CN101979800B - Electric climbing formwork system - Google Patents

Electric climbing formwork system Download PDF

Info

Publication number
CN101979800B
CN101979800B CN201010524255XA CN201010524255A CN101979800B CN 101979800 B CN101979800 B CN 101979800B CN 201010524255X A CN201010524255X A CN 201010524255XA CN 201010524255 A CN201010524255 A CN 201010524255A CN 101979800 B CN101979800 B CN 101979800B
Authority
CN
China
Prior art keywords
bearing bracket
formwork
guide rail
support
chain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201010524255XA
Other languages
Chinese (zh)
Other versions
CN101979800A (en
Inventor
余志钢
郝海涛
鲁成胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co.,Ltd.
Original Assignee
BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co Ltd filed Critical BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co Ltd
Priority to CN201010524255XA priority Critical patent/CN101979800B/en
Publication of CN101979800A publication Critical patent/CN101979800A/en
Application granted granted Critical
Publication of CN101979800B publication Critical patent/CN101979800B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to an electric climbing formwork system, which is used for the construction of cast-in-place concrete walls. The electric climbing formwork system comprises a formwork system, a branch formwork support body, an outrigger, and parts such as a working platform, climbing equipment, a wall-attached support, a guide rail, an anti-dropping device, a control system and the like, wherein the guide rail is in longitudinal sliding connection with the wall-attached support and the outrigger respectively; the branch formwork support body and the outrigger are in transverse sliding connection; the climbing of the formwork system and the working platform is realized through alternative rising and bearing in place of the guide rail and the outrigger; mold opening and mold closing of the formwork system are realized through the sliding of the branch formwork support body and the outrigger; the climbing equipment consists of a chain and an electric block; the chain encircles the upper end and the lower end of the guide rail and the outrigger by a pulley block; and the electric block rotates positively and reversely to drive the outrigger and the guide rail to rise alternatively and bear in place so as to realize the climbing of the formwork system and the working platform. The invention has the advantages that: the electric climbing formwork system is convenient to use, is easy to assemble and disassemble and has high safety performance.

Description

Electronic jumping formwork system
Technical field
The invention belongs to building operations equipment, relate in particular to a kind of electronic jumping formwork system.
Background technology
In China, along with high-rise and super highrise building emerge in multitude is accelerated in the high speed development of urban construction scale and the increasing of national urbanization pace of construction; High building in the city is more and more intensive; The construction plant is more and more narrower, and the template of the manual work of traditional conventional lifting is because " thick, stupid; heavy " faces abominable conditions of work such as limit installation with the serious tower crane and a large amount of of relying on, and more and more is difficult to adapt to high level and the needs of super highrise building of the Urban Large scale of high speed.At present, the outer creeping formwork plate body of the hydraulic pressure that some countries produce system is also introduced by China and uses.These outer creeping formwork plate bodys systems because have that the Synchronization Control of a plurality of hydraulic systems is difficult to solve, the leakage of hydraulic oil brings the defectives such as fall arrest poor performance of pollution, product to structure wall, not only has operating difficulties, also has potential safety hazard.Therefore design a kind of easy to usely, peace is torn open simple, and the electronic jumping formwork system that security performance is good is the needs in market.
Summary of the invention
The object of the invention is to overcome the defective of prior art, provides a kind of easy to use, and peace is torn open simple, the electronic jumping formwork system that security performance is good.
The electronic jumping formwork of the present invention system is a kind of equipment that is used for in-situ concrete wall construction, its structure comprise template system, support shuttering the formwork support body, support the formwork support body bearing bracket, be fitted in the platform on the bearing bracket; Be used to be packed in vertical sliding guide rail, the vertical sliding bearing bracket of joining of guide rail of joining of attached wall bearing of concrete wall; Formwork support body level cunning fits on the bearing bracket, is equipped with falling proof device and lifting means between guide rail and the bearing bracket, and its special feature is; Said lifting means is made up of the electric block of flexible chain and drive flexible chain; Said flexible chain one end the rising to the bait of assembly pulley that be linked and packed, the chain other end passes the electric block on the bearing bracket, walks around tractive structure and fixed block group on the bearing bracket; The following hook of assembly pulley is linked and packed; Said rising to the bait is connected with the guide rail upper end, and said hook down is connected with the guide rail lower end, and the main story through electric block after the chain tightens is climbed lifting mutually with the alternately load-bearing that realizes bearing bracket and guide rail of reversing.
As optimization; The grid type cross bar is set on guide rail; Falling proof device is set on bearing bracket; Said falling proof device be one with the grid type cross bar of the guide rail roughly pocket-wheel of engaged transmission and the assembly of a unidirectional centering block, in order to realize bearing bracket climb with the course of work in the short distance fall arrest.
As optimization; The mechanism that drives formwork support body horizontal die sinking matched moulds on bearing bracket is a general Electric Chain Blocks; The main hook of electric block is hooked on the bearing bracket bottom; Chain one end walks around the bearing bracket front end through assembly pulley and the formwork support body is affixed, and the chain other end walks around the bearing bracket rear end through assembly pulley and the formwork support body is affixed.Realize the die sinking and the matched moulds of template system after the chain tightens through rotating and reverse of cucurbit.
In sum, the present invention is a kind of construction equipment of in-situ concrete wall, comprises parts such as template system, formwork support body, bearing bracket and platform, lifting means, attached wall bearing, guide rail, falling proof device.Said lifting means is made up of flexible chain and motor, and said flexible chain realizes that around guide rail two ends and bearing bracket the alternately load-bearing of bearing bracket and guide rail is climbed mutually; The die sinking mold closing mechanism of said formwork support body is made up of flexible chain and motor; Said flexible chain makes template system on bearing bracket, slide through electronic control and realizes its die sinking matched moulds through being connected with described template system around described bearing bracket front end rear end; Described falling proof device is arranged on the bearing bracket, and grid type cross bar and the organic fall arrest function that realizes support body that cooperates of falling proof device are set on the guide rail.
The electronic jumping formwork of the present invention system; Practicality simple to operate, convenient to use, security of operation is orderly; Equipped electronic stripper apparatus has realized that mechanization is anti-fall automatically, and the integral body or the packet fragmentation that are adapted to high-rise and super highrise building core tube inner and outer template system are climbed.
Description of drawings
Fig. 1 is the cross-sectional side structural representation of the electronic jumping formwork of the present invention system;
Fig. 2 is the main TV structure sketch map of the electronic jumping formwork of the present invention system;
Fig. 3 is the structural representation of falling proof device embodiment in the electronic jumping formwork of the present invention system;
Fig. 4 is a lifting means structural representation in the electronic jumping formwork of the present invention system;
Fig. 5 is lifting means and guide rail and a bearing bracket connected mode sketch map in the electronic jumping formwork of the present invention system;
Fig. 6 is a die sinking matched moulds electric driver configuration status structural representation in the electronic jumping formwork of the present invention system;
Fig. 7 is the course of work associating sketch map of six steps of the electronic jumping formwork of the present invention system.Among the figure: the first step is that the first floor is built; Second step is for installing formwork support body (bearing frame) and support shuttering (template); The 3rd step is for building second layer concrete; The 4th step was die sinking, installation lifting means (Hoisting System), and the 5th step, the 6th step was installation frame body bottom entering normal circulation in order to promote first floor.
Represented parts or the position of label does among the figure,
1-formwork support body 2-bearing bracket 3-attached wall bearing 4-guide rail 5-flexible chain
6-falling proof device 7-platform 10-structure wall 11-template system
41-grid type cross bar 51-electric block 52-tractive structure 53-fixed block group 54-rises to the bait
The unidirectional centering block of hook 60-pocket-wheel 61-under the 55-.
The specific embodiment
As shown in the figure, the electronic jumping formwork of the present invention system is a kind of construction equipment of in-situ concrete wall, its structure comprise template system 11, support shuttering formwork support body 1, support formwork support body 1 bearing bracket 2, be fitted in the platform 7 on the bearing bracket; Be used to be packed in attached wall bearing 3 vertical sliding guide rail 4, the guide rail 4 vertical sliding bearing brackets 2 of joining of joining of concrete wall 10, be fitted in the platform 7 on the bearing bracket 2; Formwork support body 1 level cunning fits on the bearing bracket 2, is furnished with falling proof device 6 between guide rail 4 and the bearing bracket 2, is fitted with lifting means between guide rail 4 and the bearing bracket 2; Said lifting means is made up of the electric block 51 of flexible chain 5 and drive flexible chain.What said flexible chain 5 one ends had been linked and packed assembly pulley rises to the bait 54; Chain 5 other ends pass the electric block 51 on the bearing bracket 2; Walk around tractive structure 52 and fixed block group 53 on the bearing bracket 2, the following hook 55 of the assembly pulley that has been linked and packed, said rising to the bait 54 is connected with guide rail 4 upper ends; Said hook 55 down is connected with guide rail 4 lower ends, and the main story through electric block after the chain tightens is climbed lifting mutually with the alternately load-bearing that realizes bearing bracket and guide rail of reversing.
Falling proof device 6 is the rotatable reverse then one-way movement mechanisms of jam of forward: grid type cross bar 41 is set on the guide rail 4, the pocket-wheel 60 that cooperates with cross bar 41 is set on the bearing bracket 2, the unidirectional centering block 61 that cooperates with pocket-wheel 60 further is set again.
The jumping formwork system climbs and the course of work is to realize fall arrest like this: when guide rail 4 climbs, unidirectional centering block 61 is shown that at Fig. 3 the position turns over turnback and place, star-wheel 60 as Fig. 3 show the no jam of clockwise rotation, and guide rail 4 climbs smoothly and puts in place; When bearing bracket 2 climbs, unidirectional centering block 61 is shown placement like Fig. 3, star-wheel 60 shows the anticlockwise rotation in position like Fig. 3, and bearing bracket 2 climbs smoothly and puts in place; Unidirectional centering block 61 shows placement like Fig. 3; Bearing bracket 2 is as falling downwards in the process of climbing or in the course of work; Then star-wheel 60 can as Fig. 3 show that clockwise rotates, can be blocked by unidirectional centering block 61 during the very little angle of one of star-wheel 60 rotation, prevented bearing bracket 2 continue fall.
Formwork support body 1 level cunning fits on the bearing bracket 2; Driving formwork support body 1 is a general Electric Chain Blocks along the mechanism of the die sinking matched moulds that bearing bracket 2 moves horizontally; The main hook of electric block 51 is hooked on bearing bracket 2 bottoms; One end of flexible chain 5 walk around bearing bracket 2 front ends through assembly pulley and formwork support body 1 affixed, the other end of chain 5 walk around bearing bracket 2 rear ends through assembly pulley and formwork support body 1 affixed.Chain 5 is tightened rotate and reverse die sinking and the matched moulds of realizing template system of back through cucurbit.

Claims (3)

1. an electronic jumping formwork system is used for the in-situ concrete wall construction, its structure comprise template system, support shuttering the formwork support body, support the formwork support body bearing bracket, be fitted in the platform on the bearing bracket; Be used to be packed in that the attached wall bearing of concrete wall is vertical slidingly joins that guide rail, guide rail are vertical slidingly joins bearing bracket, formwork support body level cunning fits on the bearing bracket, is equipped with falling proof device and lifting means between guide rail and the bearing bracket; It is characterized in that; Said lifting means is made up of the electric block of flexible chain and drive flexible chain, said flexible chain one end the rising to the bait of assembly pulley that be linked and packed, and the flexible chain other end passes the electric block on the bearing bracket; Walk around tractive structure and fixed block group on the bearing bracket; The be linked and packed following hook of assembly pulley, said rising to the bait is connected with the guide rail upper end, and said time hook is connected with the guide rail lower end.
2. electronic jumping formwork according to claim 1 system is characterized in that said falling proof device is that the grid type cross bar is set on guide rail, the pocket-wheel that cooperates with cross bar is set, the unidirectional centering block that further again setting cooperates with pocket-wheel on bearing bracket.
3. electronic jumping formwork according to claim 1 and 2 system; It is characterized in that; The mechanism that drives formwork support body horizontal die sinking matched moulds on bearing bracket is a general Electric Chain Blocks; The main hook of Electric Chain Blocks is hooked on the bearing bracket bottom, and an end of Electric Chain Blocks chain walks around the bearing bracket front end through assembly pulley and the formwork support body is affixed, and the Electric Chain Blocks chain other end walks around the bearing bracket rear end through assembly pulley and the formwork support body is affixed.
CN201010524255XA 2010-10-29 2010-10-29 Electric climbing formwork system Active CN101979800B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010524255XA CN101979800B (en) 2010-10-29 2010-10-29 Electric climbing formwork system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010524255XA CN101979800B (en) 2010-10-29 2010-10-29 Electric climbing formwork system

Publications (2)

Publication Number Publication Date
CN101979800A CN101979800A (en) 2011-02-23
CN101979800B true CN101979800B (en) 2012-05-09

Family

ID=43600334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010524255XA Active CN101979800B (en) 2010-10-29 2010-10-29 Electric climbing formwork system

Country Status (1)

Country Link
CN (1) CN101979800B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155091B (en) * 2011-03-17 2012-11-21 北城致远集团有限公司 Creeping formwork platform
CN103883120B (en) * 2014-03-25 2016-04-20 中国三冶集团有限公司 A kind of creeping formwork structure with auto-lock function
CN105908967A (en) * 2016-06-29 2016-08-31 江苏省苏中建设集团股份有限公司 Self-elevating elevator shaft shear wall creeping formwork operation platform and construction method thereof
CN109424503B (en) * 2017-09-01 2020-07-14 赵晓军 Installation method of center tower and construction method of tower barrel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4403460A (en) * 1981-10-01 1983-09-13 Pittsburgh-Des Moines Corporation Method of erecting an elevated tank using formwork
CN2197410Y (en) * 1993-06-05 1995-05-17 唐玉霞 Scaffolding installation
US5630482A (en) * 1993-01-27 1997-05-20 Peri Gmbh Climbing device, in particular for a climbing scaffold
CN2670497Y (en) * 2003-11-13 2005-01-12 上海市第一建筑有限公司 Hydraulic drop-proofing system for climbing formwork
CN101319560A (en) * 2008-07-08 2008-12-10 上海建工股份有限公司 Double-acting integral hydraulic automatic lifting platform system and construction method using the same

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102006029653B4 (en) * 2006-06-28 2009-02-12 Doka Industrie Gmbh Lifting platform and method for building a lifting platform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4403460A (en) * 1981-10-01 1983-09-13 Pittsburgh-Des Moines Corporation Method of erecting an elevated tank using formwork
US5630482A (en) * 1993-01-27 1997-05-20 Peri Gmbh Climbing device, in particular for a climbing scaffold
CN2197410Y (en) * 1993-06-05 1995-05-17 唐玉霞 Scaffolding installation
CN2670497Y (en) * 2003-11-13 2005-01-12 上海市第一建筑有限公司 Hydraulic drop-proofing system for climbing formwork
CN101319560A (en) * 2008-07-08 2008-12-10 上海建工股份有限公司 Double-acting integral hydraulic automatic lifting platform system and construction method using the same

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
浦键.爬升模板工艺在超高层建筑筒体施工中的应用.《应用能源技术》.2007,(第2期),第5-9页. *

Also Published As

Publication number Publication date
CN101979800A (en) 2011-02-23

Similar Documents

Publication Publication Date Title
CN101979800B (en) Electric climbing formwork system
CN201843335U (en) Electric climbing formwork device
CN203412327U (en) Rotary lift type stereo garage
CN203559582U (en) Integrated hydraulic creeping formwork
CN106400951B (en) A kind of level and vertical structure method for synchronously constructing of super high-rise building
CN203702179U (en) Single-track tunnel lining trolley with ventilating duct
CN104343263A (en) Rotary lifting type three-dimensional garage
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
CN100526581C (en) Reciprocating self-climbing type climbing form system and its climbing form method
CN202090591U (en) Lift type climbing formwork of building operations
KR20140130688A (en) A scaffold with an automatic installation characteristic
CN201962944U (en) Hydraulic climbing formwork for building construction
CN104727545A (en) Large water tower cylinder hydraulic slip-form vertical-transportation system and method
CN107043060A (en) A kind of installation method of inverse formula installation lift
CN201224661Y (en) Apparatus for mounting indoor large-sized apparatus in small space
CN105540446A (en) Interior-climbing type lifting platform
CN102718109A (en) Method for transforming construction elevator into passenger-goods elevator
CN103867215B (en) The overall lining trolley of a kind of freeway tunnel groove
CN108286332A (en) A kind of concrete of crossing soars aloft beam from climbing monoblock type bylinder system and construction method
CN105952123B (en) A kind of vertical lifting mechanism of the automatic Semi-automatic plastering machine of metope
CN103991802A (en) Large tower crane capable of carrying driver
CN203112386U (en) Tower type truss mounting structure without assistance of high altitude hoisting equipment
CN103101847A (en) Tower type truss installing structure and method without cooperation with altitude hoisting equipment
CN102587644B (en) Single-side side wall slip form and construction method
CN203555689U (en) Electric hanging basket for vertical shaft

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
GR01 Patent grant
C14 Grant of patent or utility model
CP03 "change of name, title or address"

Address after: 101113 8 Guang Li street, Tongzhou District Industrial Development Zone, Beijing

Patentee after: Sunrise safety technology (Beijing) Co., Ltd.

Address before: 101104 No. 8, Zhang Feng Road, Niu Bao Tun, Tongzhou District, Beijing.

Patentee before: Beijing Tosun Technology Development Co., Ltd.

Address after: 101113 8 Guang Li street, Tongzhou District Industrial Development Zone, Beijing

Patentee after: Sunrise safety technology (Beijing) Co., Ltd.

Address before: 101104 No. 8, Zhang Feng Road, Niu Bao Tun, Tongzhou District, Beijing.

Patentee before: Beijing Tosun Technology Development Co., Ltd.

CP03 "change of name, title or address"
TR01 Transfer of patent right

Effective date of registration: 20210120

Address after: 101149 3-027, building 2, 7 Yunbin Road, Tongzhou District, Beijing

Patentee after: BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co.,Ltd.

Address before: 101113 8 Guang Li street, Tongzhou District Industrial Development Zone, Beijing

Patentee before: Sunrise safety technology (Beijing) Co.,Ltd.

TR01 Transfer of patent right