CN101705429A - Wire rod of high-speed railroad no-slag sleeper slab steel wire and production method thereof - Google Patents

Wire rod of high-speed railroad no-slag sleeper slab steel wire and production method thereof Download PDF

Info

Publication number
CN101705429A
CN101705429A CN200910228812A CN200910228812A CN101705429A CN 101705429 A CN101705429 A CN 101705429A CN 200910228812 A CN200910228812 A CN 200910228812A CN 200910228812 A CN200910228812 A CN 200910228812A CN 101705429 A CN101705429 A CN 101705429A
Authority
CN
China
Prior art keywords
wire
slag
steel
wire rod
temperature
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910228812A
Other languages
Chinese (zh)
Other versions
CN101705429B (en
Inventor
吴波
孙国庆
巩文旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Iron and Steel Group Co Ltd
Original Assignee
Tianjin Iron and Steel Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Iron and Steel Group Co Ltd filed Critical Tianjin Iron and Steel Group Co Ltd
Priority to CN2009102288120A priority Critical patent/CN101705429B/en
Publication of CN101705429A publication Critical patent/CN101705429A/en
Application granted granted Critical
Publication of CN101705429B publication Critical patent/CN101705429B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention belongs to the technical field of steel and iron smelting technology, and particularly provides a high wire rod of a high-speed railroad no-slag sleeper slab steel wire and a production method thereof. The traditional single sleeper does not meet the requirements of high-speed railroad, and is upgraded into a sleeper slab. Aiming at the requirements for the wire rod of the high-speed train sleeper slab wire, the invention designs a special wire rod of a high-speed railroad no-slag sleeper slab steel wire and a manufacture method thereof. The wire rod comprises the following control components in percent by weight: 0.34-0.39% of C, 1.55-1.85% of Si, 0.75-1.00 % of Mn, 0.35-0.60 % of Cr, no more than 0.025% of P, no more than 0.025%of S, no less than 0.0008% of B and the balance of Fe. The production process of the wire rod comprises the following steps of: top-bottom blowing smelting by adopting high-quality concentrate and synthesizing of slag charge and wash during tapping; LF refining which adopts calcium carbide, carborundum and the like to form white slag; continuous casting protection pouring under the conditions that the degree of superheat is controlled in the range of 20-40 DEG C and the pulling rate is 1.9-2.8m/min; steel rolling under the conditions of controlling the tapping temperature of steel billet in the range of 950-1010 DEG C, cooling by the control of a water tank and the control of large amount wind during rolling and controlling the spinning temperature in the range of 840-860 DEG C.

Description

Wire rod of high-speed railroad no-slag sleeper slab steel wire and production method thereof
Technical field
The invention belongs to smelting iron and steel Technology field, production and the manufacture method of a kind of high-speed railway sleeper steel wire with high wire rod particularly are provided.
Technical background
The railroad sleeper steel wire, tradition adopts steel wires such as light face, indentation.Development along with railway, particularly travelling speed is up to 350 kilometers high-speed railway, the requirement of incompatibility high ferro of originally single sleeper, upgrading becomes 2.4 meters * 0.5 meter concrete slab sleeper, corresponding sleeper steel wire is also brought up to more than 9.0 millimeters by 7.0 millimeters, tensile strength requires more than the 1420Mpa, elongation after fracture L 100〉=8%, relaxation rate 1000h requires≤2.5%, and to the higher requirement of proposition fatigue lifetime, and must do fatigue test and " hydrogen embrittlement " test etc.The former wire rod that is used as producing the sleeper steel wire is owing to the requirement of the more high reason incompatibility of intensity sleeper steel wire.
The present invention adopts and reduces the C element, increase the composition design of Si, Mn element, be beneficial to post-production plasticity, increase alloying elements cr content, remedy and fall the loss of strength that C brings, add micro-B, improve hardening capacity, improve the steel over-all properties, simultaneously, further lower S, P element, improve the purity of steel.
Summary of the invention
The present invention meets or exceeds 350 kilometers bullet train concrete slab sleepers with the demand of steel wire to wire rod for adapting to speed per hour, formerly do that the sleeper steel wire is higher with wire rod intensity, hardness is bigger for overcoming, incompatibility is done proposing the concrete slab sleeper steel wire of requirements at the higher level fatigue lifetime, designs wire rod and the manufacture method of a kind of access railroad concrete slab sleeper with steel wire.
Wire rod of high-speed railroad no-slag sleeper slab steel wire of the present invention and production method thereof realize by following means.
High-speed railway concrete slab sleeper steel wire wire rod of the present invention, control composition (weight percentage) is C=0.34-0.39%, Si=1.55-1.85%, Mn=0.75-1.00%, Cr=0.35-0.60%, P≤0.025%, S≤0.025%, B 〉=0.0008%, all the other Fe.
The manufacture method of high-speed railway concrete slab sleeper steel wire wire rod of the present invention is that blast-melted → converter smelting → LF refining → continuous casting → high-speed wire rolling becomes wire rod.Particular content comprises:
1. blast-melted employing winding-up particle magnesium technology is carried out the desulfurization pre-treatment, makes into the converter hot metal composition to reach Si]=0.30-0.85%, [P]=0-0.080%, [S]=0-0.030%;
2. converter adopts top and bottom complex blowing to smelt, and employing oxygen pressure is 22800-23200m for 0.8-0.85MPa, flow 3The low oxygen pressure of/h, big flow oxygen supply system; Take dephosphorization in preceding, mid-term, the intermediary and later stages are sulfur removal technology again, takes the pushing off the slag tapping, adds synthetic slag charge in the tapping process and carry out wash heat in ladle, [C], a[O during the tapping of final deoxygenation, and control again] amount;
3. LF refining process employing calcium carbide, silicon carbide deacidizing agent are main deoxidization technique, refining process white slag refining time 10-20 minute, and the LF refining treatment time taked omnidistance argon bottom-blowing to stir at 30-40 minute; And according to pre-blowing, bio-occlusion electricity, the stirring of 3 kinds of pattern control of soft blow argon bottom-blowing;
4. continuous casting process requires ladle to take whole process to add protective casing protection cast to tundish, tundish to crystallizer, and molten steel overheat is controlled in the 20-40 ℃ of scope, and stable pulling rate is 1.9-2.8m/min; Control casting machine secondary cooling water distributes and the secondary cooling water specific water; Tundish adopts MgCa matter coating, and barricade is set; Use the crystallizer electromagnetic agitating technology;
5. high speed wire rolling, adopt the double heat storage type process furnace, optimize heating cycle, control steel billet tapping temperature is 950 ℃-1010 ℃, between pre-finish rolling and finishing train, finishing train with subtract between the sizing, subtract and respectively have two groups of water tanks to control the rolled piece temperature between sizing and the Laying head, take big air quantity controlled chilling, laying temperature is controlled at 840-860 ℃, temperature fluctuation≤20 ℃;
Described high-speed railway concrete slab sleeper steel wire wire rod is high line wire rod, and wherein preferred component is C=0.36-0.39%, Si=1.60-1.70%, Mn=0.82-0.88%, Cr=0.42-0.48%, P≤0.025%, S≤0.015%, B 〉=0.0008%, all the other Fe.
Described high-speed railway concrete slab sleeper steel wire high speed wire bar and production method thereof in the converter operation, are strengthened the slag making dephosphorization preceding, the mid-term of smelting, and the phosphorus in the intermediary and later stages stabilizing slag is also realized molten steel desulfurizing, adds CaF in the tapping process in ladle 2, the synthetic slag charge of CaO carries out wash heat, and control quantity of slag 0-50mm down adopts sial barium final deoxygenation, controls out composition of steel [C]=0.10-0.15%, [P]=0-0.012%, makes to enter dissolved oxygen a[0 in the LF refining station steel]=0-15ppm.In the LF refining process, after finishing the temperature composition and adjusting, add ferro-boron 15-25Kg, feed the CaSi silk again the soft blow argon stirred 5-10 minute, making the molten steel out-station temperature is 1555 ℃-1575 ℃.Being distributed as of continuous caster water coolant, one section accounts for 33%, two section and accounts for 48%, three section and account for 19%, specific water 1.00-1.10L/Kg.At rolling process, optimize the process furnace heating cycle, make furnace temperature poor≤50 ℃, single steel billet head and tail temperature difference≤40 ℃, closed loop control system is adopted in the control of rolled piece temperature, the Stanermo wind-cooling linear that prolongs 20-40 rice is realized big air quantity controlled chilling.
The invention has the advantages that provides high-speed railway concrete slab sleeper steel wire high speed wire bar and production method.The optimum optimization combination of this steel grade alloy element component has guaranteed the every comprehensive mechanical property optimum of wire rod, and the supply of material is even by the gross, fluctuation is little; Adopt top bottom compound blowing technology, the oxygen supply of low pressure and mass flow oxygen rifle, blowing is steady, and composition and temperature shoot straight; In bag, add special-purpose synthetic slag during tapping, carry out wash heat, further desulfurization, removal is mingled with; The LF refining procedure adopts and to make white slag technology fast, guarantees that temperature, composition adjustment are even, are beneficial to desulfurization and Control and Inclusion Removal simultaneously; The LF refining procedure is furnished with ladle whole process BOTTOM ARGON BLOWING and ladle wire feeding equipment, realizes the inclusion modification processing, reduces inclusion content of steel, improves the molten steel cleanliness factor; Continuous casting adopts crystallizer induction stirring technology, improves slab quality; The process furnace strictness is controlled heat-up time, is guaranteed that the burning steel is even; Roughing mill, finishing mill system realize the control of rolled piece temperature closed loop, owing to subtract the precision mill pass schedule, the last a few passage distortion of rolled piece are less, the refinement more of wire rod surface microstructure, and surface quality is better; Utilize the state-of-the-art in the world at present air-cooled line of root stelmor overlength that rubs (total length is 113mm, than the air-cooled line length 30m of generalized case), realize big air quantity controlled chilling, make the cooling performance of wire rod better, obtain best wire rod tissue and performance.Online application caliper in time monitors size and carries out online adjustment that dimensional precision reaches ± 0.01mm, reaches world-class levels.
The high-speed railway concrete slab sleeper steel wire high speed wire bar that adopts wire rod of the present invention and manufacture method thereof to produce, the tensile strength 700-1000Mpa of its wire rod, the face shrinking percentage is greater than 30%, and unit elongation is greater than 18%.
Embodiment
Concrete slab sleeper steel wire high speed wire bar composition of the present invention is: control composition (weight percentage) C=0.34-0.39%, Si=1.55-1.85%, Mn=0.75-1.00%, P≤0.025%, S≤0.025%, Cr=0.35-0.60%, B 〉=0.0008%.
The present invention optimizes composition (weight percentage): C=0.36-0.39%, Si=1.60-1.70%, Mn=0.82-0.88%, Cr=0.42-0.48%, P≤0.025%, S≤0.015%.
Production technique of the present invention:
Blast furnace → top and bottom combined blown converter → LF refining furnace → 150 * 150mm billet continuous casting → turn over cooling bed → process furnace → high speed wire rolling → stelmor controlled chilling → check → warehouse-in.
Concrete processing step:
(1) raw material: take the fine fodder principle, go into the requirement of stove molten iron: Si=0.30-0.85%, P=0-0.080%, S=0-0.030%.
(2) converter smelting: adopt top and bottom combined blown converter technology, strengthened in the smelting process the stirring in molten bath, promote the carrying out of various metallurgical reactions and temperature, composition evenly.Top and bottom combined blown converter adopts low oxygen pressure, big flow top oxygen gun oxygen supply, and it is that 0.8-0.85MPa, flow are 22800-23200m that oxygen is pressed 3/ h; The gas mixing of bottom blowing nitrogen/argon is mixed; Preceding, the medium profit of converter smelting is strengthened the slag making dephosphorization with the lower favourable condition of liquid steel temperature, and the phosphorus in the intermediary and later stages stabilizing slag is also realized molten steel desulfurizing; Take pushing off the slag tapping in the converter tapping process, control is quantity of slag 0-50mm down, prevents rephosphorization, improves yield of alloy and reduces non-metallic inclusion in the steel; (major ingredient is CaF to add synthetic slag charge in the tapping process in ladle 2, CaO) carry out wash heat, carry out the upgrading of ladle top slag simultaneously, further desulfurization goes to be mingled with; Final deoxygenation adopts the deoxidation of sial barium, guarantees the LF refining dissolved oxygen a[0 in the steel that enters the station]=0-15ppm.Take catch carbon practice, converter tapping target call molten steel [C]=0.10-0.15%, [P]=0-0.012%.
(3) LF refining: because this steel grade is mainly as high-speed railway concrete slab sleeper steel wire, every over-all properties of steel requires very high, therefore kind and content, the gas content etc. to this steel grade chemical ingredients, steel inclusion propose to be strict with, and the LF refining procedure is around adjusting and aspects such as the removal of evening chemical composition, nonmetallic inclusionsin steel, adjustment temperature are controlled.The span of control of molten steel chemical ingredients is in the LF refining process: [C]=0.36-0.39%, [Si]=1.60-1.70%, [Mn]=0.82-0.88%, [Cr]=0.42-0.48%, [P]≤0.025%, [S]≤0.015%, [B]=0.0010-0.0020%
In the refining process, adopting calcium carbide, silicon carbide deacidizing agent is main deoxidization technique; White slag refining time 10-20 minute, the LF refining treatment time was at 30-40 minute.In the refining process, omnidistance argon bottom-blowing stirs, and according to the gas flow that pre-blowing, bio-occlusion electricity, 3 kinds of pattern control of soft blow argon bottom-blowing stir, guarantees the Argon effect.After the adjustment of temperature composition finishes, add ferro-boron 15-25Kg, total analysis is done in sampling.Feed CaSi silk (Φ 13mm) 100m at last.5-10 minute soft blow argon gas of soft blow argon stirred after hello silk finished.Guarantee molten steel out-station temperature target: 1575 ± 5 ℃ in first stove connects and waters 1555 ± 5 ℃ in stove
(4) continuous casting: 150 * 150mm billet continuous casting, for guaranteeing carrying out smoothly of slab quality and continuous casting, emphasis control the following aspects:
● ladle takes whole process to add protective casing protection cast to tundish, tundish to crystallizer in the casting process, prevents secondary oxidation of steel, guarantees the purity of molten steel;
● control casting machine secondary cooling water distributes and the secondary cooling water specific water, guarantees that two cold refrigerative are even; Being distributed as one section and accounting for 33%, two section and account for 48%, three section and account for 19% of water; The specific water is 1.10L/Kg;
● molten steel overheat is controlled in 20~40 ℃ of scopes, and stable pulling rate is 2.0-2.8m/min;
● tundish is provided with barricade, removes to promote inclusion floating.The tundish coating adopts the MgCa material, and what alleviate that the tundish refractory corrosion brings is mingled with pollution to molten steel;
● use the crystallizer induction stirring, guarantee strand crystal structure densification, even, reduce strand column crystal rate, avoid defectives such as strand crackle, shrinkage cavity.
(5) high speed wire rolling: produce and satisfy high-speed railway concrete slab sleeper steel wire high speed wire bar, for guaranteeing to obtain the inside and outside higher wire rod of quality level, emphasis control the following aspects:
● heating process: strict control heat-up time make the abundant austenitizing of steel billet, guarantee to burn steel quality, tapping temperature: 950-1050 ℃, guarantee the steel billet homogeneous heating, bonding props up steel billet head and tail temperature difference≤40 ℃, and furnace temperature is poor≤and 50 ℃.
● rolling process: between pre-finish rolling and the finishing train, finishing train with subtract between the sizing, subtract two groups of water tanks control rolled piece temperature are respectively arranged between sizing and the Laying head, and rolled piece temperature realization closed-loop control.Owing to subtract the precision mill pass schedule, the last a few passage distortion of rolled piece are less, the refinement more of wire rod surface microstructure, and surface quality is better.
● control cooling working procedure: utilize the state-of-the-art in the world at present air-cooled line of root stelmor overlength that rubs (total length is 113mm, than the air-cooled line length 30m of generalized case), realize big air quantity controlled chilling, make the cooling performance of wire rod better.Select laying temperature: 840-860 ℃; Use the 1-6# blower fan: 50%; Insulation cover: standard-sized sheet; Suitable roller table speed.For guaranteeing the poker characteristic of wire rod, the finished product tissue and performance are guaranteed in≤20 ℃ of controlled temperature fluctuations simultaneously.
● finishing procedure: for guaranteeing wire rod poker characteristic and dimensional precision, the uneven part of distortion and water-cooled is all cut end to end.Adopted to subtract the precision mill pass, formed ellipse-circle-circle-system of circles system, utilized online caliper in time to monitor the dimensional change situation simultaneously, and in time carry out online adjustment, guaranteed that dimensional precision reaches world-class levels ± 0.01mm.
Embodiment
Blast furnace → top and bottom combined blown converter → LF refining furnace → 150 * 150mm billet continuous casting → turn over cooling bed → process furnace → high speed wire rolling → stelmor controlled chilling → check → warehouse-in.
(1) goes into stove molten iron: Si=0.45%, P≤0.07%, S≤0.028%
(2) converter smelting:
Smelt steel grade 16MnVH, top and bottom combined blown converter adopts the oxygen supply of low pressure and mass flow oxygen rifle, and it is that 0.8MPa, flow are 23000m that bottom blowing nitrogen/argon gas, oxygen are pressed 3/ h, P is taken off in preceding, slag making in mid-term, and S is taken off in the intermediary and later stages slag making; Tapping [C]=0.10%, [P]=0.009%; Converter tapping adopts pushing off the slag tapping, following slag thickness 50mm.In ladle, add special-purpose synthetic slag charge 400kg in the tapping process.
(3) LF refining
Composition Control: [C]=0.38%, [Si]=1.62%, [Mn]=0.82%, [S]=0.008%; [B]=0.0012% enters the station and decides oxygen a[O]=12ppm; White slag refining time 18 minutes; Feed silico-calcium silk Φ 13mm, 100m, improve fluidity molten steel and inclusion modification and handle; Soft blow operation 7 minutes; 38 minutes LF refining treatment time; Adjust continuous casting 1570 ℃ of the temperature (first stove) of arriving at a station.
(4) continuous casting working procedure: casting blank section 150 * 150mm
● continuous casting is big to wrap tundish, tundish takes whole process to add protective casing protection cast to crystallizer;
● the casting machine secondary cooling water distributes and the secondary cooling water specific water, and one section accounts for 33%, two section and accounts for 48%, three section and account for 19%, specific water 1.10L/Kg;
● 25 ℃ of the superheating temperature of tundish molten steel, pulling rate 2.6m/min;
● tundish is provided with barricade;
● use the crystallizer induction stirring.
(5) high speed wire rolling: Φ 14mm wire rod
● tapping temperature: 970-1010 ℃
● roll speed: 26.25m/s
● roller table speed: 35.7-37.5-39.4-41.4-43.4-45.6-47.9-50.3-52.8-52.8-47.5-4 2.7-36.3 (m/min)
● blower fan uses: 1-16# 50%
● insulation cover: standard-sized sheet
● advance to subtract 900-920 ℃ of sizing temperature, go out final rolling temperature 960-980 ℃, laying temperature 840-860 ℃.

Claims (6)

1. high-speed railway concrete slab sleeper steel wire wire rod is characterized in that controlling composition (weight percentage) C=0.34-0.39%, Si=1.55-1.85%, Mn=0.75-1.00%, Cr=0.35-0.60%, P≤0.025%, S≤0.025%, B 〉=0.0008%, all the other Fe.
2. according to the described high-speed railway concrete slab sleeper steel wire of claim 1 wire rod, and manufacture method is that blast-melted → converter smelting → LF refining → continuous casting → high-speed wire rolling becomes wire rod; It is characterized in that:
1. blast-melted employing winding-up particle magnesium technology is carried out the desulfurization pre-treatment, makes into the converter hot metal composition to reach [Si]=0.30-0.85%, [P]=0-0.080%, [S]=0-0.030%;
2. converter adopts top and bottom complex blowing to smelt, and employing oxygen pressure is 22800-23200m for 0.8-0.85MPa, flow 3The low oxygen pressure of/h, big flow oxygen supply system; Take dephosphorization in preceding, mid-term, the intermediary and later stages are sulfur removal technology again, takes the pushing off the slag tapping, adds synthetic slag charge in the tapping process and carry out wash heat in ladle, [C], a[O during the tapping of final deoxygenation, and control again] amount;
3. LF refining process employing calcium carbide, silicon carbide deacidizing agent are main deoxidization technique, refining process white slag refining time 10-20 minute, and the LF refining treatment time taked omnidistance argon bottom-blowing to stir at 30-40 minute; And according to pre-blowing, bio-occlusion electricity, the stirring of 3 kinds of pattern control of soft blow argon bottom-blowing;
4. continuous casting process requires ladle to take whole process to add protective casing protection cast to tundish, tundish to crystallizer, and molten steel overheat is controlled in the 20-40 ℃ of scope, and stable pulling rate is 1.9-2.8m/min; Control casting machine secondary cooling water distributes and the secondary cooling water specific water; Tundish adopts MgCa matter coating, and barricade is set; Use the crystallizer electromagnetic agitating technology;
5. high speed wire rolling, adopt the double heat storage type process furnace, optimize heating cycle, control steel billet tapping temperature is 950 ℃-1010 ℃, between pre-finish rolling and finishing train, finishing train with subtract between the sizing, subtract and respectively have two groups of water tanks to control the rolled piece temperature between sizing and the Laying head, take big air quantity controlled chilling, laying temperature is controlled at 840-860 ℃, temperature fluctuation≤20 ℃;
3. according to the manufacture method of the described high-speed railway concrete slab sleeper steel wire of claim 2 high speed wire bar, it is characterized in that strengthening the slag making dephosphorization in preceding, the mid-term of converter smelting, phosphorus in the intermediary and later stages stabilizing slag is also realized molten steel desulfurizing, adds CaF in the tapping process in ladle 2, the synthetic slag charge of CaO carries out wash heat, and control quantity of slag 0-50mm down adopts sial barium final deoxygenation, controls out composition of steel [C]=0.10-0.15%, [P]=0-0.012%, makes to enter dissolved oxygen a[O in the LF refining station steel]=0-15ppm;
4. according to the manufacture method of the described high-speed railway concrete slab sleeper steel wire of claim 2 high speed wire bar, it is characterized in that, in the LF refining process, after finishing the adjustment of temperature composition, add ferro-boron 15-25Kg, hello CaSi silk soft blow argon again stirred 5-10 minute, and making the molten steel out-station temperature is 1555 ℃-1575 ℃.
5. according to the manufacture method of the described high-speed railway concrete slab sleeper steel wire of claim 2 high speed wire bar, it is characterized in that being distributed as of continuous caster water coolant, one section accounts for 33%, two section and accounts for 48%, three section and account for 19%, specific water 1.00-1.10L/Kg.
6. according to the manufacture method of the described high-speed railway concrete slab sleeper steel wire of claim 2 high speed wire bar, it is characterized in that, optimize the process furnace heating cycle, make furnace temperature poor≤50 ℃, single steel billet head and tail temperature difference≤40 ℃, closed loop control system is adopted in the control of rolled piece temperature, and the Stanermo wind-cooling linear that prolongs 20-40 rice is realized big air quantity controlled chilling.
CN2009102288120A 2009-11-27 2009-11-27 Production method of wire rod of high-speed railroad no-slag sleeper slab steel wire Expired - Fee Related CN101705429B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009102288120A CN101705429B (en) 2009-11-27 2009-11-27 Production method of wire rod of high-speed railroad no-slag sleeper slab steel wire

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009102288120A CN101705429B (en) 2009-11-27 2009-11-27 Production method of wire rod of high-speed railroad no-slag sleeper slab steel wire

Publications (2)

Publication Number Publication Date
CN101705429A true CN101705429A (en) 2010-05-12
CN101705429B CN101705429B (en) 2012-05-23

Family

ID=42375680

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009102288120A Expired - Fee Related CN101705429B (en) 2009-11-27 2009-11-27 Production method of wire rod of high-speed railroad no-slag sleeper slab steel wire

Country Status (1)

Country Link
CN (1) CN101705429B (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102703804A (en) * 2012-06-11 2012-10-03 首钢水城钢铁(集团)有限责任公司 Production method of wire rod for high-strength prestressed steel bar
CN102899554A (en) * 2012-10-23 2013-01-30 鞍钢股份有限公司 Annealing-free low-carbon steel coil rod and production method thereof
CN102978307A (en) * 2012-11-29 2013-03-20 德龙钢铁有限公司 Process for reducing production of pipeline steel
CN103372565A (en) * 2012-04-27 2013-10-30 宝山钢铁股份有限公司 Manufacturing method of 28 mm diameter specification of steel wire rods and through high-speed wire rod production line
CN103436687A (en) * 2013-07-31 2013-12-11 南京钢铁股份有限公司 Controlled cooling technology of high-alloy tool steel
CN103667925A (en) * 2013-12-16 2014-03-26 天津钢铁集团有限公司 Production technology of wire rod for solid surfacing welding wires
CN103667877A (en) * 2013-12-16 2014-03-26 天津钢铁集团有限公司 Production method for wire rod for steel wool
CN104056862A (en) * 2014-07-07 2014-09-24 首钢总公司 Control method for reducing specified non-proportional extension strength fluctuation
TWI560276B (en) * 2014-06-04 2016-12-01 China Steel Corp Steel making method
CN107675068A (en) * 2017-09-27 2018-02-09 武汉钢铁有限公司 The production method of superfine welding wire steel wire rod
CN107779546A (en) * 2016-08-31 2018-03-09 河南凤宝特钢有限公司 A kind of steelmaking converter Calcium treatment technique
CN107893188A (en) * 2017-12-20 2018-04-10 山东泰山钢铁集团有限公司 A kind of smelting process of high intensity manganese-boron steel
CN110722118A (en) * 2019-09-26 2020-01-24 江苏省沙钢钢铁研究院有限公司 Wire rod for deep drawing and method for manufacturing blank thereof
CN112626408A (en) * 2020-11-27 2021-04-09 中国铁建重工集团股份有限公司道岔分公司 Method for producing switch tie and switch tie
CN112792310A (en) * 2020-12-11 2021-05-14 阳春新钢铁有限责任公司 Continuous casting production process for producing low-carbon low-silicon wiredrawing steel at high drawing speed

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100523262C (en) * 2005-04-18 2009-08-05 河南省强力机械有限公司 Meta-bainite steel and application of the same in railway
CN101386958A (en) * 2007-09-14 2009-03-18 首钢总公司 Steel for high speed rail non-slag concrete slab sleeper steel wire and producing method thereof

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103372565A (en) * 2012-04-27 2013-10-30 宝山钢铁股份有限公司 Manufacturing method of 28 mm diameter specification of steel wire rods and through high-speed wire rod production line
CN103372565B (en) * 2012-04-27 2015-07-22 宝山钢铁股份有限公司 Manufacturing method of 28 mm diameter specification of steel wire rods and through high-speed wire rod production line
CN102703804B (en) * 2012-06-11 2014-05-28 首钢水城钢铁(集团)有限责任公司 Production method of wire rod for high-strength prestressed steel bar
CN102703804A (en) * 2012-06-11 2012-10-03 首钢水城钢铁(集团)有限责任公司 Production method of wire rod for high-strength prestressed steel bar
CN102899554A (en) * 2012-10-23 2013-01-30 鞍钢股份有限公司 Annealing-free low-carbon steel coil rod and production method thereof
CN102978307A (en) * 2012-11-29 2013-03-20 德龙钢铁有限公司 Process for reducing production of pipeline steel
CN103436687A (en) * 2013-07-31 2013-12-11 南京钢铁股份有限公司 Controlled cooling technology of high-alloy tool steel
CN103667877B (en) * 2013-12-16 2015-12-02 天津钢铁集团有限公司 A kind of Production method for wire rod for steel wool
CN103667877A (en) * 2013-12-16 2014-03-26 天津钢铁集团有限公司 Production method for wire rod for steel wool
CN103667925A (en) * 2013-12-16 2014-03-26 天津钢铁集团有限公司 Production technology of wire rod for solid surfacing welding wires
TWI560276B (en) * 2014-06-04 2016-12-01 China Steel Corp Steel making method
CN104056862A (en) * 2014-07-07 2014-09-24 首钢总公司 Control method for reducing specified non-proportional extension strength fluctuation
CN107779546A (en) * 2016-08-31 2018-03-09 河南凤宝特钢有限公司 A kind of steelmaking converter Calcium treatment technique
CN107675068A (en) * 2017-09-27 2018-02-09 武汉钢铁有限公司 The production method of superfine welding wire steel wire rod
CN107893188A (en) * 2017-12-20 2018-04-10 山东泰山钢铁集团有限公司 A kind of smelting process of high intensity manganese-boron steel
CN107893188B (en) * 2017-12-20 2019-07-16 山东泰山钢铁集团有限公司 A kind of smelting process of high intensity manganese-boron steel
CN110722118A (en) * 2019-09-26 2020-01-24 江苏省沙钢钢铁研究院有限公司 Wire rod for deep drawing and method for manufacturing blank thereof
CN110722118B (en) * 2019-09-26 2021-07-20 江苏省沙钢钢铁研究院有限公司 Wire rod for deep drawing and method for manufacturing blank thereof
CN112626408A (en) * 2020-11-27 2021-04-09 中国铁建重工集团股份有限公司道岔分公司 Method for producing switch tie and switch tie
CN112792310A (en) * 2020-12-11 2021-05-14 阳春新钢铁有限责任公司 Continuous casting production process for producing low-carbon low-silicon wiredrawing steel at high drawing speed

Also Published As

Publication number Publication date
CN101705429B (en) 2012-05-23

Similar Documents

Publication Publication Date Title
CN101705429B (en) Production method of wire rod of high-speed railroad no-slag sleeper slab steel wire
CN107099728B (en) A kind of manufacturing method of the high Ti abrasion-resistant stees NM450 of Thin Specs
CN100513613C (en) Wire rod for prestressed concrete steel stick and manufacturing process
CN101514423B (en) Aluminiferous low-carbon cold heading wire rod steel and production method thereof
Emi Steelmaking technology for the last 100 years: toward highly efficient mass production systems for high quality steels
CN104911497B (en) A kind of high intensity carbonized Gear Steel 19CrNi5 production method
CN102069157B (en) Method for preparing high-aluminum steel
CN102719759B (en) Elastic bar steel for high-speed rail fastener and smelting production method thereof
CN105369150B (en) A kind of superhigh intensity armor manufacture method
CN101701277A (en) Method for smelting steel round blank of air cylinder by convertor process
CN108568503B (en) Method for accurately controlling carbon content of molten steel in 600MPa dual-phase steel tundish
CN102345055A (en) Weldable fine grain structural steel S355NL/S355NLZ35 steel plate and its production method
CN101701276A (en) Method for smelting steel round blank of pipeline with hydrogen sulfide corrosion resistance by convertor process
CN111979475A (en) Wire rod for ultrahigh-strength steel strand and preparation method thereof
CN113322364B (en) Low-cost smelting method of ultra-high phosphorus molten iron of steel for polar region
CN102676948A (en) Boron-containing tire cord steel and preparation method thereof
CN104988434A (en) Thick sulfur-containing plastic mould steel plate and production process thereof
CN102825236A (en) Method for removing transverse crack defects of continuous casting billet corner of boron steel
CN107245637A (en) A kind of AOD smelts the method and a kind of AOD furnace of high manganese stainless steel
CN111363976B (en) Microalloyed steel with long service life, high strength and toughness for high-speed rail plate spring and production process thereof
CN107099730B (en) A kind of manufacturing method of the high Ti anti-wear steel NM360s of Thin Specs
CN109112246B (en) Production method of steel wire rod for railway elastic strip fastener formed by direct cold bending
CN105331895A (en) Chromium-containing tire cord steel and preparation method thereof
CN102899563B (en) A kind of production method of ultra-high strength steel plate
CN100522417C (en) Converter process of producing continuously cast circular steel billet for high pressure boiler pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120523

Termination date: 20151127

EXPY Termination of patent right or utility model