CN102274857B - Method for adjusting dynamic balance of high-speed wire spinning machine - Google Patents
Method for adjusting dynamic balance of high-speed wire spinning machine Download PDFInfo
- Publication number
- CN102274857B CN102274857B CN2011101953909A CN201110195390A CN102274857B CN 102274857 B CN102274857 B CN 102274857B CN 2011101953909 A CN2011101953909 A CN 2011101953909A CN 201110195390 A CN201110195390 A CN 201110195390A CN 102274857 B CN102274857 B CN 102274857B
- Authority
- CN
- China
- Prior art keywords
- spinneret
- pipe clamp
- dynamic balance
- counterweight
- standard pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Winding, Rewinding, Material Storage Devices (AREA)
- Spinning Methods And Devices For Manufacturing Artificial Fibers (AREA)
Abstract
The invention provides a method and a device for adjusting dynamic balance of a high-speed wire spinning machine. The method for adjusting dynamic balance comprises the following steps: A) confirming the mounting positions of standard spinning pipe blocks on a spinning pipe, acquiring reduced masses of all sections of wires at the mounting positions of the standard spinning pipe blocks according to the mass distribution of the wires in the spinning pipe under the steel spinning state of the spinning machine, and acquiring the to-be-added pre-balancing weights of all the standard spinning pipe blocks according to the reduced mass; B) manufacturing pre-balancing weight pipe blocks corresponding to the standard spinning pipe blocks according to the pre-balancing weights and correspondingly mounting the pre-balancing weight pipe blocks at the mounting positions; C) using an on-site dynamic balancing instrument to correct the dynamic balance of each spinning head balance weight plane till meeting the demand on dynamic balance correcting level; and D) taking off all the pre-balancing weight pipe blocks and mounting the standard spinning pipe blocks.
Description
Technical field
The present invention relates to technical field of steel rolling, belong to a kind of adjusting dynamic balance of high-speed wire spinning machine method.
Background technology
Laying head is the visual plant in the high-speed wire production line unit, and as shown in Figure 1, its primary structure is: motor is delivered to rotatablely moving on the hollow shaft of Laying head 1 by a pair of Helical Bevel Gear.The steel of finishing mill of high-speed wire rod mill roll forming are pinched by pinch roll, enter in the Laying head hollow shaft of High Rotation Speed, pass through spinneret 4 stress deformations again.Steel have become approximate static circle by the high-speed straight-line motion, are scattered on the air-cooled roller-way, become wire coiling, the wire rod that namely is commonly called as again after packing.
Making the parts of wire rod distortion lopping in the Laying head is laying head 2 and spinneret, spinneret 4 is provided with the spinneret standard pipe clamp 3 ' that a plurality of orders are arranged, standard pipe clamp 3 ' is used for fixedly spinneret 4, because spinneret 4 is the elongated tubular of arc, usually, standard pipe clamp 3 ' is distributed on the different curvature radius of spinneret 4.Extremely shown in Figure 4 such as Fig. 2, described spinneret standard pipe clamp 3 ' is U-shaped platy structure, described U-shaped platy structure comprises: be parallel to each other first dull and stereotyped 31 be connected flat board 32, connect link and the pin-and-hole 35 of the sealing of described first dull and stereotyped and the second flat board, described pin-and-hole 35 runs through described first dull and stereotyped the 31 and second flat board 32, the link of described sealing contains described spinneret 4, described spinneret is fixed in the link of described sealing by alignment pin 37 and the screw 33 that passes described pin-and-hole, and fixing by pipe clamp retainer ring 5.
Because laying head 2 be asymmetric cantilever design, complex contour, and the working speed angle is high, equipment centre of gyration line and Mass Distribution center line disalignment therefore very easily occur, and then the phenomenon of initiation Laying head high vibration when working.Vibration when uneven exciting can cause equipment operation increases, and causes the damage of equipment vital part, reduces Laying head service life, affects high-speed rod productivity ratio.Therefore Laying head all will use dynamic balance instrument that the Laying head complete machine is carried out dynamic balance calibration before dispatching from the factory.
Unbalance dynamic when solving equipment operation, the Laying head complete machine after each Laying head manufacturer mainly adopts spot dynamic balance instrument to assembling at present carries out dynamic balance calibration, the method that adopts such as patent CN101642777A.Do not carry out the condition that dynamic balancing is adjusted because device fabrication producer does not all possess under as-rolled condition, the dynamic balancing of Laying head is all proofreaied and correct by each producer under Light Condition before Laying head dispatches from the factory at present.Bearing calibration is probably as follows: under the Light Condition, be when not having wire rod to pass in the spinneret, respectively to laying head weight plane 21 and laying head weight plane 22 usefulness rectify an instrument (spot dynamic balance instrument) proofread and correct, according to the result who proofreaies and correct, laying head 2 on laying head weight plane 21 and laying head weight plane 22, increases respectively counterweight, so that can be issued to balance in working order.
Because what Laying head adopted is the unloaded dynamic balance method of proofreading and correct, there is not wire rod to pass in the spinneret, the Mass Distribution of Laying head had different when wire rod passed spinneret under this and the duty, and unloaded weight of proofreading and correct balance can't consider that Laying head is in rolling real conditions when crossing steel.Therefore proofread and correct that the dynamic balance calibration under the duty requires certain distance on result and the high-speed wire production line.So it is good Laying head test run working order after zero load is proofreaied and correct to occur, and becomes large phenomenon but show vibration values when production line is worked.
The time that Laying head is told steel at production line accounts for more than 90% of its total run time, therefore the Laying head dynamic balancing adjustment of telling under the steel state is seemed particularly important.
Summary of the invention
The present invention aims to provide a kind of adjusting dynamic balance of high-speed wire spinning machine method, proofreaies and correct Laying head to solve prior art under Light Condition, and the dynamic balance calibration under correction result and the duty requires to have the problem of larger gap.
For this reason, the present invention proposes a kind of adjusting dynamic balance of high-speed wire spinning machine method, and described adjusting dynamic balance method may further comprise the steps:
A, determine that the spinneret standard pipe is stuck in the installation site on the spinneret, the Mass Distribution of wire rod in spinneret under the steel state told in work according to Laying head, obtain every section wire rod in the reduced mass of the described installed position of each spinneret standard pipe clamp, draw the pre-balance weight that each spinneret standard pipe calorie requirement increases according to each described reduced mass;
B, the pre-balance weight that increases according to each described spinneret standard pipe calorie requirement are made each pre-counterweight pipe clamp of corresponding each described spinneret standard pipe clamp, and each described pre-counterweight pipe clamp correspondence is installed in described installation site;
C, site of deployment dynamic balance instrument carry out dynamic balance calibration to each laying head weight plane, adjust the counterweight of each laying head weight plane according to correction numerical value, repeat the counterweight of described dynamic balance calibration and each laying head weight plane of described adjustment, until reach the dynamic balance calibration class requirement;
After D, dynamic balance calibration are finished each described pre-counterweight pipe clamp is taken off, be replaced by described spinneret standard pipe clamp.
Further, order is placed with 14 spinneret standard pipe clamps on the described spinneret, and the quantity of described pre-counterweight pipe clamp is 14 altogether.
Further, among the described step B, each described pre-counterweight pipe clamp correspondence is installed on the position of each described spinneret standard pipe clamp.
Further, described spinneret standard pipe clamp is U-shaped platy structure, described U-shaped platy structure comprises: first dull and stereotyped and the second flat board that is parallel to each other, the link and the pin-and-hole that connect the sealing of described the first flat board and the second flat board, described pin-and-hole runs through described first dull and stereotyped and the second flat board, the link of described sealing contains described spinneret, described spinneret is fixed in the link of described sealing by the alignment pin that passes described pin-and-hole, among the described step B, by on the lateral surface of described first dull and stereotyped and the second flat board of described spinneret standard pipe clamp respectively the pre-balancing weight of symmetrical increase obtain described pre-counterweight pipe clamp.
Further, among the described step B, the making of described pre-counterweight pipe clamp is for example as follows: make first the identical described spinneret standard pipe clamp of two covers, one cover is installed on the described spinneret, another set of be used to making described pre-counterweight pipe clamp, then on the lateral surface of described first dull and stereotyped and the second flat board of described another set of spinneret standard pipe clamp respectively the pre-balancing weight of symmetrical increase obtain described pre-counterweight pipe clamp.
Further, described steps A also comprises; Described spinneret standard pipe clamp is installed on the spinneret, and described step B also comprises: each described spinneret standard pipe clamp is pulled down, sequentially be replaced by described pre-counterweight pipe clamp according to correspondence.
The present invention also provides a kind of dynamic balance adjusting device for high-speed wire spinning machine, and described dynamic balance adjusting apparatus comprises: the pre-counterweight pipe clamp that the pre-balance weight that increases according to spinneret standard pipe calorie requirement is made.
Further, described pre-counterweight pipe clamp is U-shaped platy structure, described U-shaped platy structure comprises: be parallel to each other first dull and stereotyped and be connected flat board, connect link and the pin-and-hole of the sealing of described the first flat board and the second flat board, described pin-and-hole runs through described first dull and stereotyped and the second flat board, the link of described sealing contains described spinneret, described spinneret is fixed on by the alignment pin that passes described pin-and-hole in the link of described sealing, is symmetrically arranged with respectively pre-balancing weight on the lateral surface of described the first flat board and the second flat board.
Further, the number of described pre-counterweight pipe clamp is a plurality of, and correspondence is installed on the position of described spinneret standard pipe clamp.
The present invention has simulated the dynamic balancing adjustment under the normal as-rolled condition of Laying head, Laying head work being told the quality of wire rod under the steel state takes into account the impact of Laying head vibration, avoided the error that the dynamic balancing adjustment brings under the Light Condition, thereby dynamic balance accuracy of the present invention is high, vibration values is low, noise is little, high efficiency, with strong points.
Description of drawings
Fig. 1 is the structural representation of existing laying head;
Fig. 2 is the local structure for amplifying at C place among Fig. 1;
Fig. 3 is the cross-section structure of spinneret standard pipe clamp among Fig. 1;
Fig. 4 is the main TV structure of spinneret standard pipe clamp among Fig. 1;
Fig. 5 is according to the structure of the laying head of the embodiment of the invention;
Fig. 6 is the local structure for amplifying at D place among Fig. 5;
Fig. 7 is the cross-section structure of pre-counterweight pipe clamp among Fig. 5;
Fig. 8 is the main TV structure of pre-counterweight pipe clamp among Fig. 5.
The drawing reference numeral explanation:
1, Laying head 2, laying head 21, laying head weight plane 22, laying head weight plane
3 ', spinneret standard pipe clamp 3, pre-counterweight pipe clamp 31, the first flat board 32, the second flat board 33, screw
34, pre-balancing weight 35, pin-and-hole 37, alignment pin 4, spinneret 5, pipe clamp retainer ring
The specific embodiment
Understand for technical characterictic of the present invention, purpose and effect being had more clearly, now contrast description of drawings the specific embodiment of the present invention.
The present invention proposes a kind of adjusting dynamic balance of high-speed wire spinning machine method, and described adjusting dynamic balance method may further comprise the steps:
A, as shown in Figure 1, determine that the spinneret standard pipe is stuck in the installation site on the spinneret, then spinneret standard pipe clamp 3 ' can be installed on the spinneret 4, order is placed with a plurality of spinneret standard pipe clamps 3 ' on the described spinneret, the Mass Distribution of wire rod in spinneret 4 under the steel state told in work according to Laying head, obtain every section wire rod in the reduced mass at each spinneret standard pipe clamp place, draw the pre-balance weight that each spinneret standard pipe calorie requirement increases according to each described reduced mass; Thereby the quality of Laying head work being told wire rod under the steel state is taken into account the impact of Laying head vibration, when being equivalent to the spinneret vibration, every section wire rod is converted on each spinneret standard pipe clamp the impact of vibration, the dynamic mass of wire rod under the steel state or the pre-balance weight that the impulse force conversion increases for each spinneret standard pipe calorie requirement are told in Laying head work, the present invention the simulation dynamic operating condition under to Laying head dynamic balancing proofread and correct, the dynamic effects of Laying head work being told wire rod under the steel state is reflected in each spinneret standard pipe clamp qualitatively, quality with the spinneret standard pipe clamp that increases replaces the dynamic effects of wire rod, thereby more tells the steel state near Laying head work.
The determining and under the condition of actual installation spinneret standard pipe clamp not, to finish of reduced mass, can adopt the whole bag of tricks about the reduced mass of every section wire rod at each spinneret standard pipe clamp place, for example, to normal when rolling steel calculate in the quality of spinneret inside, the weight of pre-balancing weight can be concentrated conversion in the distributed mass at pipe clamp place according to wire rod, and adjusts according to the practical operation experience.The quality of general each pre-balancing weight is not wait between the 30-100 gram.
B, the pre-balance weight that increases according to each described spinneret standard pipe calorie requirement are made each pre-counterweight pipe clamp of corresponding each described spinneret standard pipe clamp, for example, obtain the pre-balance weight that first spinneret standard pipe calorie requirement increases, produce first counterweight pipe clamp according to this pre-balance weight; Obtain the pre-balance weight that second spinneret standard pipe calorie requirement increases, produce second counterweight pipe clamp according to this pre-balance weight, by that analogy, so that each described spinneret standard pipe clamp has corresponding pre-counterweight pipe clamp, the structure of each described spinneret standard pipe clamp can be identical, but the pre-balance weight that each described spinneret standard pipe calorie requirement increases might be different, the structural similarity of each pre-counterweight pipe clamp, but weight might be different.
After making each described pre-counterweight pipe clamp, each described pre-counterweight pipe clamp correspondence is installed in described installation site.If spinneret standard pipe clamp has been installed first, need each described spinneret standard pipe clamp is pulled down, sequentially be replaced by each described pre-counterweight pipe clamp according to correspondence, each described pre-counterweight pipe clamp correspondence is installed on the position of each described spinneret standard pipe clamp, as shown in Figure 5.Before and after changing, pre-counterweight pipe clamp is identical with spinneret standard pipe card position, and the installation site is fixing all the time, in order to avoid affect the dynamic balance calibration effect.
C, site of deployment dynamic balance instrument carry out dynamic balance calibration to each laying head weight plane 21 and 22, according to the counterweight of proofreading and correct numerical value and adjust each laying head weight plane, for example, weld counterweight piece etc. on laying head weight plane 21 and 22.Repeat the counterweight of described dynamic balance calibration and each laying head weight plane of described adjustment, until reach the dynamic balance calibration class requirement; Dynamic balance calibration is finished according to the G2.5 grade standard.Dynamic balancing adjustment equipment is spot dynamic balance instrument, adopts two-sided dynamic balance calibration to proofread and correct the method that combines with single-side dynamic balance, the amount of unbalance of equipment is adjusted within the standard allowable of G2.5 level requirement.
After D, dynamic balance calibration are finished each described pre-counterweight pipe clamp is taken off, be replaced by described spinneret standard pipe clamp, like this, during work, each laying head weight plane 21 and 22 has been provided with counterweight according to alignment requirements, and dynamic balance calibration has higher precision and stronger specific aim.
Further, order is placed with 14 spinneret standard pipe clamps on the described spinneret 4, and the quantity of described pre-counterweight pipe clamp is 14 altogether, respectively corresponding each spinneret standard pipe clamp.The spinneret standard pipe clamp of quantity like this is set, and reasonable stress can reduce vibrations on the one hand, increase fixing stablizing, on the other hand, because segmentation is more, be convenient to accurately obtain the pre-balance weight that each described spinneret standard pipe calorie requirement increases, the precision of dynamic balance calibration is provided.
Described spinneret standard pipe clamp is U-shaped platy structure, described U-shaped platy structure comprises: be parallel to each other first dull and stereotyped 31 be connected flat board 32, connect link and the pin-and-hole 35 of the sealing of described first dull and stereotyped and the second flat board, described pin-and-hole 35 runs through described first dull and stereotyped the 31 and second flat board 32, the link of described sealing contains described spinneret 4, described spinneret is fixed in the link of described sealing by alignment pin 37 and the screw 33 that passes described pin-and-hole, and fixing by pipe clamp retainer ring 5., among the described step B, increase pre-balancing weight 34 and obtain described pre-counterweight pipe clamp by symmetrical respectively on the lateral surface of described first dull and stereotyped the 31 and second flat board 32 of described spinneret standard pipe clamp to shown in Figure 8 such as Fig. 6.Like this, be convenient to make, be convenient to balance and reduce vibrations.
Further, among the described step B, being produced as follows of described pre-counterweight pipe clamp: make first the identical described spinneret standard pipe clamp of two covers, one cover is installed on the described spinneret, another set of be used to making described pre-counterweight pipe clamp, then on the lateral surface of described first dull and stereotyped and the second flat board of described another set of spinneret standard pipe clamp respectively the pre-balancing weight of symmetrical increase obtain described pre-counterweight pipe clamp, namely, with behind the upper pre-balancing weight of spinneret standard pipe clamp welding as an one-piece parts integral installation.
To shown in Figure 8, the present invention also provides a kind of dynamic balance adjusting device for high-speed wire spinning machine such as Fig. 5, and described dynamic balance adjusting apparatus comprises: the pre-counterweight pipe clamp 3 that the pre-balance weight that increases according to spinneret standard pipe calorie requirement is made.
Further, as shown in Figure 7 and Figure 8, described pre-counterweight pipe clamp 3 is U-shaped platy structure, described U-shaped platy structure comprises: first dull and stereotyped the 31 and second flat board 32 that is parallel to each other, the link and the pin-and-hole 35 that connect the sealing of described the first flat board and the second flat board, described pin-and-hole 35 runs through described first dull and stereotyped the 31 and second flat board 32, as shown in Figure 6, the link of described sealing contains described spinneret 4, described spinneret 4 is fixed in the link of described sealing by the alignment pin 32 that passes described pin-and-hole 35, is symmetrically arranged with respectively pre-balancing weight 34 on the lateral surface of described the first flat board and the second flat board.The number of described pre-counterweight pipe clamp 3 is a plurality of, and correspondence is installed on the position of described spinneret standard pipe clamp 3 '.
The adjusting dynamic balance that the present invention relates to has been simulated the equipment quality distribution situation under the normal as-rolled condition of Laying head, has avoided the error that the dynamic balancing adjustment brings under the Light Condition, and dynamic balance calibration has higher precision and stronger specific aim.
The above only is the schematic specific embodiment of the present invention, is not to limit scope of the present invention.For each part of the present invention can make up under the condition of not conflicting mutually, any those skilled in the art, the equivalent variations of having done under the prerequisite that does not break away from design of the present invention and principle and modification all should belong to the scope of protection of the invention.
Claims (6)
1. an adjusting dynamic balance of high-speed wire spinning machine method is characterized in that, described adjusting dynamic balance method may further comprise the steps:
A, determine that the spinneret standard pipe is stuck in the installation site on the spinneret, the Mass Distribution of wire rod in spinneret under the steel state told in work according to Laying head, obtain every section wire rod in the reduced mass of the described installed position of each spinneret standard pipe clamp, draw the pre-balance weight that each spinneret standard pipe calorie requirement increases according to each described reduced mass;
B, the pre-balance weight that increases according to each described spinneret standard pipe calorie requirement are made each pre-counterweight pipe clamp of corresponding each described spinneret standard pipe clamp, and each described pre-counterweight pipe clamp correspondence is installed in described installation site;
C, site of deployment dynamic balance instrument carry out dynamic balance calibration to each laying head weight plane, adjust the counterweight of each laying head weight plane according to correction numerical value, repeat the counterweight of described dynamic balance calibration and each laying head weight plane of described adjustment, until reach the dynamic balance calibration class requirement;
After D, dynamic balance calibration are finished each described pre-counterweight pipe clamp is taken off, be replaced by described spinneret standard pipe clamp.
2. adjusting dynamic balance of high-speed wire spinning machine method as claimed in claim 1 is characterized in that, order is placed with 14 spinneret standard pipe clamps on the described spinneret, and the quantity of described pre-counterweight pipe clamp is 14 altogether.
3. adjusting dynamic balance of high-speed wire spinning machine method as claimed in claim 1 is characterized in that, among the described step B, each described pre-counterweight pipe clamp correspondence is installed on the position of each described spinneret standard pipe clamp.
4. adjusting dynamic balance of high-speed wire spinning machine method as claimed in claim 1, it is characterized in that, described spinneret standard pipe clamp is U-shaped platy structure, described U-shaped platy structure comprises: first dull and stereotyped and the second flat board that is parallel to each other, the link and the pin-and-hole that connect the sealing of described the first flat board and the second flat board, described pin-and-hole runs through described first dull and stereotyped and the second flat board, the link of described sealing contains described spinneret, described spinneret is fixed in the link of described sealing by the alignment pin that passes described pin-and-hole, among the described step B, by on the lateral surface of described first dull and stereotyped and the second flat board of described spinneret standard pipe clamp respectively the pre-balancing weight of symmetrical increase obtain described pre-counterweight pipe clamp.
5. adjusting dynamic balance of high-speed wire spinning machine method as claimed in claim 4, it is characterized in that, among the described step B, being produced as follows of described pre-counterweight pipe clamp: make first the identical described spinneret standard pipe clamp of two covers, one cover is installed on the described spinneret, another set of be used to making described pre-counterweight pipe clamp, then on the lateral surface of described first dull and stereotyped and the second flat board of described another set of spinneret standard pipe clamp respectively the pre-balancing weight of symmetrical increase obtain described pre-counterweight pipe clamp.
6. adjusting dynamic balance of high-speed wire spinning machine method as claimed in claim 1 is characterized in that, described steps A also comprises; Described spinneret standard pipe clamp is installed on the spinneret, and described step B also comprises: each described spinneret standard pipe clamp is pulled down, sequentially be replaced by described pre-counterweight pipe clamp according to correspondence.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101953909A CN102274857B (en) | 2011-07-12 | 2011-07-12 | Method for adjusting dynamic balance of high-speed wire spinning machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2011101953909A CN102274857B (en) | 2011-07-12 | 2011-07-12 | Method for adjusting dynamic balance of high-speed wire spinning machine |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102274857A CN102274857A (en) | 2011-12-14 |
CN102274857B true CN102274857B (en) | 2013-04-24 |
Family
ID=45100768
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2011101953909A Active CN102274857B (en) | 2011-07-12 | 2011-07-12 | Method for adjusting dynamic balance of high-speed wire spinning machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102274857B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103230939B (en) * | 2013-05-08 | 2015-02-25 | 中冶赛迪工程技术股份有限公司 | Silking machine spindle assembly, silking machine and method for balancing dynamic unbalance of silking machine |
CN105964726A (en) * | 2016-06-20 | 2016-09-28 | 江苏永钢集团有限公司 | Fixing device for loop laying tube of loop laying head |
CN109174987B (en) * | 2018-08-30 | 2020-03-17 | 阳春新钢铁有限责任公司 | Control method and system for high-speed wire laying, storage medium and computing equipment |
CN114260323A (en) * | 2021-11-24 | 2022-04-01 | 中冶赛迪技术研究中心有限公司 | High-speed laying head |
CN117718934B (en) * | 2023-12-22 | 2024-05-14 | 山东高速新材料科技有限公司 | Storage device is used in production of high-speed wire laying pipe |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6196486B1 (en) * | 1998-06-19 | 2001-03-06 | Sms Schloemann-Siemag Ag | Counterweighted wire-coiling head |
CN101642777A (en) * | 2009-08-24 | 2010-02-10 | 哈尔滨哈飞工业有限责任公司 | Process method for solving on-site dynamic balance of laying head by using Pulufv dynamic balancing instrument |
CN201454980U (en) * | 2009-08-24 | 2010-05-12 | 哈尔滨哈飞工业有限责任公司 | Spinning tube fixing device of high-speed wire rod wire-feeding machine |
CN201603762U (en) * | 2009-11-13 | 2010-10-13 | 福建三钢闽光股份有限公司 | Wire spinning plate |
CN202155368U (en) * | 2011-07-12 | 2012-03-07 | 北京京诚瑞信长材工程技术有限公司 | Dynamic balance adjusting device for high-speed wire spinning machine |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3310092B2 (en) * | 1994-02-01 | 2002-07-29 | 新日本製鐵株式会社 | Laying head |
US7973588B2 (en) * | 2006-05-26 | 2011-07-05 | Mitsubishi Electric Corporation | Analog insulation/multiplexer |
-
2011
- 2011-07-12 CN CN2011101953909A patent/CN102274857B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6196486B1 (en) * | 1998-06-19 | 2001-03-06 | Sms Schloemann-Siemag Ag | Counterweighted wire-coiling head |
CN101642777A (en) * | 2009-08-24 | 2010-02-10 | 哈尔滨哈飞工业有限责任公司 | Process method for solving on-site dynamic balance of laying head by using Pulufv dynamic balancing instrument |
CN201454980U (en) * | 2009-08-24 | 2010-05-12 | 哈尔滨哈飞工业有限责任公司 | Spinning tube fixing device of high-speed wire rod wire-feeding machine |
CN201603762U (en) * | 2009-11-13 | 2010-10-13 | 福建三钢闽光股份有限公司 | Wire spinning plate |
CN202155368U (en) * | 2011-07-12 | 2012-03-07 | 北京京诚瑞信长材工程技术有限公司 | Dynamic balance adjusting device for high-speed wire spinning machine |
Non-Patent Citations (1)
Title |
---|
JP特開平7-214159B2 1995.08.15 |
Also Published As
Publication number | Publication date |
---|---|
CN102274857A (en) | 2011-12-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102274857B (en) | Method for adjusting dynamic balance of high-speed wire spinning machine | |
CN103230939B (en) | Silking machine spindle assembly, silking machine and method for balancing dynamic unbalance of silking machine | |
CN202155368U (en) | Dynamic balance adjusting device for high-speed wire spinning machine | |
CN103567601A (en) | Method for welding tower in vertical assembling mode by utilizing jacks and crane | |
CN102430918A (en) | Coaxiality guide and correction device and guide and correction method using same | |
CN110261036A (en) | A kind of small aero multistage axis joint rotor dynamic balance method | |
CN115072491A (en) | Cable sleeve dynamic tension reading device and adjusting device | |
CN208004531U (en) | A kind of stirring shaft straightener | |
CN103056198A (en) | Speed regulating method and system of straightening roller of vertical roller type straightener | |
CN102825342A (en) | Method for testing error of centralization of herringbone tooth and testing ball | |
CN102708935B (en) | Nuclear Power Plant Simulation C&P systems | |
CN202045535U (en) | Numerical control floor type boring and milling machine main spindle box balancing compensation system | |
CN102384819A (en) | Device and method for correcting dynamic balance of crankshaft | |
CN110781613A (en) | Customized spinning pipe dynamic balance analysis method | |
CN106802996B (en) | Checking calculation method for contact load of two-stage auxiliary spring type unequal frequency bias gradient-type plate spring | |
CN210981217U (en) | Coaxiality automatic detection and correction device | |
CN106763384B (en) | The design method for the offset frequencys type progressive rate leaf spring tangent line camber such as two-stage auxiliary spring formula is non- | |
CN202793691U (en) | Adjustable static balance test device | |
CN204439281U (en) | A kind of centrifugal blower fan blade wheel dynamic balance calibration device | |
CN112213031B (en) | Static balance adjusting process and static balance test rack for strip-shaped workpiece | |
CN219715113U (en) | Steel wire rope fatigue test device | |
CN216012087U (en) | High, middle and pressure rotor centering device for steam turbine | |
CN103742393A (en) | Compressor unit installation method | |
CN217104221U (en) | Upper pin adjusting table | |
CN108801180A (en) | The method of vertical type speed reducer (change gear) and roll-box centering centering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |