CN102383611A - 一种钢结构梁穿柱的施工方法 - Google Patents
一种钢结构梁穿柱的施工方法 Download PDFInfo
- Publication number
- CN102383611A CN102383611A CN2011102688741A CN201110268874A CN102383611A CN 102383611 A CN102383611 A CN 102383611A CN 2011102688741 A CN2011102688741 A CN 2011102688741A CN 201110268874 A CN201110268874 A CN 201110268874A CN 102383611 A CN102383611 A CN 102383611A
- Authority
- CN
- China
- Prior art keywords
- prick post
- post node
- node
- prick
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 35
- 239000010959 steel Substances 0.000 title claims abstract description 35
- 238000010276 construction Methods 0.000 title claims abstract description 17
- 230000000149 penetrating effect Effects 0.000 title abstract 4
- 238000003466 welding Methods 0.000 claims description 8
- 210000001503 joint Anatomy 0.000 claims description 7
- 238000001816 cooling Methods 0.000 claims description 6
- 238000000034 method Methods 0.000 claims description 3
- 230000011218 segmentation Effects 0.000 claims description 3
- 238000005516 engineering process Methods 0.000 abstract description 4
- 238000004519 manufacturing process Methods 0.000 description 4
- 230000002787 reinforcement Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 235000019628 coolness Nutrition 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000008521 reorganization Effects 0.000 description 1
- 239000003351 stiffener Substances 0.000 description 1
Images
Abstract
本发明公开了一种既有钢结构穿越新增结构的施工方法,在不拆除既有结构的情况下,根据实测数据,定制梁穿柱构件,按照一定的施工顺序和工艺,装配既有结构和新增结构,同时在关键位置设置加劲板,使得梁穿柱构件能有效传力。该施工技术无需截断既有结构,对于承重结构而言,具有很大的应用前景。
Description
技术领域
本发明涉及钢结构工程扩建领域,尤其涉及一种适用于既有钢梁穿越新立钢柱的施工方法。
背景技术
钢结构工程,特别是工业厂房,由于改变或者增加生产工艺,既有建筑不能满足更多的要求,常常需要在既有工程基础上扩建项目。一般而言,既有生产线往往不能停产,这意味着在原有结构承受荷载的基础上进行改扩建施工。
由于改变、新增生产工艺,结构计算图形可能会发生改变,扩建部分和既有结构互相交错,扩建部分和既有结构的连接主要三种,一是在既有结构基础上新增结构;二是新增结构穿越既有结构;三是既有结构穿越新增结构。第一种做法适用于新老结构连接处,已被广泛采纳应用;第二种做法需要拆除或者截断既有结构,这对于承受设备的构件,显然是难以实施的。因此开拓既有结构穿越新增结构的施工方法具有很大的现实意义。
发明内容
本发明的目的在于针对现有技术的不足,提供一种钢结构梁穿柱的施工方法。
本发明的目的是通过以下技术方案来实现的:一种钢结构梁穿柱的加固方法,该方法包括以下步骤:
(1)节点以下施工:在梁穿柱节点以下安装钢柱;
(2)梁穿柱节点施工:吊装梁穿柱节点配件,并安装连接用耳板,通过引弧板和衬板对接焊接钢柱之间的腹板和翼缘。等焊缝冷却之后,拆除安装连接用耳板,对接焊接梁穿柱构件柱腹板,再分段焊接新柱腹板和老梁腹板,最后焊接或用角钢连接新柱腹板和老梁翼缘。
(3)节点以上施工:梁穿柱构件焊缝冷却之后,吊装上部钢柱,对接焊接钢柱和梁穿柱构件,逐次完成施工。
本发明的有益效果是,本发明对承受设备的钢梁提供新的扩建方法,使得原有钢梁无需拆除或截断,新增钢柱根据既有钢梁设置孔洞,并合理布置节点加强构件。扩建后结构能承受新增荷载作用,是一种可以广泛应用于钢结构扩建的施工方法,具有广阔的应用前景。
附图说明
图1为本发明梁穿柱的示意图;
图2为图1的A-A剖视图;
图3为图1的B-B剖视图;
图中,耳板1、引弧板2、衬板3、梁穿柱节点构件4、下部钢柱5、上部钢柱6。
具体实施方式
如图1-3所示,本发明钢结构柱的加固方法,包括以下步骤:
1、节点以下施工。
在梁穿柱节点下面安装下部钢柱5。
2、梁穿柱节点施工。
在梁穿柱节点两边吊装两块梁穿柱节点构件4,两块梁穿柱节点构件4之间以及梁穿柱节点构件4与下部钢柱5之间之间均通过耳板1拼接,再通过引弧板2和衬板3对接焊接梁穿柱节点构件4和下部钢柱5之间的腹板和翼缘;等焊缝冷却之后,拆除耳板1,对接焊接两块梁穿柱节点构件4柱腹板,再分段焊接梁穿柱节点构件4的新柱腹板和梁穿柱节点的老梁腹板,最后焊接或用角钢连接梁穿柱节点构件4的新柱腹板和梁穿柱节点的老梁翼缘。
3、节点以上施工。
梁穿柱节点构件4焊缝冷却之后,吊装上部钢柱5,梁穿柱节点构件4与上部钢柱6之间之间通过耳板1拼接,再对接焊接上部钢柱5和梁穿柱节点构件4,逐次完成施工。
Claims (1)
1.一种钢结构梁穿柱的施工方法,其特征在于,该方法包括以下步骤:
(1)节点以下施工:在梁穿柱节点下面安装下部钢柱(5);
(2)梁穿柱节点施工:在梁穿柱节点两边吊装两块梁穿柱节点构件(4),两块梁穿柱节点构件(4)之间以及梁穿柱节点构件(4)与下部钢柱(5)之间之间均通过耳板(1)拼接,再通过引弧板(2)和衬板(3)对接焊接梁穿柱节点构件(4)和下部钢柱(5)之间的腹板和翼缘;等焊缝冷却之后,拆除耳板(1),对接焊接两块梁穿柱节点构件(4)柱腹板,再分段焊接梁穿柱节点构件(4)的新柱腹板和梁穿柱节点的老梁腹板,最后焊接或用角钢连接梁穿柱节点构件(4)的新柱腹板和梁穿柱节点的老梁翼缘;
(3)节点以上施工:梁穿柱节点构件(4)焊缝冷却之后,吊装上部钢柱(5),梁穿柱节点构件(4)与上部钢柱(6)之间之间通过耳板(1)拼接,再对接焊接上部钢柱(5)和梁穿柱节点构件(4),逐次完成施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102688741A CN102383611B (zh) | 2012-01-11 | 2012-01-11 | 一种钢结构梁穿柱的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011102688741A CN102383611B (zh) | 2012-01-11 | 2012-01-11 | 一种钢结构梁穿柱的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102383611A true CN102383611A (zh) | 2012-03-21 |
CN102383611B CN102383611B (zh) | 2013-11-13 |
Family
ID=45823411
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011102688741A Expired - Fee Related CN102383611B (zh) | 2012-01-11 | 2012-01-11 | 一种钢结构梁穿柱的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102383611B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561522A (zh) * | 2012-04-09 | 2012-07-11 | 浙江大学 | 一种钢结构新老结构的连接方法 |
CN103806672A (zh) * | 2014-01-21 | 2014-05-21 | 浙江天地环保工程有限公司 | 一种既有梁与缀条式格构钢柱相碰节点的补强方法 |
CN110530218A (zh) * | 2018-05-24 | 2019-12-03 | 中钢集团武汉安全环保研究院有限公司 | 一种免打孔爆破拆除角钢的方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09277041A (ja) * | 1996-12-20 | 1997-10-28 | Kenichi Nakano | H型鋼軸の溶接法 |
CN1804254A (zh) * | 2006-01-11 | 2006-07-19 | 贵阳铝镁设计研究院 | 高层铰接钢框架梁柱连接节点构造及连接方法 |
CN1807785A (zh) * | 2006-01-11 | 2006-07-26 | 贵阳铝镁设计研究院 | 铰接钢框架h型支撑构件与梁柱的节点连接方法及构造 |
CN101555706A (zh) * | 2009-05-18 | 2009-10-14 | 长安大学 | H形梁与h形柱弱轴连接节点及连接方法 |
-
2012
- 2012-01-11 CN CN2011102688741A patent/CN102383611B/zh not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09277041A (ja) * | 1996-12-20 | 1997-10-28 | Kenichi Nakano | H型鋼軸の溶接法 |
CN1804254A (zh) * | 2006-01-11 | 2006-07-19 | 贵阳铝镁设计研究院 | 高层铰接钢框架梁柱连接节点构造及连接方法 |
CN1807785A (zh) * | 2006-01-11 | 2006-07-26 | 贵阳铝镁设计研究院 | 铰接钢框架h型支撑构件与梁柱的节点连接方法及构造 |
CN101555706A (zh) * | 2009-05-18 | 2009-10-14 | 长安大学 | H形梁与h形柱弱轴连接节点及连接方法 |
Non-Patent Citations (1)
Title |
---|
龚顺风等: "加固钢柱的非线性屈曲性能研究", 《钢结构》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561522A (zh) * | 2012-04-09 | 2012-07-11 | 浙江大学 | 一种钢结构新老结构的连接方法 |
CN102561522B (zh) * | 2012-04-09 | 2014-02-19 | 浙江大学 | 一种钢结构新老结构的连接方法 |
CN103806672A (zh) * | 2014-01-21 | 2014-05-21 | 浙江天地环保工程有限公司 | 一种既有梁与缀条式格构钢柱相碰节点的补强方法 |
CN110530218A (zh) * | 2018-05-24 | 2019-12-03 | 中钢集团武汉安全环保研究院有限公司 | 一种免打孔爆破拆除角钢的方法 |
CN110530218B (zh) * | 2018-05-24 | 2021-09-07 | 中钢集团武汉安全环保研究院有限公司 | 一种免打孔爆破拆除角钢的方法 |
Also Published As
Publication number | Publication date |
---|---|
CN102383611B (zh) | 2013-11-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102733492B (zh) | H型钢梁与h型钢柱弱轴可变梁高装配式节点及施工方法 | |
CN103015536B (zh) | 一种多高层装配式钢结构体系的梁柱节点连接装置 | |
CN104100007A (zh) | 双耳板式方管柱与h型钢架可变梁高装配节点及施工方法 | |
CN102733489B (zh) | H型钢梁与h型钢柱强轴可变梁高装配式节点及施工方法 | |
CN202644735U (zh) | 一种钢结构梁柱装配式刚性节点 | |
CN102936924A (zh) | 一种钢梁嵌入式带肋贯穿隔板方钢管混凝土柱-h型钢梁组合节点 | |
CN203808248U (zh) | 新型方钢管柱-h型钢梁拼接外套筒式连接节点 | |
CN214696138U (zh) | 一种装配式骨形抗震节点 | |
CN103015537A (zh) | 一种装配式钢结构体系的梁柱节点连接装置 | |
CN204174787U (zh) | 预制混凝土外墙与钢结构的连接结构 | |
CN105625585A (zh) | 屈曲约束钢结构梁柱连接节点和钢结构建筑 | |
CN205444492U (zh) | 一种h型悬臂钢梁柱几何截面拼接结构 | |
CN103835374A (zh) | 新型方钢管柱-h型钢梁拼接外套筒式连接方法 | |
CN105464221A (zh) | 用于矩形钢管混凝土柱与箱型钢梁连接的隔板贯通节点 | |
CN107338873B (zh) | 单边屈曲约束式钢梁柱连接节点和钢结构建筑 | |
CN104652617A (zh) | 一种多高层装配式钢结构体系的梁柱节点连接装置 | |
CN102383611A (zh) | 一种钢结构梁穿柱的施工方法 | |
CN205024832U (zh) | 一种与十字柱非正交的连接节点 | |
CN203361167U (zh) | 一种基坑围护用围檩转角构件 | |
CN105220767A (zh) | 一种与十字柱非正交的连接节点及施工方法 | |
CN203603022U (zh) | 铁路钢桁梁对接式节点 | |
CN109736430A (zh) | 一种适用于h型钢弱轴连接双槽钢加强型装配式节点 | |
CN202706211U (zh) | H型钢梁与h型钢柱弱轴可变梁高装配式节点 | |
CN104863266A (zh) | 箱形柱-工形梁预制装配式高延性梁柱节点 | |
CN205557838U (zh) | 装配式抗震蜂窝钢梁-剪力墙连接结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20131113 |
|
CF01 | Termination of patent right due to non-payment of annual fee |