CN101696566A - Construction method of mutilevel overpass scaffold - Google Patents
Construction method of mutilevel overpass scaffold Download PDFInfo
- Publication number
- CN101696566A CN101696566A CN200910190917A CN200910190917A CN101696566A CN 101696566 A CN101696566 A CN 101696566A CN 200910190917 A CN200910190917 A CN 200910190917A CN 200910190917 A CN200910190917 A CN 200910190917A CN 101696566 A CN101696566 A CN 101696566A
- Authority
- CN
- China
- Prior art keywords
- scaffold
- scaffolding
- bridge
- construction
- iron
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 52
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 27
- 239000010959 steel Substances 0.000 claims abstract description 27
- 238000012544 monitoring process Methods 0.000 claims abstract description 20
- 238000012360 testing method Methods 0.000 claims abstract description 11
- 238000007689 inspection Methods 0.000 claims abstract description 4
- 238000003466 welding Methods 0.000 claims description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims 16
- 229910052742 iron Inorganic materials 0.000 claims 8
- 210000001320 hippocampus Anatomy 0.000 claims 2
- 238000000034 method Methods 0.000 description 12
- 239000004567 concrete Substances 0.000 description 4
- 230000007812 deficiency Effects 0.000 description 2
- 239000004744 fabric Substances 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 230000036316 preload Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种多层立交桥脚手架施工方法,搭设底层脚手架,底层脚手架搭设有供车辆和行人通行的钢架门洞,进行检查并安装变形监测系统,对底层脚手架进行荷载试压;在底层脚手架上搭设至少两层桥梁脚手架,桥梁脚手架搭设有供桥梁施工所用的箱梁门洞,箱梁门洞上安装变形监测系统,进行综合荷载试验。本发明的底层脚手架设有钢架门洞,以满足车辆流量大的通行要求;中部各层既可在同一水平面内设置相互交叉的箱梁门洞,也可在垂直方向上设置相互交错的箱梁门洞,根据需要选择性施工;整个脚手架只需搭拆一次即可,既缩短了脚手架搭拆时间,又降低了搭拆脚手架的危险性;各层桥梁可同时施工,施工周期短,施工成本低。
The invention discloses a scaffolding construction method for a multi-layer overpass bridge. The scaffolding at the bottom layer is erected. The scaffolding at the bottom layer is provided with a steel frame door opening for vehicles and pedestrians to pass through. The inspection is carried out and a deformation monitoring system is installed, and a load pressure test is carried out on the scaffolding at the bottom layer; At least two layers of bridge scaffolding shall be erected on the bridge scaffolding, and a box girder door opening for bridge construction shall be erected on the bridge scaffolding. A deformation monitoring system shall be installed on the box girder door opening for comprehensive load test. The bottom scaffold of the present invention is provided with steel frame door openings to meet the traffic requirements of large vehicle traffic; each layer in the middle can be provided with intersecting box beam door openings in the same horizontal plane, and can also be provided with interlaced box girder door openings in the vertical direction , Selective construction according to needs; the entire scaffold only needs to be erected and disassembled once, which not only shortens the scaffold erection and dismantling time, but also reduces the risk of erecting and dismantling the scaffold; each layer of bridges can be constructed at the same time, the construction period is short, and the construction cost is low.
Description
技术领域 technical field
本发明涉及一种立交桥脚手架施工方法,尤其涉及一种适应同时施工的多层立交桥脚手架施工方法。The invention relates to a method for constructing an overpass scaffold, in particular to a method for constructing a multi-layer overpass scaffold suitable for simultaneous construction.
背景技术 Background technique
现有技术中,修建多层立交桥时大多采用首先搭建底层脚手架,在底层脚手架的基础上搭建第一层桥梁脚手架,铺模板,布钢筋,浇注混泥土,第一层桥梁浇注成型后,拆卸第一层桥梁脚手架,重新从地面搭建脚手架直到第二层桥梁高度的位置,第二层脚手架搭建好后铺模板,布钢筋,浇注混泥土,如此往复,一层桥梁浇注好后重新再搭建到上一层桥梁的高度。因此,这种立交桥脚手架搭建施工适用于逐座逐联逐层单独施工的方式,大多设计和施工人员认为这种脚手架搭建施工方式属于现有成熟施工工艺,在施工上比较安全,施工难度小,但现有技术的立交桥脚手架施工方法也存在下述不足:一、桥梁钢筋混凝土浇注方式单一,只能从底层逐渐向上浇注,无法实现上下层同时浇注,因此施工周期长;二、一层桥梁浇注成型后,需拆卸脚手架,重新搭建至上一层桥梁高度,这样,底层脚手架需重复安装和拆卸,脚手架搭建时间长,人工成本高;三、这种搭设脚手架施工方法在交通拥挤的交通路上,容易引起交通堵塞,搭设时需另行设置车辆和行人通道;四、脚手架监控采用水准仪,分时段进行,不能全天候、全日程随时进行监控,无法保证整个施工过程均处于受控状态;五、由于脚手架多次搭拆,在交通主干道施工,通行车辆、人员众多,交通隐患大。In the prior art, when building a multi-storey overpass, mostly adopt firstly to build the bottom scaffold, build the first floor bridge scaffold on the basis of the bottom scaffold, lay the formwork, cloth steel bars, pour concrete, after the first layer of bridge is poured and formed, dismantle the second For the bridge scaffolding on the first floor, re-build the scaffolding from the ground to the height of the bridge on the second floor. After the second-story scaffolding is built, formwork is laid, steel bars are laid, and concrete is poured, and so on. The height of a bridge. Therefore, the scaffolding construction of this overpass bridge is suitable for separate construction one by one, one by one, and one by one. Most designers and construction personnel believe that this kind of scaffold construction belongs to the existing mature construction technology, which is relatively safe in construction and has low construction difficulty. But also there are following deficiencies in the overpass scaffolding construction method of prior art: one, the bridge reinforced concrete pouring method is single, can only pour upwards gradually from the bottom layer, can't realize the simultaneous pouring of the upper and lower floors, so the construction period is long; two, one deck bridge pouring After forming, the scaffolding needs to be dismantled and rebuilt to the height of the bridge on the upper floor. In this way, the lower scaffolding needs to be repeatedly installed and disassembled, and the scaffolding takes a long time to build and the labor cost is high. It will cause traffic jams, and it is necessary to set up additional vehicle and pedestrian passages during erection; 4. Scaffolding monitoring uses a level gauge, which is carried out in time intervals, and cannot be monitored all-weather and on a full schedule at any time, and it is impossible to ensure that the entire construction process is under control; 5. Due to the large number of scaffolding Building and dismantling for the second time, the construction is on the main traffic road, there are many vehicles and people passing through, and the traffic hazards are great.
因此,采用上述方式的脚手架搭建施工,既要考虑行人和车辆的通行道路,而且施工工期长,施工成本高,施工方式单一,不灵活,并且脚手架的监控按经验进行。Therefore, the construction of scaffolding in the above-mentioned manner not only needs to consider the passing roads of pedestrians and vehicles, but also has a long construction period, high construction cost, single construction method and inflexibility, and the monitoring of scaffolding is carried out according to experience.
发明内容 Contents of the invention
针对现有技术中的不足之处,本发明提供了一种特别适用于交通主干道,车流量大,不能阻断交通,需要快速完工,并尽可能减少交通压力的多层立交桥脚手架施工方法,采用该施工方法不仅施工工期短,施工成本低,而且浇注混泥土灵活。Aiming at the deficiencies in the prior art, the present invention provides a multi-layer overpass scaffolding construction method that is especially suitable for traffic arterial roads, where the traffic volume is large, the traffic cannot be blocked, the construction needs to be completed quickly, and the traffic pressure is reduced as much as possible. Adopting this construction method not only has short construction period and low construction cost, but also has the flexibility to pour concrete.
本发明提供的多层立交桥脚手架施工方法,包括下述步骤:Multi-storey overpass scaffolding construction method provided by the invention comprises the following steps:
a、搭设底层脚手架,底层脚手架搭设有供车辆和行人通行的钢架门洞,对脚手架的搭设质量进行检查,然后在底层脚手架上安装变形监测系统,对底层脚手架进行货载试压,在立交桥整个施工过程对脚手架的变形进行监测;a. Set up the bottom scaffolding. The bottom scaffolding is equipped with steel frame door openings for vehicles and pedestrians. The quality of the scaffolding is checked, and then the deformation monitoring system is installed on the bottom scaffolding, and the cargo pressure test is carried out on the bottom scaffolding. During the construction process, the deformation of the scaffold is monitored;
b、在底层脚手架上搭设至少两层桥梁脚手架,桥梁脚手架搭设有供桥梁施工所用的箱梁门洞,整个桥梁脚手架搭设完后,对整个脚手架搭设质量进行检查,在箱梁门洞上安装变形监测系统,并进行综合货载预压试验,用以检查脚手架的搭设质量和对搭设前的计算进行验证,查看脚手架及型钢的变形是否在规范要求之内,在立交桥整个施工过程对脚手架的变形进行监测。b. Set up at least two layers of bridge scaffolding on the bottom scaffolding. The bridge scaffolding is equipped with box girder door openings for bridge construction. After the entire bridge scaffolding is erected, check the quality of the entire scaffolding and install a deformation monitoring system on the box girder door openings. , and conduct a comprehensive cargo preload test to check the erection quality of the scaffold and verify the calculation before erection, check whether the deformation of the scaffold and section steel is within the specification requirements, and monitor the deformation of the scaffold during the entire construction process of the overpass .
进一步,所述变形监测系统包括变形传感器、采集仪和监测中心计算机,变形传感器设置在钢架门洞的横梁上,其信号输出端与采集仪连接,采集仪的数据输出端与监测中心计算机连接;Further, the deformation monitoring system includes a deformation sensor, a collector and a monitoring center computer, the deformation sensor is arranged on the beam of the steel frame door opening, its signal output terminal is connected to the collector, and the data output terminal of the collector is connected to the monitoring center computer;
进一步,所述钢架门洞和箱梁门洞主要由两侧碗扣式脚手架和顶部设置的工字钢结构形成,工字钢结构包括主工字钢梁、底部工字钢以及顶部工字钢,所述底部工字钢为两层,分别固定设置在两侧碗扣式脚手架上托上,所述主工字钢梁以与车辆通行方向相垂直的方式固定设置在底部工字钢梁上,顶部工字钢以一定的间隔铺设在主工字钢上,顶部工字钢与其上的碗扣式脚手架下托固定连接;Further, the steel frame door opening and the box girder door opening are mainly formed by bowl buckle scaffolding on both sides and the I-beam structure on the top. The I-beam structure includes the main I-beam, the bottom I-beam and the top I-beam. The bottom I-beam has two layers, which are respectively fixed on the bowl-buckle scaffolding brackets on both sides, and the main I-beam is fixed on the bottom I-beam in a manner perpendicular to the vehicle traffic direction. The top I-beam is laid on the main I-beam at a certain interval, and the top I-beam is fixedly connected with the lower support of the bowl-buckle scaffolding on it;
进一步,所述顶部工字钢与其上的碗扣式脚手架下托通过焊接固定连接,底部工字钢通过碗扣式脚手架上托焊接固定连接;Further, the top I-beam is fixedly connected to the bottom support of the bowl-buckle scaffolding by welding, and the bottom I-beam is fixedly connected by welding the top support of the bowl-buckle scaffold;
进一步,所述脚手架由钢管通过碗扣件连接而成。Furthermore, the scaffolding is formed by connecting steel pipes through bowl fasteners.
本发明的有益效果在于:本发明的多层立交桥脚手架施工方法采用底层设置有供车辆和行人通行的钢架门洞,中部各层设有供立交桥桥梁施工所用的箱梁门洞,使该施工方法具有下述优点:The beneficial effect of the present invention is: multi-storey overpass scaffold construction method of the present invention adopts that the bottom layer is provided with the steel frame door opening for vehicles and pedestrians, each layer in the middle is provided with the used box girder door opening for overpass bridge construction, makes this construction method have The following advantages:
1、该脚手架底层设置有供车辆和行人通行的钢架门洞,适用于交通主干道,车流量大,不能阻断交通,需要快速完工,并尽可能减少交通压力的施工要求。1. The bottom of the scaffold is equipped with steel frame door openings for vehicles and pedestrians, which is suitable for traffic arterial roads. The traffic flow is large, and the traffic cannot be blocked. It needs to be completed quickly and the construction requirements of reducing traffic pressure as much as possible.
2、中部各层设有供桥梁施工所用的箱梁门洞,箱梁门洞的数量可根据所修建桥梁的数量确定,既可在同一水平面内设置相互交叉的箱梁门洞,也可在垂直方向上设置相互交错的箱梁门洞,根据需要可对某一层桥梁先行施工,也可对所有的桥梁同时施工,因此桥梁施工组织方式灵活。2. There are box girder door openings for bridge construction on each floor in the middle. The number of box girder door openings can be determined according to the number of bridges to be built. Intersecting box girder door openings can be set in the same horizontal plane, or in the vertical direction By setting interlaced box girder door openings, one layer of bridges can be constructed first according to needs, and all bridges can also be constructed simultaneously, so the bridge construction organization method is flexible.
3、在钢架门洞的横梁上设置变形传感器,通过变形传感器检测作为横梁的工字钢梁在受力情况下的变形量,并把变形量数据通过采集仪输入中心计算机,由中心计算机显示工字钢梁的变形情况,若变形量超过工字钢梁的规定的变形值,中心计算机发出危险报警信号,监测手段科学,全程监测安全可靠。3. Set a deformation sensor on the beam of the steel frame door opening, and use the deformation sensor to detect the deformation of the I-shaped steel beam as the beam under stress, and input the deformation data into the central computer through the acquisition instrument, and the central computer will display the work For the deformation of the beam, if the deformation exceeds the specified deformation value of the I-beam, the central computer will send out a danger alarm signal. The monitoring method is scientific and the whole process of monitoring is safe and reliable.
4、整个施工范围内的脚手架只需搭拆一次即可,无需重复搭建和拆卸,既缩短了脚手架搭建时间,又降低了搭拆脚手架的危险性;而且各层桥梁可同时施工,因此施工周期短,施工成本低。4. The scaffolding within the entire construction scope only needs to be erected and disassembled once, without repeated erection and disassembly, which not only shortens the scaffolding construction time, but also reduces the risk of erecting and dismantling the scaffolding; Short and low construction cost.
附图说明 Description of drawings
下面结合附图和具体实施方式对本发明作进一步详细地说明。The present invention will be described in further detail below in conjunction with the accompanying drawings and specific embodiments.
图1为本发明的结构示意图;Fig. 1 is a structural representation of the present invention;
图2为图1中钢架门洞或箱梁门洞的局部平面视图;Fig. 2 is a partial plane view of a steel frame door opening or a box girder door opening in Fig. 1;
图3为图2的A向视图。Fig. 3 is a view along the direction A of Fig. 2 .
具体实施方式 Detailed ways
图1为本发明的结构示意图,图2为图1中钢架门洞或箱梁门洞的局部平面视图,图3为图2的A向视图,如图所示:多层立交桥脚手架施工方法包括下述步骤:a、利用已经施工成型的桥梁柱作为核心筒,并以此为中心采用碗扣式脚手架和型钢向外发散搭设底层脚手架,底层脚手架搭设有供车辆和行人通行的钢架门洞2,对底层脚手架搭设质量进行认真仔细检查,然后在底层脚手架上安装变形监测系统,对底层脚手架进行货载试压,在立交桥整个施工过程对脚手架的变形进行监测;b、在底层脚手架上搭设至少两层桥梁脚手架,桥梁脚手架搭设有供桥梁施工所用的箱梁门洞3,整个桥梁脚手架搭设完后,对整个脚手架搭设质量进行认真仔细检查后,在箱梁门洞上安装变形监测系统,进行综合的脚手架货载预压试验,用以检查脚手架的搭设质量和对搭设前的计算进行验证,查看脚手架及型钢的变形是否在规范要求之内,对立交桥整个施工过程中的脚手架的变形进行监测。Fig. 1 is a schematic structural view of the present invention, Fig. 2 is a partial plane view of a steel frame door opening or a box girder door opening in Fig. 1, and Fig. 3 is an A-direction view of Fig. 2, as shown in the figure: the construction method of multi-layer overpass scaffolding includes the following Described steps: a. Utilize the bridge column that has been constructed as the core tube, and use bowl button scaffolding and section steel to diverge outwards to build the bottom scaffold around this. The bottom scaffold is equipped with a steel frame door opening 2 for vehicles and pedestrians to pass through. Carefully inspect the erection quality of the bottom scaffolding, then install a deformation monitoring system on the bottom scaffold, carry out a cargo pressure test on the bottom scaffold, and monitor the deformation of the scaffold during the entire construction process of the overpass; b. Set up at least two scaffolds on the bottom scaffold The bridge scaffolding is equipped with a box girder door opening 3 for bridge construction. After the entire bridge scaffolding is erected, the quality of the entire scaffolding is carefully checked, and a deformation monitoring system is installed on the box girder door opening to carry out comprehensive scaffolding inspection. Cargo preload test is used to check the quality of scaffolding and verify the calculation before erection, check whether the deformation of scaffolding and section steel is within the specification requirements, and monitor the deformation of scaffolding during the entire construction process of the overpass.
本实施例为双层立交桥脚手架,底层设有三个供车辆和行人通行的钢架门洞2,以方便车辆和行人通行;第一层桥梁与第二层桥梁为垂直方向上交错的桥梁,第二层桥梁脚手架设有供第一层桥梁施工所用的箱梁门洞3,主要以便于铺模板,布钢筋,浇混凝图,同时也是修建好第一层桥梁上车辆和行人通过的洞口。This embodiment is a double-layer overpass scaffolding, the bottom is provided with three steel frame door openings 2 for vehicles and pedestrians to facilitate the passage of vehicles and pedestrians; the first floor bridge and the second floor bridge are vertically staggered bridges, the second The first floor bridge scaffolding is provided with the used box girder door opening 3 for the construction of the first floor bridge, which is mainly for the convenience of laying templates, cloth reinforcement, and concrete pouring. It is also the opening for vehicles and pedestrians to pass on the first floor bridge.
钢架门洞2和箱梁门洞3主要由两侧碗扣式脚手架4和顶部设置的工字钢结构5形成,工字钢结构5包括主工字钢梁6、底部工字钢7以及顶部工字钢8,底部工字钢7为两层,分别固定设置在两侧碗扣式脚手架4上,主工字钢梁6以与车辆通行方向相垂直的方式固定设置在底部工字钢7上,顶部工字钢8以一定的间隔铺设在主工字钢梁6上,顶部工字钢与其上的碗扣式脚手架下托通过焊接固定连接,底部工字钢通过碗扣式脚手架上托焊接固定连接。The steel frame door opening 2 and the box
变形监测系统包括变形传感器、采集仪和监测中心计算机,变形传感器设置在作为横梁的主工字钢梁上,其信号输出端与采集仪连接,采集仪的数据输出端与监测中心计算机连接。脚手架及工字钢的变形监控由传统人工使用的水准仪改为采用变形监测系统进行主监测,人工使用水准仪对变形监测系统进行辅助监测、检查,由传统的分时段监测改变为电子化、数字化、全天候、全日程的检测。The deformation monitoring system includes a deformation sensor, an acquisition instrument and a monitoring center computer. The deformation sensor is set on the main I-beam as a beam, and its signal output terminal is connected to the acquisition instrument, and the data output end of the acquisition instrument is connected to the monitoring center computer. The deformation monitoring of scaffolding and I-beams is changed from the traditional manual use level to the deformation monitoring system for main monitoring, and the manual use of the level is used to assist the deformation monitoring system for monitoring and inspection. All-weather, all-day testing.
在脚手架搭建完后,需进行货载试压,货载为恒载的1.2倍和活载的1.4倍,以检测整个脚手架的承载能力,并观测监测中心计算机上主工字钢梁的变形情况,确保整个脚手架结构的稳定性、安全性能。与整个工字钢连接的部位均采用焊接,以确保牢固连接。After the scaffolding is built, it is necessary to conduct a cargo pressure test. The cargo load is 1.2 times the dead load and 1.4 times the live load to test the bearing capacity of the entire scaffold and observe the deformation of the main I-beam on the computer of the monitoring center. , to ensure the stability and safety performance of the entire scaffold structure. The parts connected with the entire I-beam are welded to ensure a firm connection.
脚手架由钢管通过碗扣件连接而成。用碗扣件连接钢管,不但安装或拆卸方便,而且可提高施工速度。The scaffolding is made of steel pipes connected by bowl fasteners. Using bowl fasteners to connect steel pipes is not only convenient for installation or disassembly, but also can increase the construction speed.
最后说明的是,以上实施例仅用以说明本发明的技术方案而非限制,尽管参照较佳实施例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,并不脱离本技术方案的宗旨和范围,其均应涵盖在本发明的权利要求范围当中。Finally, it is noted that the above embodiments are only used to illustrate the technical solutions of the present invention without limitation. Although the present invention has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical solutions of the present invention can be carried out Modifications or equivalent replacements do not depart from the spirit and scope of the technical solution, and all of them should be included in the scope of the claims of the present invention.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101909171A CN101696566B (en) | 2009-09-21 | 2009-09-21 | Construction method of mutilevel overpass scaffold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2009101909171A CN101696566B (en) | 2009-09-21 | 2009-09-21 | Construction method of mutilevel overpass scaffold |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101696566A true CN101696566A (en) | 2010-04-21 |
CN101696566B CN101696566B (en) | 2011-01-05 |
Family
ID=42141692
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2009101909171A Expired - Fee Related CN101696566B (en) | 2009-09-21 | 2009-09-21 | Construction method of mutilevel overpass scaffold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101696566B (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101906820A (en) * | 2010-07-29 | 2010-12-08 | 中建三局建设工程股份有限公司 | System capable of constructing in vertical structure and horizontal structure simultaneously in core tube |
CN103031810A (en) * | 2011-09-29 | 2013-04-10 | 李跃军 | Prestress hole channel grouting quality control method based on double parameters of flow and density |
CN108394848A (en) * | 2018-03-22 | 2018-08-14 | 中国十七冶集团有限公司 | A kind of simple kerbstone handling device and application method |
CN110878525A (en) * | 2019-11-06 | 2020-03-13 | 武船重型工程股份有限公司 | Double-layer steel box girder bridge installation method and combined support for installation |
CN111535200A (en) * | 2020-05-28 | 2020-08-14 | 中交路桥建设有限公司 | Anti-falling full-hall support structure and construction method |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1020645C (en) * | 1989-09-12 | 1993-05-12 | 上海市第五建筑工程公司 | Integral lifting system for outer scaffold of ultrahigh building mould |
CN2128653Y (en) * | 1992-07-24 | 1993-03-24 | 同济大学 | Multi-function mutual rise and fall framing scaffold |
JP2006307506A (en) * | 2005-04-27 | 2006-11-09 | Gifu Kogyo Co Ltd | Scaffolding |
CN201176726Y (en) * | 2008-04-16 | 2009-01-07 | 中冶天工建设有限公司 | Deviated gravity center thick wall super large reinforced concrete structures formwork sectional steel support system |
-
2009
- 2009-09-21 CN CN2009101909171A patent/CN101696566B/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101906820A (en) * | 2010-07-29 | 2010-12-08 | 中建三局建设工程股份有限公司 | System capable of constructing in vertical structure and horizontal structure simultaneously in core tube |
CN101906820B (en) * | 2010-07-29 | 2013-12-04 | 中建三局建设工程股份有限公司 | System capable of constructing in vertical structure and horizontal structure simultaneously in core tube |
CN103031810A (en) * | 2011-09-29 | 2013-04-10 | 李跃军 | Prestress hole channel grouting quality control method based on double parameters of flow and density |
CN108394848A (en) * | 2018-03-22 | 2018-08-14 | 中国十七冶集团有限公司 | A kind of simple kerbstone handling device and application method |
CN110878525A (en) * | 2019-11-06 | 2020-03-13 | 武船重型工程股份有限公司 | Double-layer steel box girder bridge installation method and combined support for installation |
CN110878525B (en) * | 2019-11-06 | 2022-04-05 | 武船重型工程股份有限公司 | Double-layer steel box girder bridge installation method and combined support for installation |
CN111535200A (en) * | 2020-05-28 | 2020-08-14 | 中交路桥建设有限公司 | Anti-falling full-hall support structure and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN101696566B (en) | 2011-01-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111254796B (en) | Single-side integral hoisting long-span overbridge for multiple railway business lines and construction method | |
CN100503977C (en) | Tower column of cable-stayed bridge and its construction method | |
CN107060275B (en) | A modular elevator shaft construction technology | |
CN201339250Y (en) | Stiffness structure framework beam preformed steel reinforcement framework structure | |
CN105863257B (en) | The erection method of plate-beam separated high-support form-connected brackets for multi- and high-rise reinforced concrete structures | |
CN101696566A (en) | Construction method of mutilevel overpass scaffold | |
CN115467421B (en) | Hoisting construction method for complex large-span steel roof | |
CN110106972A (en) | Between a kind of prefabricated reinforced concrete column and earth pillar or the connection method of itself and girder steel | |
CN106835930B (en) | A kind of bolt connecting type steel concrete combination beam | |
CN110863563B (en) | Ultra-long cantilever and pull rod combined structure and construction method | |
CN112502714A (en) | Assembled shaft barrel structure and design and construction method | |
CN111424948A (en) | Construction method and construction platform for cantilever structure layer of high-rise building | |
CN109424072A (en) | The connecting node and construction method of spacer bar concrete column on a kind of girder steel | |
CN204282803U (en) | To encorbelment formwork structure for mounting platform | |
CN106545115A (en) | Assembled steel Combined concrete superstructure and its construction method | |
CN203475310U (en) | Formwork for concrete slabs of composite steel-concrete box girders | |
CN113323446A (en) | Building construction supporting device, monitoring system and dismounting method | |
CN108824484B (en) | Vehicle section covered steel frame and covered reinforced concrete frame mixed structure | |
CN103821355A (en) | Reinforcing structure and reinforcing method for internal climbing type tower crane supporting beam | |
CN209723337U (en) | A prefabricated steel frame structure composite floor | |
CN201502165U (en) | Falsework structure for multi-layer overpass synchronous construction | |
CN104831928A (en) | Construction method for high-altitude large-span concrete connected structure formwork supporting steel platform | |
CN209686592U (en) | The flat column combination structure of discrete type width | |
CN106381927B (en) | An earthquake-damaged replaceable steel beam structure | |
CN212452288U (en) | Steel-concrete composite beam concrete bridge deck construction support |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110105 Termination date: 20130921 |