CN101560828B - 剪刀撑扣件式钢管脚手架模板支架 - Google Patents

剪刀撑扣件式钢管脚手架模板支架 Download PDF

Info

Publication number
CN101560828B
CN101560828B CN200910143839XA CN200910143839A CN101560828B CN 101560828 B CN101560828 B CN 101560828B CN 200910143839X A CN200910143839X A CN 200910143839XA CN 200910143839 A CN200910143839 A CN 200910143839A CN 101560828 B CN101560828 B CN 101560828B
Authority
CN
China
Prior art keywords
vertical
formwork support
support
steel pipe
adjustable bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200910143839XA
Other languages
English (en)
Other versions
CN101560828A (zh
Inventor
张国庆
方忠明
王莉瑛
刘群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Erjian Construct Co., Ltd.
Original Assignee
HANGZHOU ERJIAN CONSTRUCT CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to CN200820139562 priority Critical
Priority to CN200820139562.4 priority
Application filed by HANGZHOU ERJIAN CONSTRUCT CO Ltd filed Critical HANGZHOU ERJIAN CONSTRUCT CO Ltd
Priority to CN200910143839XA priority patent/CN101560828B/zh
Publication of CN101560828A publication Critical patent/CN101560828A/zh
Application granted granted Critical
Publication of CN101560828B publication Critical patent/CN101560828B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及一种扣件式钢管脚手架模板支架,支架纵向5跨,横向5跨,在5跨×5跨范围内加载;在加载区外围四周各立面每隔四排立杆设竖向剪刀撑,剪刀撑靠近节点,与横杆或立杆交接处用扣件扣接;支架高宽比为2.71。架高8.15m,立杆步距0.9m,立杆纵向间距0.65m,立杆横向间距0.6m,用Φ48×3.5钢管搭设,各节点用扣件连接。支架上部由可调托座托顶Φ48×3.5双钢管作为支托模板的主梁,可调托座底部插入支架立杆固定,可调托座上表面至支架纵向水平杆上表面的距离为0.55m,可调托座伸出立杆0.32m,在0.32m范围内调节。本发明的扣件式钢管脚手架模板支架结构安全稳固,搭拆方便。

Description

剪刀撑扣件式钢管脚手架模板支架
技术领域
[0001] 本发明涉及一种建筑工地用的模板支架,尤其是一种扣件式钢管脚手架模板支
^K O
背景技术
[0002] 目前建筑工地使用的扣件式钢管脚手架模板支架,没有系列的搭设结构尺寸,没 有准确的设计规定,没有对扣件式钢管脚手架模板支架临界荷载进行限制,没有系列模板 支架搭设结构一一对应的临界荷载要求。现场凭经验搭设,一方面,造成材料浪费成本增 加,另一方面,造成安全隐患,有的甚至发生重大安全事故。
发明内容
[0003] 本发明的目的在于提供一种具有合理结构尺寸的扣件式钢管脚手架模板支架,并 给出对应的临界荷载,使钢管脚手架模板支架经济合理,安全适用。
[0004] 本发明是这样来实现上述目的的:
[0005] 一种扣件式钢管脚手架模板支架,包括立杆钢管、纵向水平杆和横向水平杆;节点 用可锻铸铁扣件连接,支架上部由可调托座托顶Φ48Χ3.5双钢管(2)作为支托模板的主 梁,可调托座底部插入支架立杆钢管内固定;支架纵向5跨,横向5跨,在5跨X 5跨范围内 加载;在加载区外围四周各立面每隔四排立杆设竖向剪刀撑,剪刀撑靠近节点,与横杆或立 杆交接处用扣件扣接,加载区外围四周各立面竖向剪刀撑斜杆与水平横杆夹角48度至50 度,剪刀撑底跨5跨;支架高宽比为2. 71。
[0006] 由可调托座上表面到立杆钢管底面距离,即架高8. 15m,相邻纵向水平杆或相邻横 向水平杆轴线距离,即立杆步距0. 9m,立杆钢管纵向间距0. 65m,立杆钢管横向间距0. 6m。
[0007] 可调托座上表面至支架最上纵向水平杆上表面的距离为0. 55m,可调托座伸出立 杆钢管的长度不大于0. 32m。
[0008] 这种扣件式钢管脚手架模板支架结构安全稳固,支架结构简单,搭拆方便,钢管脚 手架模板支架经济合理,安全适用。
附图说明
[0009] 图1是扣件式钢管脚手架模板支架主视图;
[0010] 图2是扣件式钢管脚手架模板支架俯视图;
[0011] 图3是扣件式钢管脚手架模板支架侧视图;
[0012] 图4是扣件式钢管脚手架模板支架载荷试验装配主视图;
[0013] 图5是扣件式钢管脚手架模板支架加载区俯视图;
[0014] 图6是扣件式钢管脚手架模板支架载荷试验装配侧视图;
[0015] 图中:1、可调托座;2、双钢管;3、纵向水平杆;4、立杆钢管;5、横向水平杆;6、可 锻铸铁扣件;7、反力架;8、固定反力架钢管;9、分配梁;10、工字钢;11、千斤顶、12竖向剪刀撑。
具体实施方式
[0016] 一种扣件式钢管脚手架模板支架,包括立杆钢管4、纵向水平杆3和横向水平杆5 ; 节点用可锻铸铁扣件6连接,支架上部由可调托座1托顶Φ48Χ3.5双钢管(2)作为支托 模板的主梁,可调托座1底部插入支架立杆钢管4内固定。支架纵向5跨,横向5跨,在5 跨X5跨范围内加载,在加载区外围四周各立面每隔四排立杆设竖向剪刀撑,剪刀撑靠近 节点,与横杆或立杆交接处用扣件扣接,加载区外围四周各立面竖向剪刀撑斜杆与水平横 杆夹角48度至50度,剪刀撑底跨5跨;支架高宽比=8. 15+ (5X0. 6) = 2. 71 ;扫地杆为 支架下部横杆,D为扫地杆高度。
[0017] 由可调托座上表面到立杆钢管底面距离,即架高C为8. 15m,相邻纵向水平杆或相 邻横向水平杆轴线距离,即立杆步距E为0. 9m,立杆钢管纵向间距A为0. 65m,立杆钢管横 向间距B为0. 6m,扫地杆高度D为0. 4m。
[0018] 可调托座1上表面至支架最上纵向水平杆3上表面的距离F为0. 55m,可调托座1 伸出立杆钢管4的长度不大于0. 32m(图中G所示)。
[0019] 试验如图4-6所示,这种扣件式钢管脚手架模板支架经千斤顶11加荷,顶反力架 7主梁,反力架回顶将荷载传至分配梁9,分配梁9将荷载传至工字钢10,工字钢10将荷载 传至支架双钢管2,实现支架荷载试验。经荷载试验确定,支架临界荷载每平米128. 34kN, 平均单立杆临界荷载34. 76kN。

Claims (4)

  1. 一种扣件式钢管脚手架模板支架,包括立杆钢管(4)、纵向水平杆(3)和横向水平杆(5);其特征是:节点用可锻铸铁扣件(6)连接;支架上部由可调托座(1)托顶Φ48×3.5双钢管(2)作为支托模板的主梁,可调托座(1)底部插入支架立杆钢管(4)内固定;支架纵向5跨,横向5跨;加载区为5跨×5跨的范围;在加载区外围四周各立面每隔四排立杆设竖向剪刀撑(12),剪刀撑靠近节点,与横杆或立杆交接处用扣件扣接,支架高宽比为2.71。
  2. 2.根据权利要求1所述的一种扣件式钢管脚手架模板支架,其特征在于:可调托座(1) 上表面到立杆钢管(4)底面距离为8. 15m,相邻纵向水平杆(3)轴线距离为0. 9m,相邻横向 水平杆(5)轴线距离为0. 9m,相邻立杆钢管(4)纵向间距0. 65m,相邻立杆钢管(4)横向间 距 0. 6m。
  3. 3.根据权利要求1所述的一种扣件式钢管脚手架模板支架,其特征在于可调托座(1) 上表面至支架最上纵向水平杆(3)上表面的距离为0. 55m,可调托座(1)伸出立杆钢管(4) 的长度不大于0. 32m。
  4. 4.根据权利要求1所述的一种扣件式钢管脚手架模板支架,其特征在于加载区外围四 周各立面竖向剪刀撑(12)斜杆与水平横杆夹角48度至50度,剪刀撑(12)底跨5跨。
CN200910143839XA 2008-10-27 2009-06-01 剪刀撑扣件式钢管脚手架模板支架 Active CN101560828B (zh)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN200820139562 2008-10-27
CN200820139562.4 2008-10-27
CN200910143839XA CN101560828B (zh) 2008-10-27 2009-06-01 剪刀撑扣件式钢管脚手架模板支架

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910143839XA CN101560828B (zh) 2008-10-27 2009-06-01 剪刀撑扣件式钢管脚手架模板支架

Publications (2)

Publication Number Publication Date
CN101560828A CN101560828A (zh) 2009-10-21
CN101560828B true CN101560828B (zh) 2011-01-26

Family

ID=41219787

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910143839XA Active CN101560828B (zh) 2008-10-27 2009-06-01 剪刀撑扣件式钢管脚手架模板支架

Country Status (1)

Country Link
CN (1) CN101560828B (zh)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101761229B (zh) * 2009-12-14 2012-02-01 山东万鑫建设有限公司 空心叠合密肋板支撑体系施工方法
CN102587659A (zh) * 2012-03-12 2012-07-18 中天建设集团有限公司 一种以混凝土柱支顶后浇带两侧结构的施工方法

Also Published As

Publication number Publication date
CN101560828A (zh) 2009-10-21

Similar Documents

Publication Publication Date Title
CN201381637Y (zh) 一种扣件式钢管脚手架模板支架
CN102182300B (zh) 一种增加水平剪刀撑提高并确定支撑架承载力的方法
CN100554629C (zh) 一种扣件式钢管脚手架模板支架
CN101560829B (zh) 大高宽比扣件式钢管脚手架模板支架
CN101560828B (zh) 剪刀撑扣件式钢管脚手架模板支架
CN201284559Y (zh) 一种扣件式钢管脚手架模板支架
CN102322134B (zh) 一种扣件式满堂支撑架与满堂脚手架
CN204531341U (zh) 一种用于建筑物与施工升降机间的过道平台
CN201924284U (zh) 一种螺杆座管双拼贝雷架
CN201284550Y (zh) 一种扣件式钢管满堂脚手架
CN100540826C (zh) 一种扣件式钢管脚手架模板支架
CN201381638Y (zh) 一种扣件式钢管脚手架模板支架
CN201284556Y (zh) 一种扣件式钢管脚手架模板支架
CN203145432U (zh) 钢管脚手架爬梯
CN211114732U (zh) 便携可移动式钢筋绑扎操作平台
CN201310191Y (zh) 一种扣件式钢管脚手架模板支架
CN211286215U (zh) 一种可拆支撑的装配式叠合楼板
CN203977833U (zh) 一种附墙式悬挑脚手架
CN101566006B (zh) 大步距扣件式钢管脚手架模板支架
CN201310182Y (zh) 一种扣件式钢管满堂脚手架
CN201284558Y (zh) 一种扣件式钢管脚手架模板支架
CN201284557Y (zh) 一种扣件式钢管脚手架模板支架
CN100540825C (zh) 一种扣件式钢管脚手架模板支架
CN205116749U (zh) 用于大跨度钢结构整体滑移的轨道支撑装置
CN102182311B (zh) 一种增加连墙件提高并确定支撑架承载力方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
C41 Transfer of patent application or patent right or utility model
C53 Correction of patent for invention or patent application
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 065000 ROOM 102, UNIT 2, BUILDING 6, SHENGCHUNLI, JINGUANG AVENUE, GUANGYANG DISTRICT, LANGFANG CITY, HEBEI PROVINCE TO: 310005 NO. 226, MOGANSHAN ROAD, HANGZHOU CITY

Free format text: CORRECT: INVENTOR; FROM: LIU QUN TO: ZHANG GUOQING FANG ZHONGMING WANG LIYING LIU QUN

CB03 Change of inventor or designer information

Inventor after: Zhang Guoqing

Inventor after: Fang Zhongming

Inventor after: Wang Liying

Inventor after: Liu Qun

Inventor before: Liu Qun

TA01 Transfer of patent application right

Effective date of registration: 20101123

Address after: Hangzhou city 310005 Moganshan Road No. 226

Applicant after: Hangzhou Erjian Construct Co., Ltd.

Address before: Langfang City, Hebei Province, Jinguang road 065000 Guangyang District Sheng Chunli 6 Building 2 unit 102 room

Applicant before: Liu Qun

ASS Succession or assignment of patent right

Owner name: HANGZHOU ERJIAN CONSTRUCT CO., LTD.

Free format text: FORMER OWNER: LIU QUN

Effective date: 20101123

C14 Grant of patent or utility model
GR01 Patent grant