig. 4 is a schematic diagram of the A-A cross-sectional structure of the track foundation in the heavy-duty area in a specific embodiment of the present invention;
图5为本发明的具体实施例中轻载区轨道基础平面结构示意图;Fig. 5 is a schematic diagram of the plane structure of the track foundation in the light load area in a specific embodiment of the present invention;
图6为本发明的具体实施例中轻载区轨道基础立面结构示意图;Fig. 6 is a schematic diagram of the facade structure of the track foundation in the light load area in a specific embodiment of the present invention;
图7为本发明的具体实施例中轻载区轨道基础B-B断面结构示意图。Fig. 7 is a schematic diagram of the B-B cross-sectional structure of the track foundation in the light load area in a specific embodiment of the present invention.
附图标记说明:Explanation of reference signs:
1-重载区轨道基础;2-轻载区轨道基础;3-钢轨联结预埋件;4-钢轨;5-T型梁外侧模预埋件;6-灰土垫层;7-弯钩钢筋;8-钢板;9-扣轨板。1-track foundation in heavy-duty area; 2-track foundation in light-load area; 3-rail connection embedded parts; 4-rail; 5-T-beam outer mold embedded parts; 6-lime soil cushion; ; 8-steel plate; 9-buckle rail plate.
具体实施方式Detailed ways
本发明的快速预制T型梁生产台座,其较佳的具体实施方式如图1~图7所示:The preferred specific implementation of the rapid prefabricated T-beam production pedestal of the present invention is shown in Figures 1 to 7:
包括重载区轨道基础1、轻载区轨道基础2;Including
所述重载区轨道基础1的上平面为长方形,其长大于或等于预制T型梁的长度,其宽大于预制T型梁的顶板宽度;The upper plane of the
所述轻载区轨道基础2位于所述重载区轨道基础1的纵向长度方向的顶端,其上平面为长方形,其长大于或等于预制T型梁的长度;The
所述重载区轨道基础1和所述轻载区轨道基础2分别设有两排钢轨联结预埋件3,所述钢轨联结预埋件3上安装有钢轨4,所述重载区轨道基础1上的钢轨与所述轻载区轨道基础2上的钢轨4连续对接;The
所述重载区轨道基础1上设有T型梁外侧模预埋件5,所述T型梁外侧模预埋件5设于两排钢轨联结预埋件3的外侧;The
所述重载区轨道基础1和轻载区轨道基础2下铺设有灰土垫层6。A lime-soil cushion 6 is laid under the
所述重载区轨道基础1和轻载区轨道基础2分别为钢筋混凝土结构,所述重载区轨道基础1和轻载区轨道基础2通过钢轨4连接为一个整体。The
所述重载区轨道基础1为整体式钢筋混凝土结构,顶面高出周边地面。The
所述轻载区轨道基础2为两道互相平行的钢筋混凝土结构,顶面与重载区轨道基础1顶面相平。The
所述钢轨联结预埋件3包括钢板8,所述钢板8的下表面焊接有弯钩钢筋7,所述钢板8的上表面安装有扣轨板9。The rail connection embedded part 3 includes a
所述钢轨4通过扣轨板9与所述钢轨联结预埋件3联结。The rail 4 is connected to the rail connection embedded part 3 through a
所述T型梁外侧模预埋件包括钢板8,所述钢板8的下表面焊接有弯钩钢筋7。The embedded part of the T-beam outer formwork includes a
下面对本发明的设计原理进行论述:The design principle of the present invention is discussed below:
重载区轨道基础分为三种可能最不利工况:T型梁浇筑完毕尚未张拉为第一工况,初张拉完毕移梁之前为第二工况,重载张拉后纵向滑动移梁为第三工况;第一工况荷载基本均布于重载区轨道基础上,第二工况荷载较集中于重载区轨道基础两端,第三工况应考虑重载移动荷载在钢轨上重载走行;应分别对三种工况下制梁台座建立模型以进行构件内力和地基反力计算,并取最不利工况控制计算和设计。The track foundation in the heavy-load area is divided into three possible most unfavorable working conditions: the first working condition after the T-beam is poured and not stretched; The beam is the third working condition; the load of the first working condition is basically evenly distributed on the track foundation in the heavy-duty area, the load of the second working condition is more concentrated on both ends of the track foundation in the heavy-loading zone, and the third working condition should consider the heavy-duty moving load at Heavy load running on the rails; models should be established for the beam-making pedestal under the three working conditions to calculate the internal force of the member and the reaction force of the foundation, and the most unfavorable working condition is used to control the calculation and design.
轻载区轨道基础分为两种可能最不利工况:T型梁钢筋模板安装完毕静置与轻载区轨道基础为第一工况,T型梁钢筋模板安装完毕后纵向滑动为第二工况;第一工况荷载基本均布于轻载区轨道基础上,第二工况应考虑轻载移动荷载在钢轨上轻载走行;应分别对两种工况下制梁台座建立模型以进行构件内力和地基反力计算,并取最不利工况控制计算和设计。The track foundation in the light-load area is divided into two possible most unfavorable working conditions: the T-beam steel formwork is installed and the track foundation is static and the light-load area is the first working condition, and the T-beam steel formwork is installed. After the longitudinal sliding is the second working condition In the first working condition, the load is basically evenly distributed on the track foundation in the light-loaded area, and in the second working condition, light-load moving loads should be considered to run lightly on the rail; models should be established for the beam-making pedestal under the two working conditions respectively. Calculation of component internal force and foundation reaction force, and take the most unfavorable working condition to control calculation and design.
在具体的结构设计和计算中,需要实现自动化快速作业,设置了重载区轨道基础和轻载区轨道基础,并通过钢轨予以连接,在轻载区轨道基础上完成钢筋绑扎、模板安装等工序,在重载区轨道基础上完成混凝土浇筑、拆模、张拉、养护等工序,重载区轨道基础和轻载区轨道基础各司其职,互不冲突;考虑重载区和轻载区轨道基础荷载的不同,分别按重载荷载和轻载荷载控制轨道基础的结构设计,并根据计算结果采用不同的基础截面形式和地基处理形式;在构造上,考虑重复周转利用钢轨,将钢轨置于重载区轨道基础和轻载区轨道基础联结预埋钢板之上,采用扣轨板进行拆装。In the specific structural design and calculation, it is necessary to realize automatic and fast operation. The track foundation in the heavy-load area and the track foundation in the light-load area are set up and connected by steel rails. The steps of steel bar binding and formwork installation are completed on the track foundation in the light-load area. , Concrete pouring, form removal, tensioning, maintenance and other processes are completed on the track foundation in the heavy-load area. The track foundation in the heavy-load area and the track foundation in the light-load area perform their duties without conflicting with each other; Depending on the load of the track foundation, the structural design of the track foundation is controlled according to the heavy load and light load respectively, and different foundation section forms and foundation treatment forms are adopted according to the calculation results; On the heavy-duty area track foundation and the light-load area track foundation joint embedded steel plate, the buckle rail plate is used for disassembly and assembly.
在具体实例中,制梁区地基为卵碎石,承载力300kPa,故对重载区轨道基础和轻载区轨道基础下地基进行了夯实处理,夯实深度80cm,密实度94%,地基承载力320kPa,其上铺设20cm三七灰土垫层并夯实,承载力300kPa,地基处理满足重载区轨道基础三种工况下和轻载区轨道基础两种工况下轨道基础对地基的承载力和沉降要求。重载区轨道基础为整体式钢筋混凝土结构,平面尺寸为34m×2.25m,厚度为400mm。轨道基础内的钢轨联结预埋件布置间距为500mm,其上安装扣轨板与钢轨联结。重载区轨道基础长度方向上间断布置两道T型梁外侧模预埋件,预埋件由厚度12mm钢板和Φ12mm螺纹钢筋焊接而成。轻载区轨道基础为两道分离式钢筋混凝土结构,单道平面尺寸为34m×0.5m,厚度为300mm。轨道基础上的钢轨及其联结预埋件与重载区轨道基础相同。In the specific example, the foundation of the beam-making area is pebble gravel, with a bearing capacity of 300kPa. Therefore, the track foundation in the heavy-load area and the foundation under the track foundation in the light-load area have been tamped. The tamping depth is 80cm, the density is 94%, and the bearing capacity of the foundation 320kPa, on which a 20cm notoginseng lime soil cushion is laid and compacted, with a bearing capacity of 300kPa. The foundation treatment meets the bearing capacity and Settlement requirements. The track foundation in the heavy-duty area is an integral reinforced concrete structure with a plane size of 34m×2.25m and a thickness of 400mm. The rail connection embedded parts in the track foundation are arranged at a spacing of 500mm, and the buckle rail plate is installed on it to connect with the rail. In the length direction of the track foundation in the heavy-duty area, two T-beam outer mold embedded parts are intermittently arranged. The embedded parts are welded by 12mm thick steel plate and Φ12mm threaded steel bar. The track foundation in the light load area is two separated reinforced concrete structures, the plane size of a single track is 34m×0.5m, and the thickness is 300mm. The rails and their joint embedded parts on the track foundation are the same as the track foundation in the heavy-duty area.
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到的变化或替换,都应涵盖在本发明的保护范围之内。The above is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any person skilled in the art within the technical scope disclosed in the present invention can easily think of changes or Replacement should be covered within the protection scope of the present invention.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201110337792 CN102407567B (en) | 2011-10-31 | 2011-10-31 | Production pedestal for quickly prefabricating T-shaped beam |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 201110337792 CN102407567B (en) | 2011-10-31 | 2011-10-31 | Production pedestal for quickly prefabricating T-shaped beam |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102407567A CN102407567A (en) | 2012-04-11 |
| CN102407567B true CN102407567B (en) | 2013-10-09 |
Family
ID=45910070
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN 201110337792 Expired - Fee Related CN102407567B (en) | 2011-10-31 | 2011-10-31 | Production pedestal for quickly prefabricating T-shaped beam |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102407567B (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103128851B (en) * | 2013-03-06 | 2015-03-25 | 中铁二十五局集团建筑安装工程有限公司 | Manufacturing method of nonstandard T-shaped beam suitable for different spans |
| CN104047229A (en) * | 2014-06-09 | 2014-09-17 | 葛洲坝集团项目管理有限公司 | Method for prefabricating T-beam on girder |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101649603A (en) * | 2008-08-15 | 2010-02-17 | 龙建路桥股份有限公司 | 50-meter T-shaped beam prefabricated assembling process |
| CN201762661U (en) * | 2010-08-12 | 2011-03-16 | 中铁二十二局集团第一工程有限公司 | Entablement |
| CN202293022U (en) * | 2011-10-31 | 2012-07-04 | 中铁第五勘察设计院集团有限公司 | Rapid prefabricating T-beam production table seat |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| KR101196472B1 (en) * | 2009-04-20 | 2012-11-01 | 경희대학교 산학협력단 | Steel-Concrete composite Crossbeam having T-shaped beam and construction methods using the same |
-
2011
- 2011-10-31 CN CN 201110337792 patent/CN102407567B/en not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101649603A (en) * | 2008-08-15 | 2010-02-17 | 龙建路桥股份有限公司 | 50-meter T-shaped beam prefabricated assembling process |
| CN201762661U (en) * | 2010-08-12 | 2011-03-16 | 中铁二十二局集团第一工程有限公司 | Entablement |
| CN202293022U (en) * | 2011-10-31 | 2012-07-04 | 中铁第五勘察设计院集团有限公司 | Rapid prefabricating T-beam production table seat |
Non-Patent Citations (4)
| Title |
|---|
| 50m预应力砼T型梁的预制与安装;胡孝民等;《山西建筑》;20010228;第27卷(第1期);第88-89页 * |
| 浅谈T型梁预制施工工艺;蔡丽萍;《甘肃科技》;20081130;第24卷(第21期);第200-201页 * |
| 胡孝民等.50m预应力砼T型梁的预制与安装.《山西建筑》.2001,第27卷(第1期),第88-89页. |
| 蔡丽萍.浅谈T型梁预制施工工艺.《甘肃科技》.2008,第24卷(第21期),第200-201页. |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102407567A (en) | 2012-04-11 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| JP2022023107A (en) | System and method for construction of compound U-shaped reinforcing girder bridge deck | |
| CN103469733B (en) | A kind of from falling molding box joist steel Guan Beilei door opening support and bearing method thereof | |
| CN104097253B (en) | Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system | |
| CN206245139U (en) | precast slab ballast bed | |
| CN102261145A (en) | Integrally two-way and locally one-way steel-concrete slab composite floor system and construction method thereof | |
| CN204356595U (en) | Medium-and low-speed maglev railway is low puts circuit continuous arch support rail girder construction | |
| CN207172364U (en) | Precast beam pedestal | |
| CN106498814A (en) | A kind of construction equipment of city track traffic U type beam solid concrete roabed and method | |
| CN106976157A (en) | A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape | |
| CN102587282B (en) | Large-section simply-supported box girder precasting and assembly process under conditions of strong wind and high altitude | |
| CN110409318A (en) | A kind of large span freely-supported steel reinforced concrete bondbeam assembling method | |
| CN204109135U (en) | Cross-saddle single-track traffic environment protection movable formula pre-track beam forms system | |
| CN107386246A (en) | A kind of lock chamber wall Construction Through Form on Traveler method | |
| CN105696453B (en) | A kind of steel-concrete combination beam | |
| CN205474612U (en) | Prefabricated track board of H type for urban rail transit | |
| CN102407567B (en) | Production pedestal for quickly prefabricating T-shaped beam | |
| CN108222051A (en) | A kind of contact net upright post basic of railway steel reinforced concrete bondbeam and steel reinforced concrete combination bridge | |
| CN104652661A (en) | Semirigid frame-external recycled concrete wall panel and fabrication method | |
| CN203603073U (en) | Reinforced concrete lattice type composite platform beam of elevated station | |
| CN112211085A (en) | Concrete floor slab walking trestle device for large crawler crane and mounting method thereof | |
| CN206571049U (en) | Precast block formula secondary prestress Wavelike steel webplate combination beam | |
| CN207027858U (en) | A kind of post stretching precast beam pedestal for being applicable different length and cross sectional shape | |
| CN104612063A (en) | Concrete box beam first-aid repair method with prefabricated part on-site assembling combination beam | |
| CN203878460U (en) | Prefabricated assembly combined type portal pier | |
| CN202323721U (en) | Precast pedestal for lattice type box girder |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20131009 |