CN101938378B - Veneer charging and discharging management system and application method thereof - Google Patents

Veneer charging and discharging management system and application method thereof Download PDF

Info

Publication number
CN101938378B
CN101938378B CN201010286830.7A CN201010286830A CN101938378B CN 101938378 B CN101938378 B CN 101938378B CN 201010286830 A CN201010286830 A CN 201010286830A CN 101938378 B CN101938378 B CN 101938378B
Authority
CN
China
Prior art keywords
veneer
control unit
power
single board
board information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201010286830.7A
Other languages
Chinese (zh)
Other versions
CN101938378A (en
Inventor
刘敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZTE Corp
Original Assignee
ZTE Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZTE Corp filed Critical ZTE Corp
Priority to CN201010286830.7A priority Critical patent/CN101938378B/en
Publication of CN101938378A publication Critical patent/CN101938378A/en
Priority to PCT/CN2011/072606 priority patent/WO2012034396A1/en
Application granted granted Critical
Publication of CN101938378B publication Critical patent/CN101938378B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/02Protocols based on web technology, e.g. hypertext transfer protocol [HTTP]
    • H04L67/025Protocols based on web technology, e.g. hypertext transfer protocol [HTTP] for remote control or remote monitoring of applications

Abstract

The invention discloses a veneer charging and discharging management system and an application method thereof. The veneer charging and discharging management system comprises a management unit and a veneer, wherein the management unit is used for ensuring whether the veneer can be charged or discharged according to the current information of the veneer and transmitting a control message with an ensured result to the veneer; and the veneer is used for receiving the control message transmitted by the management unit and carrying out charging and discharging according to the control message. The veneer charging and discharging management system and the application method thereof are capable of increasing the safety of the veneer and prolonging the service life of the veneer.

Description

Veneer power-on and power-off management system and application process thereof
Technical field
The present invention relates to the communications field, in particular to a kind of veneer power-on and power-off management system and apply the method that this system carries out veneer power-on and power-off management.
Background technology
At optical communication field, as SDH (Synchronous Digital Hierarchy, SDH (Synchronous Digital Hierarchy)) and the transmission equipment such as PTN (Private Telecommunication Network, private wire network) in, an equipment often comprises multiple veneer, in the application, normally directly veneer to be powered on or lower electricity, damage may be caused to veneer, thus reduce the veneer life-span, simultaneously also convenient not, flexible on veneer maintenance, cause product cost higher.
Directly to power on for the veneer existed in correlation technique or lower electricity can damage veneer, reduce veneer life-span and problem difficult in maintenance, not yet propose effective solution at present.
Mention in correlation technique, in present applications ' the tail must be taken, normally directly veneer to be powered on or lower electricity, damage may be caused to veneer, thus reduce the veneer life-span, simultaneously also convenient not, flexible on veneer maintenance, cause product cost higher, for solving the problems of the technologies described above, embodiments provide a kind of veneer power-on and power-off management system, as shown in Figure 1, comprise administrative unit 101 and veneer 102, the concrete function of each structure is as follows for concrete structure:
Whether administrative unit 101, can carry out powering on or lower electricity for the single board information determination veneer 102 current according to veneer 102, the control message carrying determination result is sent to veneer 102;
Veneer 102, for the control message that receiving management unit 101 sends, carries out powering on or lower electricity according to control message.
In the present embodiment, use management unit manages veneer, when veneer receives the control message of administrative unit transmission, carry out powering on or lower electricity according to control message, instead of directly power on or lower electricity, avoid directly powering on or lower electricity damages veneer, occur reducing veneer life-span and problem difficult in maintenance, improve the security performance of veneer, extend the life-span of veneer, shorten the time that artificial plug veneer consumes, effectively improve the efficiency of veneer power-on and power-off.
During enforcement, administrative unit 101 can manage at least one veneer 102, can manage one, also can manage two, can also manage more than three, and concrete veneer number is determined according to actual conditions.
In one embodiment, as shown in Figure 2, administrative unit 101 can comprise webmaster 201, decision center 202 and control unit 203:
Webmaster 201, for sending directive command to decision center 202, under directive command comprises Board Power up order and veneer, electricity is ordered;
Whether decision center 202, for receiving directive command, can carry out powering on or lower electricity according to directive command and the current single board information determination veneer 102 of veneer 102, determination result being sent to control unit 203;
Control unit 203, for receiving determination result, being carried at determination result in control message and being sent to veneer 102, controls veneer 102 and carries out powering on or lower electricity.
In one embodiment, structure as shown in Figure 2, decision center 202 can be further used for when directive command is Board Power up order, sends diagnostic command to control unit 203; And the single board information that reception control unit 203 reports, determines whether veneer 102 can power on;
Control unit 203 can be further used for receiving diagnostic command, gathers the single board information that veneer 102 is current, and the single board information of employing is reported to decision center 202.
In one embodiment, structure as shown in Figure 2, decision center 202 can be further used for, when single board information is mated with single board information threshold value, determining that veneer can power on; And, when single board information is not mated with single board information threshold value, determine that veneer does not power on, be in wait state.
During enforcement, single board information threshold value can comprise many-side, and concrete threshold value root single board information is correlated with, such as, single board information is temperature, voltage, board type, power etc., then corresponding single board information threshold value also corresponding temperature threshold, voltage threshold, board type threshold value, the power threshold of comprising, etc.
In one embodiment, control unit 203 can be further used for when single board information is not mated with single board information threshold value, periodically gather the single board information after veneer 102 renewal being in wait state, report to decision center 202, until decision center 202 determines that veneer 102 can power on.
In one embodiment, decision center 202 can be further used for when single board information and the unmatched reason of single board information threshold value be veneer 102 insert slot mistake time, return error code to webmaster 201, concurrent activation command of sending to is to control unit 203;
Webmaster 201 can be further used for prompting user and extract veneer 102;
Control unit 203 can be further used for receiving deactivation command, controls veneer 102 and is in wait state.
In one embodiment, decision center 202 can be further used for when single board information and the unmatched reason of single board information threshold value be that veneer power is excessive, temperature or voltage out-of-limit time, send deactivation command to control unit 203;
Control unit 203 can be further used for receiving deactivation command, controls veneer 102 and is in wait state.
In one embodiment, decision center 202 can be further used for when single board information is mated with single board information threshold value, sends active information to control unit 203;
Control unit 203 can be further used for receiving active information, controls veneer 102 and powers on.
In one embodiment, decision center 202 can be further used for, when directive command is electricity order under veneer, sending deactivation command to control unit 203;
Control unit 203, is further used for receiving deactivation command, controls veneer 102 and carries out lower electricity.
In one embodiment, control unit 203 can be further used for: the single board information periodically gathering lower electric veneer 102, and is reported to decision center 202, until decision center 202 sends activation command.
As can be seen here, in this example, the slot mistake inserted if occur or power consumption is too high or the problem such as voltage out-of-limit time, be not directly extract veneer, and be control veneer to be in wait state, and regularly or single board information can be periodically updated further, reactivate when single board information is mated with single board information threshold value and enable veneer, the utilance of veneer can be improved.
Based on same inventive concept, the embodiment of the present invention additionally provides the method that the veneer power-on and power-off management system shown in a kind of application drawing 1 carries out veneer power-on and power-off management, and its handling process as shown in Figure 3, comprising:
Whether step 302, the administrative unit single board information determination veneer current according to veneer can carry out powering on or lower electricity, and the control message carrying determination result is sent to veneer;
The control message that step 304, veneer receiving management unit send, carries out powering on or lower electricity according to control message.
During enforcement, preferably, administrative unit can comprise webmaster, decision center and control unit, now, in veneer power-on and power-off management method administrative unit determination veneer can power on or lower electricity handling process as shown in Figure 4, comprising:
Step 402, webmaster send directive command to decision center, and under directive command comprises Board Power up order and veneer, electricity is ordered;
Whether step 404, decision center receive directive command, can carry out powering on or lower electricity, determination result is sent to control unit according to directive command and the current single board information determination veneer of veneer;
Step 406, control unit receive determination result, determination result are carried in control message and are sent to veneer, control veneer and carry out powering on or lower electricity.
In embodiments of the present invention, decision center, control unit can be respectively independently module, also can be integrated in other modules, and such as, decision center and control unit can as independently module integration on veneers, and control veneer and directly power on.
In order to scheme is explained clearer, now be described with specific embodiment, in the following embodiments, veneer power-on and power-off management system comprises webmaster, decision center D, upper electric control unit C1, C2 and board B 1, B2, B3, B4, specifically refer to Fig. 5, certainly, upper electric control unit not only comprises C1, C2, veneer also not only comprises B1, B2, B3, B4, represents in the drawings with ellipsis.In addition, because embodiment can relate to multiple scene, at this, multiple scene is illustrated respectively.
Summary of the invention
Main purpose of the present invention is to provide a kind of veneer power-on and power-off management system and application process thereof, directly to power on or lower electricity can damage veneer, reduce veneer life-span and problem difficult in maintenance at least to solve the veneer existed in above-mentioned correlation technique.
According to an aspect of the present invention, provide a kind of veneer power-on and power-off management system, comprise administrative unit and veneer:
For the single board information current according to described veneer, described administrative unit, determines whether described veneer can carry out powering on or lower electricity, and the control message carrying determination result is sent to described veneer;
Described veneer, for receiving the control message that described administrative unit sends, carries out powering on or lower electricity according to described control message.
Preferably, described administrative unit comprises webmaster, decision center and control unit:
Described webmaster, for sending directive command to described decision center, under described directive command comprises Board Power up order and veneer, electricity is ordered;
According to described directive command and the current single board information of described veneer, described decision center, for receiving described directive command, determines whether described veneer can carry out powering on or lower electricity, and determination result is sent to described control unit;
Described control unit, for receiving described determination result, being carried at described determination result in control message and being sent to described veneer, controls described veneer and carries out powering on or lower electricity.
Preferably, described decision center, is further used for when described directive command is Board Power up order, sends diagnostic command to described control unit; And, receive the single board information that described control unit reports, determine whether described veneer can power on;
Described control unit, is further used for receiving described diagnostic command, gathers the single board information that described veneer is current, and the single board information of employing is reported to described decision center.
Preferably, described decision center, is further used for, when described single board information is mated with described single board information threshold value, determining that described veneer can power on; And
When described single board information is not mated with described single board information threshold value, determine that described veneer does not power on, be in wait state.
Preferably, described control unit, is further used for when described single board information is not mated with described single board information threshold value, periodically gathers the single board information after the veneer renewal being in wait state, report to described decision center, until described decision center determines that described veneer can power on.
Preferably, described decision center, be further used for when described single board information and the unmatched reason of described single board information threshold value be described veneer insert slot mistake time, return error code to described webmaster, concurrent activation command of sending to is to described control unit;
Described webmaster, is further used for prompting user and extracts described veneer;
Described control unit, is further used for receiving described deactivation command, controls described veneer and is in wait state.
Preferably, described decision center, be further used for when described single board information and the unmatched reason of described single board information threshold value be that described veneer power is excessive, temperature or voltage out-of-limit time, send deactivation command to described control unit;
Described control unit, is further used for receiving described deactivation command, controls described veneer and is in wait state.
Preferably, described decision center, is further used for when described single board information is mated with described single board information threshold value, sends active information to described control unit;
Described control unit, is further used for receiving described active information, controls described veneer and powers on.
Preferably, described decision center, is further used for, when described directive command is electricity order under veneer, sending deactivation command to described control unit;
Described control unit, is further used for receiving described deactivation command, controls described veneer and carries out lower electricity.
Preferably, described control unit is further used for: the single board information periodically gathering lower electric veneer, and is reported to described decision center, until described decision center sends activation command.
According to a further aspect in the invention, provide and a kind ofly apply the method that above-mentioned veneer power-on and power-off management system carries out veneer power-on and power-off management, described veneer power-on and power-off control system comprises administrative unit and veneer, and described method comprises:
The described administrative unit single board information current according to described veneer determines whether described veneer can carry out powering on or lower electricity, and the control message carrying determination result is sent to described veneer;
Described veneer receives the control message that described administrative unit sends, and carries out powering on or lower electricity according to described control message.
Preferably, when described administrative unit comprises webmaster, decision center and control unit, described method also comprises:
Described webmaster sends directive command to described decision center, and under described directive command comprises Board Power up order and veneer, electricity is ordered;
Described decision center receives described directive command, determines whether described veneer can carry out powering on or lower electricity, and determination result is sent to described control unit according to described directive command and the current single board information of described veneer;
Described control unit receives described determination result, described determination result is carried in control message and is sent to described veneer, controls described veneer and carries out powering on or lower electricity.
Pass through the present invention, administrative unit is adopted to manage veneer, when veneer receives the control message of administrative unit transmission, carry out powering on or lower electricity according to control message, instead of directly power on or lower electricity, avoid directly powering on or lower electricity damages veneer, occur reducing veneer life-span and problem difficult in maintenance, improve the security performance of veneer, extend the life-span of veneer, shorten the time that artificial plug veneer consumes, effectively improve the efficiency of veneer power-on and power-off.
Accompanying drawing explanation
Accompanying drawing described herein is used to provide a further understanding of the present invention, and form a application's part, schematic description and description of the present invention, for explaining the present invention, does not form inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is the structural representation of the veneer power-on and power-off management system that the embodiment of the present invention provides;
Fig. 2 is the structural representation of the administrative unit that the embodiment of the present invention provides;
Fig. 3 is that the veneer power-on and power-off management system that utilizes that the embodiment of the present invention provides carries out the flow chart of veneer power-on and power-off management;
Fig. 4 is that can administrative unit determination veneer that the embodiment of the present invention provides power on or the flow chart of lower electricity;
Fig. 5 is the veneer power-on and power-off management system concrete structure schematic diagram in an embodiment that the embodiment of the present invention provides;
Fig. 6 is the flow chart of the Board Power up that the embodiment of the present invention provides;
Fig. 7 is the flow chart of electricity under the veneer that provides of the embodiment of the present invention;
Fig. 8 is the flow chart of the instantiation of the Board Power up that the embodiment of the present invention provides;
Fig. 9 is the flow chart of the instantiation of electricity under the veneer that provides of the embodiment of the present invention.
Embodiment
Hereinafter also describe the present invention in detail with reference to accompanying drawing in conjunction with the embodiments.It should be noted that, when not conflicting, the embodiment in the application and the feature in embodiment can combine mutually.
Embodiment one
In the present embodiment, veneer does not power on, and concrete handling process refers to Fig. 6:
Step 602, Board Power up order are issued to decision center by webmaster;
Step 604, decision center receive the order that webmaster issues, and preserve this command information, and send diagnostic command on control unit;
The order at step 606, control unit Response Decision center, and receive the address of decision center, set up communication path;
Step 608, control unit gather the single board information such as temperature, voltage, board type, power of veneer, report, ask the Board Power up controlled it to decision center;
Step 610, decision center judge that whether veneer institute's slot position is correct, if incorrect, return error code to webmaster (prompting user pulls out plate), and issue deactivation command to control unit, terminate current process; If institute's slot position correctly, go to step 612;
Step 612, decision center, according to the single board information collected and system information, judge whether to allow Board Power up, if do not allow Board Power up, then go to step 614; If allow to power on, issue activation command, go to step 618;
Step 614, when veneer power demand is excessive, temperature of single plate or voltage out-of-limit, then decision-making does not allow to power on, and decision center issues deactivation command, and control unit enters wait state, and wait is activated;
Step 616, decision center preserve unactivated single board information, timing upgrades the information of whole equipment, as the veneer that powers in equipment, the veneer that do not power on, equipment dump power etc., and by information reporting webmaster (prompting user operation), then judge whether to issue activation command, if do not issue activation command, control unit then keeps wait state; If veneer power demand can meet and temperature of single plate, voltage normal, then issue activation command, go to step 618;
Step 618, control unit receive and activate veneer order;
Step 620, control unit control Board Power up, and step terminates.
Embodiment two
In the present embodiment, carry out lower electricity to veneer, concrete handling process refers to Fig. 7:
Under step 702, veneer, electricity order is issued to decision center by webmaster;
Step 704, decision center receive the order that webmaster issues, and preserve this configuration information, and transmitting single plate deactivation command is on control unit;
Step 706, control unit receive deactivation command, and to electricity under veneer, and wait reactivates its veneer controlled;
Step 708, decision center preserve the single board information do not powered on, the single board information that reception control unit sends, and timing upgrades, and the single board information after upgrading is reported webmaster (prompting user operation), then judge whether to need to issue activation command, if do not issue activation command, control unit then keeps wait state.
Embodiment three
In this example, decision center D manages two control unit C1 and C2, and a corresponding veneer of control unit (the corresponding B2 of C1 corresponding B1, C2), it is specifically implemented as shown in Figure 8:
Step 802, Board Power up order are issued to decision center D by webmaster;
Step 804, decision center D receive the order that webmaster issues, and preserve this configuration information, then send out on control unit C1 and C2 of corresponding veneer in diagnostic command to equipment according to presetting power supply sequence of single board timing;
The order at step 806, control unit C1 and C2 Response Decision center successively, and receive the address of decision center, set up communication link;
Step 808, control unit C1 and C2 report the single board information of veneer successively, and the information such as such as temperature, voltage, board type, power are to decision center, and request powers on;
Step 810, decision center D judge that whether veneer institute's slot position is correct, if incorrect, return error code to webmaster (prompting user pulls out plate), and issue deactivation command to control unit C1 and C2, step terminates; If correct, go to step 812;
Step 812, decision center D judge whether to allow board B 1, B2 powers on, and allow to power on, issue activation command, go to step 818;
If step 814 does not allow to power on, decision center D issues deactivation command, and control unit C1, C2 enter wait state, waits for issuing of activation command;
Step 816, decision center D preserve unactivated single board information, and timing upgrades the information of whole equipment, and by information reporting webmaster (prompting user operation), then judges whether to issue activation command, if do not issued, control unit continues to wait for; Otherwise issue activation command, go to step 818;
Step 818, control unit C1, C2 receive and activate veneer order;
Step 820, control unit C1, C2 power on to board B 1, B2, and step terminates.
Embodiment four
In the present embodiment, decision center D manages two control unit C1 and C2, and the corresponding veneer of control unit (the corresponding B2 of C1 corresponding B1, C2), its concrete implementing procedure as shown in Figure 9:
Under step 902, veneer, electricity order is issued to decision center D by webmaster;
Step 904, decision center D preserve this configuration information, and transmitting single plate deactivation command is on the control unit in equipment;
Step 906, control unit C1, C2 receive deactivation command, and to electricity under board B 1, B2, and wait reactivates board B 1, B2;
Step 908, decision center D preserve unactivated single board information, upgrade single board information, judge whether to need to issue activation command, if do not issue activation command, control unit C1, C2 continue to wait for.
As can be seen from the above description, present invention achieves following technique effect:
In the above-described embodiments, use management unit manages veneer, when veneer receives the control message of administrative unit transmission, carry out powering on or lower electricity according to control message, instead of directly power on or lower electricity, avoid directly powering on or lower electricity damages veneer, occur reducing veneer life-span and problem difficult in maintenance, improve the security performance of veneer, extend the life-span of veneer, shorten the time that artificial plug veneer consumes, effectively improve the efficiency of veneer power-on and power-off.
Obviously, those skilled in the art should be understood that, above-mentioned of the present invention each module or each step can realize with general calculation element, they can concentrate on single calculation element, or be distributed on network that multiple calculation element forms, alternatively, they can realize with the executable program code of calculation element, thus, they can be stored and be performed by calculation element in the storage device, and in some cases, step shown or described by can performing with the order be different from herein, or they are made into each integrated circuit modules respectively, or the multiple module in them or step are made into single integrated circuit module to realize.Like this, the present invention is not restricted to any specific hardware and software combination.
The foregoing is only the preferred embodiments of the present invention, be not limited to the present invention, for a person skilled in the art, the present invention can have various modifications and variations.Within the spirit and principles in the present invention all, any amendment done, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (12)

1. a veneer power-on and power-off management system, is characterized in that, comprises administrative unit and veneer:
Described administrative unit, determine whether described veneer can carry out powering on or lower electricity for the single board information current according to described veneer, the control message carrying determination result is sent to described veneer, wherein, when described veneer is in wait state, described administrative unit periodically gathers the single board information being in the described veneer of wait state, until determine that described veneer can power on;
Described veneer, for receiving the control message that described administrative unit sends, carries out powering on or lower electricity according to described control message.
2. system according to claim 1, is characterized in that, described administrative unit comprises webmaster, decision center and control unit:
Described webmaster, for sending directive command to described decision center, under described directive command comprises Board Power up order and veneer, electricity is ordered;
According to described directive command and the current single board information of described veneer, described decision center, for receiving described directive command, determines whether described veneer can carry out powering on or lower electricity, and determination result is sent to described control unit;
Described control unit, for receiving described determination result, being carried at described determination result in control message and being sent to described veneer, controls described veneer and carries out powering on or lower electricity.
3. system according to claim 2, is characterized in that,
Described decision center, is further used for when described directive command is Board Power up order, sends diagnostic command to described control unit; And, receive the single board information that described control unit reports, determine whether described veneer can power on;
Described control unit, is further used for receiving described diagnostic command, gathers the single board information that described veneer is current, and the single board information of employing is reported to described decision center.
4. system according to claim 3, is characterized in that, described decision center, is further used for, when described single board information is mated with described single board information threshold value, determining that described veneer can power on; And
When described single board information is not mated with described single board information threshold value, determine that described veneer does not power on, be in wait state.
5. system according to claim 4, it is characterized in that, described control unit, be further used for when described single board information is not mated with described single board information threshold value, periodically gather the single board information after the veneer renewal being in wait state, report to described decision center, until described decision center determines that described veneer can power on.
6. the system according to any one of claim 4 or 5, is characterized in that,
Described decision center, be further used for when described single board information and the unmatched reason of described single board information threshold value be described veneer insert slot mistake time, return error code to described webmaster, concurrent activation command of sending to is to described control unit;
Described webmaster, is further used for prompting user and extracts described veneer;
Described control unit, is further used for receiving described deactivation command, controls described veneer and is in wait state.
7. the system according to any one of claim 4 or 5, is characterized in that,
Described decision center, be further used for when described single board information and the unmatched reason of described single board information threshold value be that described veneer power is excessive, temperature or voltage out-of-limit time, send deactivation command to described control unit;
Described control unit, is further used for receiving described deactivation command, controls described veneer and is in wait state.
8. the system according to any one of claim 4 or 5, is characterized in that,
Described decision center, is further used for when described single board information is mated with described single board information threshold value, sends active information to described control unit;
Described control unit, is further used for receiving described active information, controls described veneer and powers on.
9. system according to claim 2, is characterized in that,
Described decision center, is further used for, when described directive command is electricity order under veneer, sending deactivation command to described control unit;
Described control unit, is further used for receiving described deactivation command, controls described veneer and carries out lower electricity.
10. system according to claim 9, is characterized in that, described control unit is further used for: the single board information periodically gathering lower electric veneer, and is reported to described decision center, until described decision center sends activation command.
11. 1 kinds of application rights require that the veneer power-on and power-off management system described in 1 carries out the method for veneer power-on and power-off management, and it is characterized in that, described veneer power-on and power-off control system comprises administrative unit and veneer, and described method comprises:
The described administrative unit single board information current according to described veneer determines whether described veneer can carry out powering on or lower electricity, and the control message carrying determination result is sent to described veneer;
Described veneer receives the control message that described administrative unit sends, and carries out powering on or lower electricity according to described control message.
12. methods according to claim 11, is characterized in that, when described administrative unit comprises webmaster, decision center and control unit, described method also comprises:
Described webmaster sends directive command to described decision center, and under described directive command comprises Board Power up order and veneer, electricity is ordered;
Described decision center receives described directive command, determines whether described veneer can carry out powering on or lower electricity, and determination result is sent to described control unit according to described directive command and the current single board information of described veneer;
Described control unit receives described determination result, described determination result is carried in control message and is sent to described veneer, controls described veneer and carries out powering on or lower electricity.
CN201010286830.7A 2010-09-13 2010-09-13 Veneer charging and discharging management system and application method thereof Active CN101938378B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201010286830.7A CN101938378B (en) 2010-09-13 2010-09-13 Veneer charging and discharging management system and application method thereof
PCT/CN2011/072606 WO2012034396A1 (en) 2010-09-13 2011-04-11 System for power-on and power-off management for single board and an application method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010286830.7A CN101938378B (en) 2010-09-13 2010-09-13 Veneer charging and discharging management system and application method thereof

Publications (2)

Publication Number Publication Date
CN101938378A CN101938378A (en) 2011-01-05
CN101938378B true CN101938378B (en) 2015-01-28

Family

ID=43391524

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010286830.7A Active CN101938378B (en) 2010-09-13 2010-09-13 Veneer charging and discharging management system and application method thereof

Country Status (2)

Country Link
CN (1) CN101938378B (en)
WO (1) WO2012034396A1 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101938378B (en) * 2010-09-13 2015-01-28 中兴通讯股份有限公司 Veneer charging and discharging management system and application method thereof
CN103068017B (en) * 2012-12-24 2016-09-14 华为技术有限公司 Device energy conservation control method and system
CN204241867U (en) * 2014-11-13 2015-04-01 中兴通讯股份有限公司 A kind of power-on and power-off control device
CN107135514A (en) * 2016-02-26 2017-09-05 大唐移动通信设备有限公司 Electric control method and device on a kind of BBU of base station machine frame
CN107360004B (en) * 2016-05-10 2021-04-20 中兴通讯股份有限公司 Method and device for controlling service node to power on and power off by utilizing reset signal
CN105871626B (en) * 2016-05-26 2019-05-10 烽火通信科技股份有限公司 A kind of method and system of communication equipment power supply centralized management

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1984208A (en) * 2006-05-17 2007-06-20 华为技术有限公司 Telecommunication monoboard and system kit and power-supply switching method
CN101001171A (en) * 2006-06-20 2007-07-18 华为技术有限公司 Single board and method for controlling power supply of it
CN101702648A (en) * 2009-11-12 2010-05-05 中兴通讯股份有限公司 Power-on and power-off control method, device and system of single board

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1250977C (en) * 2002-12-23 2006-04-12 华为技术有限公司 Electric power on/off module
CN100502291C (en) * 2005-08-22 2009-06-17 华为技术有限公司 Method for saving quiescent power dissipation of communication device
CN2919265Y (en) * 2006-04-14 2007-07-04 华为技术有限公司 Veneer upper and lower electricity controlling device
CN101169746B (en) * 2006-10-26 2010-05-12 华为技术有限公司 Method, device and system for implementing panel power up and down
CN101938378B (en) * 2010-09-13 2015-01-28 中兴通讯股份有限公司 Veneer charging and discharging management system and application method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1984208A (en) * 2006-05-17 2007-06-20 华为技术有限公司 Telecommunication monoboard and system kit and power-supply switching method
CN101001171A (en) * 2006-06-20 2007-07-18 华为技术有限公司 Single board and method for controlling power supply of it
CN101702648A (en) * 2009-11-12 2010-05-05 中兴通讯股份有限公司 Power-on and power-off control method, device and system of single board

Also Published As

Publication number Publication date
WO2012034396A1 (en) 2012-03-22
CN101938378A (en) 2011-01-05

Similar Documents

Publication Publication Date Title
CN101938378B (en) Veneer charging and discharging management system and application method thereof
US11695593B2 (en) Systems and methods for high capacity power delivery to remote nodes
US7603570B2 (en) Power delivery over ethernet cables
CN101060412B (en) Ethernet power supply system, master control module and Ethernet power supply method
US8346082B2 (en) Method of saving power in optical access network
CN104429020A (en) Power over ethernet supervision
CN102761422A (en) Cascaded Ethernet power supply system and Ethernet power supply method thereof
CN102970146B (en) The power supply unit of a kind of POE and method of supplying power to
CN104281511A (en) Intelligent platform management interface system, substrate management controller and implementation method
US20210120487A1 (en) Energy-saving method and device for base station device
CN104898435B (en) Home services system and its fault handling method, household appliance, server
US11460908B2 (en) Storage system and method for transmitting signal in storage system
KR102313705B1 (en) Method of handling power failure and method and device of obtaining connection relationship
CN106341180B (en) A kind of optical module and optical module control method, device
US20080102765A1 (en) Wireless Adaptor Power Control
EP2937963B1 (en) Power supply control device, battery device, power supply system, and power supply control method
CN106789109B (en) Power management method and device
CN105391582A (en) Shared access system based on short-wave communication network
US10749375B2 (en) System and method for supplying uninterruptible power to a PoE device for a power supply input for direct current power
EP3163794B1 (en) Power supply method, apparatus, and system
CN102647018B (en) A kind of single home unit is for electric method for supervising and system
CN110784365A (en) Standby device of station control layer and entity device of transformer substation and automatic online method thereof
CN101668298B (en) method for controlling power-on of single board of base station power module and carrier manager
US11402892B2 (en) Device power savings and extended telemtry messaging
KR102278336B1 (en) Smart switch for eliminating afterglow and method for eliminating afterglow thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant