CN101906820B - 核心筒内上下水平结构同时施工体系 - Google Patents
核心筒内上下水平结构同时施工体系 Download PDFInfo
- Publication number
- CN101906820B CN101906820B CN2010102400053A CN201010240005A CN101906820B CN 101906820 B CN101906820 B CN 101906820B CN 2010102400053 A CN2010102400053 A CN 2010102400053A CN 201010240005 A CN201010240005 A CN 201010240005A CN 101906820 B CN101906820 B CN 101906820B
- Authority
- CN
- China
- Prior art keywords
- vertical
- core tube
- constructing
- hard
- hard protection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Rod-Shaped Construction Members (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
一种核心筒内上下水平结构同时施工体系,该体系含有硬质防护层及硬质防护转换层,所述的硬质防护层位于硬质转换层的上部,所述的硬质防护层包括若干个平行的榀桁架,每个榀桁架两端固定连接在核心筒的侧壁上,相邻的榀桁架之间设有连接侧片,该硬质防护层上面为脚手板和铁皮;所述的硬质转换层包括若干个平行的工字钢主梁,每个工字钢主梁两端插入核心筒的侧壁内,相邻的工字钢主梁之间连接有角钢副梁,该硬质防护转换层的上面为脚手板和铁皮。该体系能够将核心筒内分成上下两节或者多节,能够实现上下同时开工水平结构施工,并且具有安全防护性能,能够实现上部水平结构施工的支撑,能够提高施工效率,缩短工期。
Description
技术领域
本发明涉及一种建筑施工技术领域,特别是涉及一种核心筒内上下水平结构同时施工体系。
背景技术
核心筒就是在建筑的中央部分,由电梯井道、楼梯、通风井、电缆井、公共卫生间、部分设备间围护形成中央核心筒,与外围框架形成一个外框内筒结构,以钢筋混凝土浇筑。此种结构十分有利于结构受力,并具有极优的抗震性。是国际上超高层建筑广泛采用的主流结构形式。同时,这种结构的优越性还在于可争取尽量宽敞的使用空间,使各种辅助服务性空间向平面的中央集中,使主功能空间占据最佳的采光位置,并达到视线良好、内部交通便捷的效果。
现有技术中,超高层建筑核心筒采用爬模施工工艺,施工方法大多是竖向结构先行,水平结构后做,这样施工的时间就过长,不利于施工效率的提高。
发明内容
本发明的目的是针对上述问题,提出一种核心筒内上下水平结构同时施工体系。
本发明的技术方案是:一种核心筒内上下水平结构同时施工体系,该体系含有硬质防护层及硬质防护转换层,所述的硬质防护层位于硬质转换层的上部,所述的硬质防护层包括若干个平行的榀桁架,每个榀桁架两端固定连接在核心筒的侧壁上,相邻的榀桁架之间设有连接侧片,该硬质防护层上面为脚手板和铁皮;所述的硬质转换层包括若干个平行的工字钢主梁,每个工字钢主梁两端插入核心筒的侧壁内,相邻的工字钢主梁之间连接有角钢副梁,该硬质防护转换层的上面为脚手板和铁皮。
所述的榀桁架含有上横梁和下横梁,上下横梁之间连接有若干个斜撑,所述上横梁和下横梁均为角钢,在上横梁的两端设有加强辅助角钢,该加强辅助角钢和上横梁角钢对焊形成方管,在该方管内焊接有端部加强钢筋。
所述的上横梁和下横梁的中部均布有若干个中部加强钢筋组,该加强钢筋为两个,对称焊接在上横梁或下横梁角钢立板的两个表面。
所述的榀桁架两端通过支架与核心筒连接。
所述的支架为槽钢焊接成的三角形支架,该支架含有上部的支撑杆,贴墙的安装杆,以及斜撑杆,所述的安装杆通过穿墙螺栓固定安装在核心筒侧壁上。
所述的连接侧片含有两端的竖向立杆和中部的横杆,竖向立杆和横杆均为角钢,横杆的两端通过钢板和竖向立杆焊接在一起,所述的竖向立杆和所述的榀桁架侧面固定连接。
本发明的有益效果
本发明通过在核心筒内设置硬质防护层及硬质防护转换层,能够将核心筒内分成上下两节或者多节,能够实现上下同时水平结构施工,并且具有安全防护性能,能够实现上部水平结构施工的支撑,能够提高施工效率,缩短工期。
附图说明
图1为该核心筒内上下水平结构同时施工体系的硬质防护层俯视结构图;
图2为图1中的榀桁架的安装结构示意图;
图3为图2中的支架的结构示意图;
图4为图2中的1-1截面结构示意图;
图5为图2中的2-2截面结构示意图;
图6为图2中的3-3截面结构示意图;
图7为图1的连接侧片结构示意图;
图8为该核心筒内上下水平结构同时施工体系的硬质防护转换层俯视结构图。
具体实施方式
参见图1-图2,图中1.榀桁架、2.连接侧片、3.核心筒侧壁、4.穿墙螺栓、5.支架、6.工字钢主梁、7.角钢副梁;其中1-1.上横梁、1-2.端部加强钢筋、1-3.中部加强钢筋、1-4.斜撑、1-5.下横梁、2-1.侧片、2-2.上横梁。
实施例:一种核心筒内上下水平结构同时施工体系,该体系含有硬质防护层及硬质防护转换层,所述的硬质防护层位于硬质转换层的上部,所述的硬质防护层包括若干个平行的榀桁架,每个榀桁架两端固定连接在核心筒的侧壁上,相邻的榀桁架之间设有连接侧片,该硬质防护层上面为脚手板和铁皮;所述的硬质转换层包括若干个平行的工字钢主梁,每个工字钢主梁两端插入核心筒的侧壁内,相邻的工字钢主梁之间连接有角钢副梁,该硬质防护转换层的上面为脚手板和铁皮。
所述的榀桁架含有上横梁和下横梁,上下横梁之间连接有若干个斜撑,所述上横梁和下横梁均为角钢,在上横梁的两端设有加强辅助角钢,该加强辅助角钢和上横梁角钢对焊形成方管,在该方管内焊接有端部加强钢筋。
所述的上横梁和下横梁的中部均布有若干个中部加强钢筋组,该加强钢筋为两个,对称焊接在上横梁或下横梁角钢立板的两个表面。
所述的榀桁架两端通过支架与核心筒连接。
所述的支架为槽钢焊接成的三角形支架,该支架含有上部的支撑杆,贴墙的安装杆,以及斜撑杆,所述的安装杆通过穿墙螺栓固定安装在核心筒侧壁上。
所述的连接侧片含有两端的竖向立杆和中部的横杆,竖向立杆和横杆均为角钢,横杆的两端通过钢板和竖向立杆焊接在一起,所述的竖向立杆和所述的榀桁架侧面固定连接。
Claims (6)
1.一种核心筒内上下水平结构同时施工体系,该体系含有硬质防护层及硬质防护转换层,其特征是:所述的硬质防护层位于硬质转换层的上部,所述的硬质防护层包括若干个平行的榀桁架,每个榀桁架两端固定连接在核心筒的侧壁上,相邻的榀桁架之间设有连接侧片,该硬质防护层上面为脚手板和铁皮;所述的硬质转换层包括若干个平行的工字钢主梁,每个工字钢主梁两端插入核心筒的侧壁内,相邻的工字钢主梁之间连接有角钢副梁,该硬质防护转换层的上面为脚手板和铁皮。
2.根据权利要求1所述的核心筒内上下水平结构同时施工体系,其特征是:所述的榀桁架含有上横梁和下横梁,上下横梁之间连接有若干个斜撑,所述上横梁和下横梁均为角钢,在上横梁的两端设有加强辅助角钢,该加强辅助角钢和上横梁角钢对焊形成方管,在该方管内焊接有端部加强钢筋。
3.根据权利要求2所述的核心筒内上下水平结构同时施工体系,其特征是:所述的上横梁和下横梁的中部均布有若干个中部加强钢筋组,该加强钢筋为两个,对称焊接在上横梁或下横梁角钢立板的两个表面。
4.根据权利要求1所述的核心筒内上下水平结构同时施工体系,其特征是:所述的榀桁架两端通过支架与核心筒连接。
5.根据权利要求1所述的核心筒内上下水平结构同时施工体系,其特征是:所述的支架为槽钢焊接成的三角形支架,该支架含有上部的支撑杆,贴墙的安装杆,以及斜撑杆,所述的安装杆通过穿墙螺栓固定安装在核心筒侧壁上。
6.根据权利要求1所述的核心筒内上下水平结构同时施工体系,其特征是:所述的连接侧片含有两端的竖向立杆和中部的横杆,竖向立杆和横杆均为角钢,横杆的两端通过钢板和竖向立杆焊接在一起,所述的竖向立杆和所述的榀桁架侧面固定连接。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010102400053A CN101906820B (zh) | 2010-07-29 | 2010-07-29 | 核心筒内上下水平结构同时施工体系 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010102400053A CN101906820B (zh) | 2010-07-29 | 2010-07-29 | 核心筒内上下水平结构同时施工体系 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101906820A CN101906820A (zh) | 2010-12-08 |
| CN101906820B true CN101906820B (zh) | 2013-12-04 |
Family
ID=43262395
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2010102400053A Active CN101906820B (zh) | 2010-07-29 | 2010-07-29 | 核心筒内上下水平结构同时施工体系 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101906820B (zh) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103015693A (zh) * | 2012-11-28 | 2013-04-03 | 泰兴市第一建筑安装工程有限公司 | 一种超高层核心筒梁板结构立体施工装置 |
| CN106065668B (zh) * | 2016-08-01 | 2019-03-19 | 中建八局第四建设有限公司 | 一种建筑施工方法 |
| CN107905379B (zh) * | 2017-10-27 | 2019-09-06 | 中国建筑第八工程局有限公司 | 超高层建筑核心筒内全封闭层施工方法 |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5007501A (en) * | 1989-09-01 | 1991-04-16 | Baston Peter J | Apparatus for facilitating the internal inspection and repair of large pressure vessels |
| CN2191248Y (zh) * | 1994-04-09 | 1995-03-08 | 电力工业部电力建设研究所 | 烟囱滑模施工钢结构平台 |
| CN1313923A (zh) * | 1999-07-28 | 2001-09-19 | 汇隆棚业有限公司 | 脚手架 |
| CN101333869A (zh) * | 2008-07-03 | 2008-12-31 | 上海市第四建筑有限公司 | 整体提升钢平台整体穿越桁架层施工方法 |
| CN101696566A (zh) * | 2009-09-21 | 2010-04-21 | 中冶建工有限公司 | 多层立交桥脚手架施工方法 |
| CN201512940U (zh) * | 2009-09-27 | 2010-06-23 | 巢湖皖东架业有限公司 | 门式建筑脚手架 |
| CN101824905A (zh) * | 2010-06-04 | 2010-09-08 | 中建三局建设工程股份有限公司 | 装配式可变钢桁架平台及其布置方法和组装方法 |
| CN201762974U (zh) * | 2010-07-29 | 2011-03-16 | 中建三局建设工程股份有限公司 | 核心筒内上下水平结构同时施工体系 |
-
2010
- 2010-07-29 CN CN2010102400053A patent/CN101906820B/zh active Active
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5007501A (en) * | 1989-09-01 | 1991-04-16 | Baston Peter J | Apparatus for facilitating the internal inspection and repair of large pressure vessels |
| CN2191248Y (zh) * | 1994-04-09 | 1995-03-08 | 电力工业部电力建设研究所 | 烟囱滑模施工钢结构平台 |
| CN1313923A (zh) * | 1999-07-28 | 2001-09-19 | 汇隆棚业有限公司 | 脚手架 |
| CN101333869A (zh) * | 2008-07-03 | 2008-12-31 | 上海市第四建筑有限公司 | 整体提升钢平台整体穿越桁架层施工方法 |
| CN101696566A (zh) * | 2009-09-21 | 2010-04-21 | 中冶建工有限公司 | 多层立交桥脚手架施工方法 |
| CN201512940U (zh) * | 2009-09-27 | 2010-06-23 | 巢湖皖东架业有限公司 | 门式建筑脚手架 |
| CN101824905A (zh) * | 2010-06-04 | 2010-09-08 | 中建三局建设工程股份有限公司 | 装配式可变钢桁架平台及其布置方法和组装方法 |
| CN201762974U (zh) * | 2010-07-29 | 2011-03-16 | 中建三局建设工程股份有限公司 | 核心筒内上下水平结构同时施工体系 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101906820A (zh) | 2010-12-08 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203924696U (zh) | 顶模挂架快装体系 | |
| CN107060275B (zh) | 一种模块化电梯井道施工工艺 | |
| CN201661021U (zh) | 预制钢筋砼楼梯 | |
| CN103422434B (zh) | 波形钢板组合结构桥面系 | |
| CN207296386U (zh) | 一种施工电梯与爬模架体的组合结构 | |
| CN201762974U (zh) | 核心筒内上下水平结构同时施工体系 | |
| CN101914947A (zh) | 超高层的新型框架-核心筒混合结构体系 | |
| CN102454218B (zh) | 钢筋混凝土核心筒与装配整体式空间钢网格的筒中筒结构 | |
| CN101906820B (zh) | 核心筒内上下水平结构同时施工体系 | |
| CN202466844U (zh) | 钢管混凝土柱与型钢混凝土梁顶层节点连接结构 | |
| CN204455858U (zh) | 一种大节段钢箱梁的吊耳 | |
| CN201778389U (zh) | 超高层的新型框架-核心筒混合结构体系 | |
| CN202215006U (zh) | 施工用工具式爬梯 | |
| CN202220400U (zh) | 搭接式模架支撑梁 | |
| CN201211999Y (zh) | 大跨度自动扶梯桁架及由其构成的大跨度自动扶梯 | |
| CN205591450U (zh) | 一种悬挂式楼梯 | |
| CN110469054B (zh) | 一种格构式钢骨混凝土组合柱梁柱节点 | |
| CN211473320U (zh) | 一种用于连廊处的工具式外挂架 | |
| CN204780601U (zh) | 钢筋节段拼装胎架 | |
| CN201843089U (zh) | 检修立交桥匝道桥的垂直升降仓 | |
| CN203782619U (zh) | 一种施工台车 | |
| CN210002576U (zh) | 一种斜钢骨柱与斜钢骨梁的连接结构 | |
| CN205116431U (zh) | 梁柱偏心对齐的连接结构 | |
| CN213806076U (zh) | 一种新型建筑安全施工组合板 | |
| CN206256537U (zh) | 带栏杆的大跨钢连廊 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |