CN101992384A - Manufacturing process of shearing rib mold - Google Patents
Manufacturing process of shearing rib mold Download PDFInfo
- Publication number
- CN101992384A CN101992384A CN 201010520138 CN201010520138A CN101992384A CN 101992384 A CN101992384 A CN 101992384A CN 201010520138 CN201010520138 CN 201010520138 CN 201010520138 A CN201010520138 A CN 201010520138A CN 101992384 A CN101992384 A CN 101992384A
- Authority
- CN
- China
- Prior art keywords
- shearing ribs
- shearing
- finished product
- mold
- fire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention discloses a manufacturing process of a shearing rib mold, which is characterized by comprising the following steps: (1) splicing plates, and lofting; (2) folding a metal edge: folding a steel plate into a right angle at the edge of the steel plate to manufacture the edge of a shearing rib, and ensuring the angle; (3) welding a flat plate; (4) maintaining pressure of welded seams; (5) manufacturing an inner cavity of the mold; (6) laying heating strips; (7) laying heat-insulating cotton; and (8) adjusting the level of the mold. In the invention, the problems that in the prior art, the shearing rib mold is manufactured by adopting glass fiber reinforced plastics, the cost is high, and the shrinkage rate and the deformation rate of the finished mold are higher are solved. The invention provides the manufacturing process for manufacturing the shearing rib mold by using the steel plate as a raw material.
Description
Technical field
The present invention relates to a kind of mold production process, particularly relate to a kind of shearing ribs mold production process.
Background technology
The mould that is used for doing fiberglass at present has a variety of, as: wooden model, silica gel mould, plaster mold, glass punching block, punching block etc.The preparation method of fiber reinforced plastic mold: shop fiberglass cloth, re-lay copper pipe, be used for heating, resin and aluminium powder are stirred, above being layered on, repave one deck fiberglass cloth.The glass punching block has former, and formpiston to matched moulds etc., specifically selects for use type in which kind of will see the structure of product, technology, quality requirement etc.At first be that original shape spare one is exactly a formpiston, made of wooden mostly before domestic, but so long that external majority employing pasty state is constructed for wood and one will be operated with machine for fan blade.On this formpiston, turn over cavity block then, do well die joint after, can hand stick with paste or vacuum imports.
The problem that fiber reinforced plastic mold often runs in manufacturing process comprises: the steelframe die surface for wood layer cracking, yoke die surface for wood layer cracking, that the male mold surfaces light is handled is unnecessary, there is bubble at the former turning, the female mold surfaces frp layer is thicker, former fiberglass is out of shape with the hard junction of steelframe, the former steelframe does not have the thermal expansion expansion joint (E.J.), former mozzle joint is too much etc.
The shearing ribs mold production process of prior art adopts fiberglass simultaneously, and adopt glass-reinforced plastic material to make the shearing ribs mould and have following shortcoming: 1, cost of manufacture is higher.2, inefficiency, the secondary mould time of making is longer.3, die width can not be regulated as required.4, the shearing ribs mould adopts glass-reinforced plastic material, and mold shrinkage and deformation rate are higher, and be fragile, causes and can not continue to use.5, the heating system of mould is difficult to safeguard and keep in repair.
Summary of the invention
Adopt the fiberglass manufacturing in order to solve in the prior art manufacturing of shearing ribs mould, the cost height, its shrinkage factor and deformation rate problem of higher mould is finished after the invention provides a kind of manufacturing process of utilizing steel plate as raw material manufacturing shearing ribs mould.
In order to achieve the above object, the technical solution adopted in the present invention is:
1, a kind of shearing ribs mold production process is characterized in that: may further comprise the steps:
(1), jigsaw, setting-out
After 1.5 meters X2.5 rice cold rolled plates are combined into a plane, the shearing ribs finished product is positioned on the plane;
(2), metal flanging
The cold rolled plate of putting well is converted into the flange that shearing ribs is made at the right angle, leans against on the shearing ribs finished product with newly-increased L shaped plate, 1 meter one section, determine the flange size according to the shearing ribs finished size, the width of flange is 20 centimeters, highly is 9 centimeters;
(3), welding plate
The slit that to roll between the cold rolled plate behind the limit by electric welding machine welds;
(4), weld seam pressurize
Every weld seam to flat board carries out pressurize, pastes the sealing doctrine earlier at position while welding, lays water conservancy diversion net and vacuum bag film then, with vavuum pump pressure is evacuated to below the 10mbar at last;
(5), do dies cavity
The mould that has welded is stood up, shearing ribs finished product conformal is put into inner chamber, cutting width is 8.5 centimeters, thickness is that the cold rolled plate of 3mm leans against on the shearing ribs finished product limit, use electric welding machine spot welding, tamp with polyurethane foam for the hollow area beyond the shearing ribs finished product, be enclosed in above the shearing ribs finished product with the thick cold rolled plate of 3mm again;
(6), lay fire-bar
After finishing dies cavity, mould is stood up, below by the fixing fire-bar of laying of aluminum foil and adhesive tape, fire-bar is taped against small end from the big end of shearing ribs, begins to spread one every 9 centimeters from flange at mould;
(7), lay heat-preservation cotton
Heat-preservation cotton is covered the bottom of entire die, be fixed with wire netting;
(8), adjust die horizontal
Adjust die horizontal with laser leveler.
Aforesaid a kind of shearing ribs mold production process is characterized in that: heated by resistance wire at fire-bar described in the step (6), the heating-up temperature of fire-bar is 130 °.
The invention has the beneficial effects as follows: shearing ribs mold production process of the present invention utilizes steel plate materials to replace glass-reinforced plastic material, saves cost, has improved efficiency, and mold shrinkage and deformation rate will be lower than fiber reinforced plastic mold.Guarantee that by accurate manufacturing formpiston and employing segmented metal flanging the angle of dies cavity is to meet the requirements.The mould air-tightness is to guarantee mould metal seam seal by positive and negative no seam welding.The mould removable section passes through, and locating slot and locking device are fixed, and fixing back is carried out once more fixing to mould by shrouding, guarantees that the mould removable section does not occur loosening and moves phenomenon such as position.
Description of drawings
Fig. 1 is a shearing ribs mold production process flow chart of the present invention;
Fig. 2 is a shearing ribs turnup structure schematic diagram of the present invention;
Fig. 3 is a dies cavity structural representation of the present invention.
The specific embodiment
As shown in Figure 1, specific embodiment is as follows:
1, a kind of shearing ribs mold production process is characterized in that: may further comprise the steps:
(1), jigsaw, setting-out
After 1.5 meters X2.5 rice cold rolled plates are combined into a plane, the shearing ribs finished product is positioned on the plane;
(2), metal flanging
The cold rolled plate of putting well is converted into the flange that shearing ribs is made at the right angle, leans against on the shearing ribs finished product with newly-increased L shaped plate, 1 meter one section, as shown in Figure 2, determine the flange size according to the shearing ribs finished size, the width of flange is 20 centimeters, highly is 9 centimeters;
(3), welding plate
The slit that to roll between the cold rolled plate behind the limit by electric welding machine welds;
(4), weld seam pressurize
Every weld seam to flat board carries out pressurize, pastes the sealing doctrine earlier at position while welding, lays water conservancy diversion net and vacuum bag film then, with vavuum pump pressure is evacuated to below the 10mbar at last;
(5), do dies cavity
As shown in Figure 3, the mould that has welded is stood up, shearing ribs finished product 2 conformals are put into inner chamber 1, cutting width is 8.5 centimeters, thickness is that the cold rolled plate 3 of 3mm leans against on shearing ribs finished product 2 both sides, use electric welding machine spot welding, tamp with polyurethane foam 4 for the hollow area beyond the shearing ribs finished product 2, above being enclosed in the thick cold rolled plate of 3mm again;
(6), lay fire-bar
After finishing dies cavity, mould is stood up, fix below by aluminum foil and adhesive tape at mould and lay fire-bar, fire-bar is taped against small end from the big end of shearing ribs, begin to spread one every 9 centimeters from flange, described fire-bar is heated by resistance wire, and the heating-up temperature of fire-bar is 130.;
(7), lay heat-preservation cotton
Heat-preservation cotton is covered the bottom of entire die, be fixed with wire netting;
(8), adjust die horizontal
Adjust die horizontal with laser leveler.
Show and described basic principle of the present invention and principal character and advantage of the present invention.The technical staff of the industry should understand; the present invention is not restricted to the described embodiments; that describes in the foregoing description and the specification just illustrates principle of the present invention; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications, and these changes and improvements all fall in the claimed scope of the invention.The claimed scope of the present invention is defined by appending claims and equivalent thereof.
Claims (2)
1. shearing ribs mold production process is characterized in that: may further comprise the steps:
(1), jigsaw, setting-out
After 1.5 meters X2.5 rice cold rolled plates are combined into a plane, the shearing ribs finished product is positioned on the plane;
(2), metal flanging
The cold rolled plate of putting well is converted into the flange that shearing ribs is made at the right angle, leans against on the shearing ribs finished product with newly-increased L shaped plate, 1 meter one section, determine the flange size according to the shearing ribs finished size, the width of flange is 20 centimeters, highly is 9 centimeters;
(3), welding plate
By electric welding machine the slit between the above-mentioned cold rolled plate is welded;
(4), weld seam pressurize
Every weld seam to flat board carries out pressurize, pastes the sealing doctrine earlier at position while welding, lays water conservancy diversion net and vacuum bag film then, with vavuum pump pressure is evacuated to below the 10mbar at last;
(5), do dies cavity
The mould that has welded is stood up, shearing ribs finished product conformal is put into inner chamber, cutting width is 8.5 centimeters, thickness is that the cold rolled plate of 3mm leans against on the shearing ribs finished product limit, use electric welding machine spot welding, tamp with polyurethane foam for the hollow area beyond the shearing ribs finished product, be enclosed in above the shearing ribs finished product with the thick cold rolled plate of 3mm again;
(6), lay fire-bar
After finishing dies cavity, mould is stood up, below by the fixing fire-bar of laying of aluminum foil and adhesive tape, fire-bar is taped against small end from the big end of shearing ribs, begins to spread one every 9 centimeters from flange at mould;
(7), lay heat-preservation cotton
Heat-preservation cotton is covered the bottom of entire die, be fixed with wire netting;
(8), adjust die horizontal
Adjust die horizontal with laser leveler.
2. a kind of shearing ribs mold production process according to claim 1 is characterized in that: heated by resistance wire at fire-bar described in the step (6), the heating-up temperature of fire-bar is 130 °.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010520138 CN101992384B (en) | 2010-10-26 | 2010-10-26 | Manufacturing process of shearing rib mold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010520138 CN101992384B (en) | 2010-10-26 | 2010-10-26 | Manufacturing process of shearing rib mold |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101992384A true CN101992384A (en) | 2011-03-30 |
CN101992384B CN101992384B (en) | 2013-02-06 |
Family
ID=43783388
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010520138 Expired - Fee Related CN101992384B (en) | 2010-10-26 | 2010-10-26 | Manufacturing process of shearing rib mold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101992384B (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102241141A (en) * | 2011-04-29 | 2011-11-16 | 昆山华风风电科技有限公司 | Rear edge soft-pressing method for fan blade |
CN102794616A (en) * | 2012-09-04 | 2012-11-28 | 龙岩市新罗区八合汽车配件厂(普通合伙) | Manufacturing process of brake drum safety loops of heavy trucks |
CN102806616A (en) * | 2012-07-18 | 2012-12-05 | 同济大学 | Novel method for manufacturing wind turbine blade rib plate die |
CN103072223A (en) * | 2013-01-31 | 2013-05-01 | 中材科技风电叶片股份有限公司 | Fabrication method of wind power vane web mold |
CN103240576A (en) * | 2013-04-27 | 2013-08-14 | 哈尔滨飞机工业集团有限责任公司 | Method for machining split quenched pattern dies |
CN106964949A (en) * | 2017-04-17 | 2017-07-21 | 江苏帝尔保机械有限公司 | A kind of rolling die group and its production method for producing closed shape tube |
CN108161380A (en) * | 2017-12-04 | 2018-06-15 | 南通斯迈尔精密设备有限公司 | A kind of pocket machining technique of semiconductor packaging mold |
CN109807547A (en) * | 2017-11-22 | 2019-05-28 | 苏州市艾西依钣金制造有限公司 | The welding of stainless steel wire drawing plate, polishing, drawing process |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE4021381A1 (en) * | 1990-07-05 | 1992-01-09 | Weinsberg Karosseriewerke | Process for forming mould for thin fibre-reinforced sheet material - uses perforated sheet metal formed on negative patterns |
US5156786A (en) * | 1990-07-02 | 1992-10-20 | Hudson Products Corporation | Method for manufacuring fan blades |
CN2774743Y (en) * | 2005-04-15 | 2006-04-26 | 同济大学 | Forming mould for composite material wind power machine blade |
CN101628373A (en) * | 2009-08-11 | 2010-01-20 | 天津市瑞福科技发展有限公司 | Preparation technology of detachable welding type mold insert (core) |
CN101791833A (en) * | 2010-03-19 | 2010-08-04 | 昆山华风风电科技有限公司 | Mold used for manufacturing fan blade shearing ribs of wind generating set |
-
2010
- 2010-10-26 CN CN 201010520138 patent/CN101992384B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5156786A (en) * | 1990-07-02 | 1992-10-20 | Hudson Products Corporation | Method for manufacuring fan blades |
DE4021381A1 (en) * | 1990-07-05 | 1992-01-09 | Weinsberg Karosseriewerke | Process for forming mould for thin fibre-reinforced sheet material - uses perforated sheet metal formed on negative patterns |
CN2774743Y (en) * | 2005-04-15 | 2006-04-26 | 同济大学 | Forming mould for composite material wind power machine blade |
CN101628373A (en) * | 2009-08-11 | 2010-01-20 | 天津市瑞福科技发展有限公司 | Preparation technology of detachable welding type mold insert (core) |
CN101791833A (en) * | 2010-03-19 | 2010-08-04 | 昆山华风风电科技有限公司 | Mold used for manufacturing fan blade shearing ribs of wind generating set |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102241141A (en) * | 2011-04-29 | 2011-11-16 | 昆山华风风电科技有限公司 | Rear edge soft-pressing method for fan blade |
CN102241141B (en) * | 2011-04-29 | 2013-10-16 | 昆山华风风电科技有限公司 | Rear edge soft-pressing method for fan blade |
CN102806616A (en) * | 2012-07-18 | 2012-12-05 | 同济大学 | Novel method for manufacturing wind turbine blade rib plate die |
CN102806616B (en) * | 2012-07-18 | 2015-02-18 | 同济大学 | Novel method for manufacturing wind turbine blade rib plate die |
CN102794616A (en) * | 2012-09-04 | 2012-11-28 | 龙岩市新罗区八合汽车配件厂(普通合伙) | Manufacturing process of brake drum safety loops of heavy trucks |
CN102794616B (en) * | 2012-09-04 | 2016-05-25 | 龙岩市新罗区八合汽车配件厂(普通合伙) | Trunk brake drum safety loop manufacture craft |
CN103072223A (en) * | 2013-01-31 | 2013-05-01 | 中材科技风电叶片股份有限公司 | Fabrication method of wind power vane web mold |
CN103240576A (en) * | 2013-04-27 | 2013-08-14 | 哈尔滨飞机工业集团有限责任公司 | Method for machining split quenched pattern dies |
CN103240576B (en) * | 2013-04-27 | 2015-08-05 | 哈尔滨飞机工业集团有限责任公司 | A kind of split quenching pattern processing method |
CN106964949A (en) * | 2017-04-17 | 2017-07-21 | 江苏帝尔保机械有限公司 | A kind of rolling die group and its production method for producing closed shape tube |
CN109807547A (en) * | 2017-11-22 | 2019-05-28 | 苏州市艾西依钣金制造有限公司 | The welding of stainless steel wire drawing plate, polishing, drawing process |
CN108161380A (en) * | 2017-12-04 | 2018-06-15 | 南通斯迈尔精密设备有限公司 | A kind of pocket machining technique of semiconductor packaging mold |
Also Published As
Publication number | Publication date |
---|---|
CN101992384B (en) | 2013-02-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101992384B (en) | Manufacturing process of shearing rib mold | |
CN103453240B (en) | Double-plastics finned wound corrugated pipe and method for manufacturing same | |
CN103072223B (en) | Fabrication method of wind power vane web mold | |
CN108638541B (en) | Blade shell and web integrated forming method and blade forming method | |
CN105346100B (en) | A kind of preparation method of the big beam mould of wind electricity blade | |
CN103560332B (en) | A kind of manufacture method of caliber high-precision composite antenna surface | |
CN105128358A (en) | Manufacturing method for wind power blade | |
CN104999672B (en) | A kind of hyperbolicity variable-section variable thickness leads to the forming method of beam | |
CN202878541U (en) | Wind power blade web mold | |
CN109353026A (en) | It is a kind of to manufacture the mold and method for emitting shape Composite Material Stiffened Panel | |
CN206335937U (en) | A kind of particular manufacturing craft of hyperboloid honeycomb core plate | |
CN103753935A (en) | Composite metal plate process | |
CN104002402A (en) | Universal web mould structure for wind power blade | |
CN103587149B (en) | Luggage case material and preparation method thereof | |
CN112677378B (en) | Preparation method of prefabricated pasting angle of rear edge of fan blade | |
CN109203516A (en) | A kind of manufacturing method of wind electricity blade | |
CN103817763B (en) | Circle bamboo environment-friendly light shape extrusion method | |
CN102672978A (en) | Technique for manufacturing blade of wind-driven generator | |
CN108819290B (en) | Wind blade front edge pasting angle die positioning device and manufacturing method thereof | |
CN110733188A (en) | wind power blade trailing edge vertical surface area filling method | |
CN106182828A (en) | A kind of blade " work " belly board mold and preparation method thereof | |
CN113561523A (en) | Wind power blade I-shaped web die and preparation method thereof | |
CN104912450A (en) | Integrally formed composite door leaf and manufacturing method of composite door leaf | |
CN109927310A (en) | Foam core composite material process planning | |
CN102806616B (en) | Novel method for manufacturing wind turbine blade rib plate die |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130206 Termination date: 20191026 |
|
CF01 | Termination of patent right due to non-payment of annual fee |