CN102134621B - Blast furnace iron notch patching method - Google Patents
Blast furnace iron notch patching method Download PDFInfo
- Publication number
- CN102134621B CN102134621B CN2010105402559A CN201010540255A CN102134621B CN 102134621 B CN102134621 B CN 102134621B CN 2010105402559 A CN2010105402559 A CN 2010105402559A CN 201010540255 A CN201010540255 A CN 201010540255A CN 102134621 B CN102134621 B CN 102134621B
- Authority
- CN
- China
- Prior art keywords
- brown corundum
- brick
- filler
- stones
- iron mouth
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 title claims abstract description 74
- 229910052742 iron Inorganic materials 0.000 title claims abstract description 37
- 238000000034 method Methods 0.000 title claims abstract description 15
- 239000011449 brick Substances 0.000 claims abstract description 70
- 229910052593 corundum Inorganic materials 0.000 claims abstract description 58
- 239000010431 corundum Substances 0.000 claims abstract description 58
- 239000000945 filler Substances 0.000 claims abstract description 26
- 238000001816 cooling Methods 0.000 claims abstract description 13
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 claims abstract description 10
- 229910052799 carbon Inorganic materials 0.000 claims abstract description 10
- 239000004575 stone Substances 0.000 claims description 21
- 238000004519 manufacturing process Methods 0.000 description 5
- 230000002829 reductive effect Effects 0.000 description 3
- 230000003245 working effect Effects 0.000 description 3
- 238000003723 Smelting Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000012423 maintenance Methods 0.000 description 2
- 229910000805 Pig iron Inorganic materials 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000155 melt Substances 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
Landscapes
- Blast Furnaces (AREA)
Abstract
The invention discloses a blast furnace iron notch patching method. The key improvement of the method is that the method comprises the following steps: (1) the brown corundum bricks and carbon bricks below the central line of the iron notch are dismantled; the dismantling range uses the central line of the iron notch as a reference and is eudipleural, the width of the dismantling range is more than 1200mm, the height is more than 600mm and the depth of the dismantling range from the shell of the furnace to the inside is more than 600mm; (2) the inner wall of the iron notch is finished; (3) brown corundum bricks are laid; at least two layers of brown corundum bricks are laid at the bottom of the cavity formed after the brown corundum bricks and carbon bricks are dismantled; (4) a cooling coil is arranged in the cavity after the brown corundum bricks are laid; (5) a brown corundum filler is poured in the cavity after the cooling coil is arranged; and (6) mud is jacked on the shell of the furnace: after the brown corundum filler is poured, mud is jacked between the poured brown corundum filler and the shell of the furnace and between the laid brown corundum bricks. The invention has the following advantage: the service life of the iron notch can be effectively increased.
Description
Technical field
The present invention relates to a kind of blast furnace method for maintaining, particularly a kind of blast furnace taphole restorative procedure.
Background technology
Blast furnace ironmaking is to utilize reductive agent at high temperature iron ore or iron-bearing material to be reduced into the process of liquid pig iron; In the whole production smelting process; Blast-furnace body is a nucleus equipment, running efficiency and production efficiency that the efficient height of iron-smelting blast furnace body and the length in life-span will directly influence whole ironmaking workshop system equipment; Existing blast furnace taphole generally adopts brown corundum brick to build by laying bricks or stones, but in use, the iron mouth occurs through regular meeting and burn the phenomenon of metalling run out; Directly influence the normal operation of blast furnace; Also shorten the work-ing life of blast furnace, increased the maintenance and repair cost, reduced the production efficiency in whole workshop.
Summary of the invention
Technical problem to be solved by this invention provides a kind of blast furnace taphole work-ing life of can effectively prolonging, and improves the blast furnace taphole restorative procedure of blast furnace production efficiency.
For solving the problems of the technologies described above, the technical scheme that the present invention adopted is: a kind of blast furnace taphole restorative procedure, and its key improvements is: may further comprise the steps: brown corundum brick and the carbon brick below the iron mouth medullary ray removed in (1); The dismounting scope is the benchmark left-right symmetric with iron mouth medullary ray, and the width of removing scope is greater than 1200 millimeters, and height is greater than 600 millimeters, the dismounting scope from the inside depth of stove skin greater than 600 millimeters; (2) revise iron mouth inwall; Melt on the Tie Kou two side is rooted out; (3) build brown corundum brick by laying bricks or stones; The bottom that behind brown corundum brick of dismounting and carbon brick, forms is built two-layer at least brown corundum brick by laying bricks or stones; (4) spiral coil cooling tube is installed; In building the later cavity of brown corundum brick by laying bricks or stones, spiral coil cooling tube is installed; (5) the brown corundum filler of cast; The brown corundum filler of cast in the later cavity of spiral coil cooling tube is installed; (6) stove skin mud jacking; Accomplish after the cast of brown corundum filler, at mud jacking between the brown corundum filler of cast and the stove skin and between the brown corundum brick of building by laying bricks or stones.
Said step (5) also is included in the brown corundum filler top of cast and builds iron mouth brick by laying bricks or stones, and iron mouth brick and iron mouth frame seam crossing are poured into a mould brown corundum filler.
Adopt the beneficial effect that technique scheme produced to be: the brown corundum brick that replaces original piecemeal to build by laying bricks or stones with integrated poured brown corundum filler below the iron mouth; Improve the high-temperature capability of iron mouth below; Can effectively prolong iron mouth work-ing life, reduce maintenance cost, through experimental verification on 460 cubes of blast furnaces; Also occurred in 3 years leaking slag iron phenomenon through continuous use of the iron mouth of repairing again, can effectively improve the production efficiency of blast furnace.
Embodiment
For making above-mentioned purpose of the present invention, characteristic and beneficial effect can be more obviously understandable, will combine the embodiment of the invention and embodiment below, and the technical scheme in the embodiment of the invention is carried out clear, intactly description.
A kind of blast furnace taphole restorative procedure, its key improvements is: may further comprise the steps: brown corundum brick and the carbon brick below the iron mouth medullary ray removed in (1); The dismounting scope is the benchmark left-right symmetric with iron mouth medullary ray, and the width of removing scope is greater than 1200 millimeters, and height is greater than 600 millimeters, the dismounting scope from the inside depth of stove skin greater than 600 millimeters; (2) revise iron mouth inwall; Melt on the Tie Kou two side is rooted out, consistent until iron mouth inner wall shape and original-shape; (3) build brown corundum brick by laying bricks or stones; The bottom that behind brown corundum brick of dismounting and carbon brick, forms is built two-layer at least brown corundum brick by laying bricks or stones; (4) spiral coil cooling tube is installed; In building the later cavity of brown corundum brick by laying bricks or stones, spiral coil cooling tube is installed; (5) the brown corundum filler of cast; The brown corundum filler of cast in the later cavity of spiral coil cooling tube is installed; (6) stove skin mud jacking; Accomplish after the cast of brown corundum filler, at mud jacking between the brown corundum filler of cast and the stove skin and between the brown corundum brick of building by laying bricks or stones.
Said step (5) also is included in the brown corundum filler top of cast and builds iron mouth brick by laying bricks or stones, and iron mouth brick and iron mouth frame seam crossing are poured into a mould brown corundum filler.
In concrete application process; At first remove with the stove skin around the iron mouth with by the cooling stave of scaling loss; And be that benchmark is removed below the medullary ray each side 600 millimeters brown corundum brick and carbon brick with iron mouth medullary ray, removing depth is benchmark with former stove skin, inwardly depth is 600 millimeters; Repair the melt on the Tie Kou two side then, be trimmed to Tie Kou two side regular shape; The 3rd step carried out brown corundum brick and builds by laying bricks or stones, built two-layer brown corundum brick by laying bricks or stones removing the cavity inner bottom part that forms behind brown corundum brick and the carbon brick; The 4th step is the brown corundum filler of cast in laying the cavity of brown corundum brick, and the height of pouring into a mould brown corundum filler is consistent with former iron mouth outer bottom height, and spiral coil cooling tube was installed before cast; The 5th step was on the brown corundum filler end face of cast, to build two-layer iron mouth brick by laying bricks or stones; The 6th step was carried out mud jacking, pressed in the slit between the slit that the brown corundum filler of cast forms later on and the brown corundum brick of building by laying bricks or stones and annotated the refractory seals slurry; The stove skin is installed at last.
Claims (1)
1. a blast furnace taphole restorative procedure is characterized in that: may further comprise the steps: brown corundum brick and carbon brick below (1) dismounting iron mouth medullary ray; The dismounting scope is the benchmark left-right symmetric with iron mouth medullary ray, and the width of removing scope is greater than 1200 millimeters, and height is greater than 600 millimeters, the dismounting scope from the inside depth of stove skin greater than 600 millimeters; (2) finishing iron mouth inwall; Melt on the Tie Kou two side is rooted out; (3) build brown corundum brick by laying bricks or stones; The bottom that behind brown corundum brick of dismounting and carbon brick, forms is built two-layer at least brown corundum brick by laying bricks or stones; (4) spiral coil cooling tube is installed; In building the later cavity of brown corundum brick by laying bricks or stones, spiral coil cooling tube is installed; (5) the brown corundum filler of cast; The brown corundum filler of cast in the later cavity of spiral coil cooling tube is installed; (6) stove skin mud jacking; Accomplish after the cast of brown corundum filler, at mud jacking between the brown corundum filler of cast and the stove skin and between the brown corundum brick of building by laying bricks or stones; Said step (5) also is included in the brown corundum filler top of cast and builds iron mouth brick by laying bricks or stones, and iron mouth brick and iron mouth frame seam crossing are poured into a mould brown corundum filler.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010105402559A CN102134621B (en) | 2010-11-11 | 2010-11-11 | Blast furnace iron notch patching method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010105402559A CN102134621B (en) | 2010-11-11 | 2010-11-11 | Blast furnace iron notch patching method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102134621A CN102134621A (en) | 2011-07-27 |
| CN102134621B true CN102134621B (en) | 2012-06-20 |
Family
ID=44294547
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2010105402559A Active CN102134621B (en) | 2010-11-11 | 2010-11-11 | Blast furnace iron notch patching method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102134621B (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102384653A (en) * | 2011-11-03 | 2012-03-21 | 云南新立有色金属有限公司 | Method for changing refractory brick at tapping hole of direct current electric arc furnace |
| CN108977603B (en) * | 2018-08-23 | 2020-07-31 | 中国二十二冶集团有限公司 | Repairing method for iron notch frame burn-through of iron-making blast furnace |
| CN114659370B (en) * | 2022-03-24 | 2023-07-28 | 新疆西部合盛硅业有限公司 | Hot furnace hole-cutting maintenance technology for industrial silicon ore smelting furnace |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101790587A (en) * | 2007-09-10 | 2010-07-28 | 新日本制铁株式会社 | Taphole Structure and Repair Method of Melting Furnace |
-
2010
- 2010-11-11 CN CN2010105402559A patent/CN102134621B/en active Active
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101790587A (en) * | 2007-09-10 | 2010-07-28 | 新日本制铁株式会社 | Taphole Structure and Repair Method of Melting Furnace |
Non-Patent Citations (2)
| Title |
|---|
| 柯显峰.湖北新冶钢2#380m3高炉中修探索.《2007年中小高炉炼铁学术年会论文集》.2007,494-496. * |
| 梁荣利等.包钢6#高炉铁口冷却壁修复技术.《包钢技术》.2008,第34卷(第5期),23-25. * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102134621A (en) | 2011-07-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103736985B (en) | A kind of ladle working lining and slag lining thereof build by laying method | |
| CN101412109B (en) | Building and laying method capable of extending service lifetime of RH ladle working lining | |
| CN103276130A (en) | Maintenance method for air leakage from pipeline of hot-air system of blast furnace | |
| CN102019417A (en) | Method for building steel ladle pouring working lining | |
| CN104759611B (en) | What a kind of ladle was combined working lining and slag lining thereof builds by laying method | |
| CN103302280B (en) | A kind of building method of steel ladle bottom for ultra-low carbon steel | |
| CN102134621B (en) | Blast furnace iron notch patching method | |
| CN104293994B (en) | Cast steel stave for blast furnace and manufacturing method thereof | |
| CN101921887B (en) | Maintenance method of blast furnace liner | |
| CN104647570A (en) | Blast furnace front refractory casting mold and casting method | |
| CN101509050A (en) | Method for producing and mending slag separator | |
| CN203559063U (en) | Blast furnace thin-wall lining | |
| CN104019666B (en) | A kind of method that intermediate frequency furnace body crucible is repaired immediately | |
| JP5817959B2 (en) | Lined structure of vertical furnace refractories | |
| CN204525714U (en) | Before a kind of State of Blast Furnace, mould built by resistance to material | |
| CN107299171B (en) | Method for repairing refractory lining on side wall of blast furnace hearth and refractory lining body | |
| CN108842018A (en) | A kind of blast-furnace tuyere blocks up mud device and its installation and method for dismounting | |
| CN106630550A (en) | Brick binding operation method for tank wall brick of large-tonnage melting furnace | |
| CN103045794B (en) | Water cooling furnace mouth and converter | |
| CN205077081U (en) | Novel "bosh of blast furnace hearth cooling wall links up structure | |
| CN107254559B (en) | A kind of cooling wall and its processing method | |
| CN206308387U (en) | A kind of RH vacuum chambers bottom masonry construction | |
| CN205803515U (en) | A kind of can be with the ferrum mouth cooling wall of integral replacing | |
| CN107779556A (en) | Method for repairing bottom groove of vacuum chamber of RH refining furnace | |
| CN223129342U (en) | Torpedo tank masonry structure and torpedo tank |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |