CN101922254B - Assembled square-barrel multi-layer concrete underground garage and manufacturing method thereof - Google Patents

Assembled square-barrel multi-layer concrete underground garage and manufacturing method thereof Download PDF

Info

Publication number
CN101922254B
CN101922254B CN2010102533074A CN201010253307A CN101922254B CN 101922254 B CN101922254 B CN 101922254B CN 2010102533074 A CN2010102533074 A CN 2010102533074A CN 201010253307 A CN201010253307 A CN 201010253307A CN 101922254 B CN101922254 B CN 101922254B
Authority
CN
China
Prior art keywords
ground tackle
layer
prestressing tendon
unbonded prestressing
square tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2010102533074A
Other languages
Chinese (zh)
Other versions
CN101922254A (en
Inventor
王志乐
郭晓
刘志刚
王立军
张富国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA NORTHEAST MUNICIPAL ENGINEERING DESIGN & RESEARCH INSTITUTE CO., LTD.
Original Assignee
China Northeast Architectural Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Northeast Architectural Design and Research Institute Co Ltd filed Critical China Northeast Architectural Design and Research Institute Co Ltd
Priority to CN2010102533074A priority Critical patent/CN101922254B/en
Publication of CN101922254A publication Critical patent/CN101922254A/en
Application granted granted Critical
Publication of CN101922254B publication Critical patent/CN101922254B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention relates to an assembled square-barrel multi-layer concrete underground garage and a manufacturing method thereof, belonging to an assembled multi-layer concrete underground garage and a manufacturing method thereof. The underground garage of the invention comprises a body composed of a ground transferring room, a top cover plate, a platform, square tube wall, a parking girder, an underground equipment room and the like. Except that the underground garage bottom and the equipment base in the construction structure of the garage adopt cast-in-place concrete, other equipment is formed by combining, assembling and fastening various concrete prefabricated parts by non-splicing prestressed tendons and anchors. The whole assembling and fixing process does not need to weld and to be fastened by bolts. The structure has high combination speed, high strength and high precision. The square-barrel multi-layer concrete underground garage of the invention has simple construction, convenient manufacture and low construction cost, is safe and reliable and does not need large equipment. The open caisson construction has small land occupation, and construction and building can be carried out in the yard, out of the building and on the wayside.

Description

Assembling square tube shape multi-layer concrete underground garage and preparation method thereof
Technical field
The invention belongs to a kind of assembling multi-layer concrete underground garage and preparation method thereof.
Background technology
Along with the car industry fast development, car flies into common people house as swallow.But the parking lot is pitiably little, and parking difficulty has restricted the development of car industry, has also influenced the incity traffic and the appearance of the city.At present, parking lot is built all at the eyebrows and eyelashes in each big and medium-sized cities, but the old town can not build with having, and Xincheng District ground is expensive is reluctant to build, and the construction underground parking, its cost also is high.The underground garage of underground parking, particularly multilayer can't have been built again because conventional architectural design and job practices are used in the restriction of existing urban layout in the old town.Its main cause is to build the underground parking to need a cubic metre of earth heavy excavation.Fetch earth and put the slope, the occupation of land face area of construction operation is far longer than the floor space of building itself, and adopt open caisson method to construct, though need not put the slope, owing to be the on-site layering concreting, the on-the-spot operations such as reinforcing bar, a template, concreting, maintenance of compiling repeat repeatedly to carry out, inner frame construction has a strong impact on the open caisson construction operation, complex process, long in time limit, the cost height.And its price of the underground garage of steel work is expensive especially.
Summary of the invention
The invention provides a kind of assembling square tube shape multi-layer concrete underground garage and preparation method thereof, take up an area of big, complicated, the low high problem of valency of constructing of face to solve present garage.The technical scheme that the present invention takes is: comprise concrete foundation, establishing the equipment room that the mutual corner connection of precast member for reinforcing bar concrete of unbonded prestressing tendon makes in four is connected with this concrete foundation upper fixed, the square tube wall tightens together by docking with this equipment room top, this square tube wall includes horizontal cross by piece, the vertical vertically mutual corner connection combine and assemble of prefabricated units side fascia of unbonded prestressing tendon tightens together, butt joint tightens together between each layer, in establish unbonded prestressing tendon the precast member for reinforcing bar concrete parking beam fix with the corresponding preformed hole cross-under of every layer of square tube wall, in establish unbonded prestressing tendon precast member for reinforcing bar concrete transhipment stop platform connect fixing with the square tube corner that is positioned at the place, ground, in establish unbonded prestressing tendon the right wall of precast member for reinforcing bar concrete transhipment layer and the left wall of transhipment layer dock with the square tube wall respectively fixing, in establish unbonded prestressing tendon precast member for reinforcing bar concrete transhipment layer lamina tecti and the right wall of transhipment layer with transport a layer left corner and connect fixing.
Preparation method of the present invention comprises the following steps:
(1) adopts corner connection method combine and assemble punching press square spade
(1), the no bonding prestress muscle at 4 pre-system structure spare Blade angles is combined into the punching press square spade of four frame types with ground tackle and steel angle anchor plate;
(2), breast boards, fixedly jack are installed;
(2), adopt corner connection method combine and assemble square tube wall
(1), 1 block of side fascia is pressed on the jack on the punching press square spade, and the screw thread ground tackle of butt joint ground tackle will its longitudinal rib upper end be installed, the common ground tackle in the lower end butt joint ground tackle, stretch-draw screw thread ground tackle is temporarily fixed at side fascia on the punching press square spade;
(2), second block of side fascia is pressed on the punching press square spade, and after with first block of side fascia vertical sealing mat being installed, ground tackle is installed after the corresponding horizontal bar of two blocks of side fascias is worn angle anchor plate corresponding aperture by top step (1);
(3), by the 3rd, the 4th block of side fascia of top step (2) assembling;
(4), 4 side fascia longitudinal ribs are withdrawed from punching press square spade preformed hole, stretch-draw is fastening; Excise unnecessary muscle head, ground tackle stretch-draw on the horizontal bar is fastening;
(5), the square tube wall props up template for four jiaos, concrete perfusion, shutoff angle anchor plate and ground tackle, first floor square tube wall combine and assemble is finished;
(3), adopt docking calculation that each layer square tube wall longitudinal rib is coupled together;
(1), the longitudinal rib of second layer side fascia is installed the butt joint ground tackle, the screw thread ground tackle of butt joint ground tackle is installed in its longitudinal rib upper end, the common ground tackle and the adapter sleeve of butt joint ground tackle installed in the lower end, and with the screw thread ground tackle of corresponding first floor square tube wall wallboard longitudinal rib, connect two ground tackles with the adapter sleeve spiral, fill sealing agent, stretch-draw is fastening;
(2), install equally the second layer second and third, four blocks of side fascias;
(3), when last layer square tube wall longitudinal rib docks with ground tackle with the corresponding longitudinal rib of following one deck square tube wall, except that first pretensioning was fixing, other were temporary fixed, treat the installation of angle anchor plate, after horizontal tension of prestressed tendon is fastening, the fastening longitudinal rib of stretch-draw again;
(4), adopt cross-under method combine and assemble parking beam;
(1), the parking beam presstressed reinforcing steel is worn the corresponding preformed hole of the side fascia that is combined into the square tube wall, fix with ground tackle stretch-draw;
(2), excise the muscle head, with concrete shutoff preformed hole;
(5), open caisson construction
(1), the artificial shoveling, grab bucket is fetched earth, square spade jack punching press soil layer,
(2), first floor square tube wall is sunk to underground,
(3), repeat (two), (three), the operation of (four) step, with square tube wall and parking beam combine and assemble to underground top layer;
(6), transhipment layer combine and assemble;
(1), transhipment stop platform is installed
The minor face of two blocks of side fascias is installed steel angle anchor plate and ground tackle, and stretch-draw is fastened to design stress; Angle anchor plate preformed hole is worn the corresponding longitudinal rib of underground top layer square tube wall, withholds on the top layer square tube wall that parking beam is installed, and stretch-draw is fastening;
(2), the left and right wall of transhipment layer installed;
To anchor plate and ground tackle, stretch-draw is fastened to design stress with two side fascia horizontal bar established angles; And its longitudinal rib installed the butt joint ground tackle, and its upper end is installed screw thread ground tackle, lower end in butt joint ground tackle common ground tackle and adapter sleeve in the butt joint ground tackle is installed, and with the screw thread ground tackle butt joint of the longitudinal rib of corresponding underground top layer square tube wall, stretch-draw is fastening respectively;
(3), transhipment layer lamina tecti installed
(a), with the minor face established angle of a side fascia to anchor plate and ground tackle, stretch-draw is fastened to design stress;
(b), again it is installed in the middle part of the left wall of transhipment layer, the right wall of transhipment layer, its two ends angle anchor plate is worn the corresponding longitudinal rib of this two wallboard and is withheld on the wall of the left and right sides, fixes with the vertical muscle corner connection of this two wallboard;
(c), about two blocks of side fascias are divided, add mutual corresponding horizontal bar of sealing mat and the middle part that is installed in left and right sides wall and connect, stretch-draw is fastening;
(d), two side fascia presstressed reinforcing steels fix with corresponding transhipment layer left side wall, the vertical muscle corner connection of the right wall of transhipment layer, the angle anchor plate is worn earlier the left wall of transhipment layer, the right wall longitudinal rib of transhipment layer respectively, wears the horizontal bar of back two side fascia correspondences again;
(7), bottom of the reservior and equipment room Equipment Foundations are made:
(1), puts concrete pad, the jack on the taking-up punching press square spade, excavation equipment foundation pit;
(2), clear up bottom of the reservior and foundation pit, concreting bed course;
(3), tie up bottom of the reservior and foundation pit reinforcing bar, concreting.
It is non-caked in concrete that technical scheme of the present invention makes full use of unbonded prestressing tendon, can slide.By very heavy stretch-draw, ground tackle locking makes the unbonded prestressing tendon of concrete component produce powerful tensile stress.Reaction force that this power produces acts on the interface and the prefabricated units itself of prefabricated units combine and assemble, makes it bear compressive stress.This power meets the stressed principle of concrete resistance to compression greater than tension.By ground tackle and very heavy accurate stretch-draw locking, it is accurate, error free to reach concrete prefabricated element combine and assemble size, the intensity height of its building structure combine and assemble.
Square tube shape underground garage design of building structures has the following advantages
1, its structure of multi-layer concrete underground garage all is made up of concrete prefabricated element, and prefabricated units can be produced in batches in factory, and the output height, quality is good, cost is low, efficient energy-saving.
2, the construction of assembling concrete prefabricated units is simple, convenient at the scene, speed is fast, need not large-scale hanging device.
3, adopt new method and proprietary material, facility, equipment combine and assemble concrete prefabricated element, building structure intensity is big, and the member group is to the precision height, and is safe and reliable.
4, open caisson construction can be built underground garage at narrow and small ground construction, uses the punching press square spade, promptly can accomplish cubic metre of earth zero backbreaking, and can guarantee the square tube shape exterior wall level that makes up, even, vertical subsidence again.
The square tube shape multi-layer concrete underground garage of the present invention design can be in narrow and small location, incity, city, old parking lot, and outside the buildings such as enterprise, hospital, office, hotel, market, in the institute, the roadside carries out construction.Under each surface area of 6 meters of length and width, can build every layer and stop 2, the underground parking garage that underground 11 layers of parking are 20.
Description of drawings
Fig. 1 is a structural representation of the present invention;
Fig. 2 is a vertical view of the present invention;
Fig. 3 is parking beam of the present invention and the cross-under of square tube wall, corner connection structural representation.
Fig. 4 A is the structural representation of side fascia of the present invention;
Fig. 4 B is the structural representation of parking beam of the present invention;
Fig. 4 C is the structural representation of the basil of the present invention;
Fig. 4 D is the structural representation of steel angle anchor plate of the present invention;
Fig. 4 E is the structural representation of ground tackle of the present invention;
Fig. 4 F is the structural representation that ground tackle is docked in the present invention;
Fig. 4 G is the structural representation of steel angle anchor plate of the present invention.
Fig. 5 is a partial structurtes schematic diagram of the present invention, shows the docking structure schematic diagram.
The specific embodiment
Comprise concrete foundation 8, establishing the equipment room 7 that the mutual corner connection of precast member for reinforcing bar concrete of unbonded prestressing tendon makes in four is connected with this concrete foundation upper fixed, square tube wall 5 tightens together by docking with this equipment room top, this square tube wall includes horizontal cross by 4, the vertical vertically prefabricated units side fascia 501 mutual corner connection combine and assemble of unbonded prestressing tendon tighten together, butt joint tightens together between each layer, in establish unbonded prestressing tendon precast member for reinforcing bar concrete parking beam 6 fix with the corresponding preformed hole cross-under of every layer of square tube wall, in establish unbonded prestressing tendon precast member for reinforcing bar concrete transhipment stop platform 4 connect fixing with the square tube corner that is positioned at the place, ground, in establish unbonded prestressing tendon the right wall 2 of precast member for reinforcing bar concrete transhipment layer and the left wall 3 of transhipment layer dock with the square tube wall respectively fixing, in establish unbonded prestressing tendon precast member for reinforcing bar concrete transhipment layer lamina tecti 1 and the right wall 2 of transhipment layer with transport layer left wall 3 corner connection and fix.
Butt joint of the present invention, cross-under, corner connection method are specific as follows:
(1) butt joint:
(1), unbonded prestressing tendon is set in concrete prefabricated element;
(2), the butt joint ground tackle 9 making, be provided with common ground tackle 901 in the adapter sleeve, screw thread ground tackle 902 is connected with these adapter sleeve 903 internal threads; Shown in Fig. 4 F.
(3), ground tackle 10 is installed on the unbonded prestressing tendon of a concrete prefabricated element one end, shown in Fig. 4 E, the other end is installed the screw thread ground tackle in the butt joint ground tackle, stretch-draw is fastening;
(4), at another concrete prefabricated element unbonded prestressing tendon one end of butt joint with it common ground tackle and the adapter sleeve that docks in the ground tackle is installed, screw thread ground tackle in the other end installation butt joint ground tackle;
(5), the common ground tackle that the screw thread ground tackle in the butt joint ground tackle on the unbonded prestressing tendon of a concrete prefabricated element is docked concrete prefabricated element with another docks mutually by adapter sleeve;
(6), the screw thread ground tackle in the butt joint ground tackle of fastening another concrete prefabricated element of stretch-draw, the butt joint of two prefabricated units is combined.
(2) cross-under
(1), unbonded prestressing tendon is set in concrete prefabricated element;
(2), another concrete prefabricated element in combine and assemble is provided with preformed hole;
(3), the unbonded prestressing tendon of concrete prefabricated element is worn the preformed hole of another concrete prefabricated element, the unbonded prestressing tendon two ends are fastening with ground tackle stretch-draw, and its connection is tightened together.
(3) corner connection
(1), unbonded prestressing tendon is set in concrete prefabricated element;
(2), angle anchor plate 11 is made: making has angle and wears the anchor plate in muscle hole; Shown in Fig. 4 D and Fig. 4 G;
(3), the unbonded prestressing tendon in each prefabricated unit passed steel angle anchor plate wear the muscle hole, with the fastening presstressed reinforcing steel of ground tackle stretch-draw, make each concrete prefabricated element make certain angle each other and connect.
The preparation method of assembling square tube shape multi-layer concrete underground garage of the present invention:
(1) adopts corner connection method combine and assemble punching press square spade
(1), the no bonding prestress muscle at the angle of pre-system structure spare Blade shown in 4 Fig. 4 C 12 is combined into the punching press square spade of four frame types with steel angle anchor plate shown in ground tackle shown in Fig. 4 E and Fig. 4 G.
(2), breast boards, fixedly jack are installed.
(2), adopt corner connection method combine and assemble square tube wall
(1), 1 block of side fascia shown in Fig. 4 A is pressed on the jack on the punching press square spade, and the screw thread ground tackle of ground tackle will be docked shown in the installation drawing 4F of its longitudinal rib upper end, common ground tackle in the ground tackle of butt joint shown in the installation drawing 4F of lower end, stretch-draw screw thread ground tackle is temporarily fixed at side fascia on the punching press square spade;
(2), second block of side fascia is pressed on the punching press square spade, and after with first block of side fascia vertical sealing mat being installed, the corresponding horizontal bar of two blocks of side fascias is worn ground tackle shown in the installation drawing 4E behind the corresponding aperture of angle anchor plate shown in Fig. 4 D by top step (1);
(3), by the 3rd, the 4th block of side fascia of top step (2) assembling;
(4), 4 side fascia longitudinal ribs are withdrawed from punching press square spade preformed hole, stretch-draw is fastening; Excise unnecessary muscle head, ground tackle stretch-draw on the horizontal bar is fastening;
(5), the square tube wall props up template for four jiaos, concrete perfusion, shutoff angle anchor plate and ground tackle, first floor square tube wall combine and assemble is finished;
(3), adopt docking calculation that each layer square tube wall longitudinal rib is coupled together;
(1), shown in the longitudinal rib installation drawing 4F of second layer side fascia, docks ground tackle, the screw thread ground tackle of butt joint ground tackle is installed in its longitudinal rib upper end, the common ground tackle and the adapter sleeve of butt joint ground tackle installed in the lower end, and with the screw thread ground tackle of corresponding first floor square tube wall wallboard longitudinal rib, connect two ground tackles with the adapter sleeve spiral, fill sealing agent, stretch-draw is fastening;
(2), install equally the second layer second and third, four blocks of side fascias;
(3), when last layer square tube wall longitudinal rib docks with ground tackle with the corresponding longitudinal rib of following one deck square tube wall, except that first pretensioning was fixing, other were temporary fixed, treat the installation of angle anchor plate, after horizontal tension of prestressed tendon is fastening, the fastening longitudinal rib of stretch-draw again;
(4), adopt cross-under method combine and assemble parking beam;
(1), parking beam presstressed reinforcing steel shown in Fig. 4 B is worn the corresponding preformed hole of the side fascia that is combined into the square tube wall, fix with 10 stretch-draw of ground tackle shown in Fig. 4 E;
(2), excise the muscle head, with concrete shutoff preformed hole;
(5), open caisson construction
(1), the artificial shoveling, grab bucket is fetched earth, square spade jack punching press soil layer,
(2), first floor square tube wall is sunk to underground,
(3), repeat (two), (three), the operation of (four) step, with square tube wall and parking beam combine and assemble to underground top layer.
(6), transhipment layer combine and assemble;
(1), transhipment stop platform is installed.
With ground tackle shown in steel angle anchor plate shown in the minor face installation drawing 4D of two blocks of side fascias shown in Fig. 4 A and Fig. 4 E, stretch-draw is fastened to design stress; Angle anchor plate preformed hole is worn the corresponding longitudinal rib of underground top layer square tube wall, withholds on the top layer square tube wall that parking beam is installed, and stretch-draw is fastening;
(2), the left and right wall of transhipment layer installed.
With ground tackle shown in angle anchor plate shown in two side fascia horizontal bar installation drawing 4D shown in Fig. 4 A and Fig. 4 E, stretch-draw is fastened to design stress; And its longitudinal rib installed the butt joint ground tackle, and its upper end is installed screw thread ground tackle, lower end in butt joint ground tackle common ground tackle and adapter sleeve in the butt joint ground tackle is installed, and with the screw thread ground tackle butt joint of the longitudinal rib of corresponding underground top layer square tube wall, stretch-draw is fastening respectively;
(3), transhipment layer lamina tecti installed
(a), with ground tackle shown in angle anchor plate shown in the minor face installation drawing 4D of a side fascia shown in Fig. 4 A and Fig. 4 E, stretch-draw is fastened to design stress;
(b), again it is installed in the middle part of the left wall of transhipment layer, the right wall of transhipment layer, its two ends angle anchor plate is worn the corresponding longitudinal rib of this two wallboard and is withheld on the wall of the left and right sides, fixes with the vertical muscle corner connection of this two wallboard;
(c), about two blocks of side fascias are divided, add mutual corresponding horizontal bar of sealing mat and the middle part that is installed in left and right sides wall and connect, stretch-draw is fastening;
(d), two side fascia presstressed reinforcing steels fix with corresponding transhipment layer left side wall, the vertical muscle corner connection of the right wall of transhipment layer, the angle anchor plate is worn earlier the left wall of transhipment layer, the right wall longitudinal rib of transhipment layer respectively, wears the horizontal bar of back two side fascia correspondences again;
(7), bottom of the reservior and equipment room Equipment Foundations are made:
(1), puts concrete pad, the jack on the taking-up punching press square spade, excavation equipment foundation pit;
(2), clear up bottom of the reservior and foundation pit, concreting bed course;
(3), tie up bottom of the reservior and foundation pit reinforcing bar, concreting.
Square tube shape garage access program:
1, bicycle parking.Automobile drives transhipment layer on the ground into, and is parked on mobile trolley used on the hoist.Safety door is closed, and hoist sinks, and is parked in the storehouse layer of having vacant position.Hydraulic stem on the hoist is with the mobile trolley used empty wagons position that pushes.
2, pick up the car.Bicycle parking people plug-in card, hoist move to storehouse, bicycle parking position layer.The hoist hydraulic stem stretches out to be moved on the hoist mobile trolley used.Hoist rises up into ground transhipment layer.Safety door is opened, and the driver leaves the transhipment layer with car.

Claims (2)

1. assembling square tube shape multi-layer concrete underground garage, comprise concrete foundation, it is characterized in that: establish the equipment room that the mutual corner connection of precast member for reinforcing bar concrete of unbonded prestressing tendon makes in four and be connected with this concrete foundation upper fixed, the square tube wall tightens together by docking with this equipment room top, this square tube wall includes horizontal cross by piece, the vertical vertically mutual corner connection combine and assemble of prefabricated units side fascia of unbonded prestressing tendon tightens together, butt joint tightens together between each layer, in establish unbonded prestressing tendon the precast member for reinforcing bar concrete parking beam fix with the corresponding preformed hole cross-under of every layer of square tube wall, in establish unbonded prestressing tendon precast member for reinforcing bar concrete transhipment stop platform connect fixing with the square tube corner that is positioned at the place, ground, in establish unbonded prestressing tendon the right wall of precast member for reinforcing bar concrete transhipment layer and the left wall of transhipment layer dock with the square tube wall respectively fixing, in establish unbonded prestressing tendon precast member for reinforcing bar concrete transhipment layer lamina tecti with the transhipment right wall of layer and transport a layer left corner and connect fixing.
2. the preparation method of assembling square tube shape multi-layer concrete underground garage as claimed in claim 1: comprise the following steps:
(1), adopts corner connection method combine and assemble punching press square spade
(1), the no bonding prestress muscle at 4 pre-system structure spare Blade angles is combined into the punching press square spade of four frame types with ground tackle and steel angle anchor plate;
(2), breast boards, fixedly jack are installed;
(2), adopt corner connection method combine and assemble square tube wall
(1), 1 block of side fascia is pressed on the jack on the punching press square spade, and will the screw thread ground tackle of butt joint ground tackle be installed on its vertical vertically unbonded prestressing tendon, the common ground tackle in the butt joint ground tackle is installed in the lower end, and stretch-draw screw thread ground tackle is temporarily fixed at side fascia on the punching press square spade;
(2), second block of side fascia is pressed on the punching press square spade, and after with first block of side fascia vertical sealing mat being installed, ground tackle is installed after the corresponding horizontal cross unbonded prestressing tendon of two blocks of side fascias is worn angle anchor plate corresponding aperture by top step (1);
(3), by the 3rd, the 4th block of side fascia of top step (2) assembling;
(4), the vertical vertically unbonded prestressing tendon of 4 blocks of side fascias is withdrawed from punching press square spade preformed hole, stretch-draw is fastening; Excise unnecessary muscle head, ground tackle stretch-draw on the horizontal cross unbonded prestressing tendon is fastening;
(5), the square tube wall props up template for four jiaos, concrete perfusion, shutoff angle anchor plate and ground tackle, first floor square tube wall combine and assemble is finished;
(3), adopt docking calculation that the vertical vertically unbonded prestressing tendon of each layer square tube wall is coupled together;
(1), the vertical vertically unbonded prestressing tendon of second layer side fascia is installed the butt joint ground tackle, the screw thread ground tackle of butt joint ground tackle is installed in its vertical vertically unbonded prestressing tendon upper end, the common ground tackle and the adapter sleeve of butt joint ground tackle installed in the lower end, and the vertical vertically screw thread ground tackle of unbonded prestressing tendon with corresponding first floor square tube wall side fascia, connect two ground tackles with the adapter sleeve spiral, fill sealing agent, stretch-draw is fastening;
(2), install equally the second layer second and third, four blocks of side fascias;
When (3), the corresponding vertical vertical unbonded prestressing tendon with following one deck square tube wall of the vertical vertically unbonded prestressing tendon of last layer square tube wall docks with ground tackle, except that first pretensioning is fixing, other are temporary fixed, treat the installation of angle anchor plate, after the stretch-draw of horizontal cross unbonded prestressing tendon is fastening, the fastening vertical vertically unbonded prestressing tendon of stretch-draw again;
(4), adopt cross-under method combine and assemble parking beam;
(1), the parking beam presstressed reinforcing steel is worn the corresponding preformed hole of the side fascia that is combined into the square tube wall, fix with ground tackle stretch-draw;
(2), excise the muscle head, with concrete shutoff preformed hole;
(5), open caisson construction
(1), the artificial shoveling, grab bucket is fetched earth, square spade jack punching press soil layer,
(2), first floor square tube wall is sunk to underground,
(3), repeat (three), the operation of (four) step, with square tube wall and parking beam combine and assemble to underground top layer;
(6), transhipment layer combine and assemble;
(1), transhipment stop platform is installed
The minor face of two blocks of side fascias is installed steel angle anchor plate and ground tackle, and stretch-draw is fastened to design stress; Angle anchor plate preformed hole is worn the corresponding vertical vertically unbonded prestressing tendon of underground top layer square tube wall, withholds on the top layer square tube wall that parking beam is installed, and stretch-draw is fastening;
(2), the left and right wall of transhipment layer installed;
To anchor plate and ground tackle, stretch-draw is fastened to design stress with two side fascia horizontal cross unbonded prestressing tendon established angles; And with its vertical vertically unbonded prestressing tendon installation butt joint ground tackle, common ground tackle and the adapter sleeve that docks in the ground tackle installed in screw thread ground tackle, the lower end that install in the butt joint ground tackle its upper end, with the screw thread ground tackle butt joint of the vertical vertically unbonded prestressing tendon of corresponding underground top layer square tube wall, stretch-draw is fastening respectively;
(3), transhipment layer lamina tecti installed
(a), with the minor face established angle of a side fascia to anchor plate and ground tackle, stretch-draw is fastened to design stress;
(b), again it is installed in the middle part of the left wall of transhipment layer, the right wall of transhipment layer, its two ends angle anchor plate is worn the corresponding vertical vertically unbonded prestressing tendon of this two wallboard and is withheld on the wall of the left and right sides, and vertical vertically unbonded prestressing tendon corner connection with this two wallboard is fixed;
(c), again add the vertical vertical vertically unbonded prestressing tendon of placing of the corresponding mutually level of side fascia of sealing mat and the middle part that is installed in left and right sides wall before and after two blocks of side fascias being divided and connect, stretch-draw is fastening;
(d), the horizontal cross unbonded prestressing tendon of two side fascia horizontal cross placements is fixed with the corresponding vertical vertically unbonded prestressing tendon corner connection of transhipment layer left side wall, the right wall of transhipment layer, the angle anchor plate is worn earlier transhipment layer left wall, the vertical vertically unbonded prestressing tendon of the right wall of transhipment layer respectively, wears the horizontal cross unbonded prestressing tendon of the horizontal cross placement of back two side fascia correspondences again;
(7), bottom of the reservior and equipment room Equipment Foundations are made:
(1), puts concrete pad, the jack on the taking-up punching press square spade, excavation equipment foundation pit;
(2), clear up bottom of the reservior and foundation pit, concreting bed course;
(3), tie up bottom of the reservior and foundation pit reinforcing bar, concreting.
CN2010102533074A 2010-08-11 2010-08-11 Assembled square-barrel multi-layer concrete underground garage and manufacturing method thereof Active CN101922254B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102533074A CN101922254B (en) 2010-08-11 2010-08-11 Assembled square-barrel multi-layer concrete underground garage and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102533074A CN101922254B (en) 2010-08-11 2010-08-11 Assembled square-barrel multi-layer concrete underground garage and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN101922254A CN101922254A (en) 2010-12-22
CN101922254B true CN101922254B (en) 2011-12-28

Family

ID=43337437

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102533074A Active CN101922254B (en) 2010-08-11 2010-08-11 Assembled square-barrel multi-layer concrete underground garage and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN101922254B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102182321B (en) * 2011-03-30 2013-06-19 卢丹 Construction method of underground garage
CN102913000B (en) * 2012-10-23 2014-08-06 山东建筑大学 Method for development and utilization of underground space by building moving
CN104153619B (en) * 2014-08-08 2017-04-19 肖世富 Method for fast building prefabricated reinforced concrete self-lifting garage and garage
CN105256810B (en) * 2015-09-25 2017-03-22 江苏东合南岩土科技股份有限公司 Construction method for round underground continuous wall two-in-one structure
CN106223364B (en) * 2016-09-09 2018-06-29 陈静 Prestressed assembly sink formula room Nei Di libraries construction method and ground library structure
CN106555405B (en) * 2016-10-14 2018-09-18 岩土科技股份有限公司 A kind of building well-sinking basis
CN108086996B (en) * 2017-12-31 2019-03-29 中铁隧道集团二处有限公司 The underground parking that pipe jacking tunnel is constructed the method for underground parking and constructed
CN109083179A (en) * 2018-08-07 2018-12-25 大洋泊车股份有限公司 A kind of open caisson construction method of stereo garage
CN109371999A (en) * 2018-11-17 2019-02-22 大洋泊车股份有限公司 A kind of open caisson construction method of stereo garage

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH687093A5 (en) * 1991-12-20 1996-09-13 Frisba Ag prefabricated concrete garage installed in trench
CN1916334A (en) * 2006-09-01 2007-02-21 贾广生 Method for producing box type stereo car bay
CN201148757Y (en) * 2008-01-08 2008-11-12 白利权 Ground garage
CN201778337U (en) * 2010-08-11 2011-03-30 中国市政工程东北设计研究总院 Fabricated cylindrical multilayered concrete underground garage

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GR960100384A (en) * 1996-11-13 1998-07-31 Mechanical garage

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CH687093A5 (en) * 1991-12-20 1996-09-13 Frisba Ag prefabricated concrete garage installed in trench
CN1916334A (en) * 2006-09-01 2007-02-21 贾广生 Method for producing box type stereo car bay
CN201148757Y (en) * 2008-01-08 2008-11-12 白利权 Ground garage
CN201778337U (en) * 2010-08-11 2011-03-30 中国市政工程东北设计研究总院 Fabricated cylindrical multilayered concrete underground garage

Also Published As

Publication number Publication date
CN101922254A (en) 2010-12-22

Similar Documents

Publication Publication Date Title
CN101922254B (en) Assembled square-barrel multi-layer concrete underground garage and manufacturing method thereof
CN103912011B (en) The prefabricated assembled underground structure of open cut
CN102493603B (en) Prefabricated column of reserved concealed column channel, concealed column type complete assembled earthquake-resistant building and its method
CN105862910B (en) A kind of the inverse of assembled stereoscopic underground garage makees formula method of construction
CN109235499A (en) A kind of open cut hypogee Standard formula construction method
CN105926669A (en) Construction method of subway station
CN103104039A (en) Assembled framework beam-column joint adopting cover plate connection and construction method thereof
CN110258640B (en) Construction method of superposed wall system for cover-excavation top-down construction
CN206707124U (en) Prefabricated assembling type reinforced concrete component with joint of steel structure
CN101858082A (en) Soft soil foundation new construction post pile pressing technology and construction method thereof
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN102373820B (en) Assembled type cylindrical multi-layer concrete underground garage and manufacturing method thereof
CN115324366A (en) Hoisting method for overlong and overweight truss of framed bent structure system
CN110565510B (en) Prefabricated assembled segmental pier structure and construction method thereof
CN101936074A (en) Fast building earthquake-resisting reinforcing method and device
CN201778337U (en) Fabricated cylindrical multilayered concrete underground garage
CN202401667U (en) Prefabricated column with reserved embedded column porous channel and embedded column type full-assembly anti-seismic building
CN210066817U (en) Assembly integral vault is striden no post underground structure greatly
CN218116110U (en) Prefabricated assembled double-layer concrete-filled steel tube combined pier structure
CN201778513U (en) Assembly type cylindrical multi-layer concrete underground garage
CN207110599U (en) A kind of under(-)chassis of up-down cross sliding type multi-storied garage
CN203755171U (en) Bridge back-pulling bearing construction support
CN113718845B (en) Double-deck subway station structure of cast-in-place interior assembly in outside
CN206189891U (en) Existing building reinforcement is from load -bearing and insulating integration system
CN101487268A (en) Concrete basement structure with/without bonding prestress and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA NORTHEAST MUNICIPAL ENGINEERING DESIGN AND R

Free format text: FORMER NAME: CHINA NORTHEAST CENTROL DESIGN + RESEARCH INSTITUTE OF MUNICIPAL ENGINEERING

CP01 Change in the name or title of a patent holder

Address after: 130021 Changchun workers and peasants Road, Jilin, No. 618

Patentee after: CHINA NORTHEAST MUNICIPAL ENGINEERING DESIGN & RESEARCH INSTITUTE CO., LTD.

Patentee after: Wang Zhile

Address before: 130021 Changchun workers and peasants Road, Jilin, No. 618

Patentee before: China Northeast Centrol Design & Research Institute of Municipal Engineering

Patentee before: Wang Zhile