CN101881169A - Sublevel shrinkage caving stage open stope afterwards filling mining method - Google Patents

Sublevel shrinkage caving stage open stope afterwards filling mining method Download PDF

Info

Publication number
CN101881169A
CN101881169A CN 201010217733 CN201010217733A CN101881169A CN 101881169 A CN101881169 A CN 101881169A CN 201010217733 CN201010217733 CN 201010217733 CN 201010217733 A CN201010217733 A CN 201010217733A CN 101881169 A CN101881169 A CN 101881169A
Authority
CN
China
Prior art keywords
sublevel
ore
mining
caving
shrinkage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010217733
Other languages
Chinese (zh)
Inventor
徐庚举
孙豁然
柳小波
贾海波
李启轩
张洪海
刘永会
马吉祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YANTAI JINJIAN DESIGN RESEARCH ENGINEERING Co Ltd
Northeastern University China
Original Assignee
YANTAI JINJIAN DESIGN RESEARCH ENGINEERING Co Ltd
Northeastern University China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YANTAI JINJIAN DESIGN RESEARCH ENGINEERING Co Ltd, Northeastern University China filed Critical YANTAI JINJIAN DESIGN RESEARCH ENGINEERING Co Ltd
Priority to CN 201010217733 priority Critical patent/CN101881169A/en
Publication of CN101881169A publication Critical patent/CN101881169A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a sublevel shrinkage caving stage open afterwards filling mining method. In the earlier stage of stoping, caved ores are utilized to support surrounding rocks on a top tray, and in the later stage of stoping, a goaf area is filled with fillers to control ground pressure so as to achieve safe and efficient mining. Ore blocks are mined in two steps, mining blocks in step two are stoped after the mining blocks in step one are stoped and filled. After the ores are completely let out, the goaf area is filled with the fillers to control the ground pressure. Because the stoping modes of sublevel ore caving, sublevel shrinkage, final ore drawing and empty area afterwards filling are adopted, the mining method has large one-time filling amount and low cost; the method adopts middle-deep hole drilling and blasting and carry scraper ore removal, and the device has high level and large production capacity; the method has the advantages of large production capacity of the sublevel caving method and the stage open stope method, high recovery rate of the filling method, and earth surface protection; the safety is good, and drilling, ore removal and other operations are all carried out in a sublevel drilling and ore removal approach roadway; and the ores can be removed in advance, and the ores can be removed partially after the first sublevel is ready.

Description

A kind of sublevel shrinkage caving stage open stope afterwards filling mining method
Technical field
The present invention relates to metalliferous deposit actual mining technology field, the mining methods that particularly provide a kind of sublevel shrinkage caving mining codes to combine with stage open stope afterwards filling mining method.
Background technology
Metalliferous deposit during by back production the underground pressure management method be divided into openstope method, the method for mining by the way of filling and caved stopes three major types.Caved stopes is low with cost, efficient is high, job safety, has obtained using widely at metal mine and non-metal mine.But it is higher that its maximum defective is the loss late of ore and the rate of dilution, causes mineral resources to waste in a large number.Ore loss ratio, the basic reason that the rate of dilution is big are the ore drawing modes of cut off grade ore drawing under the covering layer, and the ore deposit rock at the drawhole place a large amount of doping has taken place.
Sweden Ji Lvna iron ore is tested the sublevel shrinkage caving mining codes since the seventies in last century, sublevel caving method without sill pillar is combined with sill pillars sublevel caving method, ore major part under extracting drift collapses stays put and emits by the stope bottom at last, not immediate shipments, ore deposit rock contact area is relatively little, and loss late, the rate of dilution are effectively controlled.This mining methods also obtain certain popularization in China, but in some mine because the face of land or top ore body need protection, it is former thereby can not use that the face of land does not allow to subside etc.
Summary of the invention
The objective of the invention is to problem at above existence, be metal and nonmetal mine inclination gentle dip, be as thin as the mining methods that middle thickness orebody provides a kind of loss and dilution is low, safe and efficient, cost is low novel sublevel shrinkage caving mining codes to combine with stage open stope mining afterwards filling method.
The technical scheme of technical solution problem of the present invention is: mining methods of the present invention, according to mining technology characteristics and country rock physico-mechanical properties, back production utilizes broken ore to support country rock in earlier stage, press on back production later-stage utilization casting resin bashing control ground, to reach safe and efficient mining.
Concrete grammar is: nugget is back production in two steps, after a step, mining blocks back production filling was finished, and two step of back production mining blocks.Nugget vertically is divided into plurality of segments, arranges the segmentation tunnel along orebody trend at the ore body lower wall, keeps at a certain distance away from the vertical orebody trend in segmentation tunnel and tunnels rock drilling ore removal route arrival dish, as the main tunnel of back production.Each segmentation explosion back production from top to bottom, explosion in rock drilling ore removal route from coil and advance to lower wall, emit about 30% of each quick-fried ore that falls by the rock drilling route, all the other are left to, and the stage casing explosion is intact emits from the stope bottom, the bottom ore drawing from lower wall upwards dish carry out successively.After ore is all emitted, use the casting resin bashing, press on control ground.
Technique effect of the present invention is: owing to adopted the back production mode of segmentation ore caving, segmentation shrink, final draw, afterwards filling dead zone, this mining methods primary filling amount is big, and cost is low; Adopt medium-length hole drilling and blasting, scraper ore removal, equipment height, production capacity are big; Ore under quick-fried can have interim supporting role to the obturation of country rock and exposure; An a large amount of ore removal stage is arranged, help guaranteeing the output equilibrium than layering, sublevel fill stoping method; Back production and filling operation are not disturbed mutually, and restricting relation is few than layering, sublevel fill stoping method.It is big and the filling method rate of recovery is high and the advantage on the protection face of land to have sublevel caving method, stage open stope method production capacity concurrently: safety is good, and operations such as rock drilling ore removal are all carried out in sublevel drilling ore removal approach roadway; Can shift to an earlier date ore removal, after first segmentation is ready to, can the part ore removal.
Description of drawings
Fig. 1 is the vertical perspective view of concrete structure of the present invention.
Fig. 2 is a concrete structure vertical view of the present invention.
Fig. 3 is a concrete structure sectional drawing of the present invention.
1, lower wall haulage way, 2, the segmentation tunnel, 3, the segmentation connection roadway, 4, People's Bank of China's ventilating shaft, 5, extracting drift, 6, filling well, 7, the airway, 8, the cutting tunnel, 9, slot raise, 10, fanhole(s), 11, drop shaft, 12, the ore removal route, 13, the moat ditch, 14, the ore removal tunnel.
The specific embodiment
Describe in detail below in conjunction with drawings and Examples:
As Fig. 1, Fig. 2 and shown in Figure 3,,, and coil on prolongation construction extracting drift (5) the arrival ore body by People's Bank of China's ventilating shaft (4) construction segmentation connection roadway (3) at ore body lower wall driving lower wall haulage way (1).Along last web circle construction cutting tunnel (8) and slot raise (9), be the production ore space that affords redress, explosion is gone up dish certainly along extracting drift (12) and is carried out successively to lower wall, the parallel fanhole(s) of Drilling (10), the quick-fried ore that falls transports about 30% by segmentation tunnel (2), remaining ore is stayed in the stope, at last by moat ditch (13), ore removal route (12), ore removal tunnel (14) and drop shaft (11) ore removal.
Constitute ventilation circuit by lower wall haulage drift (1), People's Bank of China's ventilating shaft (4), segmentation tunnel (2), segmentation connection roadway (3), airway (7) etc., ensure district ventilation.
The back production initial stage can be played stably the effect of pressing owing to persist ore, ore removal in a large number in the extracting drift, so the underground pressure management input is little, engineering maintenance is easier to.The stage casing back production is carried out underground pressure management by filling well (6) filling dead zone after finishing, for the back production in next stage casing provides condition.
The present invention is that the embodiment that mentions with reference to the accompanying drawings is illustrated, and this is one of them embodiment, and those skilled in the art can obtain to inspire from embodiment, is out of shape to obtain other embodiment.Therefore, protection scope of the present invention should be determined according to the protection domain of claim.

Claims (5)

1. sublevel shrinkage caving stage open stope afterwards filling mining method is characterized in that: back production utilizes broken ore to support country rock in earlier stage, and press on back production later-stage utilization casting resin bashing control ground, to reach safe and efficient mining.
2. sublevel shrinkage caving stage open stope afterwards filling mining method according to claim 1, it is characterized in that: nugget is back production in two steps, after a step, mining blocks back production filling was finished, two step of back production mining blocks.
3. sublevel shrinkage caving stage open stope afterwards filling mining method according to claim 1, it is characterized in that: nugget vertically is divided into plurality of segments, arrange the segmentation tunnel along orebody trend at the ore body lower wall, arrive and coil from the vertical orebody trend in the segmentation tunnel driving rock drilling ore removal route that keeps at a certain distance away, as the main tunnel of back production.
4. sublevel shrinkage caving stage open stope afterwards filling mining method according to claim 1, it is characterized in that: each segmentation explosion back production from top to bottom, explosion in rock drilling ore removal route from coil and advance to lower wall, emit about 30% of each quick-fried ore that falls by the rock drilling route, all the other are left to, and the stage casing explosion is intact emits from the stope bottom, and the bottom ore drawing upwards coils from lower wall and carries out successively.
5. sublevel shrinkage caving stage open stope afterwards filling mining method according to claim 1 is characterized in that: after ore is all emitted, use the casting resin bashing, press on control ground.
CN 201010217733 2010-06-25 2010-06-25 Sublevel shrinkage caving stage open stope afterwards filling mining method Pending CN101881169A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010217733 CN101881169A (en) 2010-06-25 2010-06-25 Sublevel shrinkage caving stage open stope afterwards filling mining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010217733 CN101881169A (en) 2010-06-25 2010-06-25 Sublevel shrinkage caving stage open stope afterwards filling mining method

Publications (1)

Publication Number Publication Date
CN101881169A true CN101881169A (en) 2010-11-10

Family

ID=43053288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010217733 Pending CN101881169A (en) 2010-06-25 2010-06-25 Sublevel shrinkage caving stage open stope afterwards filling mining method

Country Status (1)

Country Link
CN (1) CN101881169A (en)

Cited By (49)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155226A (en) * 2010-11-30 2011-08-17 淄博市王庄煤矿 Roadway backfill mining method for coal seams with medium-high thickness
CN102155228A (en) * 2011-02-21 2011-08-17 中南大学 Fully-segmented presplitting squeezing primary-blasting mining method
CN102305074A (en) * 2011-08-15 2012-01-04 鞍钢集团矿业公司 Flat-bottomed pillar sublevel caving method of reinforced concrete structure artificial roof
CN102418528A (en) * 2011-08-15 2012-04-18 鞍钢集团矿业公司 End ore-drawing caving mining technology with high efficient using steel concrete composite man-made false roofs
CN102635356A (en) * 2012-04-26 2012-08-15 中南大学 Medium-length hole mining method in multiple blasting free faces of high dipping thin veins
CN102635358A (en) * 2012-04-26 2012-08-15 辽宁科技大学 Sill pillar-free block caving method mining process capable of reducing waste rock interfusion amount through water injection
CN102644464A (en) * 2012-04-12 2012-08-22 东北大学 Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine
CN102678121A (en) * 2012-05-21 2012-09-19 山东黄金矿业(莱州)有限公司三山岛金矿 Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN102720500A (en) * 2012-05-24 2012-10-10 青海山金矿业有限公司 Mechanized underground mining method for sharply inclined thin ore body
CN102748029A (en) * 2012-07-05 2012-10-24 北京矿冶研究总院 Segmented mining method
CN102817614A (en) * 2012-05-29 2012-12-12 中钢集团马鞍山矿山研究院有限公司 Stope structure arrangement mode suitable for underground mine high productivity and low cost subsequent filling
CN103184870A (en) * 2013-03-05 2013-07-03 安徽金日盛矿业有限责任公司 Open backfilling mining method during borehole drilling period
CN103362510A (en) * 2013-08-01 2013-10-23 广西大学 Sublevel-drilling bench-combination ore-removal sublevel-room mining method
CN103527200A (en) * 2013-10-25 2014-01-22 河北省矾山磷矿有限公司 Sill-pillar-free sublevel rhombus room subsequent filling mining method
CN103615250A (en) * 2013-12-09 2014-03-05 中南大学 Subsection-studding all-open-stoping backfilling collaborative mining method
CN103775086A (en) * 2013-12-27 2014-05-07 马钢(集团)控股有限公司 Access open stope afterward filling and mining method
CN103967494A (en) * 2014-04-21 2014-08-06 安徽大昌矿业集团有限公司 Mining method for filling after shallow hole shrinkage
CN104153782A (en) * 2014-07-29 2014-11-19 长沙矿山研究院有限责任公司 Progressive caving mining method
CN104179505A (en) * 2014-02-12 2014-12-03 云南磷化集团有限公司 Phosphorus ore underground mining method
CN104343454A (en) * 2014-09-05 2015-02-11 昆明冶金研究院 Mechanical point-column type chamber and pillar method
CN104481543A (en) * 2014-12-05 2015-04-01 西安建筑科技大学 Sub-level shrinkage caving method
CN104612692A (en) * 2014-12-11 2015-05-13 中南大学 Following-forming continuous-filling mining method for segmented ore-caving bottom structure
CN104632220A (en) * 2014-12-09 2015-05-20 中南大学 Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope
CN104747190A (en) * 2015-04-02 2015-07-01 广西大学 Thin ore-body mechanized highly-layering continuous mining method
CN104806244A (en) * 2015-04-03 2015-07-29 东北大学 Filling mining method for slant middle-thick ore body
CN104863592A (en) * 2015-06-18 2015-08-26 长沙矿山研究院有限责任公司 Large-structure sublevel drilling stage ore removal mining method with delayed filling
CN104989407A (en) * 2015-06-10 2015-10-21 甘肃酒钢集团宏兴钢铁股份有限公司 Copper mine T-shaped cutting slot broaching method
CN105178961A (en) * 2015-09-01 2015-12-23 安徽金日盛矿业有限责任公司 Open-stope subsequent filling mining method in wide stope borehole drilling phase
CN105201506A (en) * 2015-09-06 2015-12-30 东北大学 Ore mining method adopting reinforcement before connection and filling after connection
CN105649631A (en) * 2016-03-02 2016-06-08 大冶有色金属有限责任公司 Efficient mechanical mining method for gently-inclined thin ore bodies
CN105673012A (en) * 2016-01-02 2016-06-15 武汉科技大学 Mining-filling combined continuous mining sublevel room mining method
CN106014414A (en) * 2016-05-24 2016-10-12 福建海峡科化富兴建设工程有限公司 Explosion stoping method for horizontal ore pillar of sublevel caving mining method
CN106089209A (en) * 2016-07-21 2016-11-09 广西大学 Flexible isolating layer serves as the sublevel caving on false top and works in coordination with mining methods
CN106121643A (en) * 2016-08-31 2016-11-16 湖北三鑫金铜股份有限公司 The reserved retaining wall ore deposit two step nesting combination method of mining by the way of filling
CN106437716A (en) * 2016-09-23 2017-02-22 北京矿冶研究总院 Method for mining underground crushed phosphorite
CN106522955A (en) * 2016-12-05 2017-03-22 广西大学 Studding recovery method for reconstructing covering layer through dead zone wastefill and top surrounding rock spallation collaboratively
CN107420103A (en) * 2017-07-06 2017-12-01 中国煤炭科工集团太原研究院有限公司 A kind of machine is adopted adopts the special thick solid potassium salt ore deposit recovery method being combined with big gun
CN107829742A (en) * 2017-11-27 2018-03-23 西北矿冶研究院 A kind of avalanche fills barnyard avalanche mining methods
CN107939399A (en) * 2017-11-25 2018-04-20 彝良驰宏矿业有限公司 A kind of more stage casings level pillar recovery method and into line structure under exploitation pattern at the same time
CN108316927A (en) * 2018-02-02 2018-07-24 长沙矿山研究院有限责任公司 A kind of stage Contining ore removal filling mining method
CN109025996A (en) * 2018-07-24 2018-12-18 周伟永 A kind of underground mine successively squeezes, photoface exploision mining methods
CN110388209A (en) * 2019-07-25 2019-10-29 长沙矿山研究院有限责任公司 A kind of high-dipping bilayer ore body stage deep hole mining method
CN110685737A (en) * 2019-09-02 2020-01-14 河北省矾山磷矿有限公司 Flat-bottom structure sublevel rock drilling stage ore removal subsequent filling mining method
CN111005721A (en) * 2019-11-25 2020-04-14 南华大学 Mining method of steeply inclined medium-thickness ore body
CN111779485A (en) * 2020-07-01 2020-10-16 长沙矿山研究院有限责任公司 Combined hole segmented open stope subsequent filling mining method
CN112031770A (en) * 2020-09-11 2020-12-04 中钢集团马鞍山矿山研究总院股份有限公司 Novel mining method suitable for multi-stope synchronous mining of thick and large ore body
CN112282837A (en) * 2020-10-27 2021-01-29 中冶沈勘秦皇岛工程设计研究总院有限公司 Novel underground mine mining and charging arrangement form
CN109490499B (en) * 2018-11-15 2021-02-05 长沙矿山研究院有限责任公司 Dynamic monitoring and predicting method for water quality of filling body
CN113047835A (en) * 2021-02-24 2021-06-29 中南大学 Deep well thick and large ore body mining method integrating emptying, caving and filling

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN86100824A (en) * 1986-01-31 1986-10-08 昆明工学院 Pillar-combinations for mining methods
RU2208162C1 (en) * 2001-12-07 2003-07-10 Институт горного дела СО РАН Method of mining of ore deposits by sublevel caving
RU2323337C2 (en) * 2005-12-14 2008-04-27 Институт горного дела Уральского отделения Российской академии наук Method for underground thick ore body mining
CN101737052A (en) * 2009-12-28 2010-06-16 河北邯邢矿冶设计院有限公司 Sublevel fill-mining method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN86100824A (en) * 1986-01-31 1986-10-08 昆明工学院 Pillar-combinations for mining methods
RU2208162C1 (en) * 2001-12-07 2003-07-10 Институт горного дела СО РАН Method of mining of ore deposits by sublevel caving
RU2323337C2 (en) * 2005-12-14 2008-04-27 Институт горного дела Уральского отделения Российской академии наук Method for underground thick ore body mining
CN101737052A (en) * 2009-12-28 2010-06-16 河北邯邢矿冶设计院有限公司 Sublevel fill-mining method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
《有色金属(矿山部分)》 20040531 饶运章,吴红 东乡铜矿分段崩落阶段矿房嗣后充填组合采矿法试验研究 第13页第1栏第2段至第15页第2栏,以及第35页第1-2栏,图1 1-5 第56卷, 第3期 2 *
《江西有色金属》 20000930 郭金峰 分段空场嗣后充填采矿方法的试验研究 8-10 1-5 第14卷, 第3期 2 *

Cited By (70)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155226A (en) * 2010-11-30 2011-08-17 淄博市王庄煤矿 Roadway backfill mining method for coal seams with medium-high thickness
CN102155228A (en) * 2011-02-21 2011-08-17 中南大学 Fully-segmented presplitting squeezing primary-blasting mining method
CN102418528B (en) * 2011-08-15 2013-11-06 鞍钢集团矿业公司 End ore-drawing caving mining technology with steel concrete composite man-made false roofs
CN102418528A (en) * 2011-08-15 2012-04-18 鞍钢集团矿业公司 End ore-drawing caving mining technology with high efficient using steel concrete composite man-made false roofs
CN102305074A (en) * 2011-08-15 2012-01-04 鞍钢集团矿业公司 Flat-bottomed pillar sublevel caving method of reinforced concrete structure artificial roof
CN102644464A (en) * 2012-04-12 2012-08-22 东北大学 Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine
CN102644464B (en) * 2012-04-12 2014-01-01 东北大学 Constructing method for mining embedded artificial boundary ore pillar from open-pit to underground mine
CN102635356A (en) * 2012-04-26 2012-08-15 中南大学 Medium-length hole mining method in multiple blasting free faces of high dipping thin veins
CN102635358A (en) * 2012-04-26 2012-08-15 辽宁科技大学 Sill pillar-free block caving method mining process capable of reducing waste rock interfusion amount through water injection
CN102635358B (en) * 2012-04-26 2014-03-12 辽宁科技大学 Pillar-free block caving method mining process capable of reducing waste rock interfusion amount through water injection
CN102678121A (en) * 2012-05-21 2012-09-19 山东黄金矿业(莱州)有限公司三山岛金矿 Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN102678121B (en) * 2012-05-21 2014-01-08 山东黄金矿业(莱州)有限公司三山岛金矿 Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN102720500A (en) * 2012-05-24 2012-10-10 青海山金矿业有限公司 Mechanized underground mining method for sharply inclined thin ore body
CN102817614B (en) * 2012-05-29 2014-12-17 中钢集团马鞍山矿山研究院有限公司 Stope structure arrangement mode suitable for underground mine high productivity and low cost subsequent filling
CN102817614A (en) * 2012-05-29 2012-12-12 中钢集团马鞍山矿山研究院有限公司 Stope structure arrangement mode suitable for underground mine high productivity and low cost subsequent filling
CN102748029A (en) * 2012-07-05 2012-10-24 北京矿冶研究总院 Segmented mining method
CN102748029B (en) * 2012-07-05 2015-03-11 北京矿冶研究总院 Segmented mining method
CN103184870A (en) * 2013-03-05 2013-07-03 安徽金日盛矿业有限责任公司 Open backfilling mining method during borehole drilling period
CN103362510A (en) * 2013-08-01 2013-10-23 广西大学 Sublevel-drilling bench-combination ore-removal sublevel-room mining method
CN103527200A (en) * 2013-10-25 2014-01-22 河北省矾山磷矿有限公司 Sill-pillar-free sublevel rhombus room subsequent filling mining method
CN103527200B (en) * 2013-10-25 2015-12-09 河北省矾山磷矿有限公司 Bottom-column-free sectional Rhombic room afterwards filling mining method
CN103615250A (en) * 2013-12-09 2014-03-05 中南大学 Subsection-studding all-open-stoping backfilling collaborative mining method
CN103775086A (en) * 2013-12-27 2014-05-07 马钢(集团)控股有限公司 Access open stope afterward filling and mining method
CN104179505B (en) * 2014-02-12 2016-01-20 云南磷化集团有限公司 A kind of underground mining method of phosphorus ore
CN104179505A (en) * 2014-02-12 2014-12-03 云南磷化集团有限公司 Phosphorus ore underground mining method
CN103967494A (en) * 2014-04-21 2014-08-06 安徽大昌矿业集团有限公司 Mining method for filling after shallow hole shrinkage
CN104153782A (en) * 2014-07-29 2014-11-19 长沙矿山研究院有限责任公司 Progressive caving mining method
CN104153782B (en) * 2014-07-29 2016-03-23 长沙矿山研究院有限责任公司 Progressive caving mining method
CN104343454A (en) * 2014-09-05 2015-02-11 昆明冶金研究院 Mechanical point-column type chamber and pillar method
CN104343454B (en) * 2014-09-05 2016-05-18 昆明冶金研究院 A kind of mechanization point pillar house column mining method
CN104481543A (en) * 2014-12-05 2015-04-01 西安建筑科技大学 Sub-level shrinkage caving method
CN104632220A (en) * 2014-12-09 2015-05-20 中南大学 Mining method with adjustable and controllable structure size of gentle dip medium-thickness ore body strip column reconstructed stope
CN104612692A (en) * 2014-12-11 2015-05-13 中南大学 Following-forming continuous-filling mining method for segmented ore-caving bottom structure
CN104612692B (en) * 2014-12-11 2016-07-27 中南大学 Formation continuous filling mining method followed by segmentation ore caving polycrystalline substance
CN104747190A (en) * 2015-04-02 2015-07-01 广西大学 Thin ore-body mechanized highly-layering continuous mining method
CN104747190B (en) * 2015-04-02 2017-04-26 广西大学 Thin ore-body mechanized highly-layering continuous mining method
CN104806244A (en) * 2015-04-03 2015-07-29 东北大学 Filling mining method for slant middle-thick ore body
CN104989407A (en) * 2015-06-10 2015-10-21 甘肃酒钢集团宏兴钢铁股份有限公司 Copper mine T-shaped cutting slot broaching method
CN104863592A (en) * 2015-06-18 2015-08-26 长沙矿山研究院有限责任公司 Large-structure sublevel drilling stage ore removal mining method with delayed filling
CN105178961A (en) * 2015-09-01 2015-12-23 安徽金日盛矿业有限责任公司 Open-stope subsequent filling mining method in wide stope borehole drilling phase
CN105178961B (en) * 2015-09-01 2018-09-28 安徽金日盛矿业有限责任公司 A kind of roomy stope borehole drilling stage open stope afterwards filling mining method
CN105201506A (en) * 2015-09-06 2015-12-30 东北大学 Ore mining method adopting reinforcement before connection and filling after connection
CN105673012A (en) * 2016-01-02 2016-06-15 武汉科技大学 Mining-filling combined continuous mining sublevel room mining method
CN105673012B (en) * 2016-01-02 2018-08-21 武汉科技大学 It is a kind of to adopt the block stoping filled in conjunction with continuously exploiting
CN105649631A (en) * 2016-03-02 2016-06-08 大冶有色金属有限责任公司 Efficient mechanical mining method for gently-inclined thin ore bodies
CN105649631B (en) * 2016-03-02 2017-09-26 大冶有色金属有限责任公司 A kind of efficient mining methods of the mechanization of slight slope and thin ore body
CN106014414B (en) * 2016-05-24 2018-02-06 福建海峡科化富兴建设工程有限公司 A kind of explosion stoping method of block stoping level pillar
CN106014414A (en) * 2016-05-24 2016-10-12 福建海峡科化富兴建设工程有限公司 Explosion stoping method for horizontal ore pillar of sublevel caving mining method
CN106089209A (en) * 2016-07-21 2016-11-09 广西大学 Flexible isolating layer serves as the sublevel caving on false top and works in coordination with mining methods
CN106121643B (en) * 2016-08-31 2018-08-14 湖北三鑫金铜股份有限公司 Reserved two step nesting of retaining wall mine combines the method for mining by the way of filling
CN106121643A (en) * 2016-08-31 2016-11-16 湖北三鑫金铜股份有限公司 The reserved retaining wall ore deposit two step nesting combination method of mining by the way of filling
CN106437716A (en) * 2016-09-23 2017-02-22 北京矿冶研究总院 Method for mining underground crushed phosphorite
CN106522955A (en) * 2016-12-05 2017-03-22 广西大学 Studding recovery method for reconstructing covering layer through dead zone wastefill and top surrounding rock spallation collaboratively
CN107420103A (en) * 2017-07-06 2017-12-01 中国煤炭科工集团太原研究院有限公司 A kind of machine is adopted adopts the special thick solid potassium salt ore deposit recovery method being combined with big gun
CN107939399A (en) * 2017-11-25 2018-04-20 彝良驰宏矿业有限公司 A kind of more stage casings level pillar recovery method and into line structure under exploitation pattern at the same time
CN107829742A (en) * 2017-11-27 2018-03-23 西北矿冶研究院 A kind of avalanche fills barnyard avalanche mining methods
CN107829742B (en) * 2017-11-27 2019-08-20 西北矿冶研究院 A kind of avalanche-filling-barnyard-avalanche mining methods
CN108316927B (en) * 2018-02-02 2019-11-19 长沙矿山研究院有限责任公司 A kind of stage Contining ore removal filling mining method
CN108316927A (en) * 2018-02-02 2018-07-24 长沙矿山研究院有限责任公司 A kind of stage Contining ore removal filling mining method
CN109025996A (en) * 2018-07-24 2018-12-18 周伟永 A kind of underground mine successively squeezes, photoface exploision mining methods
CN109025996B (en) * 2018-07-24 2019-12-10 周伟永 Underground mine layer-by-layer extrusion and smooth blasting mining method
CN109490499B (en) * 2018-11-15 2021-02-05 长沙矿山研究院有限责任公司 Dynamic monitoring and predicting method for water quality of filling body
CN110388209A (en) * 2019-07-25 2019-10-29 长沙矿山研究院有限责任公司 A kind of high-dipping bilayer ore body stage deep hole mining method
CN110685737A (en) * 2019-09-02 2020-01-14 河北省矾山磷矿有限公司 Flat-bottom structure sublevel rock drilling stage ore removal subsequent filling mining method
CN111005721A (en) * 2019-11-25 2020-04-14 南华大学 Mining method of steeply inclined medium-thickness ore body
CN111779485A (en) * 2020-07-01 2020-10-16 长沙矿山研究院有限责任公司 Combined hole segmented open stope subsequent filling mining method
CN112031770A (en) * 2020-09-11 2020-12-04 中钢集团马鞍山矿山研究总院股份有限公司 Novel mining method suitable for multi-stope synchronous mining of thick and large ore body
CN112282837A (en) * 2020-10-27 2021-01-29 中冶沈勘秦皇岛工程设计研究总院有限公司 Novel underground mine mining and charging arrangement form
CN113047835B (en) * 2021-02-24 2022-04-15 中南大学 Deep well thick and large ore body mining method integrating emptying, caving and filling
CN113047835A (en) * 2021-02-24 2021-06-29 中南大学 Deep well thick and large ore body mining method integrating emptying, caving and filling

Similar Documents

Publication Publication Date Title
CN101881169A (en) Sublevel shrinkage caving stage open stope afterwards filling mining method
CN102704934B (en) High-yield and low-cost subsequent filling mining method for underground mine
CN106223958B (en) The slant middle thick orebody subregion rock drilling stage falls ore deposit afterwards filling collaboration mining codes
CN103557002B (en) A kind of mechanized concentrates drop shaft filling-up method
CN103306720B (en) Inclined separated layer solid filling coal mining method for super thick coal seam
CN105649631B (en) A kind of efficient mining methods of the mechanization of slight slope and thin ore body
CN102392641B (en) Point pillar type full-ore-deposit middle-section-free upward high-layering continuous propelling fill mining method
CN103437769B (en) Combination is reproduced structure medium-length hole ore blast and is worked in coordination with cable bolting afterwards filling mining method
CN103967494B (en) A kind of shallow-hole shrinkage afterwards filling mining methods
CN102251773B (en) Route type upward horizontal layered filling mining method suitable for extremely complex ore body mining
CN101737052A (en) Sublevel fill-mining method
CN103104259A (en) Inclination fragmentation ore body segment top board reconstruction middle-deep hole ore break down filling mining method
CN104895566A (en) Mining method with residual ore recovery function
CN102953732A (en) Room-and-pillar major-diameter longhole inverted-step-like segmented lateral caving subsequent filling mining method
CN108547618A (en) A kind of two steps mining methods leave the recovery process of studding
CN108868771A (en) A kind of mining methods of horizontal medium-length hole back production slant middle thick orebody
CN105464700A (en) Method for determining length of filling segment of fully mechanized mining and filling mixed mining working face
Han et al. Multiple and long-term disturbance of gob-side entry retaining by grouped roof collapse and an innovative adaptive technology
CN103437768B (en) Pre-set space filling mining method without top column and bottom column
CN109869150B (en) Mine resource subsection full-mining local-charging mining method
CN103206215A (en) Precontrol top upward access cut-and-filling stopping method
CN103557001B (en) A kind of low section high oper cylinler shrink afterwards filling mining method
CN109209379A (en) A kind of mine, which picks up, fills+X exploitation pattern
CN109899070B (en) Slow-inclination medium-thickness ore body solid-waste-free filling mining method based on ellipsoid ore drawing structure
CN108104816A (en) A kind of rise working method of Steeply dipping narrow deposits

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20101110

C02 Deemed withdrawal of patent application after publication (patent law 2001)