CN101798794A - 利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法 - Google Patents

利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法 Download PDF

Info

Publication number
CN101798794A
CN101798794A CN 201010138724 CN201010138724A CN101798794A CN 101798794 A CN101798794 A CN 101798794A CN 201010138724 CN201010138724 CN 201010138724 CN 201010138724 A CN201010138724 A CN 201010138724A CN 101798794 A CN101798794 A CN 101798794A
Authority
CN
China
Prior art keywords
concrete
web
shape steel
folding shape
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010138724
Other languages
English (en)
Other versions
CN101798794B (zh
Inventor
梁立农
卢绍鸿
刘玉擎
孙颖
梁雄
王倩
刘桂红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong communication Planning and Design Institute Group Co Ltd
Original Assignee
GUANGDONG HIGHWAY DESIGN INSTITUTE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG HIGHWAY DESIGN INSTITUTE Co Ltd filed Critical GUANGDONG HIGHWAY DESIGN INSTITUTE Co Ltd
Priority to CN2010101387244A priority Critical patent/CN101798794B/zh
Publication of CN101798794A publication Critical patent/CN101798794A/zh
Application granted granted Critical
Publication of CN101798794B publication Critical patent/CN101798794B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

本发明公开了一种利用折形钢腹板钢梁先行架设组合箱梁桥,包括混凝土底板、钢梁和混凝上顶板,所述钢梁为折形钢腹板钢梁结构,所述钢梁包括竖向对称设置的一对折形钢腹板以及架设在所述一对折形钢腹板之间的空腹式横隔单元,所述折形钢腹板的上端设置有用于与所述混凝土顶板紧固相连的上连接机构,所述折形钢腹板的下端设置有用于与所述混凝土底板紧固相连的下连接机构。本发明还公开了一种利用折形钢腹板钢梁先行架设组合箱梁桥的施工方法。本发明利用折形钢腹板作为组合箱梁腹板,减轻了结构自重,提高了活载效率,解决传统混凝土箱梁腹板开裂问题;同时又能在高墩中实现无支架施工,提高施工质量并加快施工过程,具有突出的经济及社会效益。

Description

利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法
技术领域
本发明涉及一种组合箱梁桥及其施工方法,具体是指一种利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法。
背景技术
目前,普通的混凝土箱梁腹板与顶板、底板形成一体,顶板、底板的温差及其腹板的干燥收束引起的应力问题比较突出,同时梁的自重内力占设计内力比重大,混凝土腹板抗剪、抗拉强度不足等导致会出现各种各样的裂缝,严重地影响了桥梁的承载性能及其耐久性。而传统的折形钢腹板组合箱梁,虽能较好的解决上述问题,但因中小桥设计构造通常采用满堂支架,施工时严重影响桥下行车或墩较高时难以实现。
发明内容
本发明的目的之一是提供一种能够减轻结构自重、提高活载效率且抗裂性好的利用折形钢腹板钢梁先行架设组合箱梁桥。
本发明上述目的通过如下技术方案来实现的:一种利用折形钢腹板钢梁先行架设组合箱梁桥,包括混凝土底板、钢梁和混凝土顶板,所述钢梁分别与所述混凝土底板和混凝土顶板相连,其特征在于:所述钢梁为折形钢腹板钢梁结构,所述钢梁包括竖向对称设置的一对折形钢腹板以及架设在所述一对折形钢腹板之间的空腹式横隔单元,所述折形钢腹板的上端设置有用于与所述混凝土顶板紧固相连的上连接机构,所述折形钢腹板的下端设置有用于与所述混凝土底板紧固相连的下连接机构。
本发明的组合箱梁桥利用折形钢腹板作为组合箱梁腹板,减轻了结构自重,提高了活载效率,解决了传统混凝土箱梁腹板开裂问题;折形钢腹板钢梁作为结构本身的一部分又作为后吊装结构的临时支撑,免除传统施工中临支架对桥下行车的影响,同时又能在高墩中实现无支架施工,节约了造价,大部分结构工厂预制,提高施工质量并加快施工过程,具有突出的经济及社会效益。
作为本发明的一种实施方式,所述的空腹式横隔单元包括一对竖向设置的竖向加劲肋、纵向设置于所述竖向加劲肋底端的纵向加劲肋以及设置在所述竖向加劲肋之间的多根拉杆,所述竖向加劲肋与所述的折形钢腹板固定相连。
作为本发明的一种实施方式,所述混凝土顶板包括顶板板体,所述混凝土顶板底面设有连接钢板并开设有剪力槽,所述剪力槽的开设位置与所述折形钢腹板相对应;所述折形钢腹板的上连接机构包括水平设置的上翼缘板以及竖向焊接在所述上翼缘板上的具有抗剪功能的多根上翼板剪力键,所述折形钢腹板与所述上翼缘板焊接,所述上翼缘板与所述连接钢板焊接,所述上翼板剪力键穿过所述连接钢板后伸入到所述剪力槽内,所述剪力槽内浇注混凝土。
作为本发明的进一步改进,所述顶板板体纵向设置有提高桥面强度和结合力的顶板钢束。
作为本发明的一种实施方式,所述混凝土底板包括底板板体;所述折形钢腹板的下连接机构包括水平设置的下翼缘板、竖向焊接在所述下翼缘板上的具有抗剪功能的多根下翼板剪力键以及所述折形钢腹板侧面横向设置的多根腹板剪力键,所述折形钢腹板的底端与所述下翼缘板焊接,所述混凝土底板在所述底板板体与所述下连接机构之间为纵向浇注形成的浇注混凝土。
作为本发明的进一步改进,在所述下翼缘板和所述折形钢腹板之间横向设置有提高所述下翼缘板的强度和稳定性的横向加劲肋,所述横向加劲肋纵向还设有多个钢筋栓孔,多条钢筋栓纵向穿过所述的钢筋栓孔。
作为本发明的进一步改进,所述底板板体纵向设置有提高底板强度和结合力的底板钢束。
本发明的目的之二是提供上述组合箱梁桥的施工方法,该施工方法利用波折钢腹板钢梁先行架设作为混凝土顶板、底板的临时支撑,吊装预制顶板、底板,并浇注纵横湿接缝混凝土,张拉纵横预应力,纵横竖三向预制拼装结构形成组合箱梁,共同承担恒活载。
本发明上述目的通过如下技术方案来实现的:一种利用折形钢腹板钢梁先行架设组合箱梁桥的施工方法,包括如下步骤:
(1)折形钢腹板钢梁节段工厂制作,以空腹式横梁连接,形成框架,并在工厂进行预拼;对折形钢腹板钢梁分段吊装,并按设计预设拱度调整,完成合拢,形成多点支撑的波折钢腹板连续梁;
(2)以折形钢腹板钢梁为工作平台,将预制底板板体吊装至折形钢腹板钢梁下翼缘板上;
(3)在腹板横向加劲肋板孔洞中穿入钢筋,绑扎底板横向现浇段和纵向现浇段钢筋;按设计顺序及方向浇筑底板横向现浇段和纵向现浇段混凝土,部分钢横梁埋入混凝土形成劲性骨架;
(4)绑扎边跨和中跨支座附近横梁、底板和内衬混凝土内钢筋,浇筑混凝土;待现浇混凝土达到设计强度90%且龄期7天后张拉底板钢束;
(5)在已建好的桥梁结构上,吊装预制混凝土顶板;
(6)焊接混凝土顶板底部的连接钢板与折形钢腹板的上翼缘板,浇筑顶板剪力槽混凝土;
(7)中跨中向支点浇注顶板现浇段混凝土,待现浇混凝土达到设计强度90%且龄期7天后张拉混凝土顶板钢束;
(8)进行防撞栏、沥青混凝土铺装、伸缩缝等其它附属设施的施工与安装,成桥。
与现有技术相比,本发明具有如下显著效果:
(1)本发明的组合箱梁桥利用折形钢腹板作为组合箱梁腹板,减轻了结构自重,提高活载效率,解决了传统混凝土箱梁腹板开裂问题。
(2)本发明的组合箱梁桥中折形钢腹板钢梁作为结构本身的一部分又作为后吊装结构的临时支撑,免除传统施工中临支架对桥下行车的影响,同时又能在高墩中实现无支架施工,节约了造价,有良好的社会及经济效果。
(3)本发明的组合箱梁桥中折形钢腹板钢梁、混凝土顶板、混凝土底板均采用预制结构,可以缩短工期,加快施工速度,节省劳动力。
(4)本发明的组合箱梁桥中折形钢腹板钢梁、混凝土顶板、混凝土底板由于采用预制结构,可在各自的阶段施工,施工性和施工质量均可较大程度提高
附图说明
下面结合附图和具体实施方式对本发明作进一步的详细说明。
图1为本发明组合箱梁桥的整体结构截面示意图;
图2是本发明组合箱梁桥中混凝土顶板的结构示意图;
图3是本发明组合箱梁桥中钢梁的结构示意图;
图4是本发明组合箱梁桥中混凝土底板的结构示意图;
图5是本发明组合箱梁桥中钢梁和混凝土顶板的连接示意图,显示折形钢腹板和上连接机构与混凝土顶板的连接关系;
图6是本发明组合箱梁桥中钢梁和混凝土底板的连接示意图,显示折形钢腹板和下连接机构与混凝土底板的连接关系。
具体实施方式
如图1至图6所示的一种利用折形钢腹板钢梁先行架设组合箱梁桥,包括混凝土底板3、钢梁2和混凝土顶板1,钢梁2分别与混凝土底板3和混凝土顶板1相连,混凝土底板3安装在钢梁2上,并且承载混凝土顶板1,钢梁2为折形钢腹板钢梁结构,每一个钢梁2包括竖向对称设置的一对折形钢腹板21以及架设在一对折形钢腹板之间的空腹式横隔单元,折形钢腹板21的上端设置有用于与混凝土顶板1紧固相连的上连接机构,折形钢腹板21的下端设置有用于与混凝土底板3紧固相连的下连接机构。
所述的空腹式横隔单元沿桥梁纵向每隔4~6m布置一道,以保证折形钢腹板钢梁架设及预制混凝土顶底板吊装时结构整体性,空腹式横隔单元包括一对竖向设置的竖向加劲肋22、纵向设置于竖向加劲肋底端的纵向加劲肋23以及设置在竖向加劲肋之间的多根拉杆24,竖向加劲肋22与折形钢腹板21固定相连。
为改善桥梁结构运营状态抗扭性能,本发明的横隔单元也可采用实腹式隔板结构,在桥身纵向每隔8~12m,在空腹式横隔单元处浇注钢筋混凝土,形成型钢混凝土实腹式隔板单元。
所述的混凝土顶板1包括顶板板体11,顶板板体11纵向设置有提高桥面强度和结合力的顶板钢束15,混凝土顶板1底面设有连接钢板13并开设有剪力槽12,剪力槽12的开设位置与折形钢腹板相对应;折形钢腹板21的上连接机构包括水平设置的上翼缘板25以及竖向焊接在上翼缘板上的具有抗剪功能的多根上翼板剪力键25a,折形钢腹板21与上翼缘板25焊接,上翼缘板25与连接钢板13焊接,上翼板剪力键25a穿过连接钢板13后伸入到剪力槽12内,剪力槽12内浇注混凝土14。
所述的混凝土底板包括底板板体31,底板板体31纵向设置有提高底板强度和结合力的底板钢束33;折形钢腹板21的下连接机构包括水平设置的下翼缘板26、竖向焊接在下翼缘板上的具有抗剪功能的多根下翼板剪力键26a以及折形钢腹板侧面横向设置的多根腹板剪力键21a,折形钢腹板21的底端与下翼缘板26焊接,混凝土底板在底板板体31与下连接机构之间为纵向浇注形成的浇注混凝土32。为满足吊装预制混凝土底板时下翼缘板的强度及稳定,在下翼缘板26和折形钢腹板21之间横向设置有提高下翼缘板的强度和稳定性的横向加劲肋27,横向加劲肋27纵向还设有多个钢筋栓孔27a,多条钢筋栓纵向穿过钢筋栓孔27a。
本发明中的多根剪力键设置如下:上翼板剪力键横向根据计算需要布置4~6根,纵向布置间距100mm~150mm,纵向连续布置;下翼板剪力键横向根据计算需要布置3~5根,纵向布置间距100mm~150mm;为加强混凝土底板与折形钢腹板的连接,折形钢腹板下缘侧面竖向布置三排腹板剪力键,布设于两斜板段,纵向布置间距80mm~130mm。
本发明同时还提供上述利用折形钢腹板钢梁先行架设组合箱梁桥的施工方法,包括如下步骤:
(1)折形钢腹板钢梁节段工厂制作,以空腹式横梁连接,形成框架,并在工厂进行预拼;对折形钢腹板钢梁分段吊装,并按设计预设拱度调整,完成合拢,形成多点支撑的折形钢腹板连续梁;
(2)以折形钢腹板钢梁为工作平台,将预制底板板体吊装至折形钢腹板钢梁下翼缘板上;
(3)在腹板横向加劲肋板孔洞中穿入钢筋,绑扎底板横向现浇段和纵向现浇段钢筋;按设计顺序及方向浇筑底板横向现浇段和纵向现浇段混凝土,部分钢横梁埋入混凝土形成劲性骨架;
(4)绑扎边跨和中跨支座附近横梁、底板和内衬混凝土内钢筋,浇筑混凝土;待现浇混凝土达到设计强度90%且龄期7天后张拉底板钢束;
(5)在已建好的桥梁结构上,吊装预制混凝土顶板;
(6)焊接混凝土顶板底部的连接钢板与折形钢腹板的上翼缘板,浇筑顶板剪力槽混凝土;
(7)中跨中向支点浇注顶板现浇段混凝土,待现浇混凝土达到设计强度90%且龄期7天后张拉混凝土顶板钢束;
(8)进行防撞栏、沥青混凝土铺装、伸缩缝等其它附属设施的施工与安装,成桥。

Claims (8)

1.一种利用折形钢腹板钢梁先行架设组合箱梁桥,包括混凝土底板(3)、钢梁(2)和混凝土顶板(1),所述钢梁(2)分别与所述混凝土底板(3)和混凝土顶板(1)相连,其特征在于:所述钢梁(2)为折形钢腹板钢梁结构,每一个钢梁(2)包括竖向对称设置的一对折形钢腹板(21)以及架设在所述一对折形钢腹板之间的空腹式横隔单元,所述折形钢腹板(21)的上端设置有用于与所述混凝土顶板(1)紧固相连的上连接机构,所述折形钢腹板(21)的下端设置有用于与所述混凝土底板(3)紧固相连的下连接机构。
2.根据权利要求1所述的利用折形钢腹板钢梁先行架设组合箱梁桥,其特征在于:所述的空腹式横隔单元包括一对竖向设置的竖向加劲肋(22)、纵向设置于所述竖向加劲肋底端的纵向加劲肋(23)以及设置在所述竖向加劲肋之间的多根拉杆(24),所述竖向加劲肋(22)与所述的折形钢腹板(21)固定相连。
3.根据权利要求1所述的利用折形钢腹板钢梁先行架设组合箱梁桥,其特征在于:所述混凝土顶板(1)包括顶板板体(11),所述混凝土顶板底面设有连接钢板(13)并开设有剪力槽(12),所述剪力槽(12)的开设位置与所述折形钢腹板相对应;所述折形钢腹板(21)的上连接机构包括水平设置的上翼缘板(25)以及竖向焊接在所述上翼缘板上的具有抗剪功能的多根上翼板剪力键(25a),所述折形钢腹板(21)与所述上翼缘板(25)焊接,所述上翼缘板(25)与所述连接钢板(13)焊接,所述上翼板剪力键(25a)穿过所述连接钢板(13)后伸入到所述剪力槽(12)内,所述剪力槽(12)内浇注混凝土(14)。
4.根据权利要求3所述的利用折形钢腹板钢梁先行架设组合箱梁桥,其特征在于:所述顶板板体(11)纵向设置有提高桥面强度和结合力的顶板钢束(15)。
5.根据权利要求1所述的利用折形钢腹板钢梁先行架设组合箱梁桥,其特征在于:所述混凝土底板包括底板板体(31);所述折形钢腹板(21)的下连接机构包括水平设置的下翼缘板(26)、竖向焊接在所述下翼缘板上的具有抗剪功能的多根下翼板剪力键(26a)以及所述折形钢腹板侧面横向设置的多根腹板剪力键(21a),所述折形钢腹板(21)的底端与所述下翼缘板(26)焊接,所述混凝土底板在所述底板板体(31)与所述下连接机构之间为纵向浇注形成的浇注混凝土(32)。
6.根据权利要求5所述的利用折形钢腹板钢梁先行架设组合箱梁桥,其特征在于:在所述下翼缘板(26)和所述折形钢腹板(21)之间横向设置有提高所述下翼缘板的强度和稳定性的横向加劲肋(27),所述横向加劲肋(27)纵向还设有多个钢筋栓孔(27a),多条钢筋栓纵向穿过所述的钢筋栓孔(27a)。
7.根据权利要求5所述的利用折形钢腹板钢梁先行架设组合箱梁桥,其特征在于:所述底板板体(31)纵向设置有提高桥墩强度和结合力的底板钢束(33)。
8.权利要求1所述的利用折形钢腹板钢梁先行架设组合箱梁桥的施工方法,包括如下步骤:
(1)折形钢腹板钢梁节段工厂制作,以空腹式横梁连接,形成框架,并在工厂进行预拼;对折形钢腹板钢梁分段吊装,并按设计预设拱度调整,完成合拢,形成多点支撑的折形钢腹板连续梁;
(2)以折形钢腹板钢梁为工作平台,将预制底板板体吊装至折形钢腹板钢梁下翼缘板上;
(3)在腹板横向加劲肋板孔洞中穿入钢筋,绑扎底板横向现浇段和纵向现浇段钢筋;按设计顺序及方向浇筑底板横向现浇段和纵向现浇段混凝土,部分钢横梁埋入混凝土形成劲性骨架;
(4)绑扎边跨和中跨支座附近横梁、底板和内衬混凝土内钢筋,浇筑混凝土;待现浇混凝土达到设计强度90%且龄期7天后张拉底板钢束;
(5)在已建好的桥梁结构上,吊装预制混凝土顶板;
(6)焊接混凝土顶板底部的连接钢板与折形钢腹板的上翼缘板,浇筑顶板剪力槽混凝土;
(7)中跨中向支点浇注顶板现浇段混凝土,待现浇混凝土达到设计强度90%且龄期7天后张拉混凝土顶板钢束;
(8)进行防撞栏、沥青混凝土铺装、伸缩缝的施工与安装,成桥。
CN2010101387244A 2010-03-29 2010-03-29 利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法 Active CN101798794B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101387244A CN101798794B (zh) 2010-03-29 2010-03-29 利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101387244A CN101798794B (zh) 2010-03-29 2010-03-29 利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法

Publications (2)

Publication Number Publication Date
CN101798794A true CN101798794A (zh) 2010-08-11
CN101798794B CN101798794B (zh) 2012-07-25

Family

ID=42594626

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101387244A Active CN101798794B (zh) 2010-03-29 2010-03-29 利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法

Country Status (1)

Country Link
CN (1) CN101798794B (zh)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094385A (zh) * 2010-12-07 2011-06-15 中铁大桥勘测设计院有限公司 用于单索面斜拉桥的带大挑臂的钢箱结合梁主梁
CN102877407A (zh) * 2012-10-30 2013-01-16 河南省交通规划勘察设计院有限责任公司 一种曲线桥用波形钢腹板混凝土连续箱梁
CN103031810A (zh) * 2011-09-29 2013-04-10 李跃军 基于压力和密度双参数的预应力孔道注浆质量控制方法
CN103397599A (zh) * 2013-08-14 2013-11-20 中铁大桥局股份有限公司 一种适用于多联现浇箱梁梁端钢束的布置结构及方法
CN104631305A (zh) * 2014-12-22 2015-05-20 郑州市交通规划勘察设计研究院 一种波形钢腹板斜拉桥的桁架式钢横隔板
CN104762871A (zh) * 2015-04-22 2015-07-08 武汉理工大学 一种预应力混凝土-钢槽梁结合梁连续梁桥
CN105780665A (zh) * 2016-05-06 2016-07-20 中铁大桥局集团第八工程有限公司 双向可调节连接装置及其施工方法
CN105926426A (zh) * 2016-05-06 2016-09-07 烟台图文马克化工科技有限公司 一种小箱梁桥梁的建造方法
CN108004932A (zh) * 2017-12-14 2018-05-08 河南省交通规划设计研究院股份有限公司 利用梁下运梁方式施工钢混组合梁的方法
CN108316125A (zh) * 2018-02-11 2018-07-24 中交高新科技产业发展有限公司 装配式组合折腹梁桥
CN109137712A (zh) * 2018-11-07 2019-01-04 深圳市市政设计研究院有限公司 一种上下双层格室组合折腹箱梁
CN109914230A (zh) * 2019-04-18 2019-06-21 深圳市市政设计研究院有限公司 组合箱梁
CN110067186A (zh) * 2019-06-05 2019-07-30 深圳市市政设计研究院有限公司 一种钢管加劲腹板钢混组合箱梁
CN110656566A (zh) * 2019-09-23 2020-01-07 中铁二局第三工程有限公司 一种装配式组合箱梁及其施工方法
CN112376385A (zh) * 2020-12-09 2021-02-19 南京工业大学 一种预制装配式波形钢腹板组合梁桥及其施工方法
CN112523060A (zh) * 2020-12-30 2021-03-19 南京工业大学 一种采用预制uhpc腹板的装配式桥梁及施工方法
CN112523062A (zh) * 2020-12-16 2021-03-19 重庆交通大学 一种钢-混凝土组合箱梁高架桥结构
CN113605208A (zh) * 2021-08-11 2021-11-05 长安大学 波形钢腹板pc箱梁、内撑外拉装置及先撑后衬施工方法
CN110067186B (zh) * 2019-06-05 2024-03-19 深圳市市政设计研究院有限公司 一种钢管加劲腹板钢混组合箱梁

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0637647A1 (fr) * 1993-08-04 1995-02-08 Campenon Bernard Sge Elément de poutre métallique pour réaliser une structure allongée mixte à section transversale du type en caisson, procédé pour la mise en oeuvre de cet élément, et structure allongée réalisée par la mise en oeuvre de ce procédé
JP2001081720A (ja) * 1999-09-13 2001-03-27 Nippon Steel Corp 複合箱桁におけるコンクリート床版と鋼製ウエブの接合構造
JP2002250009A (ja) * 2001-02-23 2002-09-06 Nippon Steel Corp 波形鋼板ウエブを用いた鋼コンクリート複合桁
CN1721636A (zh) * 2004-07-13 2006-01-18 李勇 预应力钢─混凝土组合梁及其制造方法
KR100800393B1 (ko) * 2007-09-14 2008-02-01 노윤근 강합성 콘크리트 u거더
CN201202084Y (zh) * 2008-06-03 2009-03-04 万水 一种波形钢腹板预应力混凝土组合箱梁节段
CN101424073A (zh) * 2008-12-04 2009-05-06 中铁大桥局股份有限公司 整孔预制的钢-混凝土组合连续箱梁的桥面板与钢梁的二次结合方法
CN100507151C (zh) * 2007-11-23 2009-07-01 清华大学 双层桥面组合桁梁桥
JP2009161907A (ja) * 2007-12-28 2009-07-23 Kajima Corp 橋梁の柱頭部または桁端部の複合中空構造

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0637647A1 (fr) * 1993-08-04 1995-02-08 Campenon Bernard Sge Elément de poutre métallique pour réaliser une structure allongée mixte à section transversale du type en caisson, procédé pour la mise en oeuvre de cet élément, et structure allongée réalisée par la mise en oeuvre de ce procédé
JP2001081720A (ja) * 1999-09-13 2001-03-27 Nippon Steel Corp 複合箱桁におけるコンクリート床版と鋼製ウエブの接合構造
JP2002250009A (ja) * 2001-02-23 2002-09-06 Nippon Steel Corp 波形鋼板ウエブを用いた鋼コンクリート複合桁
CN1721636A (zh) * 2004-07-13 2006-01-18 李勇 预应力钢─混凝土组合梁及其制造方法
KR100800393B1 (ko) * 2007-09-14 2008-02-01 노윤근 강합성 콘크리트 u거더
CN100507151C (zh) * 2007-11-23 2009-07-01 清华大学 双层桥面组合桁梁桥
JP2009161907A (ja) * 2007-12-28 2009-07-23 Kajima Corp 橋梁の柱頭部または桁端部の複合中空構造
CN201202084Y (zh) * 2008-06-03 2009-03-04 万水 一种波形钢腹板预应力混凝土组合箱梁节段
CN101424073A (zh) * 2008-12-04 2009-05-06 中铁大桥局股份有限公司 整孔预制的钢-混凝土组合连续箱梁的桥面板与钢梁的二次结合方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《第十八届全国桥梁学术会议论文集(下册)》 20081231 贺君 利用折形钢腹板先行架设组合箱梁桥施工过程分析 , 1 *

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094385A (zh) * 2010-12-07 2011-06-15 中铁大桥勘测设计院有限公司 用于单索面斜拉桥的带大挑臂的钢箱结合梁主梁
CN103031810A (zh) * 2011-09-29 2013-04-10 李跃军 基于压力和密度双参数的预应力孔道注浆质量控制方法
CN102877407A (zh) * 2012-10-30 2013-01-16 河南省交通规划勘察设计院有限责任公司 一种曲线桥用波形钢腹板混凝土连续箱梁
CN102877407B (zh) * 2012-10-30 2014-09-24 河南省交通规划勘察设计院有限责任公司 一种曲线桥用波形钢腹板混凝土连续箱梁
CN103397599A (zh) * 2013-08-14 2013-11-20 中铁大桥局股份有限公司 一种适用于多联现浇箱梁梁端钢束的布置结构及方法
CN103397599B (zh) * 2013-08-14 2015-06-10 中铁大桥局集团有限公司 一种适用于多联现浇箱梁梁端钢束的布置结构及方法
CN104631305A (zh) * 2014-12-22 2015-05-20 郑州市交通规划勘察设计研究院 一种波形钢腹板斜拉桥的桁架式钢横隔板
CN104631305B (zh) * 2014-12-22 2016-06-15 郑州市交通规划勘察设计研究院 一种波形钢腹板斜拉桥的桁架式钢横隔板
CN104762871A (zh) * 2015-04-22 2015-07-08 武汉理工大学 一种预应力混凝土-钢槽梁结合梁连续梁桥
CN105780665A (zh) * 2016-05-06 2016-07-20 中铁大桥局集团第八工程有限公司 双向可调节连接装置及其施工方法
CN105926426A (zh) * 2016-05-06 2016-09-07 烟台图文马克化工科技有限公司 一种小箱梁桥梁的建造方法
CN105780665B (zh) * 2016-05-06 2017-10-27 中铁大桥局集团第八工程有限公司 双向可调节连接装置及其施工方法
CN108004932A (zh) * 2017-12-14 2018-05-08 河南省交通规划设计研究院股份有限公司 利用梁下运梁方式施工钢混组合梁的方法
CN108004932B (zh) * 2017-12-14 2023-10-03 河南省交通规划设计研究院股份有限公司 利用梁下运梁方式施工钢混组合梁的方法
CN108316125A (zh) * 2018-02-11 2018-07-24 中交高新科技产业发展有限公司 装配式组合折腹梁桥
CN109137712A (zh) * 2018-11-07 2019-01-04 深圳市市政设计研究院有限公司 一种上下双层格室组合折腹箱梁
CN109137712B (zh) * 2018-11-07 2023-11-24 深圳市市政设计研究院有限公司 一种上下双层格室组合折腹箱梁
CN109914230A (zh) * 2019-04-18 2019-06-21 深圳市市政设计研究院有限公司 组合箱梁
CN110067186A (zh) * 2019-06-05 2019-07-30 深圳市市政设计研究院有限公司 一种钢管加劲腹板钢混组合箱梁
CN110067186B (zh) * 2019-06-05 2024-03-19 深圳市市政设计研究院有限公司 一种钢管加劲腹板钢混组合箱梁
CN110656566A (zh) * 2019-09-23 2020-01-07 中铁二局第三工程有限公司 一种装配式组合箱梁及其施工方法
CN112376385A (zh) * 2020-12-09 2021-02-19 南京工业大学 一种预制装配式波形钢腹板组合梁桥及其施工方法
CN112523062A (zh) * 2020-12-16 2021-03-19 重庆交通大学 一种钢-混凝土组合箱梁高架桥结构
CN112523060A (zh) * 2020-12-30 2021-03-19 南京工业大学 一种采用预制uhpc腹板的装配式桥梁及施工方法
CN113605208A (zh) * 2021-08-11 2021-11-05 长安大学 波形钢腹板pc箱梁、内撑外拉装置及先撑后衬施工方法

Also Published As

Publication number Publication date
CN101798794B (zh) 2012-07-25

Similar Documents

Publication Publication Date Title
CN101798794B (zh) 利用折形钢腹板钢梁先行架设组合箱梁桥及其施工方法
CN100482892C (zh) 下弦开敞桁式波纹钢腹板组合梁
CN108677685B (zh) 一种超高性能混凝土-部分钢梁组合盖梁及其施工方法
CN107245934A (zh) 一种装配式钢‑压型钢板混凝土组合板小箱梁
CN103388303A (zh) 一种横向拼装波形钢腹板组合箱梁及施工方法
CN101748682A (zh) 采用波形钢腹板的钢-混凝土叠合板组合梁及其施工方法
CN108978434B (zh) 一种钢-混组合连续箱梁桥的无支架工业化施工方法
CN102704406B (zh) 基于组合槽型梁的道床板无拉应力施工方法
CN101597887A (zh) 新型组合式桥面板及其制作方法
CN101440598B (zh) 钢箱-砼组合箱板拱结构及其施工方法
CN111254800A (zh) 一种适用于城市桥梁的组合梁及其施工方法
CN110331664B (zh) 钢-混凝土混合连续箱梁桥面板接头构造及其施工方法
CN112458877A (zh) 一种装配式钢混组合刚构桥及其施工方法
CN207846187U (zh) 一种最大装配化的波形钢腹板工字组合梁桥
CN112982162A (zh) 一种钢筋桁架式钢-混组合桥面板及施工方法
CN211735002U (zh) 一种快速化安装的钢-混凝土组合梁桥
CN210086022U (zh) 拼装式单箱多室波形钢腹板箱梁
CN103205930A (zh) 一种既有简支空心板梁桥连续化改造的结构及其施工方法
CN110863417A (zh) 一种快速化安装的钢-混凝土组合梁桥及其施工方法
CN103669193B (zh) 一种横向拼装波形钢腹板组合t梁及施工方法
CN203383137U (zh) 一种横向拼装波形钢腹板组合箱梁
CN201817769U (zh) 一种利用折形钢腹板钢梁先行架设组合箱梁桥
CN211472112U (zh) 一种预制拼装波形钢腹板组合t梁桥
CN211689841U (zh) 一种钢混叠合预制组合梁桥结构
CN210596966U (zh) 一种大跨径钢混组合桥梁结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent for invention or patent application
CB02 Change of applicant information

Address after: 510507 Guangdong city of Guangzhou province Shahe tianpingjia Xinghua Road No. 22

Applicant after: Guangdong Highway Design Institute Co., Ltd.

Address before: 510507 Guangdong city of Guangzhou province Shahe tianpingjia Xinghua Road No. 22

Applicant before: Guangdong Highway Design Institute Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 510507 Xinghua Road, Guangzhou, Guangdong, No. 22, No.

Patentee after: GUANGDONG PROVINCE COMMUNICATIONS PLANNING & DESIGN INSTITUTE CO., LTD.

Address before: 510507 Guangdong city of Guangzhou province Shahe tianpingjia Xinghua Road No. 22

Patentee before: Guangdong Highway Design Institute Co., Ltd.

CP03 Change of name, title or address

Address after: No.146, huangbian North Road, Baiyun District, Guangzhou, Guangdong 510440

Patentee after: Guangdong transportation planning and Design Institute Group Co.,Ltd.

Address before: No.22 Xinghua Road, Tianhe District, Guangzhou City, Guangdong Province

Patentee before: GUANGDONG PROVINCE COMMUNICATIONS PLANNING & DESIGN INSTITUTE Co.,Ltd.

CP03 Change of name, title or address