CN101806106B - Fire-proof thermal insulation wall body poured with thermal insulation layer - Google Patents
Fire-proof thermal insulation wall body poured with thermal insulation layer Download PDFInfo
- Publication number
- CN101806106B CN101806106B CN2010101259138A CN201010125913A CN101806106B CN 101806106 B CN101806106 B CN 101806106B CN 2010101259138 A CN2010101259138 A CN 2010101259138A CN 201010125913 A CN201010125913 A CN 201010125913A CN 101806106 B CN101806106 B CN 101806106B
- Authority
- CN
- China
- Prior art keywords
- layer
- wall
- cavity
- insulation
- mortar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/24—Structural elements or technologies for improving thermal insulation
- Y02A30/244—Structural elements or technologies for improving thermal insulation using natural or recycled building materials, e.g. straw, wool, clay or used tires
Landscapes
- Building Environments (AREA)
- Finishing Walls (AREA)
Abstract
本发明涉及灌注保温层防火保温墙体,有效解决保温性能差、施工复杂、质量安全稳定性不易控制,面层易开裂的问题,其解决的技术方案是,该防火保温墙体是由带空腔的砖体砌筑成单层或双层,灌注保温层构成,外墙面垂直对齐,砖体间的砂浆内无空隙,防止灌注保温层时保温材料外流,空腔中不能有砂浆,砌筑0.6米至3.0米的高度,进行保温层灌注,向空腔内灌注保温材料,保温层灌注要饱满无空隙,待整片墙砌筑完成后,在外墙的内、外表面设找平层,待找平层的强度达到0.4MPa后,再粉刷饰面层,即成;本发明不仅克服外保温墙粘结不牢、抗老化、抗风压能力差,易开裂等问题,也减少了施工工序降低了造价,还具有防火、防水性能良好兼具可围护承重的优点。
The invention relates to a fire-proof and heat-preservation wall with perfusion heat-insulation layer, which effectively solves the problems of poor heat-preservation performance, complicated construction, difficult control of quality, safety and stability, and easy cracking of the surface layer. The brick body of the cavity is built into a single layer or double layer, and the insulation layer is poured, and the outer wall is vertically aligned. There is no gap in the mortar between the brick bodies to prevent the insulation material from flowing out when the insulation layer is poured. Build a height of 0.6m to 3.0m, pour the insulation layer, and pour the insulation material into the cavity. The insulation layer should be filled without gaps. After the strength of the leveling layer reaches 0.4MPa, paint the finish layer and it is ready; the invention not only overcomes the problems of poor bonding, anti-aging, poor wind pressure resistance, and easy cracking of the external thermal insulation wall, but also reduces the construction process The cost is reduced, and it also has the advantages of good fireproof and waterproof performance, and can be enclosed and loaded.
Description
一、技术领域1. Technical field
本发明涉及建筑领域,特别是一种灌注保温层防火保温墙体。The invention relates to the field of construction, in particular to a fire-proof and heat-retaining wall with a perfusion heat-insulation layer.
二、背景技术2. Background technology
随着经济和技术的不断发展,实现可持续的协调发展已成为人们的共识。建筑节能因其可大大减少能源消耗,减少环境污染和温室效应,已受到很多国家的重视。外墙保温技术由于有不占用室内空间等优势,而深受人们欢迎,现有的外保温墙体主要有聚苯颗粒浆料、粘贴聚苯板、现浇聚苯板、岩棉板、泡沫玻璃、灌注聚氨酯硬泡等墙体。这些墙体的保温性能、施工性、安全稳定性各异,有的保温墙体所使用的材料导热系数偏高,不适合严寒地区保温节能的需要,有的安全稳定性施工中不易控制,有的施工复杂质量控制难度大,有的面层抗裂问题难解决,加上保温层置于围护结构的外侧,难免要遭受雨、雪、大风、冻、融、干、湿,有害气体和紫外线等的破坏,近来也经常见到外保温层的脱粘空鼓、面层开裂等问题。目前,用聚氨酯硬泡制成的外保温墙,因其具备保温、防水、隔音、吸振等诸多功能在建筑保温领域应用较为广泛,现场直接发泡成型硬质聚氨酯泡沫应用于有饰面层的外保温垂直墙体,存在表面平整度难以控制、饰面层与硬质聚氨酯泡沫之间的附着力差、外饰面易开裂等主要难题。随着时代的推进,技术的发展,对围护结构提出了更高的要求,对外墙保温提出了防火保温且易于施工,造价低廉的要求,以寻找一种全功能的围护结构来满足社会发展的需要。With the continuous development of economy and technology, it has become the consensus of people to achieve sustainable and coordinated development. Building energy saving has been paid attention to by many countries because it can greatly reduce energy consumption, reduce environmental pollution and greenhouse effect. The external wall insulation technology is popular because of its advantages of not occupying indoor space. The existing external insulation walls mainly include polystyrene particle slurry, pasted polystyrene board, cast-in-place polystyrene board, rock wool board, foam Glass, poured polyurethane rigid foam and other walls. These walls have different thermal insulation performance, constructability, safety and stability. Some thermal insulation walls use materials with high thermal conductivity, which are not suitable for thermal insulation and energy saving in severe cold areas. Some security and stability are difficult to control during construction, and some The complex construction quality control is difficult, and some surface layer crack resistance problems are difficult to solve. In addition, the insulation layer is placed outside the enclosure structure, which will inevitably suffer from rain, snow, strong wind, freezing, thawing, dryness, humidity, harmful gases and Destruction by ultraviolet rays, etc., has recently seen problems such as debonding hollowing of the outer insulation layer and cracking of the surface layer. At present, the external thermal insulation wall made of rigid polyurethane foam is widely used in the field of building thermal insulation because of its functions of thermal insulation, waterproof, sound insulation, and vibration absorption. The vertical wall with external thermal insulation has major problems such as difficulty in controlling the surface flatness, poor adhesion between the facing layer and rigid polyurethane foam, and easy cracking of the outer facing. With the advancement of the times and the development of technology, higher requirements are put forward for the enclosure structure, and the requirements for fire insulation, easy construction and low cost are put forward for external wall insulation, so as to find a full-featured enclosure structure to meet the needs of society. development needs.
三、发明内容3. Contents of the invention
针对上述情况,为克服现有技术缺陷,本发明之目的就是提供一种灌注保温层防火保温墙体,可有效解决保温性能差、施工复杂、质量安全稳定性不易控制,面层易开裂的问题,其解决的技术方案是,该防火保温墙体是由带空腔的砖体(又称砌块,以下同)砌筑成单层或双层,灌注保温层构成,其砌筑方法是,外墙面垂直对齐,砖体间的砂浆内无空隙,防止灌注保温层时保温材料外流,空腔中不能有砂浆,如不慎有砂浆掉落,应尽快从空腔内清除;砌筑0.6米至3.0米的高度,进行保温层灌注,向空腔内灌注保温材料,保温层灌注要饱满无空隙,即形成灌注保温外墙;待整片墙砌筑完成后,在外墙的内、外表面设找平层,待找平层的强度达到0.4mpa后,再粉刷饰面层,即成灌注保温层防火保温墙体;所说的带空腔的砖体,其空腔有1或2个,空腔置于砖体的左端,或右端,或前部,或后部,或左右两端,或前后部上(如图1-图6所示),空腔呈上、下连通状,宽为20mm-60mm,空腔的三边腔壁和砌块侧壁的距离为0.5mm-25mm即空腔的壁厚为0.5mm-25mm;所说的砖体为烧结的有孔或无孔的粘土砌块,或粉煤灰砌块,或混凝土砌块等;所说的保温材料为聚氨酯、玻化微珠、聚苯颗粒、珍珠岩等保温隔热材料中的一种;所说的找平层是涂刷的普通砂浆(即灰浆,是由无机胶凝材料与细集料和水拌和而成,为常规通用技术),或防渗抗裂砂浆,或在温差较大地区,防渗抗裂砂浆内加有用于抗拉的网格布或耐碱的网格布;所说的饰面层为乳胶漆涂料、仿瓷涂料或饰面砖的一种;所说的防渗抗裂砂浆为苏州常熟市和成节能保温材料有限公司、福建省沙县华鸿化工有限公司、成都齐能保温材料工程有限公司等生产的市售产品。本发明不仅克服外保温墙粘结不牢、抗老化、抗风压能力差,易开裂等问题,也减少了施工工序降低了造价,本发明还具有防火、防水性能良好兼具可围护承重的优点。In view of the above situation, in order to overcome the defects of the prior art, the object of the present invention is to provide a fire-proof and heat-insulating wall with perfusion insulation layer, which can effectively solve the problems of poor heat preservation performance, complicated construction, difficult control of quality, safety and stability, and easy cracking of the surface layer. , the technical solution is that the fire-proof and thermal-insulation wall is formed by masonry of single-layer or double-layer bricks with cavities (also known as blocks, the same below), and pouring the thermal insulation layer. The masonry method is as follows: The outer wall is vertically aligned, and there is no gap in the mortar between the bricks to prevent the insulation material from flowing out when the insulation layer is poured. There must be no mortar in the cavity. If the mortar falls accidentally, it should be removed from the cavity as soon as possible; masonry 0.6 From a height of 3.0 meters to 3.0 meters, the insulation layer is poured, and the insulation material is poured into the cavity. Set a leveling layer on the surface, and after the strength of the leveling layer reaches 0.4mpa, paint the finish layer to form a fireproof and thermal insulation wall with a perfusion insulation layer; the brick body with a cavity has 1 or 2 cavities, The cavity is placed on the left end of the brick body, or the right end, or the front, or the rear, or the left and right ends, or the front and rear (as shown in Figure 1-Figure 6), the cavity is connected up and down, and the width The distance between the three sides of the cavity and the side wall of the block is 0.5mm-25mm, that is, the wall thickness of the cavity is 0.5mm-25mm; the brick body is sintered with or without holes Clay blocks, or fly ash blocks, or concrete blocks, etc.; the thermal insulation material is one of polyurethane, vitrified beads, polystyrene particles, perlite and other thermal insulation materials; the leveling The layer is painted ordinary mortar (that is, mortar, which is made of inorganic cementitious material mixed with fine aggregate and water, which is a conventional general technology), or anti-seepage and anti-crack mortar, or in areas with large temperature differences, anti-seepage and anti-crack The cracking mortar is added with mesh cloth for tensile strength or alkali-resistant mesh cloth; the said finishing layer is a kind of latex paint coating, imitation porcelain coating or facing brick; the said anti-seepage and anti-cracking mortar is Commercially available products produced by Suzhou Changshu City Hecheng Energy-saving Thermal Insulation Material Co., Ltd., Fujian Shaxian Huahong Chemical Co., Ltd., and Chengdu Qineng Thermal Insulation Material Engineering Co., Ltd. The invention not only overcomes the problems of poor bonding, anti-aging, poor wind pressure resistance, and easy cracking of the external thermal insulation wall, but also reduces the construction process and reduces the cost. The invention also has good fireproof and waterproof performance and can be enclosed and loaded The advantages.
四、附图说明4. Description of drawings
图1为本发明的带一个空腔的有孔砌块的结构立体图。Fig. 1 is a structural perspective view of a perforated block with a cavity of the present invention.
图2为本发明的带两个空腔的有孔砌块的结构立体图。Fig. 2 is a perspective view of the structure of the perforated block with two cavities of the present invention.
图3为本发明有孔砌块的另一实施例的结构立体图。Fig. 3 is a structural perspective view of another embodiment of a block with holes in the present invention.
图4为本发明的带一个空腔的无孔砌块的结构立体图。Fig. 4 is a structural perspective view of a non-porous block with a cavity of the present invention.
图5为本发明的带两个空腔的无孔砌块的结构立体图。Fig. 5 is a structural perspective view of the non-porous block with two cavities of the present invention.
图6为本发明无孔砌块的另一实施例的结构立体图。Fig. 6 is a structural perspective view of another embodiment of the non-porous block of the present invention.
图7为本发明单层灌注保温层防火保温墙体的结构立体图。Fig. 7 is a perspective view of the structure of a single-layer poured thermal insulation layer fireproof and thermal insulation wall of the present invention.
图8为本发明双层灌注保温层防火保温墙体的结构立体图。Fig. 8 is a perspective view of the structure of a fire-proof and heat-insulating wall with a double-layer perfusion heat-insulation layer of the present invention.
图9为本发明另一实施例单层灌注保温层防火保温墙体的结构立体图。Fig. 9 is a perspective view of the structure of a fire-proof and heat-insulating wall with a single-layer perfusion heat-insulation layer according to another embodiment of the present invention.
五、具体实施方式5. Specific implementation
以下结合实际情况对本发明的具体实施方式作详细说明。The specific implementation manners of the present invention will be described in detail below in combination with actual conditions.
实施例1:Example 1:
该防火保温墙体是由带1个空腔1的砖体砌筑成单层,灌注保温层构成,空腔置于砖体的前部上(如图7所示),宽为40mm,壁厚2为10mm,砖体为烧结的有孔的粘土砌块,其砌筑方法是,外墙面垂直对齐,砖体3间的砂浆内无空隙,防止灌注保温层时保温材料外流,空腔中不能有砂浆,如不慎有砂浆掉落,应尽快从空腔内清除;砌筑0.6米的高度,进行保温层4灌注,向空腔内灌注玻化微珠保温材料,保温层灌注要饱满无空隙,即形成灌注玻化微珠保温外墙;待整片墙砌筑完成后,在外墙的内、外表面粉刷防渗抗裂砂浆形成找平层,待由防渗抗裂砂浆形成的找平层的强度达到0.4mpa后,再粉刷乳胶漆涂料,形成饰面层,即成灌注保温层防火保温墙体。The fireproof and thermal insulation wall is made of bricks with a cavity 1 built into a single layer, and the thermal insulation layer is poured. The cavity is placed on the front of the brick (as shown in Figure 7), and the width is 40mm. The
实施例2:Example 2:
该防火保温墙体是由带2个空腔1的砖体砌筑成单层,灌注保温层构成,空腔置于砖体的前后部上(如图9所示),宽为25mm,壁厚2为5mm,砖体为烧结的有孔的粉煤灰砌块,其砌筑方法是,外墙面垂直对齐,砖体3间的砂浆内无空隙,防止灌注保温层时保温材料外流,空腔中不能有砂浆,如不慎有砂浆掉落,应尽快从空腔内清除;砌筑1.5米的高度,进行保温层4灌注,向空腔内灌注聚氨酯保温材料,将聚醚多元醇(B料)和异氰酸脂(A料)以1∶1混合均匀后,浇注在空腔内,保温层灌注要饱满无空隙,待聚氨酯保温材料凝结后,即形成灌注聚氨酯复合保温外墙;待整片墙砌筑完成后,在外墙的内、外表面粉刷防渗抗裂砂浆,并在防渗抗裂砂浆中铺设耐碱的网格布形成找平层,以增强抗裂性和抗冲性,待由防渗抗裂砂浆和耐碱的网格布形成的找平层的强度达到0.4mpa后,再粘贴饰面砖,形成饰面层,即成灌注保温层防火保温墙体。The fireproof and thermal insulation wall is made of bricks with two cavities 1 to form a single layer, and the insulation layer is poured. The cavity is placed on the front and back of the brick body (as shown in Figure 9), and the width is 25mm. The
实施例3:Example 3:
该防火保温墙体是由带1个空腔1的砖体砌筑成双层,灌注保温层构成,空腔置于砖体的前部上或右端上(如图8所示),宽为55mm,壁厚2为20mm,砖体为烧结的有孔的混凝土砌块,其砌筑方法是,外墙面垂直对齐,砖体3间的砂浆内无空隙,防止灌注保温层时保温材料外流,空腔中不能有砂浆,如不慎有砂浆掉落,应尽快从空腔内清除;砌筑2米的高度,进行保温层4灌注,向空腔内灌注聚苯颗粒保温材料,将聚苯颗粒保温材料浇注在空腔内,保温层灌注要饱满无空隙,即形成灌注聚苯颗粒保温外墙;待整片墙砌筑完成后,在外墙的内、外表面粉刷普通砂浆形成找平层,待由普通砂浆形成的找平层强度达到0.4mpa后,再粉刷仿瓷涂料,形成饰面层,即成灌注保温层防火保温墙体。The fireproof and heat-preserving wall is made of bricks with a cavity 1 to form a double-layer, poured with a heat-insulating layer, and the cavity is placed on the front or right end of the brick body (as shown in Figure 8), with a width of 55mm,
本发明的具有以下特点:The present invention has the following characteristics:
(1)、该保温墙体减少了恶劣条件对外保温层施工及使用时的影响,防止了粘结不牢、易鼓空开裂等问题;(1) The insulation wall reduces the impact of harsh conditions on the construction and use of the external insulation layer, and prevents problems such as weak bonding, easy hollowing and cracking;
(2)、由于该保温墙体是直接在砌筑时形成的空腔中灌注保温层,可以和砌筑同时施工,减少需等施工结束以后再专门在制作保温层的工序,降低了造价,保温层在空腔内形成一个整体,减少了热桥的发生,提高了整片墙的保温效果;(2) Since the thermal insulation wall is directly filled with the thermal insulation layer in the cavity formed during the masonry, it can be constructed simultaneously with the masonry, reducing the need to wait until the end of the construction and then specially making the thermal insulation layer process, reducing the cost, The insulation layer forms a whole in the cavity, which reduces the occurrence of thermal bridges and improves the insulation effect of the entire wall;
(3)、现场灌注保温层防火保温墙体中的砌块除了大的空腔外,其它部分和普通砌块尺寸一样所以,既可用于填充结构也可以用于承重结构。(3) Except for the large cavity, the blocks in the on-site pouring insulation layer are the same size as ordinary blocks, so they can be used for both filling structures and load-bearing structures.
经实验,吸水量0.5-0.8kg/m2,小于保温规程1.0kg/m2,砖体材料达到A级要求,聚氨酯等保温材料达B1级要求,耐冻融性能,抗冲击性能符合《外墙外保温工程技术规程》要求,30次冻融循环后,墙体无空鼓脱落无渗水裂缝,本发明防火保温墙体的拉伸粘结强度在0.1-0.3Mpa,破坏部位位于保温层,保温材料导热系数在0.024-0.060之间,人工老化性能2000次实验,墙体无开裂。并经80次高温(70℃)——降雨(15℃)循环和20次加热(50℃)——冷冻(-20℃)循环的耐候性试验没有出现空鼓、脱落及开裂。According to the experiment, the water absorption is 0.5-0.8kg/m2, which is less than 1.0kg/m2 of the thermal insulation regulations. The brick body material meets the requirements of Class A, and the polyurethane and other thermal insulation materials meet the requirements of Class B1. According to the Technical Regulations for Thermal Insulation Engineering, after 30 freeze-thaw cycles, the wall will have no hollowing and no water seepage cracks. The tensile bond strength of the fireproof and thermal insulation wall of the present invention is 0.1-0.3Mpa, and the damaged part is located in the thermal insulation layer. The thermal insulation material The thermal conductivity is between 0.024-0.060, the artificial aging performance has been tested for 2000 times, and the wall has no cracks. And after 80 high temperature (70°C)-rainfall (15°C) cycles and 20 times of heating (50°C)-freezing (-20°C) cycles in the weather resistance test, no hollowing, shedding and cracking occurred.
综上所述,本发明灌注保温层防火保温墙体和现有墙体外保温相比,不仅解决了易脱粘空鼓、面层易开裂的问题,并使防水、防火、抗冲击、抗老化等性能得到明显提高;还减少了外保温施工步骤,缩短了施工工期,降低了工程造价,该墙体是砌体结构上一次大的改革,是其它墙体无可比拟的新结构。To sum up, compared with the external heat preservation of the existing wall, the fire-proof and heat-preservation wall of the perfusion insulation layer of the present invention not only solves the problems of easy debonding, hollowing and easy cracking of the surface layer, but also makes it waterproof, fire-proof, impact-resistant, and resistant. Aging and other properties have been significantly improved; it also reduces the construction steps of external insulation, shortens the construction period, and reduces the cost of the project. This wall is a major reform of the masonry structure and is an incomparable new structure for other walls.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010101259138A CN101806106B (en) | 2010-03-17 | 2010-03-17 | Fire-proof thermal insulation wall body poured with thermal insulation layer |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2010101259138A CN101806106B (en) | 2010-03-17 | 2010-03-17 | Fire-proof thermal insulation wall body poured with thermal insulation layer |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101806106A CN101806106A (en) | 2010-08-18 |
| CN101806106B true CN101806106B (en) | 2012-07-04 |
Family
ID=42608043
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2010101259138A Expired - Fee Related CN101806106B (en) | 2010-03-17 | 2010-03-17 | Fire-proof thermal insulation wall body poured with thermal insulation layer |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101806106B (en) |
Families Citing this family (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102320799A (en) * | 2011-09-01 | 2012-01-18 | 王长河 | Light fly ash multi-row hole self-thermal insulation building block |
| CN103306397A (en) * | 2012-03-08 | 2013-09-18 | 顾世章 | Integrated load bearing and heat preservation wall structure |
| CN105060781A (en) * | 2014-09-29 | 2015-11-18 | 济南天硕新型墙材有限公司 | Self-thermal insulation concrete block |
| CN106121069A (en) * | 2016-07-29 | 2016-11-16 | 北京奥克森节能环保科技有限公司 | A kind of construction method of construction wall insulation |
| CN107620399A (en) * | 2017-11-14 | 2018-01-23 | 湖州交科规划设计有限公司 | Building heat preservation wall |
| CN114370122A (en) * | 2021-12-20 | 2022-04-19 | 翟贤明 | Hollow aerated concrete slab with reinforcing columns and processing method thereof |
| CN117306771A (en) * | 2023-10-20 | 2023-12-29 | 邓环宇 | A rigid polyurethane infused composite structure thermal insulation integrated block and its preparation method |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US5159795A (en) * | 1990-07-13 | 1992-11-03 | Colen William J | Wall construction and spacer for use therewith |
| CN2223759Y (en) * | 1995-01-25 | 1996-04-03 | 郭景阳 | Light wt. concrete hollow brick unit |
| AU3554897A (en) * | 1997-07-24 | 1999-02-16 | Kobahidze, Vitaly | Interlocking building block system and methods of constructing walls, including with a thermal insulation |
| CN1587568A (en) * | 2004-08-31 | 2005-03-02 | 翟晓莉 | Heat insulation concrete small hollow building blocks with heat insulation chamber and its construction method |
| CN1715583A (en) * | 2005-07-20 | 2006-01-04 | 上海奥伯实业有限公司 | Master-slave type heat insulation brick or block and its producing and building method |
| CN201031450Y (en) * | 2006-11-14 | 2008-03-05 | 于文艳 | Concrete small-sized hollow building block |
| RU2354784C2 (en) * | 2007-01-09 | 2009-05-10 | Ваис Хайдарович Мухамадиев | Dry-mix method of wall construction |
-
2010
- 2010-03-17 CN CN2010101259138A patent/CN101806106B/en not_active Expired - Fee Related
Also Published As
| Publication number | Publication date |
|---|---|
| CN101806106A (en) | 2010-08-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101806106B (en) | Fire-proof thermal insulation wall body poured with thermal insulation layer | |
| CN105604239B (en) | A kind of foam concrete functionally gradient composite plate and preparation method thereof | |
| CN103086661B (en) | A kind of heat-insulation slurry composition and the heat-insulation and heat-preservation sheet material containing said composition | |
| CN100564755C (en) | Light phase-change heat-insulation wall building block | |
| CN202577625U (en) | Composite insulation board with organic materials coated by inorganic materials | |
| CN201649497U (en) | A kind of building outer wall fireproof isolation belt plate | |
| CN103266686B (en) | An inflatable skeleton filled wall | |
| CN101503903A (en) | Inorganic heat-preserving metal facing one-piece type fire wall section material and its production method | |
| CN102992712A (en) | Method for preparing light thermal insulating panel by utilizing iron tailings | |
| CN104003680B (en) | Self-heat conserving masonry is built by laying bricks or stones and is used heat insulating mortar powder | |
| CN201704855U (en) | Foam concrete jacketing building block | |
| CN205242685U (en) | Cast -in -place compound self preservation temperature wall body of assembled | |
| CN101565975B (en) | Self heat preserving wall body and manufacturing method thereof | |
| CN204112508U (en) | A kind of in-situ concrete wall fire-retardant heat insulation structure | |
| CN102505800B (en) | Combined type unreinforced thermal-insulating sandwich external wall slab and manufacturing method for inner laminate and outer laminate of same | |
| CN112780037A (en) | Light decoration and heat preservation integrated external wall panel | |
| CN201794205U (en) | Interlocking-type self-heat-preserving wall body building block with air sandwich layer | |
| CN201459966U (en) | Self-insulation wall structure for building | |
| CN201031454Y (en) | An energy-saving thermal insulation wall | |
| CN107806250A (en) | Dry-hang exterior wall repairing and reinforcing method | |
| CN202595931U (en) | Novel vacuum insulation board plaster external wall insulation system | |
| CN207211495U (en) | A kind of combined wall board provided with cement foamed sandwich layer | |
| CN202644887U (en) | Fire-proof thermal-insulation and decoration integration board | |
| CN214941843U (en) | Light decoration and heat preservation integrated external wall panel | |
| CN204435597U (en) | Self-insulation wall structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| ASS | Succession or assignment of patent right |
Owner name: HENAN UNIVERSITY Free format text: FORMER OWNER: YUE JIANWEI Effective date: 20120425 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| C53 | Correction of patent for invention or patent application | ||
| CB03 | Change of inventor or designer information |
Inventor after: Yue Jianwei Inventor after: Zhang Weimin Inventor after: Yue Jianxin Inventor after: Li Liandong Inventor after: Sun Xinsheng Inventor after: Kong Kaige Inventor before: Yue Jianwei Inventor before: Zhang Weimin Inventor before: Yue Jianxin Inventor before: Li Liandong Inventor before: Sun Xinsheng |
|
| COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: YUE JIANWEI ZHANG WEIMIN YUE JIANXIN LI LIANDONG SUN XINSHENG TO: YUE JIANWEI ZHANG WEIMIN YUE JIANXIN LI LIANDONG SUN XINSHENG KONG KAIGE |
|
| TA01 | Transfer of patent application right |
Effective date of registration: 20120425 Address after: 475001 Henan province city Minglun Street No. 85, Henan University School of Civil Engineering Applicant after: Henan University Address before: 475001 Henan province city Minglun Street No. 85, Henan University School of Civil Engineering Applicant before: Yue Jianwei |
|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C17 | Cessation of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20120704 Termination date: 20130317 |
