CN102175983A - Method for testing multifunctional watt-hour meter reading time of electric quantity collector for watt-hour meter - Google Patents
Method for testing multifunctional watt-hour meter reading time of electric quantity collector for watt-hour meter Download PDFInfo
- Publication number
- CN102175983A CN102175983A CN2011100512951A CN201110051295A CN102175983A CN 102175983 A CN102175983 A CN 102175983A CN 2011100512951 A CN2011100512951 A CN 2011100512951A CN 201110051295 A CN201110051295 A CN 201110051295A CN 102175983 A CN102175983 A CN 102175983A
- Authority
- CN
- China
- Prior art keywords
- electric energy
- meter reading
- reading time
- meter
- collector
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明涉及一种电能表电量采集器抄读多功能电能表抄表时间的测试方法,其步骤如下:(1)搭建测试平台:所述测试平台包括安装有模拟测试系统的笔记本电脑、电量采集器和多功能电能表;(2)通过所述模拟测试系统模拟变电站、电厂现场采集环境;(3)进行抄表时间测试:(4)显示抄表时间并判断电量采集器的性能。本发明的有益效果是能够测试电量采集器对连接的不同通信规约的电能表的抄表时间,从而判断其性能的好坏。
The invention relates to a test method for reading time of a multi-functional electric energy meter by an electric energy collector of an electric energy meter. (2) Simulate the on-site collection environment of substations and power plants through the simulation test system; (3) Test the meter reading time: (4) Display the meter reading time and judge the performance of the power collector. The beneficial effect of the invention is that it can test the meter reading time of the electric power collector connected with the electric energy meters of different communication protocols, so as to judge whether its performance is good or bad.
Description
技术领域technical field
本发明涉及一种电能表电量采集器抄读多功能电能表抄表时间的测试方法。The invention relates to a test method for reading the meter reading time of a multifunctional electric energy meter by an electric energy collector of an electric energy meter.
背景技术Background technique
电量采集器抄读电能表的抄表时间是衡量电量采集器性能的重要指标。电量采集器与电能表之间的通信是通过通信规约来进行的,不同的电能表采用的通信规约不同,常见的通信规约有DL/T645-2007、IEC1107、DL/T645-1999、威胜规约等。同一个电量采集器在抄读不同通信规约的表计数据的时候,抄表时间差别较大。The meter reading time of the electricity collector reading the electric energy meter is an important index to measure the performance of the electricity collector. The communication between the power collector and the energy meter is carried out through communication protocols. Different energy meters use different communication protocols. Common communication protocols include DL/T645-2007, IEC1107, DL/T645-1999, Wasion Protocol wait. When the same electricity collector reads the meter data of different communication protocols, the meter reading time varies greatly.
电量采集器一般设定为每5分钟采集一次所有连接的电能表(就国内目前产品看,绝大多数电量采集器连接的电能表数量不超过32只)。若电量采集器的某个端口抄读电能表数据时间过长,就无法满足每5分钟抄读所有连接表计的要求,造成数据无法正常传输。因此,需要对电量采集器抄读多功能电能表的抄表时间进行测试,以满足变电站、电厂5分钟采集周期的要求。The power collector is generally set to collect all connected electric energy meters every 5 minutes (as far as the current domestic products are concerned, the number of electric energy meters connected to most electric power collectors does not exceed 32). If it takes too long for a certain port of the power collector to read the data of the energy meter, it cannot meet the requirement of reading all connected meters every 5 minutes, resulting in the failure of normal data transmission. Therefore, it is necessary to test the meter reading time of the power collector to read the multi-function electric energy meter to meet the requirements of the 5-minute collection period of the substation and power plant.
目前,电量采集器抄读电能表的抄表时间的测定方法主要是各电量采集器厂家利用自己的抄表软件对单一规约下的电能表进行测试,没有很好的模拟现场环境,开展多通信规约下的采集器抄表时间的方法研究,很难准确的判定现场环境下终端抄读多规约、多块电表的性能参数。At present, the measurement method of the meter reading time of the electric energy collector reading the electric energy meter is mainly that each electric energy collector manufacturer uses its own meter reading software to test the electric energy meter under a single protocol, which does not have a good simulation of the field environment and carries out multi-communication It is difficult to accurately determine the performance parameters of the multi-protocol and multi-block meter reading by the terminal under the field environment.
发明内容Contents of the invention
本发明所要解决的技术问题是提供一种电能表电量采集器抄读多功能电能表抄表时间的测试方法。The technical problem to be solved by the present invention is to provide a test method for reading the meter reading time of a multifunctional electric energy meter by an electric energy collector of an electric energy meter.
本发明解决其技术问题所采用的技术方案:The technical solution adopted by the present invention to solve its technical problems:
本发明的步骤如下:The steps of the present invention are as follows:
(1)搭建测试平台:(1) Build a test platform:
所述测试平台包括安装有模拟测试系统的笔记本电脑、电量采集器和多功能电能表;Described test platform comprises the notebook computer that simulation test system is installed, electricity collector and multi-function electric energy meter;
所述笔记本电脑与电量采集器双向连接,所述电量采集器通过其RS485接口与多功能电能表相连接,所述RS485接口的每个端口上所连接的多功能电能表具有相同的通信规约;The notebook computer is bidirectionally connected to the electricity collector, and the electricity collector is connected to the multifunctional electric energy meter through its RS485 interface, and the multifunctional electric energy meter connected to each port of the RS485 interface has the same communication protocol;
(2)通过所述模拟测试系统模拟变电站、电厂现场采集环境;(2) Simulate the on-site acquisition environment of substations and power plants through the simulation test system;
(3)进行抄表时间测试:(3) Carry out meter reading time test:
通过所述模拟测试系统向电量采集器下发抄读表计命令,所述电量采集器接到抄读表计命令后,开始抄读多功能电能表内的数据,抄表时间是从所述模拟测试系统下发抄读命令开始一直到所有多功能电能表内的数据抄完为止;所述模拟测试系统中的每条命令都带有时间标示;The meter reading command is sent to the power collector through the analog test system, and the power collector starts to read the data in the multi-function electric energy meter after receiving the meter reading command, and the meter reading time is from the described The imitation test system issues the reading command until the data in all the multi-function electric energy meters are copied; each command in the simulation test system has a time mark;
(4)显示抄表时间并判断电量采集器的性能:(4) Display the meter reading time and judge the performance of the power collector:
由笔记本电脑显示所述抄表时间;当抄表时间大于5分钟时,所述电量采集器的性能无法满足现场实际需要,必须更换。The meter reading time is displayed by a notebook computer; when the meter reading time is greater than 5 minutes, the performance of the power collector cannot meet the actual needs of the site and must be replaced.
本发明的工作原理如下:The working principle of the present invention is as follows:
本发明能测试电量采集器对连接的不同通信规约的电能表的抄读表时间。The invention can test the meter reading time of the electric energy collector connected with the electric energy meters of different communication protocols.
根据电量采集器需要连接的电能表的通信规约,将包含各种通信规约的电能表与电量采集器通过RS485接口连接,利用电量采集器抄读软件读取电能表内的数据,记录整个抄读时间,就可以得到电量采集器抄读电能表的时间,判断其是否大于5分钟,如果大于5分钟,则该电量采集器性能无法满足现场实际需要,必须更换。According to the communication protocol of the energy meter that needs to be connected to the electricity collector, connect the energy meter containing various communication protocols with the electricity collector through the RS485 interface, use the reading software of the electricity collector to read the data in the energy meter, and record the entire reading Time, you can get the time when the power collector reads the energy meter, and judge whether it is longer than 5 minutes. If it is longer than 5 minutes, the performance of the power collector cannot meet the actual needs of the site and must be replaced.
本发明的有益效果是能够测试电量采集器对连接的不同通信规约的电能表的抄表时间,从而判断其性能的好坏。The beneficial effect of the invention is that it can test the meter reading time of the electricity collector connected to the electric energy meters with different communication protocols, so as to judge its performance.
附图说明Description of drawings
图1为测试平台的硬件配置图;Figure 1 is a hardware configuration diagram of the test platform;
图2为本发明的抄表时间测试流程图。Fig. 2 is the meter reading time test flowchart of the present invention.
具体实施方式Detailed ways
本实施例的步骤如下:The steps of this embodiment are as follows:
(1)搭建测试平台:(1) Build a test platform:
所述测试平台包括安装有模拟测试系统的笔记本电脑、电量采集器和多功能电能表;Described test platform comprises the notebook computer that simulation test system is installed, electricity collector and multi-function electric energy meter;
所述笔记本电脑与电量采集器双向连接,所述电量采集器通过其RS485接口与多功能电能表相连接,所述RS485接口的每个端口上所连接的多功能电能表具有相同的通信规约;The notebook computer is bidirectionally connected to the electricity collector, and the electricity collector is connected to the multifunctional electric energy meter through its RS485 interface, and the multifunctional electric energy meter connected to each port of the RS485 interface has the same communication protocol;
其中RS485端口1与电能表之间的通信规约采用DL/T645-2007;RS485端口2与电能表之间的通信规约采用IEC1107; RS485端口3与电能表之间的通信规约采用DL/T645-1999; RS485端口4与电能表之间的通信规约采用威胜规约。采集终端的每个RS485端口可以同时连接的电能表的个数为≤8个(见图1)。The communication protocol between RS485 port 1 and the energy meter adopts DL/T645-2007; the communication protocol between RS485 port 2 and the energy meter adopts IEC1107; the communication protocol between RS485 port 3 and the energy meter adopts DL/T645-1999 ; The communication protocol between RS485 port 4 and the energy meter adopts Wasion protocol. The number of energy meters that can be connected to each RS485 port of the collection terminal at the same time is ≤8 (see Figure 1).
(2)通过所述模拟测试系统模拟变电站、电厂现场采集环境;(2) Simulate the on-site acquisition environment of substations and power plants through the simulation test system;
(3)进行抄表时间测试:(3) Carry out meter reading time test:
通过所述模拟测试系统向电量采集器下发抄读表计命令,所述电量采集器接到抄读表计命令后,开始抄读多功能电能表内的数据,抄表时间是从所述模拟测试系统下发抄读命令开始一直到所有多功能电能表内的数据抄完为止;所述模拟测试系统中的每条命令都带有时间标示;The meter reading command is sent to the power collector through the analog test system, and the power collector starts to read the data in the multi-function electric energy meter after receiving the meter reading command, and the meter reading time is from the described The imitation test system issues the reading command until the data in all the multi-function electric energy meters are copied; each command in the simulation test system has a time mark;
(4)显示抄表时间并判断电量采集器的性能:(4) Display the meter reading time and judge the performance of the power collector:
由笔记本电脑显示所述抄表时间;当抄表时间大于5分钟时,所述电量采集器的性能无法满足现场实际需要,必须更换。The meter reading time is displayed by a notebook computer; when the meter reading time is greater than 5 minutes, the performance of the power collector cannot meet the actual needs of the site and must be replaced.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011100512951A CN102175983A (en) | 2011-03-04 | 2011-03-04 | Method for testing multifunctional watt-hour meter reading time of electric quantity collector for watt-hour meter |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011100512951A CN102175983A (en) | 2011-03-04 | 2011-03-04 | Method for testing multifunctional watt-hour meter reading time of electric quantity collector for watt-hour meter |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN102175983A true CN102175983A (en) | 2011-09-07 |
Family
ID=44519186
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2011100512951A Pending CN102175983A (en) | 2011-03-04 | 2011-03-04 | Method for testing multifunctional watt-hour meter reading time of electric quantity collector for watt-hour meter |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102175983A (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102881143A (en) * | 2012-10-22 | 2013-01-16 | 杭州海兴电力科技股份有限公司 | Method for reading electric energy meter event records in AMI (Advanced Metering Infrastructure) system |
| CN104835313A (en) * | 2015-04-30 | 2015-08-12 | 中国电力科学研究院 | Electricity consumption information acquisition device data transmission performance analysis method |
| CN104881982A (en) * | 2015-05-06 | 2015-09-02 | 上海应时为节能科技有限公司 | Intelligent meter data acquiring system having self-adaptive meter reading strategy and acquiring method of intelligent meter data acquiring system |
| CN107315158A (en) * | 2017-06-22 | 2017-11-03 | 南方电网科学研究院有限责任公司 | Data callback function test method and system of cost-controlled electric energy meter |
| CN109613467A (en) * | 2018-10-30 | 2019-04-12 | 杭州海兴电力科技股份有限公司 | Test equipment and test method for realizing multi-meter test in simulated field |
| CN107576926B (en) * | 2017-08-09 | 2019-08-16 | 宁波三星医疗电气股份有限公司 | A method of generating simulation ammeter returned data |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2752786Y (en) * | 2003-12-19 | 2006-01-18 | 赵滨 | Electric energy meter interface detecting instrument |
| CN101629993A (en) * | 2009-08-06 | 2010-01-20 | 深圳市科陆电子科技股份有限公司 | Electric meter simulation test method |
| CN101907694A (en) * | 2010-07-09 | 2010-12-08 | 深圳市科陆电子科技股份有限公司 | A device for testing low-voltage centralized copying system and its testing method |
-
2011
- 2011-03-04 CN CN2011100512951A patent/CN102175983A/en active Pending
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2752786Y (en) * | 2003-12-19 | 2006-01-18 | 赵滨 | Electric energy meter interface detecting instrument |
| CN101629993A (en) * | 2009-08-06 | 2010-01-20 | 深圳市科陆电子科技股份有限公司 | Electric meter simulation test method |
| CN101907694A (en) * | 2010-07-09 | 2010-12-08 | 深圳市科陆电子科技股份有限公司 | A device for testing low-voltage centralized copying system and its testing method |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102881143A (en) * | 2012-10-22 | 2013-01-16 | 杭州海兴电力科技股份有限公司 | Method for reading electric energy meter event records in AMI (Advanced Metering Infrastructure) system |
| CN102881143B (en) * | 2012-10-22 | 2013-06-12 | 杭州海兴电力科技股份有限公司 | Method for reading electric energy meter event records in AMI (Advanced Metering Infrastructure) system |
| CN104835313A (en) * | 2015-04-30 | 2015-08-12 | 中国电力科学研究院 | Electricity consumption information acquisition device data transmission performance analysis method |
| CN104835313B (en) * | 2015-04-30 | 2018-05-04 | 中国电力科学研究院 | A kind of power information collecting device data transmission performance analysis method |
| CN104881982A (en) * | 2015-05-06 | 2015-09-02 | 上海应时为节能科技有限公司 | Intelligent meter data acquiring system having self-adaptive meter reading strategy and acquiring method of intelligent meter data acquiring system |
| CN104881982B (en) * | 2015-05-06 | 2018-03-06 | 上海应时为能源数据技术有限公司 | A kind of the intelligent gauge data collecting system and its acquisition method of adaptive meter reading strategy |
| CN107315158A (en) * | 2017-06-22 | 2017-11-03 | 南方电网科学研究院有限责任公司 | Data callback function test method and system of cost-controlled electric energy meter |
| CN107315158B (en) * | 2017-06-22 | 2019-12-31 | 南方电网科学研究院有限责任公司 | Data callback function test method and system of cost-controlled electric energy meter |
| CN107576926B (en) * | 2017-08-09 | 2019-08-16 | 宁波三星医疗电气股份有限公司 | A method of generating simulation ammeter returned data |
| CN109613467A (en) * | 2018-10-30 | 2019-04-12 | 杭州海兴电力科技股份有限公司 | Test equipment and test method for realizing multi-meter test in simulated field |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101907694B (en) | Device and method for testing low-voltage collecting meter reading system | |
| CN103021157B (en) | Device and method for completely simulating site to detect electricity consumption information acquisition terminal | |
| CN105785199B (en) | Multifunctional ligand electric terminals integrated test system and its working method | |
| CN102196047A (en) | Electricity collection terminal function tester | |
| CN102129001A (en) | Digital relay protection device testing system and method | |
| CN201839095U (en) | Intelligent transformer substation testing and simulation system | |
| CN202837423U (en) | Wireless GPRS wind power power grid electric energy quality detection device based on DSP and ARM | |
| CN105785118A (en) | Simulated intelligent electric energy meter | |
| CN202650245U (en) | Resident low-voltage centralized meter-reading terminal detecting device completely simulating spots | |
| CN202434042U (en) | Automatic meter reading system | |
| CN204331019U (en) | A kind of digital electricity meter IEC61850 compliance test system | |
| CN103605105B (en) | Smart substation digital energy meter calibration device | |
| CN204228947U (en) | A kind of single-phase real load electric energy table calibration equipment | |
| CN201477192U (en) | Digital wave-recording device of power generator transformer set/circuit | |
| CN202304874U (en) | Thermotechnical type energy efficiency data acquisition terminal | |
| CN201611372U (en) | Portable Distribution Transformer Comprehensive Tester | |
| CN201247311Y (en) | Electric meter tester | |
| CN205749669U (en) | A kind of three-phase remote bill control intelligent electric energy meter | |
| CN203811797U (en) | Analog electrician/electronic signal and digital signal electric energy meter verification apparatus | |
| CN102506932A (en) | Thermodynamic type energy-efficiency data acquisition terminal | |
| CN203133201U (en) | Integrated measurement device for energy-storage grid-connected system | |
| CN201570857U (en) | Small current grounding line selection device based on distributed measurement technology | |
| CN204065694U (en) | A kind of portable satellite synchronous clock pick-up unit | |
| CN204926481U (en) | Data collection station based on thing networking | |
| CN202103619U (en) | Generator leading phase operation monitoring system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| ASS | Succession or assignment of patent right |
Owner name: HEBEI ELECTRIC POWER CORPORATION ELECTRIC POWER RE Free format text: FORMER OWNER: HEBEI ELECTRIC POWER RESEARCH INSTITUTE Effective date: 20121224 Owner name: STATE GRID CORPORATION OF CHINA HEBEI ELECTRIC POW Effective date: 20121224 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| TA01 | Transfer of patent application right |
Effective date of registration: 20121224 Address after: 050021 No. 238 South Sports street, Yuhua Road, Hebei, Shijiazhuang Applicant after: Electric Power Research Institute of Hebei Electric Power Corporation Applicant after: State Grid Corporation of China Applicant after: Hebei Electric Power Construction & Adjustment Research Institute Address before: 050021 No. 238 South Sports street, Hebei, Shijiazhuang Applicant before: Hebei Electric Power Research Institute |
|
| C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20110907 |