CN101892849B - Reinforcing steel bar laying trolley - Google Patents

Reinforcing steel bar laying trolley Download PDF

Info

Publication number
CN101892849B
CN101892849B CN2010102290335A CN201010229033A CN101892849B CN 101892849 B CN101892849 B CN 101892849B CN 2010102290335 A CN2010102290335 A CN 2010102290335A CN 201010229033 A CN201010229033 A CN 201010229033A CN 101892849 B CN101892849 B CN 101892849B
Authority
CN
China
Prior art keywords
rocker actuator
bracing frame
steel bar
reinforcing
reinforcing steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010102290335A
Other languages
Chinese (zh)
Other versions
CN101892849A (en
Inventor
雷军
赵勇
高原荣之
李自力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHUANRONG HEAVY INDUSTRY MACHINERY (CHANGZHOU) Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
CHUANRONG HEAVY INDUSTRY MACHINERY (CHANGZHOU) Co Ltd
Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHUANRONG HEAVY INDUSTRY MACHINERY (CHANGZHOU) Co Ltd, Second Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical CHUANRONG HEAVY INDUSTRY MACHINERY (CHANGZHOU) Co Ltd
Priority to CN2010102290335A priority Critical patent/CN101892849B/en
Publication of CN101892849A publication Critical patent/CN101892849A/en
Application granted granted Critical
Publication of CN101892849B publication Critical patent/CN101892849B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to the mechanical parts technical field in tunnel excavating, in particular to a reinforcing steel bar laying trolley. The device comprises a travelling device, a rack, a traverse device, an arc support frame and a rocker; wherein the bottom of the rack is provided with the travelling device, and the rocker and the arc support frame are connected. The traverse device is arranged between the rack and the arc support frame. The invention can effectively ensure the contour dimension of reinforcement cage to meet drawing requirement, structure is simple, operation is convenient, performance is reliable, labour intensity is greatly reduced, and the gap in China is filled.

Description

Reinforcing steel bar laying trolley
Technical field
The present invention relates to mechanical parts technical field in tunnel excavating, especially a kind of reinforcing steel bar laying trolley.
Background technology
At present, in the mining process of state's inner tunnel, the laying of lining cutting reinforcing bar does not still have Special Equipment with shaping.What now, the laying of reinforcing bar was mostly adopted is simple and easy stand.In the practical operation, earlier reinforcing bar is detoured a week along stand (tunnel) section, behind reinforcing bar and tunnel bottom binding reinforcing bars, because himself rigidity and pliability effect, reinforcing bar swells automatically.At last, by artificial binding reinforcing bars in a row is become reinforcing cage.This mode of operation is difficult to not only guarantee that the shape and size of reinforcing cage meet the drawing requirement, and labour intensity is big, and efficient is low, the cost height.
Summary of the invention
For the laying labour intensity that overcomes existing reinforcing bar is big, efficient is low, and the deficiency that cost is high the invention provides a kind of reinforcing steel bar laying trolley.
The technical solution adopted for the present invention to solve the technical problems is: a kind of reinforcing steel bar laying trolley, this device comprises running gear, stand, Traverse Displacement Unit, arc bracing frame and rocker actuator, described stand bottom is provided with running gear, described rocker actuator and arc bracing frame and to wait to lay between the reinforcing cage all be the hinge connection.The outer forming surface equidistant parallel of described arc bracing frame and reinforcing cage internal layer forming surface and reinforcing cage, described Traverse Displacement Unit is between stand and arc bracing frame.
According to another embodiment of the invention, comprise that further described rocker actuator is at least 8 groups.
According to another embodiment of the invention, comprise that further the hinge connecting hole is at least 2 in the described rocker actuator.
According to another embodiment of the invention, further comprise between described rocker actuator and the arc bracing frame and being connected for hinge.
The invention has the beneficial effects as follows that the present invention can guarantee effectively that reinforcing cage appearance and size satisfies the drawing requirement, simple in structure, easy to operate, dependable performance greatly reduces labour intensity, and fills up a domestic blank.
Description of drawings
The present invention is further described below in conjunction with drawings and Examples.
Fig. 1 is a structural representation of the present invention;
Fig. 2 is the action schematic diagram of rocker actuator.
1. running gears among the figure, 2. stand, 3. Traverse Displacement Unit, 4. arc bracing frame, 5. rocker actuator, 6. reinforcing cage internal layer forming surface, the 7. outer forming surface of reinforcing cage, 8. rocking bar is propped state, 9. rocking bar collapsed state, 10. hinge.
The specific embodiment
As Fig. 1 is structural representation of the present invention, a kind of reinforcing steel bar laying trolley, this device comprises running gear 1, stand 2, Traverse Displacement Unit 3, arc bracing frame 4 and rocker actuator 5, and described stand 2 bottoms are provided with running gear 1, and described rocker actuator 5 is connected with arc bracing frame 4.Described Traverse Displacement Unit 3 is between stand 2 and arc bracing frame 4.
Described rocker actuator 5 is at least 8 groups.Guarantee the reliably accurately moulding of reinforcing bar in the tunnel.
The hinge connecting hole is at least 2 in the described rocker actuator 5.Hinge connecting hole in the rocker actuator 5 can adopt two holes, three holes even porous, to satisfy the requirement of the different outer dimension reinforcing cages of same inner layer.
Be connected for hinge 10 between described rocker actuator 5 and the arc bracing frame 4.Rocker actuator 5 is around hinge 10 rotation, can realize that rocking bar props freely switching of state 8 and rocking bar folding and unfolding state 9.Rocking bar is propped outer, the internal layer size of state 8 and the corresponding reinforcing cage of rocking bar folding and unfolding state 9 difference, can guarantee that the reinforcing cage size satisfies the drawing requirement.
Described arc bracing frame 4 and reinforcing cage internal layer forming surface 6 and outer forming surface 7 equidistant parallels of reinforcing cage.
The action schematic diagram that as Fig. 2 is rocker actuator is when rocker actuator 5 all is in when propping state, and the connection pipe outermost point of rocker actuator 5 forms the reinforcing bar forming dimension of the outer forming surface 7 of reinforcing cage; When rocker actuator 5 all is in the folding and unfolding state,, the connection pipe outermost point of rocker actuator 5 forms the reinforcing bar forming dimension of reinforcing cage internal layer forming surface 6; Arc bracing frame 4 adopts articulated manner with rocker actuator 5, so propping with folding and unfolding of rocker actuator 5 is not only easy and simple to handle, and dependable performance.
Among Fig. 1, arc bracing frame 4 is the equidistant parallel face with reinforcing cage internal layer forming surface 6, the outer forming surface 7 of reinforcing cage, can guarantee that the shape that reinforcing cage is shaped satisfies the drawing requirement, and neat appearance, attractive in appearance.
Among Fig. 1, the employing of Traverse Displacement Unit 3 can easily realize the centering requirement of reinforcing cage in the tunnel cross-section direction.
Among Fig. 2, be connected for hinge 10 between rocker actuator 5 and the arc bracing frame 4, rocker actuator 5 is around hinge 10 rotations, can realize that rocking bar props freely switching of state 8 and rocking bar folding and unfolding state 9.Rocking bar is propped outer, the internal layer size of state 8 and the corresponding reinforcing cage of rocking bar folding and unfolding state 9 difference, can guarantee that the reinforcing cage size satisfies the drawing requirement.
Among Fig. 2, hinge connecting hole in the rocker actuator 5 can adopt two holes, three holes even porous, to satisfy the requirement of the different outer dimension reinforcing cages of same inner layer.The present invention can guarantee effectively that reinforcing cage appearance and size satisfies the drawing requirement, and simple in structure, easy to operate, dependable performance greatly reduces labour intensity, and fills up a domestic blank.

Claims (4)

1. reinforcing steel bar laying trolley, it is characterized in that, this device comprises running gear (1), stand (2), Traverse Displacement Unit (3), arc bracing frame (4) and rocker actuator (5), described stand (2) bottom is provided with running gear (1), described rocker actuator (5) and arc bracing frame (4) and to wait to lay between the reinforcing cage all be the hinge connection; Described arc bracing frame (4) and reinforcing cage internal layer forming surface (6) and outer forming surface (7) equidistant parallel of reinforcing cage, described Traverse Displacement Unit (3) is positioned between stand (2) and the arc bracing frame (4).
2. reinforcing steel bar laying trolley according to claim 1 is characterized in that, described rocker actuator (5) is at least 8 groups.
3. reinforcing steel bar laying trolley according to claim 1 is characterized in that, the hinge connecting hole is at least 2 in the described rocker actuator (5).
4. according to claim 1 or 3 described reinforcing steel bar laying trolleys, it is characterized in that, be connected for hinge (10) between described rocker actuator (5) and the arc bracing frame (4).
CN2010102290335A 2010-07-19 2010-07-19 Reinforcing steel bar laying trolley Expired - Fee Related CN101892849B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102290335A CN101892849B (en) 2010-07-19 2010-07-19 Reinforcing steel bar laying trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102290335A CN101892849B (en) 2010-07-19 2010-07-19 Reinforcing steel bar laying trolley

Publications (2)

Publication Number Publication Date
CN101892849A CN101892849A (en) 2010-11-24
CN101892849B true CN101892849B (en) 2011-12-14

Family

ID=43102179

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102290335A Expired - Fee Related CN101892849B (en) 2010-07-19 2010-07-19 Reinforcing steel bar laying trolley

Country Status (1)

Country Link
CN (1) CN101892849B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102418537B (en) * 2011-10-31 2014-03-12 招商局重庆交通科研设计院有限公司 Reinforcing steel bar binding method capable of accurately positioning tunnel lining reinforcing steel bars
CN103774694B (en) * 2013-11-29 2016-06-01 中交第二航务工程局有限公司 A kind of adjustable Steel Reinforcement Cage location moulding bed
CN105736016B (en) * 2016-04-27 2018-01-19 中铁四局集团第一工程有限公司 Tunnel double-lining framework of steel reinforcement construction equipment and its application
CN106050272B (en) * 2016-07-25 2017-12-08 中车建设工程有限公司 Multifunctional rack for installing lining steel bars and laying waterproof boards special for tunnels
CN108868824B (en) * 2018-06-29 2023-08-22 涪特智能装备(重庆)有限公司 Tunnel two-lining annular reinforcing steel bar laying trolley and laying method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10135748C1 (en) * 2001-07-21 2002-08-22 Walter Bau Ag Reinforced concrete tunnel lining formation device has positioning carriage between concrete reinforcement carriage and shuttering carriage
CN101230785A (en) * 2008-02-22 2008-07-30 中铁二局股份有限公司 Construction method for large section and multiple sections tunnel lining
CN101586464A (en) * 2008-05-22 2009-11-25 中铁十一局集团第一工程有限公司 Construction method of railway tunnel lining side wall concrete
CN201843621U (en) * 2010-07-19 2011-05-25 川荣重工机械常州有限公司 Reinforcing steel bar laying trolley

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005048382A (en) * 2003-07-30 2005-02-24 Sumitomo Mitsui Construction Co Ltd Work truck, and tunnel excavator equipped with the work truck
JP3968362B2 (en) * 2004-11-04 2007-08-29 社団法人日本建設機械化協会 Tunnel repair work vehicle

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10135748C1 (en) * 2001-07-21 2002-08-22 Walter Bau Ag Reinforced concrete tunnel lining formation device has positioning carriage between concrete reinforcement carriage and shuttering carriage
CN101230785A (en) * 2008-02-22 2008-07-30 中铁二局股份有限公司 Construction method for large section and multiple sections tunnel lining
CN101586464A (en) * 2008-05-22 2009-11-25 中铁十一局集团第一工程有限公司 Construction method of railway tunnel lining side wall concrete
CN201843621U (en) * 2010-07-19 2011-05-25 川荣重工机械常州有限公司 Reinforcing steel bar laying trolley

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
JP特开2005-48382A 2005.02.24
JP特开2006-132119A 2006.05.25
余建恩.浅埋大跨隧道衬砌施工技术.《隧道建设》.2002,第22卷(第4期),20-23,26. *
李晓华等.隧洞混凝土衬砌先边顶拱后仰拱的施工方案.《水利水电技术》.2007,第38卷(第1期),59-61. *

Also Published As

Publication number Publication date
CN101892849A (en) 2010-11-24

Similar Documents

Publication Publication Date Title
CN101892849B (en) Reinforcing steel bar laying trolley
CN201843621U (en) Reinforcing steel bar laying trolley
CN204176136U (en) A kind of removable pump line switches support
CN202967052U (en) Wax mask placing support
CN203129587U (en) Screen type multi-angle combined support template
CN202820798U (en) Detachable clothes hanger
CN205189766U (en) Be fit for wheeled whole rig substructure connection structure who drags
CN101775990B (en) Three-dimensional space curved surface steel mould trolley
CN203076906U (en) Cross beam of computerized numerical control (CNC) planer type milling machine
CN203175556U (en) Rear supporting mechanism of continuous miner
CN203321028U (en) Pull rod type telescopic arm for stereo garage
CN202899437U (en) Prefabricated crossbeam
CN205876349U (en) Whole die carrier of tunnel construction inverted arch of growing up
CN202706328U (en) Cantilever support mechanism for building concrete structure
CN204146948U (en) A kind of window cleaning equipment single oil cylinder autobalance
CN205234121U (en) Multifunctional flowerpot frame
CN203998370U (en) Unpowered frame rocking arm automatic reversing apparatus
CN202247209U (en) Middle-mountain cam
CN202706329U (en) Girder reinforcing mechanism for construction concrete structure
CN201507073U (en) steelbar and plastic spacer block
CN203212775U (en) Support for warp knitting machine
CN203265563U (en) Dummy ingot storing mechanism suitable for small strand distance
CN204435851U (en) Building structure template support and building structure template assembly
CN202064962U (en) Rail type full round needle beam trolley
CN201890564U (en) Rack structure of chain conveyor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB03 Change of inventor or designer information

Inventor after: Lei Jun

Inventor after: Zhao Yong

Inventor after: Takahara Eino

Inventor after: Li Zili

Inventor before: Lei Jun

Inventor before: Zhao Yong

Inventor before: Takahara Eino

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LEI JUN ZHAO YONG GAOYUAN RONGZHI TO: LEI JUN ZHAO YONG GAOYUAN RONGZHI LIZILI

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111214

Termination date: 20140719

EXPY Termination of patent right or utility model