CN101851898B - Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof - Google Patents
Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof Download PDFInfo
- Publication number
- CN101851898B CN101851898B CN2010101957163A CN201010195716A CN101851898B CN 101851898 B CN101851898 B CN 101851898B CN 2010101957163 A CN2010101957163 A CN 2010101957163A CN 201010195716 A CN201010195716 A CN 201010195716A CN 101851898 B CN101851898 B CN 101851898B
- Authority
- CN
- China
- Prior art keywords
- guide beam
- crane
- bridge
- lower guide
- trolley
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种能通过隧道且实现隧道口架梁的架桥机,尤其涉及一种山岭地区的快速施工的架桥设备,具体涉及一种新型过隧道及隧道口架梁的架桥机。The invention relates to a bridge erecting machine capable of passing through tunnels and erecting girders at tunnel entrances, in particular to a bridge erecting device for rapid construction in mountainous areas, and in particular to a new bridge erecting machine for passing through tunnels and erecting beams at tunnel entrances.
背景技术 Background technique
随着我国基础建设的进一步加强和发展,各种基础设施的建设正在进入一个快速、稳健的发展阶段,铁路“十一五”规划表明,中国铁路已进入跨越式发展阶段,尤其是经济危机以来,我国加大对铁路、公路等基础设施的投入,铁路建设施工将达到前所未有的高峰期。随着我国铁路建设迈进持续快速发展阶段,在铁路建设施工方面首先要解决的一个关键问题是如何以较低的施工成本,较高的施工效率,进行铁路建设施工,以满足日益增长的需求,从而跟上经济发展的步伐。With the further strengthening and development of my country's infrastructure, the construction of various infrastructures is entering a rapid and steady development stage. The "Eleventh Five-Year Plan" of railways shows that China's railways have entered a stage of leapfrog development, especially since the economic crisis. my country has increased investment in infrastructure such as railways and highways, and railway construction will reach an unprecedented peak. As my country's railway construction enters a stage of continuous and rapid development, a key problem to be solved in the aspect of railway construction is how to carry out railway construction with low construction cost and high construction efficiency to meet the growing demand. So as to keep up with the pace of economic development.
目前,在铁路建设施工过程中,为了不占用土地、确保铁路的安全,铁路上的高架部分所占的比重越来越大,而在高架线路中,大型混凝土箱梁作为重量支承件成为了高架路线上的重要部件,而由于这种大型混凝土箱梁的重量大,在运输和建设高架铁路时非常困难,在常规的大吨位混凝土箱梁运架设备中,通常有以下几种架桥机进行施工架桥。At present, in the process of railway construction, in order not to occupy land and ensure the safety of the railway, the proportion of the elevated part of the railway is increasing. In the elevated line, the large concrete box girder is used as a weight support to become It is an important part on the route, and due to the heavy weight of this large concrete box girder, it is very difficult to transport and construct elevated railways. In the conventional large-tonnage concrete box girder transportation equipment, there are usually the following types of bridge erecting machines. Construction bridge.
1.辅助导梁式架桥机1. Auxiliary guide beam bridge erecting machine
辅助导梁式架桥机式架桥机后支腿后部主梁有尾悬,架桥机取梁位置在后支腿后部,运梁车驮梁小车仅在运梁车轨道上走行。Auxiliary guide beam type bridge erecting machine type bridge erecting machine has a tail suspension on the rear main girder of the rear outrigger, the bridge erecting machine picks up the beam at the rear of the rear outrigger, and the beam transport trolley only travels on the beam transport vehicle track.
2.定点起吊架桥机2. Fixed point lifting bridge erecting machine
定点起吊架桥机为运梁车驮梁台车直接从运梁车上运行到落梁位置。The fixed-point lifting bridge-erecting machine is a beam-carrying trolley and the beam trolley runs directly from the beam-carrying car to the beam-dropping position.
3.步履式架桥机3. Walking bridge erecting machine
步履式架桥机后支腿后部多了一条支腿,尾部悬臂长。架桥机不需要辅助导梁进行过孔,通过自身支腿走行或转换完成过孔。There is an extra outrigger at the rear of the rear outrigger of the walking bridge erecting machine, and the tail cantilever is long. The bridge erecting machine does not need an auxiliary guide beam to pass the hole, and completes the hole by walking or converting its own outriggers.
4.运架一体机4. All-in-one machine for transportation and racking
运架一体机主要分主机和导梁。主机兼顾运梁和架梁任务,主机需要运行到导梁上方。The all-in-one machine is mainly divided into main engine and guide beam. The main engine takes care of the tasks of beam transportation and beam erection, and the main engine needs to run above the guide beam.
而由于我国幅员辽阔,具有不同的地质条件,如平原、山岭、丘陵、高原等不同的地方对架梁都有不同的要求,而相对于山岭地区,由于其不像平坦地段,需要通过隧道、爬坡等不同的操作,因此,针对山岭地区桥隧相连工况,上述架桥机分别有以下缺点:Due to our country's vast territory and different geological conditions, different places such as plains, mountains, hills, and plateaus have different requirements for erecting beams. Compared with mountainous areas, because they are not like flat areas, they need to pass through tunnels, Different operations such as climbing, therefore, for the connection of bridges and tunnels in mountainous areas, the above-mentioned bridge erecting machines have the following disadvantages:
1.上述的1、3均无法完成洞口架梁;1. The above 1 and 3 cannot complete the opening of the beam;
2.上述的1、2、3均需要拆解才能通过隧道;2. The above 1, 2, and 3 all need to be disassembled to pass through the tunnel;
3.上述的4施工效率很低,导梁要求稳定性高。3. The construction efficiency of the above 4 is very low, and the guide beam requires high stability.
而为了解决这些现有的架桥机的缺陷,本申请的发明人提出了一种新型的架桥机,能克服这些缺陷,适于在山岭地区进行架桥。And in order to solve the defects of these existing bridge erecting machines, the inventor of the present application has proposed a kind of novel bridge erecting machine, can overcome these defects, is suitable for carrying out bridge erecting in mountain area.
发明内容 Contents of the invention
本发明的目的在于提供一种能通过隧道且实现隧道口架梁的架桥机,其能按照新的施工工艺和结构设计实现隧道口架梁及通过隧道,有效的兼顾到上述几类架桥机在桥隧相连地段的不足。The purpose of the present invention is to provide a bridge erecting machine that can pass through the tunnel and realize the erection of the tunnel mouth beam, which can realize the tunnel erection beam and pass through the tunnel according to the new construction technology and structural design, effectively taking into account the above-mentioned types of bridge erection The lack of machines in the bridge-tunnel connection section.
为实现上述目的,本发明公开了一种能通过隧道且实现隧道口架梁的架桥机,包括主机及下导梁,其特征在于:In order to achieve the above object, the present invention discloses a bridge erecting machine capable of passing through a tunnel and realizing beam erection at the tunnel entrance, including a main engine and a lower guide beam, characterized in that:
所述的主机包括主梁及从主梁后端往前端依次安装有后支腿、后导梁天车、后起重小车、前起重小车、前支腿、辅助走行支腿和前导梁天车,在主梁上设置有轨道,在轨道上运行前起重小车、后起重小车、前导梁天车及后导梁天车;The host includes a main girder and a rear outrigger, a rear guide beam crane, a rear hoisting trolley, a front hoisting trolley, a front outrigger, an auxiliary traveling outrigger and a front guide beam crane are installed sequentially from the rear end of the main beam to the front end. , a track is set on the main girder, and the front hoisting trolley, the rear hoisting trolley, the front guide beam crane and the rear guide beam crane run on the track;
所述的下导梁包括下导梁主梁及位于其后下方的后支腿和位于前下方的前支腿;The lower guide beam includes the main beam of the lower guide beam, the rear outriggers located at the rear and lower part thereof, and the front outriggers located at the front lower part;
主梁通过前支腿支撑在桥墩上,后支腿通过一走行机构支撑在已架桥面上;The main girder is supported on the pier by the front outrigger, and the rear outrigger is supported on the bridge surface by a running mechanism;
其特征在于:It is characterized by:
前起重小车、后起重小车结构相同,均由大车架、横移小车、卷筒、滑轮组、排绳装置、均衡装置、纵移驱动装置组成;所述的卷筒6、滑轮组、排绳装置、均衡装置均放置在横移小车上,所述的横移小车支撑在大车架上,通过油缸与大车架连接,通过卷筒、滑轮组、钢丝绳连接吊具,吊具通过吊杆与混凝土箱梁连接,所述的纵移驱动装置通过螺栓连接在大车架上,所述的大车架支撑在主梁顶部的轨道上,从而达到混凝土箱梁的精确定位。The front lifting trolley and the rear lifting trolley have the same structure, and are all composed of a large vehicle frame, a traverse trolley, a reel, a pulley block, a rope arrangement, an equalizing device, and a longitudinal movement drive device; the reel 6, the pulley block, the row The rope device and equalizing device are all placed on the traversing trolley, which is supported on the large frame, connected with the large frame through the oil cylinder, and connected to the spreader through the reel, pulley block, and wire rope, and the spreader passes through the boom. Connected with the concrete box girder, the longitudinal movement driving device is connected to the large frame by bolts, and the large frame is supported on the track at the top of the main beam, so as to achieve precise positioning of the concrete box girder.
其中,所述的后支腿为O型支腿,由多节钢箱梁通过螺栓及铰支座连接成一个封闭的O型,其上连接梁通过螺栓、回转铰与主梁连接在一起,回转铰实现上部前后的回转,螺栓起到固定作用。其中部连接梁为两段通过螺栓及铰支座连接而成的可折叠钢箱梁,所述的可折叠钢箱梁上部通过螺栓及铰支座与上连接梁连接,下部通过螺栓与下连接梁连接,所述的下连接梁为连接有走行机构的船型钢箱梁,走行机构采用轮胎走行。Wherein, the rear outrigger is an O-shaped outrigger, which is connected by a multi-section steel box girder through bolts and hinge supports to form a closed O-shape, and the upper connecting beam is connected with the main beam through bolts and rotary hinges. The rotary hinge realizes the front and rear rotation of the upper part, and the bolt plays a role of fixing. The middle connecting beam is a foldable steel box girder formed by connecting two sections through bolts and hinge supports, the upper part of the foldable steel box girder is connected with the upper connecting beam through bolts and hinge supports, and the lower part is connected with the lower part through bolts Beam connection, the lower connecting beam is a ship-shaped steel box girder connected with a running mechanism, and the running mechanism adopts tires to run.
其中,所述的后导梁天车由后导梁天车主梁、人字腿、走行梁、吊梁机构组成,所述的后导梁天车主梁为由多节钢箱梁通过螺栓及铰支座连接组成的可折叠式钢箱梁,其两端通过铰支座与吊梁机构连接,所述的人字腿由两段钢箱梁组成,其两端通过螺栓分别与后导梁天车主梁及走行梁连接,所述的走行梁通过车轮支撑在主梁顶部的轨道上。Wherein, the rear guide beam crane is composed of the rear guide beam crane main girder, herringbone legs, traveling beam, and hanging beam mechanism, and the rear guide beam crane main girder is made of multi-section steel box girder through bolts and hinges. The foldable steel box girder formed by the connection of the support, its two ends are connected with the hanging beam mechanism through the hinge support. The vehicle main girder is connected with the running girder, and the running girder is supported on the track at the top of the main girder through wheels.
其中,所述的前支腿上部通过走行机构的车轮支撑在主梁底部轨道上,下部通过可折叠钢箱梁支腿支撑在桥墩上,包括伸缩柱,连接伸缩柱、走行机构、可折叠钢箱梁支腿的上弯梁、横向连接梁。Wherein, the upper part of the front outrigger is supported on the bottom track of the main girder through the wheels of the running mechanism, and the lower part is supported on the pier through the foldable steel box girder outrigger, including a telescopic column, which is connected to the telescopic column, the running mechanism, and the foldable steel box girder. The upper curved beam and the transverse connecting beam of the outrigger of the box girder.
其中,所述的辅助走行支腿由上走行机构、伸缩柱、下走行机构组成。所述的上走行机构通过车轮支撑在主梁的底部轨道上,所述的下走行机构通过车轮支撑在下导梁顶部的轨道上,所述的伸缩柱通过螺栓与上走行机构、下走行机构连接。Wherein, the auxiliary running legs are composed of an upper running mechanism, a telescopic column and a lower running mechanism. The upper running mechanism is supported on the bottom track of the main beam through the wheels, the lower running mechanism is supported on the track at the top of the lower guide beam through the wheels, and the telescopic column is connected with the upper running mechanism and the lower running mechanism through bolts .
其中,前导梁天车通过车轮支撑在主梁前端的桁架鼻梁的轨道上,由钢丝绳、滑轮组连接吊具,吊具通过吊杆与下导梁连接。Among them, the front guide beam crane is supported on the track of the truss nose bridge at the front end of the main beam through wheels, and the hanger is connected by a steel wire rope and a pulley block, and the hanger is connected with the lower guide beam through a hanger rod.
其中,所述的下导梁截面为矩形,其矩形内侧设有纵向加强筋、横隔板,其上部顶端设有走行轨道,其前端下部两侧设有轨道,其前端设有吊装孔,通过吊杆与前导梁天车连接,后端设有侧面吊装孔,通过吊梁机构与后导梁天车连接。Wherein, the cross-section of the lower guide beam is rectangular, the inner side of the rectangle is provided with longitudinal reinforcing ribs and transverse partitions, the top of its upper part is provided with running rails, the lower part of its front end is provided with rails on both sides, and its front end is provided with hoisting holes. The boom is connected with the front guide beam crane, and the rear end is provided with a side hoisting hole, which is connected with the rear guide beam crane through the suspension beam mechanism.
其中,所述的下导梁后支腿顶部通过螺栓及铰支座与下导梁连接,其下部设有支撑油缸,所述的支撑油缸下部装有可调节高度的螺旋支腿。Wherein, the top of the rear leg of the lower guide beam is connected to the lower guide beam through bolts and hinge supports, and the lower part of the lower guide beam is provided with a support cylinder, and the lower part of the support cylinder is equipped with a height-adjustable spiral leg.
其中,所述的下导梁前支腿顶部通过螺栓及铰支座与下导梁连接,其顶部装有走行机构,下部设有支撑油缸,所述的支撑油缸下部装有可调节高度的螺旋支腿。Wherein, the top of the front outrigger of the lower guide beam is connected with the lower guide beam through bolts and hinge supports, the top of which is equipped with a running mechanism, and the lower part is provided with a supporting oil cylinder, and the lower part of the supporting oil cylinder is equipped with a height-adjustable screw outriggers.
其中,架桥机的架梁工序如下:Among them, the beam erecting process of the bridge erecting machine is as follows:
步骤一:架前准备,下导梁的前支腿、后支腿分别支撑在预架箱梁的桥墩上,架桥机的后支腿支撑在已架设梁面上,前支腿支撑在预架箱梁的桥墩上,其前支腿与下导梁的前支腿支撑在同一桥墩上,主机的辅助走行支腿悬空;运梁车沿着已架设的梁面载着混凝土梁行驶到架桥机后端后,其轨道与下导梁顶部的轨道连接;Step 1: Preparation before erection. The front outriggers and rear outriggers of the lower guide beam are respectively supported on the piers of the pre-erected box girder. On the pier of the box girder, the front outriggers and the front outriggers of the lower guide beam are supported on the same pier, and the auxiliary running legs of the main engine are suspended in the air; After the rear end of the bridge crane, its track is connected with the track on the top of the lower guide beam;
步骤二:前驮梁台车与后驮梁台车载着混凝土箱梁从运梁车上往下导梁纵移;Step 2: The front beam trolley and the rear beam trolley carry the concrete box girder and move longitudinally from the beam transport vehicle to the lower guide beam;
步骤三:混凝土箱梁到达指定位置后,前起重小车吊起混凝土箱梁,与后驮梁台车一起驮运至落梁位置,之后后起重小车吊起混凝土箱梁,前后驮梁台车推到运梁车上;Step 3: After the concrete box girder reaches the designated position, the front lifting trolley lifts the concrete box girder and transports it to the beam drop position together with the rear loading beam trolley, and then the rear lifting trolley lifts the concrete box girder, and the front and rear loading beam platforms The cart is pushed onto the beam transport cart;
步骤四:前吊梁天车、后导梁天车分别吊住下导梁,同时,下导梁通过缩短、折叠前后支腿,并在前后吊梁天车的作用下前行,至指定位置辅助走行支腿落下挂住下导梁中部,前导梁天车卸载后移到指定位置再次吊起下导梁,辅助走行支腿离开下导梁;Step 4: The front suspension beam crane and the rear guide beam crane respectively hang the lower guide beam. At the same time, the lower guide beam shortens and folds the front and rear outriggers, and moves forward under the action of the front and rear suspension beam cranes to the designated position. The auxiliary running outriggers drop down to hang on the middle of the lower guide beam, the crane on the front guide beam is unloaded and moved to the designated position to lift the lower guide beam again, and the auxiliary walking outriggers leave the lower guide beam;
步骤五:下导梁在前后导梁天车的起吊下到位后,其前后支腿分别支在两相邻的桥墩上,混凝土箱梁在前后起重小车作用下精确落到桥墩上;Step 5: After the lower guide girder is hoisted into place by the front and rear guide girder cranes, its front and rear outriggers are respectively supported on two adjacent bridge piers, and the concrete box girder is accurately dropped on the bridge piers under the action of the front and rear lifting trolleys;
步骤六:混凝土箱梁落到位后,取下吊具;待砂浆凝固后,将后导梁天车、前后起重小车退至主梁后端,前导梁天车退至鼻梁后端;之后辅助走行支腿支在下导梁顶部轨道上,收起架桥机前支腿,支起后支腿,在辅助走行支腿和后支腿共同推动下架桥机过跨;Step 6: After the concrete box girder falls in place, remove the spreader; after the mortar is solidified, retreat the rear guide beam crane and the front and rear lifting trolleys to the rear end of the main beam, and the front guide beam crane to the rear end of the nose bridge; then assist the running support The legs are supported on the top track of the lower guide beam, the front outriggers of the bridge erecting machine are retracted, the rear outriggers are supported, and the auxiliary running outriggers and rear outriggers jointly push the lower bridge erecting machine to cross the span;
步骤七:架桥机完成过跨后,先后支起前支腿、收起辅助走行支腿、支起后支腿准备下一混凝土箱的架设。Step 7: After the bridge erecting machine completes the span, set up the front outriggers, retract the auxiliary walking outriggers, and set up the rear outriggers to prepare for the erection of the next concrete box.
通过上述结构,本发明的架桥机和架桥架梁工序可以在山岭地区实现架桥架梁操作,通过隧道时,可以收缩和折叠多个部件,使架桥机方便的通过隧道,不会受到隧道大小的限制,而在架桥时,施工效率高,操作稳定。Through the above-mentioned structure, the bridge erecting machine and the bridge and beam erecting process of the present invention can realize the bridge and beam erection operation in mountainous areas. Size limitation, while in bridge erection, the construction efficiency is high and the operation is stable.
附图说明 Description of drawings
图1是本发明所述能通过隧道且实现隧道口架梁的架桥机的结构示意图。Fig. 1 is a structural schematic diagram of a bridge erecting machine capable of passing through a tunnel and realizing beam erection at a tunnel mouth according to the present invention.
图2是后支腿的结构示意图。Figure 2 is a schematic structural view of the rear outrigger.
图3是后导梁天车在主梁上及吊下导梁示意图。Figure 3 is a schematic diagram of the rear guide beam crane on the main girder and the guide beam being hoisted down.
图4是起重小车在主梁上吊起梁片示意图。Fig. 4 is a schematic diagram of lifting the girder on the main girder by the lifting trolley.
图5是前支腿支在桥墩上的示意图。Fig. 5 is a schematic diagram of the front outrigger supported on the pier.
图6是辅助走行支腿支在桥墩上示意图。Fig. 6 is a schematic diagram of the auxiliary running outrigger supported on the pier.
图7是前吊梁天车在主梁鼻梁上吊起下导梁示意图。Fig. 7 is a schematic diagram of the lower guide beam hoisted by the front suspension beam crane on the nose bridge of the main beam.
图8是下导梁支在桥墩上,辅助走行支腿支在其上的示意图。Fig. 8 is a schematic diagram of the lower guide beam supported on the pier and the auxiliary running legs supported thereon.
图9、图10分别是下导梁前、后支腿的示意图。Figure 9 and Figure 10 are schematic diagrams of the front and rear legs of the lower guide beam respectively.
具体实施方式 Detailed ways
参照图1,本发明的能通过隧道且实现隧道口架梁的架桥机主要包括主机及下导梁10。所述的主机包括主梁4及从主梁4后端往前端(所谓前后是以架梁方向为前,反之为后)依次安装有后支腿1、后导梁天车2、后起重小车3、前起重小车5、前支腿8、辅助走行支腿6、前导梁天车7。在主梁4上设置有轨道,在轨道上运行前起重小车5、后起重小车6、前导梁天车7及后导梁天车2。所述的下导梁10包括下导梁主梁及位于其后下方的后支腿11和位于前下方的前支腿9。架桥工作时,主梁4通过前支腿8支撑在桥墩上,后支腿1通过其走行机构17支撑在已架桥面上。Referring to FIG. 1 , the bridge erecting machine of the present invention that can pass through a tunnel and realize beam erection at the tunnel entrance mainly includes a main engine and a
参照图10所述的下导梁的前支腿9可沿下导梁10纵向走行、可折叠、可伸缩,以满足不同梁型(24m、32m梁)的支撑需求。The front legs 9 of the lower guide beam described with reference to FIG. 10 can run longitudinally along the
参照图9所述的下导梁后支腿11可折叠、可伸缩,已满足末孔梁、桥台梁的架设。Referring to Fig. 9, the
参照图1、图2所示,所述的后支腿1为“O”型支腿,由多节钢箱梁通过螺栓及铰支座连接成一个封闭的“O”型。其上连接梁15通过螺、回转铰与主梁4的两个纵向梁连接在一起,回转铰实现上部前后的回转,螺栓起到固定作用,其中部连接梁16为两段通过螺栓及铰支座连接而成的可折叠钢箱梁,所述的可折叠钢箱梁16上部通过螺栓及铰支座与上连接梁连接15,下部通过螺栓与下连接梁18连接。所述的下连接梁18为连接有走行机构17的船型钢箱梁。所述的走行机构17为自给驱动的轮组走行,且采用轮胎走行。。通过拆除走行机构17,对钢箱梁16进行折叠,上连接梁15与主梁4相对转动,从而可减小后支腿的截面尺寸,达到本发明的架桥机通过隧道的目的。Referring to Fig. 1 and Fig. 2, the rear leg 1 is an "O"-shaped leg, which is connected by multi-section steel box girders through bolts and hinge supports to form a closed "O" shape. The upper connecting
参照图1、图3所示,所述的后导梁天车2由后导梁天车主梁20、“人字”腿21、走行梁22、吊梁机构23组成。所述的后导梁天车主梁20为由多节钢箱梁通过螺栓及铰支座连接组成的可折叠式钢箱梁。其两端通过铰支座与吊梁机构23连接。所述的“人字”腿21由两段钢箱梁组成,其两端通过螺栓分别与后导梁天车主梁20及走行梁22连接。所述的走行梁22通过车轮支撑在主梁4顶部的轨道上。主机过跨前,后导梁天车2通过吊梁机构23吊起下导梁10,在其走行梁22驱动下沿主梁4纵向移动,与前导梁天车7配合吊下导梁10过跨。主机过隧道时,后导梁天车2通过折叠后导梁天车的主梁20,进而缩短吊梁机构23,可减小截面尺寸,达到本发明的架桥机通过隧道的目的。1 and 3, the rear
参照图1、图4所示,所述的前起重小车5、后起重小车3结构相同,均由大车架24、横移小车25、卷筒26、滑轮组27、排绳装置28、均衡装置30、纵移驱动装置29组成。所述的卷筒26、滑轮组27、排绳装置28、均衡装置30均放置在横移小车25上。所述的横移小车25通过移运器支撑在大车架24上,通过油缸与大车架24连接,通过卷筒26、滑轮组27、钢丝绳31连接吊具32,吊具通过吊杆33与混凝土箱梁14连接。所述的纵移驱动装置29通过螺栓连接在大车架24上。所述的大车架24通过移运器支撑在主梁4顶部的轨道上。架梁工作时,前起重小车5、后起重小车3可通过纵移驱动装置29沿主梁4纵向移动,通过横移小车25横向移动以达到混凝土箱梁14精确定位。With reference to Fig. 1, shown in Fig. 4, described front hoisting trolley 5, rear hoisting trolley 3 structures are identical, are all made up of
所述的前起重小车5的两个卷筒26通过均衡装置30可独立工作,后起重小车3的两个卷筒26通过均衡装置30可同步工作,达到整个升降系统四点起吊、三点平衡的目的。The two
参照图1、图5所示,所述的前支腿8上部通过走行机构35的车轮支撑在主梁4底部轨道上,下部通过可折叠钢箱梁支腿37支撑在桥墩上,包括伸缩柱36,连接伸缩柱36、走行机构35、可折叠钢箱梁支腿37的上弯梁39、横向连接梁38。架梁时,前支腿8可通过缩短其伸缩柱36,走行其走行机构35,达到架设不同梁型(24m、32m梁)的支撑需求。Referring to Fig. 1 and Fig. 5, the upper part of the front outrigger 8 is supported on the bottom track of the
参照图1、图6所示,所述的辅助走行支腿6由上走行机构40、伸缩柱41、下走行机构42组成。所述的上走行机构40通过车轮支撑在主梁4的底部轨道上。所述的下走行机构42通过车轮支撑在下导梁10顶部的轨道上。所述的伸缩柱41通过螺栓与上走行机构40、下走行机构42连接。架梁时,辅助走行支腿6通过缩短伸缩柱41,达到架梁时不受力的作用。过孔时,辅助走行支腿6通过缩短伸缩柱41,达到支撑主机的作用。Referring to Fig. 1 and Fig. 6, the auxiliary running leg 6 is composed of an
参照图1、图7所示,前导梁天车7通过车轮支撑在主梁4前端的桁架鼻梁的轨道上,由钢丝绳、滑轮组连接吊具45,吊具45通过吊杆与下导梁10连接。过孔前,前导梁天车7通过吊具45吊起下导梁10与后吊梁天车2配合,吊下导梁10过跨。Referring to Fig. 1 and Fig. 7, the front
参照图1、图8、图9、图10所示,所述的下导梁10截面为矩形,其矩形内侧设有纵向加强筋、横隔板,其上部顶端设有走行轨道,其前端下部两侧设有轨道,其前端设有吊装孔,通过吊杆45与前导梁天车7连接,后端设有侧面吊装孔,通过吊梁机构23与后导梁天车2连接。Referring to Fig. 1, Fig. 8, Fig. 9 and Fig. 10, the cross-section of the
所述的下导梁后支腿11顶部通过螺栓及铰支座与下导梁10连接,其下部设有支撑油缸,所述的支撑油缸下部装有可调节高度的螺旋支腿45。The top of the
所述的下导梁前支腿9顶部通过螺栓及铰支座与下导梁10连接,其顶部装有走行机构43,下部设有支撑油缸,所述的支撑油缸下部装有可调节高度的螺旋支腿45。The top of the front leg 9 of the lower guide beam is connected with the
主机过跨时,下导梁10通过其顶部的轨道支起辅助走行支腿6。下导梁10通过缩短、折叠其前支腿9、后支腿11,在前导梁天车7、后吊梁天车2的吊动下过跨,过跨后通过伸长、展开其前支腿9、后支腿11,支在桥墩上,同时下导梁前支腿9,在其走行机构43的作用下,可以沿下导梁10纵向移动,以满足(24m、32m梁)的支撑需求。架梁时,前运梁车的前驮梁台车13通过移运器支撑在下导梁10顶部的轨道上,并可沿下导梁10纵向移动。When the main engine spans, the
本发明所述的过隧道架桥机可适用如下工作条件:The tunnel bridge erecting machine described in the present invention is applicable to the following working conditions:
在桥隧相连地区作业,架桥机在运梁车的驮运下能穿过双线隧道,并在桥台距隧道进、出口4m时可以架梁。Working in areas where bridges and tunnels are connected, the bridge erecting machine can pass through the double-lane tunnel under the load of the beam transport vehicle, and can erect beams when the bridge abutment is 4m away from the entrance and exit of the tunnel.
在连续梁(24m、32m)、组合梁等类型桥及路基通过并进行架梁。Pass and erect beams on continuous beam (24m, 32m), composite beam and other types of bridges and roadbeds.
作业最大坡度:≤20‰。The maximum slope of the operation: ≤20‰.
工作曲线半径:≥2000m。Working curve radius: ≥2000m.
工作海拔高度:≤2000m。Working altitude: ≤2000m.
工作环境温度:-20~+50℃。Working environment temperature: -20~+50℃.
工作环境最大风力:工作状态6级;非工作状态12级。The maximum wind force in the working environment: level 6 in working state;
本发明所述的能通过隧道且实现隧道口架梁的架桥机架梁过程如下:设备做好架设准备,架桥机下导梁10的前支腿9、后支腿11分别支撑在预架箱梁的桥墩上,架桥机的后支腿1支撑在已架设梁面上(油缸缩回,由枕木受力),前支腿8支撑在预架箱梁的桥墩上,其前支腿8与下导梁10的前支腿9支撑在同一桥墩上。主机的辅助走行支腿6此时悬空。运梁车12沿着已架设的梁面载着混凝土梁14行驶到架桥机后端(即图1的左端)后,其轨道与下导梁10顶部的轨道连接,此时运梁车12的轨道与下导梁轨道处于同一水平面(通过调节下导梁10的前后支腿满足),且是同一直线上。之后前驮梁台车13载着混凝土梁14直接行驶到下导梁10指定位置,前小车5吊起梁片,与后驮梁台车46一起吊起混凝土梁14前行,到位后前起重小车3、后起重小车5同时起吊混凝土梁14。之后,前、后驮梁台车退出下导梁10,运梁车12返场驮运下一混凝土箱梁。前吊梁天车7、后导梁天车2分别吊住下导梁10,同时,下导梁10通过缩短、折叠前后支腿,并在前后吊梁天车的作用下,前行到下一跨上。待整个下导梁10移出后,混凝土箱梁14在前后起重小车作用下落到桥墩上。架梁结束后,架桥机辅助走行支腿6支撑在下导梁10的顶部轨道上,后支腿1支撑起油缸,取走枕木,在辅助走行支腿6和后支腿1共同作用下主机实现纵移过孔,到位后支起前支腿8就可进行下一片箱梁的架设。The process of the bridge erecting frame girder that can pass through the tunnel and realize the erection of the tunnel mouth girder according to the present invention is as follows: the equipment is ready for erection, and the front leg 9 and the
具体的架桥机过隧道架梁如下:The concrete bridge erecting machine passes through the tunnel and erects the girder as follows:
步骤一:架桥机做好架设准备,下导梁10的前支腿9、后支腿11分别支撑在预架箱梁14的桥墩上,架桥机的后支腿1支撑在已架设梁面上(油缸缩回,由枕木受力),前支腿8支撑在预架箱梁的桥墩上,其前支腿8与下导梁10的前支腿9支撑在同一桥墩上。主机的辅助走行支腿6此时悬空。运梁车12沿着已架设的梁面载着混凝土梁14行驶到架桥机后端(即图1的左端)后,其轨道与下导梁10顶部的轨道连接。参照图11所示。Step 1: The bridge erecting machine is ready for erection. The front outrigger 9 and the
步骤二:前驮梁台车13与后驮梁台车46载着混凝土箱梁14从运梁车上往下导梁纵移。参照图12所示。Step 2: the
步骤三:当混凝土箱梁14到达指定位置后,前起重小车5吊起混凝土箱梁14,与后驮梁台车46一起驮运至落梁位置,之后后起重小车3吊起梁片14,前后驮梁台车推到运梁车上。参照图13、14所示。Step 3: When the
步骤四:运梁车12返场取梁。前吊梁天车7、后导梁天车2分别吊住下导梁10,同时,下导梁10通过缩短、折叠前后支腿,并在前后吊梁天车的作用下前行,至指定位置辅助走行支腿6落下挂住下导梁中部10,前导梁天车7卸载后移到指定位置再次吊起下导梁10,辅助走行支腿6离开下导梁10。参照图15、16所示。Step 4: The
步骤五:下导梁10在前后导梁天车的起吊下到位后,其前后支腿分别支在两相邻的桥墩上。混凝土箱梁14在前后起重小车作用下精确落到桥墩上。参照图17所示。Step 5: After the
步骤六:混凝土箱梁14落到位后,取下吊具。待其砂浆凝固后,将后导梁天车2、前后起重小车退至主梁4后端,前导梁天车7退至鼻梁后端。之后辅助走行支腿6支在下导梁10顶部轨道上,收起架桥机前支腿8,支起后支腿1,在辅助走行支腿6和后支腿1共同推动下架桥机过跨。参照图18所示。Step 6: After the
步骤七:架桥机完成过跨后,先后支起前支腿8、收起辅助走行支腿6、支起后支腿1准备下一混凝土箱梁14的架设。Step 7: After the bridge erecting machine completes the span, set up the front outrigger 8, put away the auxiliary running outrigger 6, and set up the rear outrigger 1 to prepare for the erection of the next
通过本发明的架桥机,可以在山岭地区实现架桥架梁操作,通过隧道时,可以收缩和折叠多个部件,使架桥机方便的通过隧道,不会受到隧道大小的限制,而在架桥时,施工效率高,操作稳定。Through the bridge erecting machine of the present invention, the operation of erecting bridges and girders can be realized in mountainous areas. When passing through the tunnel, multiple parts can be shrunk and folded, so that the bridge erecting machine can pass through the tunnel conveniently without being limited by the size of the tunnel. When the bridge is used, the construction efficiency is high and the operation is stable.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010101957163A CN101851898B (en) | 2010-06-09 | 2010-06-09 | Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010101957163A CN101851898B (en) | 2010-06-09 | 2010-06-09 | Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101851898A CN101851898A (en) | 2010-10-06 |
| CN101851898B true CN101851898B (en) | 2012-04-11 |
Family
ID=42803568
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2010101957163A Active CN101851898B (en) | 2010-06-09 | 2010-06-09 | Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101851898B (en) |
Families Citing this family (21)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101949133B (en) * | 2010-10-08 | 2014-03-12 | 石家庄铁道大学国防交通研究所 | Straddle type bridge girder erection machine |
| CN102071641B (en) * | 2010-12-02 | 2015-11-25 | 秦皇岛天业通联重工股份有限公司 | Cement beam packs bridge machine cloth supporting leg type integration of transporting and building Bridge Erector and bridge formation engineering method thereof |
| CN102071650B (en) * | 2010-12-02 | 2015-12-09 | 秦皇岛天业通联重工股份有限公司 | Universal bridging machine inside and outside Railway Tunnel |
| CN102009911B (en) * | 2010-12-02 | 2015-03-25 | 秦皇岛天业通联重工股份有限公司 | Horizontal hanging beam travelling crane |
| CN102094394A (en) * | 2010-12-30 | 2011-06-15 | 徐州徐工铁路装备有限公司 | Through-tunnel lower pilot girder type non-moving lifting bridge girder erection machine |
| CN102619535B (en) * | 2012-04-12 | 2015-04-29 | 中铁十二局集团有限公司 | Folding tunnel widening trolley |
| CN103419781B (en) * | 2013-08-22 | 2016-01-13 | 中交第二航务工程局有限公司 | A kind ofly drive autocontrol method and the control system that beam transportation vehicle crosses tunnel |
| CN104762885B (en) * | 2015-03-31 | 2017-01-18 | 中铁工程机械研究设计院有限公司 | Large-tonnage beam erection and transportation system in tunnel and beam erection span change procedure thereof |
| CN106436586A (en) * | 2015-08-10 | 2017-02-22 | 北京万桥兴业机械有限公司 | Single-line or double-line railway bridge dismantling and replacing machine |
| CN106544958B (en) * | 2016-11-25 | 2018-07-06 | 中铁三局集团有限公司 | 900 tons of Bridge Erector low levels of auxiliary nose-girder type cross the construction method of bale handle arch |
| CN106592431B (en) * | 2016-11-25 | 2018-02-23 | 中铁三局集团有限公司 | The high-order construction method for crossing bale handle arch of 900 tons of Bridge Erectors of auxiliary nose-girder type |
| CN107401124A (en) * | 2017-09-15 | 2017-11-28 | 中铁第五勘察设计院集团有限公司 | The Bridge Erector of T-shaped beam bridge |
| CN108149589B (en) * | 2018-01-31 | 2023-11-28 | 中国铁路总公司 | Large span tunnel box girder bridge erecting machine |
| CN110273365B (en) * | 2018-03-17 | 2024-04-30 | 中铁第五勘察设计院集团有限公司 | Transport and frame integrated machine |
| CN110273373B (en) * | 2018-03-17 | 2024-04-30 | 中铁第五勘察设计院集团有限公司 | Beam guide machine with movable multifunctional trolley |
| CN109440659A (en) * | 2018-11-29 | 2019-03-08 | 襄阳协利成机车车辆工程设备有限公司 | Bridge Erector relays defeated girder system system, Bridge Erector and bridging method |
| CN110607753B (en) * | 2019-09-30 | 2024-08-09 | 合肥正浩机械科技有限公司 | Supporting leg structure for erecting bridge in tunnel of bridge girder erection machine |
| CN113215994B (en) * | 2021-05-11 | 2023-01-03 | 中交路桥华东工程有限公司 | Method for mounting bridge girder erection machine at tunnel outlet |
| CN113322819B (en) * | 2021-06-01 | 2023-02-10 | 中交路桥华东工程有限公司 | Method for erecting first-span T beam at tunnel outlet |
| CN115094772A (en) * | 2022-07-21 | 2022-09-23 | 中铁十四局集团青岛工程有限公司 | Tunnel-passing transfer system and tunnel-passing transfer method of high-speed rail bridge erecting machine |
| CN116553372A (en) * | 2023-06-12 | 2023-08-08 | 河南省交通规划设计研究院股份有限公司 | Lifting equipment for bridge construction and bridge construction method |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08134845A (en) | 1994-11-11 | 1996-05-28 | Kajima Corp | How to build a bridge |
| CN2853888Y (en) * | 2005-12-28 | 2007-01-03 | 郑州大方桥梁机械有限公司 | Guide beam type fixed point hoisting bridge girder erection machine |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2234459Y (en) * | 1995-10-16 | 1996-09-04 | 铁道部第一工程局第三工程处 | Single-arm three-upright step bridging machine |
| CN2846480Y (en) * | 2006-05-19 | 2006-12-13 | 北京万桥兴业机械有限公司 | Guide beam type bridging machine for passing through tunnel |
-
2010
- 2010-06-09 CN CN2010101957163A patent/CN101851898B/en active Active
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08134845A (en) | 1994-11-11 | 1996-05-28 | Kajima Corp | How to build a bridge |
| CN2853888Y (en) * | 2005-12-28 | 2007-01-03 | 郑州大方桥梁机械有限公司 | Guide beam type fixed point hoisting bridge girder erection machine |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101851898A (en) | 2010-10-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101851898B (en) | Bridge girder erection machine capable of passing through tunnel and realizing girder erection and bridging process thereof | |
| CN102071650B (en) | Universal bridging machine inside and outside Railway Tunnel | |
| CN110130229B (en) | A multi-span parallel double cantilever bridge erecting machine and its beam erection and span crossing method | |
| CN113309001B (en) | Bridge girder erection machine for erecting small-radius bridge | |
| CN210561749U (en) | A multi-frame juxtaposed double cantilever bridge erecting machine | |
| CN106917360A (en) | Lift leg formula frame plate machine and its frame plate method | |
| CN1609342A (en) | Down-guiding girder type bridge erecting machine and its beam erecting method | |
| CN110273375A (en) | A kind of Bridge Erector | |
| CN110409311B (en) | Single-beam bridge erecting machine and method for erecting beams, passing through holes and tunnels thereof | |
| CN116043715A (en) | A construction method for the construction of prefabricated segmental beams for complex working conditions | |
| CN100572673C (en) | Span continuous beam bridge fabrication machine in a kind of | |
| CN205576745U (en) | Divide box -like one -piece type bridge crane fast | |
| CN203878478U (en) | A bridge girder erection machine with a single arm box girder | |
| CN113322819A (en) | First-span T-beam erection method at tunnel outlet | |
| CN202415024U (en) | Crane capable of climbing over beam-arch, climbing up slope and climbing down slope | |
| CN201972096U (en) | Cross-tunnel lower guide beam type fixed-point hoisting bridge girder erection machine | |
| CN201746780U (en) | Bridge girder erection machine capable of passing through tunnel and realizing girder erection at tunnel opening | |
| CN108130862A (en) | Cross tunnel beam car | |
| CN100395411C (en) | Walking box girder bridge erecting machine | |
| CN115897387A (en) | A method for erecting curved bridges | |
| CN114481834A (en) | A pile beam erection integrated machine and erection method | |
| CN108532462A (en) | A kind of symmetrically set a roof beam in place and its is set a roof beam in place, passing method at formula Bridge Erector | |
| CN108130864B (en) | Integral prefabricated bridge whole span beam transportation and erection equipment | |
| CN207739151U (en) | Two straddle type Bridge Erectors | |
| CN207619855U (en) | One kind is hidden formula beam car |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| ASS | Succession or assignment of patent right |
Owner name: CHINA RAILWAY ENGINEERING MACHINERY RESEARCH + DES Effective date: 20150521 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20150521 Address after: 430066, 45 East Main Street, Wuchang District, Hubei, Wuhan Patentee after: China Railway Science & Industry Group Co., Ltd. Patentee after: China's Railroad Engineering Machine Research Design Institute Co., Ltd. Address before: 430066, 45 East Main Street, Wuchang District, Hubei, Wuhan Patentee before: China Railway Science & Industry Group Co., Ltd. |