CN101798931B - 一种隧道和地下工程无工作间超前大管棚施工工艺方法 - Google Patents

一种隧道和地下工程无工作间超前大管棚施工工艺方法 Download PDF

Info

Publication number
CN101798931B
CN101798931B CN 201010122486 CN201010122486A CN101798931B CN 101798931 B CN101798931 B CN 101798931B CN 201010122486 CN201010122486 CN 201010122486 CN 201010122486 A CN201010122486 A CN 201010122486A CN 101798931 B CN101798931 B CN 101798931B
Authority
CN
China
Prior art keywords
pipe
canopy
construction
hole
drilling rod
Prior art date
Application number
CN 201010122486
Other languages
English (en)
Other versions
CN101798931A (zh
Inventor
孙国庆
肖盛能
张民庆
高广义
牟松
李治国
邹明波
谢敏
Original Assignee
中铁隧道集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁隧道集团有限公司 filed Critical 中铁隧道集团有限公司
Priority to CN 201010122486 priority Critical patent/CN101798931B/zh
Publication of CN101798931A publication Critical patent/CN101798931A/zh
Application granted granted Critical
Publication of CN101798931B publication Critical patent/CN101798931B/zh

Links

Abstract

本发明提出的隧道和地下工程无工作间超前大管棚施工工艺方法,在设计隧道开挖轮廓线(1)内,利用钻机(4)按照设计参数在止浆墙(2)上钻出浅孔,安装管棚导向管(6),通过导向管(6)钻设管棚孔(9)至设计孔深,退出钻杆(3)并拆除钻头(5);钻杆(3)通过管棚连接件(10)与大管棚连接,冲击旋转逐节按次序将大管棚(9)推进管棚孔(8);下入最后一根管棚(14)时,换装上管棚推进器(13),直接将管棚推进至隧道开挖轮廓线(1)外,最后进行注浆施工。如此,逐个进行管棚施工,完成所设计的管棚。本发明工艺方法施工方便,可以大大降低工程成本和施工风险,经施工工程试验取得了良好的效果,具有很好的推广应用前景。

Description

一种隧道和地下工程无工作间超前大管棚施工工艺方法
技术领域
[0001] 本发明属于隧道和地下工程软弱围岩超前大管棚刚性支护技术,主要提出一种在无工作间前提下,进行超前大管棚施工对软弱破碎地层进行预支护,保证地下工程安全开挖的施工方法。
背景技术
[0002] 在软弱破碎地层中进行隧道和地下工程施工,最容易出现的问题是围岩大变形和开挖洞室坍塌,危及人员、设备安全,造成伤亡事故。对于浅埋隧道严重时引起地表塌陷,地表构筑物安全受到威胁,造成巨大的经济损失。为了保证施工安全,在软弱破碎地层施工过程中,国内外普遍采用超前预支护技术,施工超前刚性大管棚对软弱地层进行预棚架支护, 提高软弱围岩承载能力和周边围岩的稳定性,避免局部在开挖施工过程中发生坍塌,为安全快速开挖创造条件。
[0003] 目前国内外采用的传统大管棚施工法,均必须在工作面前扩大开挖洞室,形成大管棚施工工作间。大管棚施工工作间是沿隧道开挖轮廓线向外环向扩挖60〜80cm,纵向长度8〜10m。对于需要多循环超前管棚施工的地层,每开挖一个循环(15m)就要施工一次工作间,不仅增加了不必要的开挖工程量,而且在软弱地层扩大断面开挖施工,施工风险加大。
发明内容
[0004] 本发明提出一种隧道和地下工程无工作间超前大管棚施工工艺方法,直接利用隧道本身开挖空间进行超前大管棚支护施工,尤其适用于多循环软弱地层超前大管棚支护施工,减少开挖工程数量,降低工程成本和施工风险,达到对软弱地层超前支护的目的。
[0005] 本发明提出的一种隧道和地下工程无工作间超前大管棚施工工艺方法,是针对软弱破碎地层取消传统超前管棚施工需要的工作间,利用原设计隧道开挖空间进行超前支护施工;本发明所提出无工作间超前大管棚施工方法的工艺步骤为:先沿隧道设计的开挖轮廓线,根据设计参数标定管棚开孔位置;钻机就位后,按设计钻孔角度在止浆墙上钻出浅孔,退出钻杆,安装管棚导向管并用锚固剂固定在孔口壁上;通过导向管进行管棚孔作业, 采用高压风或水钻成孔;引孔到设计深度后,退出钻杆,拆除钻头;将管棚通过管棚连接件与钻杆连接,启动钻机,利用钻杆冲击旋转逐节按次序将大管棚推进入管棚孔内,每节管棚采用丝扣或焊接连接,为保证后续浆液充满孔,大管棚外壁设有溢浆孔;根据设计管棚长度确定使用管棚节数,按设计管棚长度,确认要下入最后一根管棚时,拆除管棚连接件,换装上管棚推进器利用丝扣和钻杆连接,在钻机动力下采用旋转及冲击作用将最后一根管棚推进管棚孔内,直到管棚末端到达隧道开挖轮廓线外,退出钻杆和管棚推进器,超前管棚安设完成;通过法兰盘连接注浆接头进行注浆施工;浆液沿管棚壁上的溢浆孔注入裂隙,通过浆液超前大管棚和软弱地层黏结成为整体,注浆到设计注浆压力或设计注浆量结束注浆, 拆除注浆管子,再进行下根管棚施工,如此循环直到所有设计管棚施工完成。[0006] 本发明所提出的取消管棚施工工作间直接利用隧道本身开挖空间进行超前大管棚支护施工工法,尤其适用与多循环软弱地层超前大管棚支护施工,减少开挖工程数量,降低工程成本和施工风险,达到对软弱地层超前支护的目的,满足不良地质条件下隧道开挖快挖、快支的技术要求,同时利用管棚推进器,将管棚末端推进至开挖轮廓线外,解决了隧道开挖施工过程钢管棚的切割问题。
附图说明
[0007] 图1-图6为本发明无工作间超前大管棚施工工艺的工艺步骤示意图。
[0008] 图7为管棚推进器的结构示意图。
[0009] 图8为图7的A向视图。
[0010] 图9为大管棚末端视图。
[0011] 图10为管棚推进器与管棚连接示意图。
[0012] 图11为无工作间超前大管棚施工成果图。
[0013] 图中,1、隧道开挖轮廓线,2、止浆墙,3、钻杆,4、钻机,5、钻头,6、导向管,7、法兰盘,8、锚固剂,9、管棚孔,10、大管棚,11、连接件,12、溢浆孔,13、管棚推进器,14、最后一根管棚,15、注浆接头,16、卡耳,17、卡槽,18、推进盘。
具体实施方式
[0014] 结合附图对本发明实施例加以说明:
[0015] 本发明所提出无工作间超前大管棚施工技术的工艺步骤为:
[0016] 如图1所示,步骤1钻浅孔。钻机4就位后,根据设计开孔位置及钻孔参数调整钻机角度,钻孔1.5m。
[0017] 如图2所示,步骤2退出钻杆,安装管棚导向管6。导向管6采用无缝钢管加工制作,一端焊接法兰盘7,导向管安装前在距法兰盘前端部30cm处开始缠绕麻丝成纺锤形,并将锚固剂8放入孔口内,采用钻机4将导向管6顶入钻孔中,导向管6外留20cm。
[0018] 如图3所示,步骤3钻设大管棚孔。通过导向管6采用和钻孔孔径相匹配的钻头 5开始钻设管棚孔9至设计孔深,退出钻杆。
[0019] 如图4所示,步骤4下入超前大管棚。拆除钻头5后,在钻杆3上安设管棚连接件 11,将大管棚10采用丝扣和连接件相连,逐节按次序,依次推进入管棚孔9内,每节管棚间采用内外丝扣或焊接相连,为保证后续浆液充满孔,大管棚10外壁设有溢浆孔12。
[0020] 如图5所示,步骤5大管棚末端推进。按设计管棚长度,确认要下入最后一根管棚 14时,拆除管棚连接件11,换装上管棚推进器13利用丝扣15和钻杆连接3,管棚推进器13 另一端卡耳16卡入最后一根管棚14的卡槽17内,推进盘18刚好可以顶住最后一根管棚 14的末端,在钻机动力下采用旋转及冲击作用直接将最后一根管棚14推进管棚孔9内,直到最后一根管棚14末端到达隧道开挖轮廓线1外,退出钻杆3和管棚推进器13,超前管棚安设完成。
[0021] 如图6所示,步骤6管棚注浆。管棚安设完成后,通过法兰盘7连接注浆接头15 进行注浆施工,浆液沿管棚壁溢浆孔12注入裂隙,通过浆液超前大管棚和软弱地层黏结成为整体,提高支护效果。[0022] 如此,逐个管棚进行施工,循环直到所有设计管棚施工完成。
[0023] 管棚推进器的结构及与管棚连接结构如图7、图8、图9、图10所示。
[0024] 在宜(昌)_万(州)铁路齐岳山隧道纵向230m长的Fll高压富水破碎断层的施工中,进行无工作间超前支护施工工艺方法的试验施工,获得成功,取得较好的经济和社会效益。

Claims (1)

1. 一种隧道和地下工程无工作间超前大管棚施工工艺方法,其特征是:所述无工作间超前大管棚施工的工艺步骤为:先沿隧道设计的开挖轮廓线(1),根据设计参数标定管棚开孔位置;钻机就位后,按设计钻孔角度在止浆墙(¾上钻出浅孔,退出钻杆,安装管棚导向管(6)并用锚固剂(8)固定在孔口壁上;通过导向管(6)进行管棚孔(9)作业,采用高压风或水钻成孔;引孔到设计孔深后,退出钻杆(3),拆除钻头(5);在钻杆C3)上安设管棚连接件(11),将大管棚(10)采用丝扣和连接件(11)连接后,启动钻机,利用钻杆冲击旋转逐节按次序将大管棚(10)推进入管棚孔(9)内,每节大管棚(10)之间采用内外丝扣或焊接连接;为保证后续浆液充满孔,大管棚(10)外壁设有溢浆孔(1¾ ;根据设计管棚长度确定使用管棚节数,按设计管棚长度,确认要下入最后一根管棚(14)时,拆除管棚连接件(11), 换装上管棚推进器(1¾利用丝扣与钻杆(¾连接,在钻机动力下采用旋转及冲击作用将最后一根管棚(14)推进管棚孔(9)内,直到最后一根管棚(14)末端到达隧道开挖轮廓线外, 退出钻杆C3)和管棚推进器(13),超前管棚安设完成;通过法兰盘(7)连接注浆接头(15) 进行注浆施工,浆液沿管棚壁上的溢浆孔注入裂隙,通过浆液超前大管棚和软弱地层黏结成为整体,注浆到设计注浆压力或设计注浆量结束注浆;拆除注浆管子,再进行下根管棚施工,如此循环直到所有设计管棚施工完成。
CN 201010122486 2010-03-12 2010-03-12 一种隧道和地下工程无工作间超前大管棚施工工艺方法 CN101798931B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010122486 CN101798931B (zh) 2010-03-12 2010-03-12 一种隧道和地下工程无工作间超前大管棚施工工艺方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010122486 CN101798931B (zh) 2010-03-12 2010-03-12 一种隧道和地下工程无工作间超前大管棚施工工艺方法

Publications (2)

Publication Number Publication Date
CN101798931A CN101798931A (zh) 2010-08-11
CN101798931B true CN101798931B (zh) 2011-09-28

Family

ID=42594757

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010122486 CN101798931B (zh) 2010-03-12 2010-03-12 一种隧道和地下工程无工作间超前大管棚施工工艺方法

Country Status (1)

Country Link
CN (1) CN101798931B (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107339108A (zh) * 2017-06-26 2017-11-10 中铁十二局集团有限公司 地下水富集的砂层地段地铁管棚施工方法
CN110242327A (zh) * 2019-06-21 2019-09-17 王亚星 一种地下工程隧道用管棚安装装置

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102128038B (zh) * 2011-01-26 2013-11-13 北京中铁瑞威基础工程有限公司 一种隧道管棚快速施工方法
CN102174894A (zh) * 2011-03-15 2011-09-07 中铁十二局集团第一工程有限公司 跟进式管棚施工方法
CN102168563B (zh) * 2011-03-18 2012-12-05 同济大学 管棚或小导管静压顶入方法
CN102182471B (zh) * 2011-03-23 2013-05-29 彬县水帘洞煤炭有限责任公司 煤矿巷道高冒区超前支护方法
CN102235171A (zh) * 2011-08-09 2011-11-09 河南理工大学 松软破碎煤岩定向注浆加固方法
CN102562087B (zh) * 2011-12-12 2015-06-24 中铁二局股份有限公司 水钻跟进管棚施工方法
CN104806267B (zh) * 2015-04-29 2017-10-03 中铁第一勘察设计院集团有限公司 卵石土地层超前大管棚的盾构端头加固体系及其施工方法
CN104879137A (zh) * 2015-05-18 2015-09-02 石家庄铁道大学 超大管棚施工方法
CN105019917B (zh) * 2015-08-13 2017-05-10 青岛业高建设工程有限公司 冲击钻进式超前旋喷管棚施工装置及施工方法
CN105781591A (zh) * 2016-01-26 2016-07-20 中铁二十二局集团第工程有限公司 一种管棚支护结构
CN105736018B (zh) * 2016-01-28 2018-06-19 上海隧道工程有限公司 用于软弱地层隧道的压入式管棚支护结构
CN106437738A (zh) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 一种管棚施工推进器及其使用方法
CN107060821A (zh) * 2017-03-24 2017-08-18 中铁十六局集团第五工程有限公司 一种掌子面多岩性支护方法
CN107013220A (zh) * 2017-05-16 2017-08-04 深圳市瑞利源工程技术有限公司 一种隧道深孔注浆方法、管棚兼后退式注浆管
CN108104840B (zh) * 2017-12-14 2019-09-06 中铁四局集团有限公司 卵石堆积层隧道超前管棚逐个钻孔空孔注浆成孔法及应用
CN108547639B (zh) * 2018-03-13 2019-12-03 北京市政路桥股份有限公司 隧道临近既有构筑物的超前同孔多导管分层注浆施工方法

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE19930504B4 (de) * 1999-07-03 2011-07-21 Klemm Bohrtechnik Zweigniederlassung der Bauer Maschinen GmbH, 57489 Verfahren zum Auffahren von Strecken in stark wasserführenden Schichten und dafür geeignete Bohreinrichtung
KR101023565B1 (ko) * 2003-11-19 2011-03-21 주식회사 케이티 이수흐름의 제어가 가능한 굴진기
CN101196118A (zh) * 2008-01-07 2008-06-11 北京市政建设集团有限责任公司 超前双排注浆小导管施工工艺
CN101285385B (zh) * 2008-05-29 2010-06-02 中交第二公路勘察设计研究院有限公司 三维管幕暗挖法
CN101387202B (zh) * 2008-10-29 2010-06-23 中铁四局集团有限公司 隧道内已成初支软弱围岩地段扩挖管棚工作室的方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107339108A (zh) * 2017-06-26 2017-11-10 中铁十二局集团有限公司 地下水富集的砂层地段地铁管棚施工方法
CN110242327A (zh) * 2019-06-21 2019-09-17 王亚星 一种地下工程隧道用管棚安装装置

Also Published As

Publication number Publication date
CN101798931A (zh) 2010-08-11

Similar Documents

Publication Publication Date Title
CN105372410B (zh) 双端封堵测漏一体化观测系统
CN102383828B (zh) 深孔水力致裂驱赶瓦斯浅孔抽采的增透与消突方法
CN101275469B (zh) 松软煤岩层下向钻孔抽采卸压瓦斯施工方法
CN103696800B (zh) 一种钻割压抽方法
CN101806217B (zh) 三线并行小净距浅埋、偏压隧道群进洞施工方法
CN101832102B (zh) 可移动双平台分区式四臂顶帮锚杆锚索施工钻车
CN103088819B (zh) 预应力锚索施工方法
CN102121395B (zh) 低渗透单一煤层瓦斯综合治理一体化的方法
CN201714392U (zh) 一种凿岩装置
KR100919628B1 (ko) 초경팁이 구비된 굴착면의 확장 및 축소가 가능한 직천공장치용 천공비트
CN102644467B (zh) 顶管直接切削管片隧道联络通道施工方法
CN101748970B (zh) 超短半径径向钻井工具系统
CN106368701A (zh) 利用水力压裂卸压控制回采巷道留巷的方法及装置
CN100513745C (zh) 机械扩孔锚杆施工方法
CN103775092B (zh) 隧道浅埋暗挖预留核心土改良crd施工工法
CN105113987A (zh) 软硬互层煤层顺层随钻测量定向钻进装备及其施工方法
CN102536252B (zh) 一种极小净距隧道后行洞开挖方法
CN104763328A (zh) 一种液压扩孔循环钻机及其扩孔桩施工工艺
CN103061785B (zh) 巷道破碎涌水围岩钻孔套管隔压渗透封固注浆装置所采用的注浆工艺
CN106285617B (zh) 天然气水平井完井方法
CN203080518U (zh) 自钻式可回收锚索
CN103899316B (zh) 钻井法竖井钻机
CN104005417A (zh) 一种松散碎裂岩质高边坡施工方法
CN103306687A (zh) 软岩隧道长悬臂水平旋喷变形控制施工方法
CN105298517A (zh) 软弱围岩隧道超前加强支护施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant