CN101941028B - Method for correcting spatially-downwarped steel beam - Google Patents

Method for correcting spatially-downwarped steel beam Download PDF

Info

Publication number
CN101941028B
CN101941028B CN2010102797392A CN201010279739A CN101941028B CN 101941028 B CN101941028 B CN 101941028B CN 2010102797392 A CN2010102797392 A CN 2010102797392A CN 201010279739 A CN201010279739 A CN 201010279739A CN 101941028 B CN101941028 B CN 101941028B
Authority
CN
China
Prior art keywords
steel
steel beam
girder
box
hydraulic jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2010102797392A
Other languages
Chinese (zh)
Other versions
CN101941028A (en
Inventor
王永善
黄金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN2010102797392A priority Critical patent/CN101941028B/en
Publication of CN101941028A publication Critical patent/CN101941028A/en
Application granted granted Critical
Publication of CN101941028B publication Critical patent/CN101941028B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种空间下挠钢梁矫正方法,其特征是:制作一个矫正装置,包括一个箱型梁,在箱型梁的两端各设有一组成对的上部有矩形孔的挂臂组,将箱型梁吊在要矫正的钢梁的正下方,将箱型梁悬挂在要矫正的钢梁的下方,在箱型梁上放置液压千斤顶,用电动液压油泵给液压千斤顶供油,液压千斤顶向上伸长,顶压钢梁的下挠处,使钢梁受到向上的压力,经过顶压、测量、再顶压、再测量,反复试顶试测,直至钢梁上挠度值达到矫正要求为止。其优点是:利用钢梁本身作为支撑,将箱型梁挂于其上,用液压千斤顶顶压下挠处,达到矫正的目的,避免了更换钢梁所造成的成本高、工期长的问题。

Figure 201010279739

The invention relates to a method for correcting a steel beam deflected in space, which is characterized in that: a correcting device is made, which includes a box-shaped beam, and a pair of hanging arm groups with rectangular holes on the upper part are respectively arranged at both ends of the box-shaped beam, Hang the box girder directly below the steel girder to be corrected, hang the box girder under the steel girder to be corrected, place a hydraulic jack on the box girder, use an electric hydraulic oil pump to supply oil to the hydraulic jack, and the hydraulic jack Stretch upward, press the downward deflection of the steel beam, so that the steel beam is subjected to upward pressure, after pressing, measuring, pressing again, measuring again, repeated testing and testing, until the deflection value of the steel beam meets the correction requirements . Its advantages are: use the steel beam itself as a support, hang the box girder on it, press down the deflection with a hydraulic jack to achieve the purpose of correction, and avoid the problems of high cost and long construction period caused by replacing the steel beam.

Figure 201010279739

Description

空间下挠钢梁矫正方法Correction method of deflected steel beam in space

技术领域 technical field

本发明涉及一种空间下挠钢梁矫正方法,用于煤气直立炉等大型炉子的大修工程中炉底成组钢梁下挠严重,但又不易拆换的原位矫正,属于空间下挠钢梁矫正技术领域。The invention relates to a method for correcting steel beams deflected under space, which is used for in-situ correction of steel beams at the bottom of a group of steel beams that are seriously deflected in the overhaul project of large furnaces such as gas vertical furnaces, but is not easy to be disassembled and replaced, and belongs to steel deflected under space Beam orthotics technology field.

背景技术 Background technique

传统大修工程对一些变形比较严重的部件采取更换的办法。但在某些情况下,由于工程的工期、费用等因素的制约,必须采取矫正的办法。In the traditional overhaul project, some parts with serious deformation are replaced. However, in some cases, corrective measures must be taken due to the constraints of the construction period and cost of the project.

煤气直立炉为是专门用于干馏煤而取得煤气的工业炉,其主产品为煤气,副产品主要有焦炭及煤气净化时产生的副产品,其主要结构是由耐火砖砌筑而成的炉体坐落在高约8米左右的钢结构炉底之上,同时由炉柱、横梁、炉顶拉条等组成护炉结构。炉顶上面安装有装煤、吸取煤气等配套设备;炉底下面安装有下落焦炭的设备。其基本生产工艺是:由炉顶装煤,煤在炉体内被高温干馏,产生煤气,由炉顶吸取煤气并送入化产工艺,焦炭由炉底漏下。炉体经过几年的生产,大多数砌体及各种设备均有不同程度的损坏需要大修,大修时砌体需全部拆除砌新砖,各种设备也被拆除,且视技术状况决定更换或修复。在大修时,往往炉体钢结构尚可使用,由于炉底钢梁上承炉体及相关设备的重量,下挂出焦设备,载荷较重,经测量炉底钢梁严重超差,一般各钢梁下挠20-50mm不等。如果采取更换的办法,不仅浪费了炉底钢梁的料,而且还需将护炉钢结构及相关设备等拆除并安装,这样做,工程量,工期,费用都将加大。如果能够矫正使其达到上挠1-5mm,就可避免更换所带来的弊端,大大节约大修成本,节省工期。然而,目前市场上没有对炉底钢梁的下挠变形进行原位矫正的专用或通用设备,也没有针对炉底钢梁的下挠变形进行原位矫正的方法。The gas vertical furnace is an industrial furnace specially used to dry coal to obtain gas. Its main product is gas, and its by-products mainly include coke and by-products generated during gas purification. Its main structure is a furnace body made of refractory bricks. On the steel structure furnace bottom with a height of about 8 meters, the furnace protection structure is composed of furnace columns, beams, and furnace top bracing. Coal charging, gas absorption and other supporting equipment are installed on the top of the furnace; equipment for falling coke is installed under the bottom of the furnace. The basic production process is as follows: coal is charged from the top of the furnace, the coal is dry-distilled at high temperature in the furnace body to produce gas, the gas is absorbed from the top of the furnace and sent to the chemical production process, and coke is leaked from the bottom of the furnace. After several years of production of the furnace body, most of the masonry and various equipment have been damaged to varying degrees and need to be overhauled. During the overhaul, the masonry must be completely removed and new bricks laid, and various equipment must also be dismantled. Depending on the technical condition, it is decided to replace or repair. During the overhaul, the steel structure of the furnace body is often still usable. Due to the weight of the furnace body and related equipment on the furnace bottom steel beam, the coke discharge equipment is hung below, and the load is heavy. The steel beams on the furnace bottom are seriously out of tolerance. The downward deflection ranges from 20-50mm. If the method of replacement is adopted, not only the material of the furnace bottom steel beam is wasted, but also the steel structure of the furnace protection and related equipment must be dismantled and installed. In this way, the amount of work, the construction period and the cost will be increased. If it can be corrected to achieve an upward deflection of 1-5mm, the disadvantages caused by replacement can be avoided, and the overhaul cost and construction period can be greatly saved. However, there is currently no special or general equipment for in-situ correction of the deflection deformation of the furnace bottom steel beam on the market, nor is there any method for in-situ correction of the downward deflection deformation of the furnace bottom steel beam.

发明内容 Contents of the invention

本发明的目的是针对煤气直立炉等大型炉子的大修工程中炉底成组钢梁下挠严重,而采取更换的办法所存在的弊端,提供一种空间下挠钢梁矫正方法。The object of the present invention is to provide a method for correcting the space deflection steel beams for the serious deflection of the steel beams at the bottom of the furnace in the overhaul project of large furnaces such as gas vertical furnaces and the method of replacement.

本发明的空间下挠钢梁矫正方法是:制作一个矫正装置,包括一个箱型梁,在箱型梁的两端各设有一组成对的上部有矩形孔的挂臂组,用吊装工具将箱型梁吊在要矫正的钢梁的正下方,向上提箱型梁,使箱型梁上的挂臂组插在要矫正的钢梁的两侧,将钢梁夹在每组挂臂组的两个挂臂之间,在每组挂臂组的两个挂臂的矩形孔中分别插入挂销,将箱型梁悬挂在要矫正的钢梁的下方,在箱型梁上放置液压千斤顶,用电动液压油泵给液压千斤顶供油,液压千斤顶向上伸长,顶压钢梁的下挠处,使钢梁受到向上的压力,经过顶压、测量、再顶压、再测量,反复试顶试测,直至钢梁上挠度值达到矫正要求为止。The method for correcting steel beams under space deflection of the present invention is as follows: make a correcting device, including a box-shaped girder, a pair of hanging arm groups with rectangular holes in the upper part are respectively arranged at both ends of the box-shaped girder, and the box is lifted by a hoisting tool. Hang the shaped girder directly below the steel girder to be corrected, lift the box girder upwards so that the hanging arm groups on the box girder are inserted on both sides of the steel girder to be corrected, and clamp the steel girder between the two hanging arm groups of each set. Between the two hanging arms, insert the hanging pins in the rectangular holes of the two hanging arms of each group of hanging arms respectively, hang the box girder under the steel beam to be corrected, place a hydraulic jack on the box girder, and use The electric hydraulic oil pump supplies oil to the hydraulic jack, and the hydraulic jack stretches upwards to press against the downward deflection of the steel beam, so that the steel beam is subjected to upward pressure. After pressing, measuring, pressing again, and measuring again, repeated testing , until the deflection value on the steel beam meets the correction requirements.

本发明的优点是:利用钢梁本身作为支撑,将箱型梁挂于其上,用液压千斤顶顶压下挠处,达到矫正的目的,避免了更换钢梁所造成的成本高、工期长的问题。The advantages of the present invention are: use the steel beam itself as a support, hang the box girder on it, press down the deflection with a hydraulic jack to achieve the purpose of correction, and avoid the high cost and long construction period caused by the replacement of the steel beam. question.

附图说明 Description of drawings

图1是空间下挠钢梁矫正装置的结构示意图;Fig. 1 is a structural schematic diagram of a deflected steel beam correction device in space;

图2是图1的左视图;Fig. 2 is the left view of Fig. 1;

图3是空间下挠钢梁矫正方法的原理图;Fig. 3 is the schematic diagram of the correction method of the deflected steel beam under the space;

图4是图3的A--A向视图。Fig. 4 is a view from A--A direction of Fig. 3 .

具体实施方式 Detailed ways

实施例:对煤气直立炉炉底成组钢梁下挠的矫正。Example: Correction of deflection of grouped steel beams at the bottom of a gas vertical furnace.

参照附图,要矫正的钢梁9的基本形状为工字型,总高600mm,上下翼缘宽200mm、厚30mm、腹板厚20mm;实现制做空间下挠钢梁矫正装置,该矫正装置包括一个箱型梁1,箱形梁1全部用20mm钢板制成,在箱型梁1的两端各焊有一组成对的上部有矩形孔3的挂臂组2。矫正方法是:用吊装工具将箱型梁1吊在要矫正的钢梁9的正下方,向上提箱型梁1,使箱型梁1上的挂臂组2插在要矫正的钢梁9的两侧,将钢梁9夹在每组挂臂组的两个挂臂之间,在每组挂臂组的两个挂臂的矩形孔3中分别插入挂销4,将箱型梁1悬挂在要矫正的钢梁9的下方,在箱型梁1上放置液压千斤顶5,在箱型梁1的下方地面上设置一个可移动工作平台8,其上可以载人和放置必要的工具。用电动液压油泵7给液压千斤顶5供油,电动液压油泵7放置在可移动工作平台8,通过高压油管6连接液压千斤顶5,电动液压油泵7接入380v电源。当启动液压泵7给油时千斤顶5的活塞杆向上顶出,顶压钢梁的下挠处,使钢梁受到向上的压力,经过顶压、测量、再顶压、再测量,反复试顶试测。顶压前在钢梁9上面安装测量用拉直的

Figure GSB00000711239800021
1mm钢线,其下表面较钢梁两端的上表面高50mm,用钢尺在钢梁的任一点可测量到该点与钢线下表面的距离,若大于50mm,表示下挠,小于50mm,表示上挠,顶压时将千斤顶5置于下挠度最大的点,(大多数在梁的中点)这样在顶压时可随时测量到上挠的程度,便可发令停压。直至达到有一定上挠度值(1-5mm)的要求为止。当矫正完一根钢梁后,用吊装工具将空间下挠钢梁矫正装置吊挂于另一根需的钢梁上,同时移动工作平台8,重复矫正动作。依次从成组钢梁的一端逐根矫正至另一端。将全部钢梁矫正完毕,直至所有钢梁上挠度值达到矫正要求为止。With reference to the accompanying drawings, the basic shape of the steel beam 9 to be corrected is I-shaped, with a total height of 600mm, a width of 200mm on the upper and lower flanges, a thickness of 30mm, and a thickness of 20mm on the web; to realize the correction device for the downward deflection of the steel beam in the manufacturing space, the correction device Comprising a box beam 1, the box beam 1 is all made of 20mm steel plates, and a pair of hanging arm groups 2 with rectangular holes 3 are respectively welded at the two ends of the box beam 1. The correction method is: hang the box girder 1 directly below the steel girder 9 to be corrected with a hoisting tool, lift the box girder 1 upwards, and insert the hanging arm group 2 on the box girder 1 into the steel girder 9 to be corrected. On both sides, clamp the steel beam 9 between the two hanging arms of each group of hanging arms, insert the hanging pins 4 into the rectangular holes 3 of the two hanging arms of each group of hanging arms, and suspend the box beam 1 Below the steel beam 9 to be corrected, a hydraulic jack 5 is placed on the box girder 1, and a movable working platform 8 is set on the ground below the box girder 1, on which people and necessary tools can be placed. The electric hydraulic oil pump 7 is used to supply oil to the hydraulic jack 5, the electric hydraulic oil pump 7 is placed on the movable work platform 8, the hydraulic jack 5 is connected through the high pressure oil pipe 6, and the electric hydraulic oil pump 7 is connected to a 380v power supply. When the hydraulic pump 7 is started to supply oil, the piston rod of the jack 5 is ejected upwards, and presses the downward deflection of the steel beam, so that the steel beam is subjected to upward pressure. After pressing, measuring, pressing again, and measuring again, try repeatedly test. Before the top pressure, install the straightened steel beam for measurement on the steel beam 9.
Figure GSB00000711239800021
1mm steel wire, the lower surface of which is 50mm higher than the upper surface of both ends of the steel beam. Use a steel ruler to measure the distance between this point and the lower surface of the steel wire at any point of the steel beam. If it is greater than 50mm, it means downward deflection. If it is less than 50mm, Represent upward deflection, and jack 5 is placed on the point of maximum deflection during jacking, (mostly at the midpoint of the beam) so that the degree of upward deflection can be measured at any time when jacking up, and the pressure can be stopped. Until the requirement of a certain upper deflection value (1-5mm) is reached. After correcting a steel beam, use the hoisting tool to hang the steel beam correction device under the space on another required steel beam, and move the working platform 8 at the same time to repeat the correcting action. Correct one by one from one end of the group of steel beams to the other end. Complete the correction of all steel beams until the deflection values on all steel beams meet the correction requirements.

Claims (1)

1.一种空间下挠钢梁矫正方法,其特征是:制作一个矫正装置,包括一个箱型梁,在箱型梁的两端各设有一组成对的上部有矩形孔的挂臂组,用吊装工具将箱型梁吊在要矫正的钢梁的正下方,向上提箱型梁,使箱型梁上的挂臂组插在要矫正的钢梁的两侧,将钢梁夹在每组挂臂组的两个挂臂之间,在每组挂臂组的两个挂臂的矩形孔中分别插入挂销,将箱型梁悬挂在要矫正的钢梁的下方,在箱型梁上放置液压千斤顶,用电动液压油泵给液压千斤顶供油,液压千斤顶向上伸长,顶压钢梁的下挠处,使钢梁受到向上的压力,经过顶压、测量、再顶压、再测量,反复试顶试测,直至钢梁上挠度值达到矫正要求为止。1. A correction method for deflected steel beams in a space is characterized in that: make a correction device, including a box beam, and a pair of hanging arm groups with rectangular holes are respectively arranged on the two ends of the box beam, The hoisting tool hangs the box girder directly below the steel girder to be corrected, lifts the box girder upwards, inserts the hanging arm groups on the box girder on both sides of the steel girder to be corrected, and clamps the steel girder on each set of hanging arms. Between the two hanging arms of the arm group, insert the hanging pins into the rectangular holes of the two hanging arms of each arm group, hang the box girder under the steel beam to be corrected, and place it on the box girder The hydraulic jack uses an electric hydraulic oil pump to supply oil to the hydraulic jack. The hydraulic jack extends upwards and presses the downward deflection of the steel beam, so that the steel beam is subjected to upward pressure. After pressing, measuring, pressing again, and measuring again, repeat Test the top until the deflection value on the steel beam meets the correction requirements.
CN2010102797392A 2010-09-01 2010-09-01 Method for correcting spatially-downwarped steel beam Active CN101941028B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102797392A CN101941028B (en) 2010-09-01 2010-09-01 Method for correcting spatially-downwarped steel beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102797392A CN101941028B (en) 2010-09-01 2010-09-01 Method for correcting spatially-downwarped steel beam

Publications (2)

Publication Number Publication Date
CN101941028A CN101941028A (en) 2011-01-12
CN101941028B true CN101941028B (en) 2012-08-08

Family

ID=43433343

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102797392A Active CN101941028B (en) 2010-09-01 2010-09-01 Method for correcting spatially-downwarped steel beam

Country Status (1)

Country Link
CN (1) CN101941028B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102728799B (en) * 2012-07-23 2013-12-18 新余钢铁集团有限公司 Transformation correction device for water spraying frame of foot roller of slab caster crystallizer
CN105382054A (en) * 2015-12-10 2016-03-09 中国二冶集团有限公司 Correcting method for plate-like steel member of symmetrical structure in constructional projects
CN113680825B (en) * 2021-08-05 2023-05-12 中国二十冶集团有限公司 Deflection deformation correction device and method for upper frame of vertical roller mill
CN115505722B (en) * 2022-09-27 2024-07-23 中车长江车辆有限公司 Box girder adjusting and straightening method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5934199A (en) * 1996-09-06 1999-08-10 Siemens Aktiengesellschaft Apparatus for temporarily increasing the load-bearing capacity of bridge girders
BE1013910A3 (en) * 2001-01-10 2002-12-03 Immo Emergo Nv METHOD FOR REINFORCING A CONSTRUCTION PART.
CN200978524Y (en) * 2006-10-31 2007-11-21 江西蓝天学院 Main beam down deflection correction device
CN201280390Y (en) * 2008-09-05 2009-07-29 济南二机床集团有限公司 Large-tonnage suspending beam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5934199A (en) * 1996-09-06 1999-08-10 Siemens Aktiengesellschaft Apparatus for temporarily increasing the load-bearing capacity of bridge girders
BE1013910A3 (en) * 2001-01-10 2002-12-03 Immo Emergo Nv METHOD FOR REINFORCING A CONSTRUCTION PART.
CN200978524Y (en) * 2006-10-31 2007-11-21 江西蓝天学院 Main beam down deflection correction device
CN201280390Y (en) * 2008-09-05 2009-07-29 济南二机床集团有限公司 Large-tonnage suspending beam

Also Published As

Publication number Publication date
CN101941028A (en) 2011-01-12

Similar Documents

Publication Publication Date Title
CN101941028B (en) Method for correcting spatially-downwarped steel beam
CN104165807A (en) Large-deflection destruction testing device and method for prestressed concrete plate beam
CN103666494A (en) Coke oven column installation method
CN101831309A (en) Dry quenching furnace chute strut replacing method and device
CN101984078B (en) Installation method for quickly removing and replacing middle-section furnace casing of large blast furnace
CN105627353A (en) Scribing installation technology for boiler film water-cooled walls
CN112080292A (en) Symmetrically hoisting furnace iron protection plate, furnace column structure and installation method
CN107097062B (en) A kind of stacker-reclaimer revolution intersects the replacing options of bearing
CN204638799U (en) Workpiece straightening press
CN202401024U (en) Sidewise bending online correction device for coke pushing rod
CN101625201A (en) Water beam overhauling equipment of walking beam type heating furnace and overhauling method thereof
CN202701040U (en) Girder down-warping repairing device for bridge crane
CN208088136U (en) A kind of girder pushing tow structure based on permanent bridge pier fulcrum
CN204689525U (en) A kind of equipment jacking apparatus being convenient to measure
CN204714472U (en) A kind of hydraulic lifting apparatus for storage tank inversion
CN104880304B (en) A kind of bar-mat reinforcement static mechanical property test device and method of testing
CN204007084U (en) A kind of resilient supporting unit of cement rotary kiln
CN102409119A (en) Deviation-correcting and resetting method for blast furnace body
CN201873448U (en) Correction device for single-beam electric hoist type crane girder
CN207987275U (en) A kind of blast furnace replaces rock drill and lifts trolley
CN202845500U (en) Straightener working roll fastening device
CN102500997B (en) Method for installing lower cross beam of fast forging machine
CN221094069U (en) Coke oven spring brace pressurization fastening device
CN204198281U (en) Support beam of walking beam reheating furnace is changing device more
CN219455356U (en) Device capable of synchronously adjusting tension of suspender

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice
DD01 Delivery of document by public notice

Addressee: Zhang Shaohua

Document name: Notification of Passing Examination on Formalities