CN101588028B - Conducting wire supporter for electrified pole operation - Google Patents
Conducting wire supporter for electrified pole operation Download PDFInfo
- Publication number
- CN101588028B CN101588028B CN2009100998784A CN200910099878A CN101588028B CN 101588028 B CN101588028 B CN 101588028B CN 2009100998784 A CN2009100998784 A CN 2009100998784A CN 200910099878 A CN200910099878 A CN 200910099878A CN 101588028 B CN101588028 B CN 101588028B
- Authority
- CN
- China
- Prior art keywords
- fixed
- movable
- insulating rod
- head
- buckle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
- Electric Cable Installation (AREA)
Abstract
本发明涉及一种用于带电立杆作业中的导线支撑工具,本发明的技术要点是:绝缘棒一端装有固定式撑杆头,另一端装有可与绝缘棒活动配合的活动式撑杆头。所述活动式撑杆头由导线卡槽和扣环上下连接,绝缘棒一端分布有若干穿孔,移动式撑杆头通过扣环扣于绝缘棒,扣环两末端由固定螺栓固定,扣环径向通过活动螺栓固定于穿孔处。本发明的有益效果是:一、本发明体积小,使用灵巧,操作方便,安装拆除耗时少;二、绝缘程度好,机械强度达到要求,安全、可靠;三、控制了成本,有效的提高了供电可靠率;四、推动了地区电网的维护工作,保障了电网的安全和稳定的运行。
The invention relates to a wire support tool used in live pole operation. The technical gist of the invention is that one end of an insulating rod is equipped with a fixed strut head, and the other end is equipped with a movable strut that can be movably matched with the insulating rod head. The movable strut head is connected up and down by a wire slot and a buckle. There are several perforations distributed at one end of the insulating rod. The movable strut head is fastened to the insulating rod through a buckle. The two ends of the buckle are fixed by fixing bolts. The diameter of the buckle is It is fixed at the perforation through movable bolts. The beneficial effects of the present invention are as follows: 1. The present invention is small in size, smart to use, convenient to operate, and less time-consuming to install and dismantle; Fourth, promote the maintenance of the regional power grid and ensure the safety and stable operation of the power grid.
Description
技术领域technical field
本发明涉及一种用于带电立杆作业中的工具,尤其是一种用于带电立杆作业中的导线支撑工具。The invention relates to a tool used in live pole operation, in particular to a wire support tool used in live pole operation.
背景技术Background technique
带电立杆作业就是在不停电的情况下,拔出、移动或更换电杆的工作。为了保证电杆与两侧的导线有足够的安全距离,需要使用绝缘工具把两侧导线向外撑开一定距离。因此,撑开导线的绝缘工具是保障带电立杆工作安全,顺利完成的重要工具。目前为止,还没有真正适合10kV带电立杆作业专用的支撑导线的工具。Live pole operation is the work of pulling out, moving or replacing poles without power failure. In order to ensure a sufficient safe distance between the pole and the wires on both sides, it is necessary to use insulating tools to spread the wires on both sides outward for a certain distance. Therefore, the insulating tool that stretches the wire is an important tool to ensure the safety and smooth completion of the live pole work. So far, there is no tool that is really suitable for supporting wires for 10kV live pole work.
发明内容Contents of the invention
本发明提供一种用于带电立杆作业的导线支撑工具,确保10kV带电立杆作业可以安全顺利的进行。The invention provides a wire support tool for live pole operation, which ensures that the 10kV live pole operation can be carried out safely and smoothly.
本发明解决其技术问题采用的技术方案:这种用于带电立杆作业的导线支撑工具,绝缘棒一端装有固定式撑杆头,另一端装有可与绝缘棒活动配合的活动式撑杆头。The technical solution adopted by the present invention to solve the technical problem: this wire support tool for live pole operation, one end of the insulating rod is equipped with a fixed strut head, and the other end is equipped with a movable strut that can be movably matched with the insulating rod head.
所述活动式撑杆头由导线卡槽和扣环上下连接,绝缘棒一端分布有若干穿孔,移动式撑杆头通过扣环扣于绝缘棒,扣环两末端由固定螺栓固定,扣环径向通过活动螺栓固定于穿孔处。The movable strut head is connected up and down by a wire slot and a buckle. There are several perforations distributed at one end of the insulating rod. The movable strut head is fastened to the insulating rod through a buckle. The two ends of the buckle are fixed by fixing bolts. The diameter of the buckle is Fixed to the hole through the movable bolt.
所述固定式撑杆头由活动式撑杆头代替,在其一端绝缘棒开有一个穿孔。The fixed strut head is replaced by a movable strut head, and an insulating rod at one end thereof has a perforation.
所述固定式撑杆头嵌于绝缘棒端部并由螺丝于径向固定。The fixed pole head is embedded in the end of the insulating rod and fixed radially by screws.
所述导线卡槽通过摇皮连接有活动勾。The wire draw-in slot is connected with a movable hook through a rocker.
所述活动螺栓的螺帽为蝴蝶状。The nut of the movable bolt is butterfly-shaped.
所述导线卡槽采用不锈钢材料。The wire clamping groove is made of stainless steel.
所述导线卡槽套有保护橡胶。The wire clamping groove is covered with protective rubber.
本发明有益的效果是:一、本发明体积小,使用灵巧,操作方便,安装拆除耗时少;二、绝缘程度好,机械强度也达到10kV带电立杆的要求,安全、可靠;三、控制了材料成本和劳动成本,且可在免停电的情况下对带电立杆进行作业,有效的提高了供电可靠率;四、是可对立杆作业进行制度化、管理化的前提和基础,推动了地区电网的维护工作,保障了电网的安全和稳定的运行。The beneficial effects of the present invention are: 1. The present invention is small in size, smart to use, convenient to operate, and less time-consuming to install and dismantle; 2. The degree of insulation is good, and the mechanical strength also meets the requirements of a 10kV live pole, which is safe and reliable; 3. Control Material cost and labor cost are reduced, and live poles can be operated without power outages, which effectively improves the reliability of power supply; Fourth, it is the premise and basis for the institutionalization and management of pole operations, which promotes The maintenance of the regional power grid ensures the safe and stable operation of the power grid.
附图说明Description of drawings
图1是本发明实施例1的结构示意图;Fig. 1 is the structural representation of
图2是本发明实施例2的结构示意图;Fig. 2 is the structural representation of
图3是本发明活动式撑杆头的结构示意图;Fig. 3 is a schematic structural view of the movable strut head of the present invention;
图4是本发明活动式撑杆头的侧视图;Fig. 4 is a side view of the movable pole head of the present invention;
附图标记说明:绝缘棒1,固定式撑杆头2,活动式撑杆头3,导线卡槽3-1,扣环3-2,固定螺栓3-3,活动螺栓3-4,摇皮3-5,活动勾3-6,穿孔4,螺丝5,限宽标志6。Explanation of reference signs:
具体实施方式Detailed ways
下面结合附图和实施例对本发明作进一步说明:Below in conjunction with accompanying drawing and embodiment the present invention will be further described:
实施例1:这种用于带电立杆作业的导线支撑工具,绝缘棒1一端装有固定式撑杆头2,另一端装有可与绝缘棒1活动配合的活动式撑杆头3,可同时满足35mm2-240mm2架空线的需要,根据带电立杆作业的规程,电杆两侧的导线之间要保持2.5m以上的安全距离,但是距离撑开点越远,两侧导线的间距越小,要保持一段导线的间距都达到安全距离,导线撑开的宽度必须大于2.5m,根据采样试验,当导线被撑开到2.8m时,撑开点两侧各10.9m的范围内导线的距离都能达到2.5m以上的安全要求。由于装有活动式撑杆头3,考虑到小档距时,两侧导线安全范围会变小,本实施例设定绝缘棒1长度为3m。从机械强度和操作灵活度角度考虑,设定绝缘棒1直径为3cm。以此规格绝缘棒1为主材,对其进行90kV的耐压实验5分钟,满足10kV带电立杆作业的绝缘要求,绝缘棒截面最大可承受应力1760N,满足机械强度要求。Embodiment 1: In this wire support tool for live pole operation, one end of the insulating
所述活动式撑杆头3由U型导线卡槽3-1和扣环3-2上下连接,采用不锈钢作为导线卡槽3-1的主材,价格适中,机械强度高且耐腐蚀,在其外面套有一层橡胶,防止其对裸导线的磨损。导线卡槽3-1宽度设为3.5cm,可满足各种直径导线的需要。在绝缘棒1的2.5m处贴有限宽标志6,然后在标志后打有一比螺栓稍大的穿孔4,其后每隔15cm再打个孔,共打有4个穿孔4。安装活动式撑杆头3时,先将其扣环3-2扣于绝缘棒1,扣环3-2两末端由固定螺栓3-3固定死,此时活动式撑杆头3可在绝缘棒1上移动,扣环径向通过活动螺栓3-4固定于合适距离的穿孔4处,由于操作人员进行作业时带有绝缘手套,因此将活动螺栓3-4的螺帽设计为蝴蝶状,方便操作。导线卡槽3-1通过摇皮3-5连接有活动勾3-6,活动勾3-6可翻动,当导线卡槽3-1卡住导线时,导线会压住活动勾3-6一端,使得活动勾3-6另一端翻起盖住导线卡槽3-1开口,防止导线滑出,使用更稳定安全可靠。The
所述固定式撑杆头2可由活动式撑杆头3代替,仅在其一端打有一个穿孔4,并用固定螺栓3-3和活动螺栓3-4将其固定死。Described
使用时,先将固定式撑杆头2将一侧导线撑开,再根据导线间安全间距,调节活动式撑杆头3至合适穿孔4处,并栓紧活动螺栓3-4,用活动式撑杆头3撑住另一侧导线。When in use, first spread the wires on one side with the
实施例2:绝缘棒1与活动式撑杆头3都与实施例1中所述相同,固定式撑杆头2嵌于绝缘棒1端部并由螺丝5于径向将其固定。Embodiment 2: Both the
除上述实施例外,本发明还可以有其他实施方式。凡采用等同替换或等效变换形成的技术方案,均落在本发明要求的保护范围。In addition to the above-mentioned embodiments, the present invention can also have other implementations. All technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the present invention.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009100998784A CN101588028B (en) | 2009-06-18 | 2009-06-18 | Conducting wire supporter for electrified pole operation |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2009100998784A CN101588028B (en) | 2009-06-18 | 2009-06-18 | Conducting wire supporter for electrified pole operation |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101588028A CN101588028A (en) | 2009-11-25 |
| CN101588028B true CN101588028B (en) | 2011-04-20 |
Family
ID=41372147
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2009100998784A Active CN101588028B (en) | 2009-06-18 | 2009-06-18 | Conducting wire supporter for electrified pole operation |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101588028B (en) |
Families Citing this family (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103806740B (en) * | 2013-12-12 | 2015-01-14 | 国家电网公司 | Insertion type erection method for electrified pole |
| CN105712231B (en) * | 2016-04-15 | 2017-11-10 | 国网上海市电力公司 | A kind of special pulley group of the powered pike pole of livewire work bucket arm vehicle |
| CN107681533B (en) * | 2017-03-16 | 2019-06-25 | 国网浙江省电力公司衢州供电公司 | A wire spreading device |
| CN107681536B (en) * | 2017-03-16 | 2019-06-25 | 国网浙江省电力公司衢州供电公司 | Auxiliary fixing device for live pole |
| CN107681534B (en) * | 2017-03-16 | 2019-06-25 | 国网浙江省电力公司衢州供电公司 | A wire-pulling and positioning device for standing and withdrawing rods |
| CN108683122B (en) * | 2018-06-08 | 2020-07-28 | 国网山东省电力公司青岛供电公司 | Auxiliary device and method for linear poles in shared corridor with electromigration |
| CN109462180B (en) * | 2018-09-19 | 2020-03-24 | 国网浙江省电力有限公司丽水供电公司 | Triangular brace for live work and how to use it |
| CN112627623A (en) * | 2020-12-03 | 2021-04-09 | 国网辽宁省电力有限公司锦州供电公司 | Method for replacing telegraph pole in electrified manner |
-
2009
- 2009-06-18 CN CN2009100998784A patent/CN101588028B/en active Active
Also Published As
| Publication number | Publication date |
|---|---|
| CN101588028A (en) | 2009-11-25 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101588028A (en) | Conducting wire supporter for electrified pole operation | |
| CN201323409Y (en) | Tool for live line replacing of high voltage transmission line V-shaped insulator chain | |
| CN204130730U (en) | A kind of multifunctional grounded rifle | |
| CN103887735A (en) | Linear charged wire lifting device of electric transmission line | |
| CN201904593U (en) | Pre-stranded two-bundle spacer | |
| CN102738737B (en) | The general suspension string holder of steel pipe tower head | |
| CN202712745U (en) | Universal straight-line clamp for steel pipe pole tower head | |
| CN202602171U (en) | A tool for power-on replacing multi-loop double split conductor insulator of 220kV line | |
| CN203277304U (en) | Built-in high-voltage fuse sleeve installation apparatus | |
| CN105449612A (en) | A conductive wire insulation support plate apparatus | |
| CN202308856U (en) | Electricity-transforming carrier fluid live treatment heat generation short-circuit shunt device | |
| CN105048377B (en) | A kind of low voltage house line fixing device | |
| CN203522053U (en) | Cable protection steel pipe | |
| CN203760919U (en) | Drainage wire bracket for live working | |
| CN203339323U (en) | Power transmission overhead line turning and grounding device | |
| CN203891535U (en) | Special-purpose door type electric pole for jumper operation | |
| CN104143781B (en) | Live installation method of electrical inspection grounding ring and installation tool for electrical inspection grounding ring | |
| CN209016299U (en) | Portable combined auxiliary earthing apparatus | |
| CN202977751U (en) | Electric-power line grounding apparatus | |
| CN205335800U (en) | Wire insulated supporting plate device | |
| CN206023125U (en) | A kind of tubular bus connector | |
| CN205159909U (en) | Change extra -high voltage earthing pole circuit dead end insulator's instrument with electricity | |
| CN204118591U (en) | A kind of protection rope for conductor | |
| CN204144631U (en) | A kind of distribution transforming inspection earthing line is met an urgent need crossover tool | |
| CN202586154U (en) | Insulating operation rod for replacing overvoltage protector in distribution line in live-line manner |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| ASS | Succession or assignment of patent right |
Owner name: STATE ELECTRIC NET CROP. Free format text: FORMER OWNER: DONGYANG CITY POWER SUPPLY BUREAU Effective date: 20140109 Owner name: JINHUA POWER SUPPLY COMPANY, STATE GRID ZHEJIANG E Effective date: 20140109 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 322100 JINHUA, ZHEJIANG PROVINCE TO: 100031 XICHENG, BEIJING |
|
| TR01 | Transfer of patent right |
Effective date of registration: 20140109 Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing Patentee after: State Grid Corporation of China Patentee after: Jinhua Power Supply Company, State Grid Zhejiang Electric Power Company Patentee after: STATE GRID ZHEJIANG DONGYANG POWER SUPPLY COMPANY Address before: 322100 No. 58 Renmin Road, Zhejiang, Dongyang Patentee before: Dongyang City Power Supply Bureau |