Railway bed laying emergency stone self-discharging train Download PDF

Info

Publication number
CN101475003A
CN101475003A CNA2009100605677A CN200910060567A CN101475003A CN 101475003 A CN101475003 A CN 101475003A CN A2009100605677 A CNA2009100605677 A CN A2009100605677A CN 200910060567 A CN200910060567 A CN 200910060567A CN 101475003 A CN101475003 A CN 101475003A
Authority
CN
China
Prior art keywords
head
train
full
tail
material box
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2009100605677A
Other languages
Chinese (zh)
Other versions
CN101475003B (en
Inventor
袁建明
李勇智
胡吉全
赵章焰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN2009100605677A priority Critical patent/CN101475003B/en
Publication of CN101475003A publication Critical patent/CN101475003A/en
Application granted granted Critical
Publication of CN101475003B publication Critical patent/CN101475003B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

铁路路基铺设抢险石料自卸列车包括火车机车、平板列车组和供电及控制系统;在平板列车组上装有石料输送和装卸物流系统,该系统由料箱(3)、一个头部和尾部输送单元及多个中间输送单元组成;每个中间输送单元设有一个两层结构的整体支架(7),下层安装两套满箱输送机(5)形成下输送线的一段,上层安装一套空箱输送机(6)形成上输送线的一段,这两段输送线是料箱在立面内的循环运行通道,各个中间输送单元中的循环运行通道连通,则料箱通过连通的下输送线将其箱内的石料在列车的正前方或正前方两侧自动卸出,然后料箱由连通的上输送线运至列车尾部,由尾部输送单元送回下输送线。本列车用于为铁路路基塌方抢险或正常路基建设供给所需石料。

Figure 200910060567

The emergency stone dump train for laying the railway embankment includes a train locomotive, a flat train set, and a power supply and control system; a stone conveying and loading and unloading logistics system is installed on the flat train set, and the system consists of a material box (3), a head and a tail conveying unit and a plurality of intermediate conveying units; each intermediate conveying unit is provided with a two-layer structure integral support (7), and two sets of full container conveyors (5) are installed on the lower layer to form a section of the lower conveying line, and a set of empty containers is installed on the upper layer Conveyor (6) forms a section of the upper conveying line. These two sections of conveying line are the circulation passages of the feed boxes in the facade. The circulation passages in each intermediate conveying unit are connected, and the feed boxes will be transported through the connected lower conveying line The stones in the box are automatically unloaded at the front of the train or on both sides of the front, and then the material box is transported to the rear of the train by the connected upper conveying line, and sent back to the lower conveying line by the tail conveying unit. This train is used to supply the required stones for emergency rescue of railway embankment collapse or normal embankment construction.

Figure 200910060567

Description

Railway bed laying emergency stone self-discharging train
Technical field
The present invention relates to engineering machinery field, particularly relate to a kind of railway bed laying emergency stone self-discharging train.
Background technology
Railway transportation is the artery of national economy.The improper transportation of railway is interrupted will having a strong impact on railway transportation with obstruction, the operation that influence is economic.China has the railway of very long distance to be among lofty mountains and steep hills, owing to be subjected to flood, disasteies such as mud-rock flow, the influence of factors such as the roadbed situation is bad, a lot of roadbed landslides and the disconnected road of railway accident all can take place every year inevitably, had a strong impact on the normal operation of railway, caused great economic loss and social influence for country and place, particularly be in Fujian, the railway on ground such as Guizhou, owing to be located in the mountain area, and mostly be single line, in case run into disconnected road of railway and roadbed landslide accident, railway transportation is substantially just in paralyzed state, and economic loss that causes like this and social influence will be unable to estimate.Disaster can't be avoided, and has only the time that shortens railway recovery as much as possible, guarantees that disrupted circuit is unobstructed as early as possible, and the economic loss and the social influence that it could be brought drop to minimum level.
To in the speedily carrying out rescue work of roadbed landslide and the disconnected road of railway accident, often need a large amount of building stones in order to fill up the roadbed of landslide, normally with the high side train building stones are transported to and close on the landslide point, then by manually building stones being discharged to the railway both sides from train, the building stones that will pile up along the line are transported to landslide place and fill up again, at a lot of remote places, mountain area, big machinery can't participate in work at all, and the building stones carrying can only be with artificial master, and therefore the labour intensity of speedily carrying out rescue work is big, efficient is low, poor stability.
Also unspecial both at home and abroad at present the equipment of speedily carrying out rescue work at roadbed landslide and the disconnected road of railway accident.In order to shorten the time of repairing railway as early as possible, guarantee that disrupted circuit is unobstructed as early as possible, reduce economic loss as far as possible, it is very to be necessary that the professional railway recovery equipment of developing a kind of automation solves this class problem.
China drops into the construction that a large amount of funds is used for railway at present, and the laying of railroad bed will need a large amount of building stones, adopt this equipment to be used among the normal railway construction, can improve the efficient of railway construction undoubtedly, saves construction cost.
Summary of the invention
Technical matters to be solved by this invention is: a kind of railway bed laying emergency stone self-discharging train is provided, be railroad bed landslide to be speedily carried out rescue work or normal roadbed is built required building stones and is loaded on the hopper of this train in the stone pit, be transported to from the stone pit by this train again and close on landslide ground or lay ground, and a special-purpose train that can automatically building stones be unloaded to the landslide point or lay.
The present invention solves its technical matters and adopts following technical scheme:
Railway bed laying emergency stone self-discharging train provided by the invention, its structure is: comprise engine, dull and stereotyped train groups and power supply and control system.Building stones are housed on dull and stereotyped train groups carry and load and unload logistics system, the processing unit that described system carries and loads and unloads as containerization with hopper, this system is made up of a plurality of hoppers, head supply unit, afterbody supply unit and a plurality of middle transport unit between these two unit, and two middle transport unit headtotails are contained on the flat truck; Each middle transport unit is provided with an integral support with double-layer structure, lower floor installs two cover trunkful conveyers and forms a section of travel line under the described system, the upper strata is installed a cover empty van conveyer and is formed a section of travel line in the described system, and these two sections travel lines are hopper circular flow passages in facade; The hopper of the fully loaded building stones in each middle transport unit is migrated to the head supply unit by the following travel line that is communicated with, head unloader by this head supply unit draws off dead ahead or the dead ahead both sides of the building stones in the hopper at the train head automatically, unloaded hopper after discharging is intact is migrated to last vehicle of train by the last travel line that is communicated with, and sends down travel line back to by the afterbody supply unit.
Railway bed laying emergency stone self-discharging train provided by the invention, its purposes is: railroad bed landslide is speedily carried out rescue work or normal roadbed is built required building stones and is loaded on the hopper of this train by the stone pit, be transported to from the stone pit by this train again and close on landslide ground or lay ground, and can automatically building stones be unloaded to the landslide point or lay point.
Railway bed laying emergency stone self-discharging train provided by the invention mainly contains following remarkable result:
The building stones that utilize railway freight dressing plate car and engine to transport to be mounted with emergency stone carry and the loading and unloading logistics system to landslide ground or lay ground, carry and load and unload the material self-loopa of logistics system and unload function certainly by building stones, can automatically all building stones be offloaded to the landslide point or lay point, reduction manpower labour intensity that will be bigger, raise the efficiency and safety, shortening are speedily carried out rescue work the time, the normal operation of train can be recovered as early as possible, can also improve the quick reaction capability of railway, will have remarkable social benefit and economic benefit emergent accident.In addition, train provided by the invention also can be used for supplying with required building stones for the laying of roadbed in the normal construction of railway, improves railway construction efficient.
Description of drawings
Fig. 1 is the composition scheme drawing of railway bed laying emergency stone self-discharging train of the present invention.
Fig. 2 is a middle transport unit scheme drawing.
Fig. 3 is the lateral plan of Fig. 2.
Fig. 4 is the structural representation of hopper 3.
Fig. 5 is the lateral plan of Fig. 4.
Fig. 6 is that trunkful conveyer 5 is formed scheme drawing.
Fig. 7 is the birds-eye view of Fig. 6.
Fig. 8 is that empty van conveyer 6 is formed scheme drawing.
Fig. 9 is the birds-eye view of Fig. 8.
Figure 10 is that head lifter 8 is formed scheme drawing.
Figure 11 is the lateral plan of Figure 10.
Figure 12 is that afterbody elevator 10 is formed scheme drawing.
Figure 13 is the birds-eye view of Figure 12.
Figure 14 is that head unloader 9 is formed scheme drawing.
Figure 15 is the lateral plan of Figure 14.
Figure 16 is hopper 3 mobile scheme drawing between head lifter 8 and head unloader 9.
Among the figure: 1. engine; 2. dull and stereotyped train; 3. hopper; 4. power and control system; 5. trunkful conveyer; 6. empty van conveyer; 7. integral support; 8. head lifter; 9. head unloader; 10. afterbody elevator; 11. carrying roller track; 12. guide roller track; 13. side direction baffle plate; 14. latching device; 15. casing; 16. lance; 17. trunkful carrying roller; 18. sprocket wheel; 19. trunkful guide roller; 20. trunkful feed drive reducing motor; 21. transmission shaft; 22. chain; 23. drive sprocket; 24. empty van carrying roller set; 25. empty van orienting roll wheels; 26. empty van chain type driving device; 27. head lifting table; 28. head fixed support; 29. horizontal guide wheel; 30. vertical guide wheel; 31. the head lifting drives reducing motor; 32. reel; 33. steel rope; 34. afterbody lifting drive; 35. afterbody lifting table; 36. afterbody fixed support; 37. cantilever girder; 38. support cylinder base; 39. tilt stand; 40. pitch drives reducing motor; 41. gear; 42. tooth bar; 43. reel cage; 44. hook; 45. power hydraulic pressure push rod; 46. swing bearing; 47. revolution drives reducing motor; 48. miniature gears.
The specific embodiment
Railway bed laying emergency stone self-discharging train provided by the invention, be railroad bed landslide to be speedily carried out rescue work or normal roadbed is built required building stones and is loaded on the hopper of this train in the stone pit, be transported to from the stone pit by this train again and close on landslide ground or lay ground, and a roadbed laying emergency stone self-discharging train that can automatically building stones be unloaded to the landslide point or lay.
The invention will be further described below in conjunction with embodiment and accompanying drawing.
Railway bed laying emergency stone self-discharging train provided by the invention comprises engine 1, dull and stereotyped train groups and power supply and control system 4, building stones is housed on dull and stereotyped train groups carries and load and unload logistics system.
The structure of dull and stereotyped train groups is as shown in Figure 1: be made up of 12 joint flat trucks 2.Engine 1 is common engine, and it moves on railway for the dull and stereotyped train groups of permutation power is provided.Flat truck 2 is a railway freight dressing plate car, and it is used to load, and building stones are carried and the loading and unloading logistics system.
Building stones are carried and the loading and unloading logistics system, its structure as shown in Figure 1: form by 20 middle transport unit, head supply unit, afterbody supply unit, 40 hoppers 3 and power supply and control control system 4.Building stones are carried and the loading and unloading logistics system is carried as containerization with hopper 3 and the processing unit of loading and unloading, the hopper 3 that will be fully loaded with building stones in the stone pit successively is placed on the trunkful conveyer 5 of each middle transport unit lower floor, place a fully loaded hopper 3 on each trunkful conveyer 5, after transporting landslide ground to or lay ground from the stone pit by dull and stereotyped train groups, by the up and down circular flow of two strip transmission lines of hopper 3 in facade, each fully loaded hopper 3 on the train is migrated to the train head by following travel line, by head unloader 9 dead ahead or the dead ahead both sides of building stones at the train head are drawn off automatically, unloaded hopper 3 after discharging is intact is migrated to last vehicle of train by last travel line, sends back to travel line down by afterbody elevator 10.
Middle transport unit: referring to Fig. 1, Fig. 2, it is made up of two cover trunkful conveyers 5, a cover empty van conveyer 6 and an integral support 7.Integral support 7 comprises two-layer up and down, lower floor install that two cover trunkful conveyers 5 form that building stones are carried and the loading and unloading logistics system under a section of travel line, the upper strata install that a cover empty van conveyer 6 forms that building stones are carried and the loading and unloading logistics system on a section of travel line, these two sections travel lines are hopper 3 circular flow passages in facade.The integral support 7 that two cover trunkful conveyers 5, a cover empty van conveyer 6 are installed constitutes a middle transport unit, and two middle transport unit headtotails are installed on the flat truck 2.Circular flow channel connection in each middle transport unit, the following travel line that is communicated be will fully loaded building stones hopper 3 be sent to the train head and by the passage of the head supply unit discharging at this place, the last travel line of connection is that the unloaded hopper after discharging is finished is sent last vehicle of train back to and returned down the passage of travel line by the afterbody supply unit at this place.
The head supply unit: referring to Fig. 1, Figure 16, it comprises a cover head elevator 8, two cover trunkful conveyers 5 and a cover head unloader 9.In head lifter 8 and head unloader 9 a cover trunkful conveyer 5 is installed respectively.Head lifter 8 realizes the transition of fully loaded hopper from following delivery conduit to head unloader 9, and with the upwards transition of delivery conduit transfer of unloader 9 from the head of unloaded hopper.Head unloader 9 is realized dead ahead or the dead ahead both sides of all building stones from the train head are drawn off.The head supply unit is installed on the flat truck 2 of train head.
The afterbody supply unit: referring to Fig. 1, Figure 12, it comprises a cover afterbody elevator 10, a cover empty van conveyer 6.Empty van conveyer 6 is installed on the afterbody elevator 10, and afterbody elevator 10 is realized the transition of unloaded hopper from last delivery conduit to following delivery conduit.Afterbody supply unit and power supply and control control system 4 are installed on the flat truck 2 of last vehicle of train.
Hopper 3: referring to Fig. 4, Fig. 5, the processing unit that it is carried as the containerization loading and unloading of loading building stones, the open top container body structure that adopts the steel plate welding to make.The bottom of hopper 3 and side are welded with carrying roller track 11 and guide roller track 12, the bearing track that carrying roller track 11 moves on conveyer as hopper 3, the guide track that guide roller track 12 moves on conveyer as hopper 3.The two ends of hopper 3 are provided with side direction baffle plate 13 to be opened/closed, side direction baffle plate 13 tops and casing 15 are hinged, side direction baffle plate 13 belows have latching device 14 to be connected with casing 15, when hopper 3 inclination dischargings, the latching device 14 of side direction baffle plate 13 belows is opened, and building stones are pushed the baffle plate lower edge open and drawn off automatically under the effect of gravity.The two ends of hopper 3 also are provided with lance 16, when hopper 3 moves on the tilt stand 39 of head unloader 9 can with hook 44 automatic engagements on the tilt stand 39, when hopper 3 is tilted with tilt stand 39, can not come off from support.
Trunkful conveyer 5: referring to Fig. 6, Fig. 7, the roller mode of movement that it adopts chain type to drive, be used to transport hopper 3 that building stones are housed from after move forward or move backward in the past.Trunkful conveyer 5 respectively is provided with two covers on each middle transport unit, on head lifter 8 and head unloader 9 cover is set respectively.Trunkful conveyer 5 is made up of trunkful carrying roller set, trunkful orienting roll wheels and trunkful chain type driving device.Trunkful carrying roller set comprises two groups of parallel trunkful carrying rollers 17, on each trunkful carrying roller 17 sprocket wheel 18 is housed all, actuating device drives each trunkful carrying roller 17 by chain-driving and rotates, when hopper 3 is placed on the trunkful carrying roller 17, realize the parallel motion of hopper 3 on trunkful carrying roller 17.At the bearing of integral support 7 lower floors, at the bearing of the head lifting table 27 of head lifter 8 with on the bearing of tilt stand 39, trunkful carrying roller set 17 is housed all.Trunkful orienting roll wheels comprise two groups of parallel trunkful guide rollers 19, be installed in the two sides of integral support 7 or head lifting table 27 or afterbody lifting table 35 respectively, when hopper 3 is mobile on trunkful carrying roller 17, the mobile of hopper 3 play the guiding role, prevent that hopper 3 from wandering off.When the roller pitch arrangement of trunkful carrying roller set and trunkful orienting roll wheels need guarantee to make hopper 3 to move, the bottom of hopper 3 and the track of side strode across three pair rollers all the time at least, made the stressed even of hopper 3 tracks and carrying roller, and guiding steadily.The roller height of trunkful carrying roller set at every joint flat truck 2 both ends is designed to from low to high, can guarantee that hopper 3 can overcome the differences of height between the two joint flat trucks 2 during transition automatically between two joint flat trucks 2, and pulsation-free moves.The two side wheel spacings of trunkful orienting roll wheels at every joint flat truck 2 both ends are designed to descending, can guarantee to stop at when working on the bend when train, and guiding hopper 3 moves smooth and easy transition along bend between two joint flat trucks 2.The actuating device of trunkful conveyer 5 is made of trunkful feed drive reducing motor 20, transmission shaft 21, chain 22, drive sprocket 23.
Empty van conveyer 6: referring to Fig. 8, Fig. 9, the roller mode of movement that it also adopts chain type to drive, be used to transport empty charging box 3 by move behind the forward direction or from after move forward.Empty van conveyer 6 respectively is provided with a cover on each middle transport unit, a cover is set on afterbody elevator 10.Empty van conveyer 6 is made up of empty van carrying roller set 24, empty van orienting roll wheels 25 and empty van chain type driving device 26.Empty van chain type driving device 26 is made of empty van feed drive reducing motor, transmission shaft, chain.The actuating device of empty van conveyer 6, the composition of roller set and layout and trunkful conveyer 5 are similar, and just relevant parameters is less.
Head lifter 8: referring to Figure 10, Figure 11, it realizes the transition of full hopper 3 from following delivery conduit to head unloader 9, and with the upwards transition of delivery conduit transfer of unloader 9 from the head of unloaded hopper.Head lifter 8 is made up of head lifting drive and head lifting table 27 and head fixed support 28.Head lifting table 27 is at horizontal guide wheel 29, vertically under the draw of the directional tagging of guide wheel 30 and head lifting drive, can on the guide rail of head fixed support 28, move vertically, and be connected mutually with upper and lower delivery conduit and head unloader 9 respectively.One cover trunkful conveyer 5 is installed on the head lifting table 27.The head lifting drive adopts two cover duplex hoist machines, and this winch is made up of major parts such as head lifting reducing motor 31, reel 32, steel ropes 33, moves up and down by steel rope 33 traction head lifting tables 27.Whole head lifter 8 is installed on the flat truck 2 by head fixed support 28.
Afterbody elevator 10: referring to Figure 12, Figure 13, it realizes the transition of empty van from last delivery conduit to following delivery conduit.Afterbody elevator 10 is made up of afterbody lifting drive 34, afterbody lifting table 35 and afterbody fixed support 36.Afterbody lifting table 35 can move vertically on the guide rail of afterbody fixed support 36, and be connected mutually with upper and lower delivery conduit respectively under the draw of directional tagging horizontal, vertically guide wheel and afterbody lifting drive.One cover empty van conveyer 6 is installed on the afterbody lifting table 35.The composition of afterbody lifting drive 34 is similar to the head lifting drive, and just correlation parameter is less.Afterbody lifting drive 34 moves up and down by rope traction afterbody lifting table 35.Whole afterbody elevator 10 is installed on the flat truck 2 by afterbody fixed support 36.
Head unloader 9: referring to Figure 14, Figure 15, it is full circle swinging, cantilevered unloader, is made up of leaning device, swing type mechanism, cantilever girder 37 and support cylinder base 38.Leaning device comprises reclining drive device, tilt stand 39 and hopper hooking device, and leaning device is installed on the cantilever girder 37; Be furnished with a cover trunkful conveyer 5 on the tilt stand 39, an end and the cantilever girder 37 of tilt stand 39 are hinged, and tooth bar 42 ends of the other end and reclining drive device are hinged; Reclining drive device adopts the rack-and-gear transmission, form by pitch drives reducing motor 40, gear 41, tooth bar 42 and reel cage 43 etc., tooth bar 42 is done straight reciprocating motion under the driving of pitch drives reducing motor 40, order about the hinge of tilt stand 39 on cantilever girder 37 and rotate, thereby realize making the hopper 3 inclination dischargings that are fixed on the tilt stand 39; Reel cage 43 can be provided with the back lash that gear 41 and tooth bar 42 could be adjusted and guarantee to three track adjusting wheels around fixedly hinge rotation as the guide piece of tooth bar 42 motions on the reel cage 43.The hopper hooking device comprises hook 44 and power hydraulic pressure push rod 45, when hopper 3 moves on the tilt stand 39, lance 16 on the hopper 3 hits the into gib head of hook 44, when hopper 3 is tilted with tilt stand 39, hook 44 hooks hopper 3 can not come off it from support, after hopper 3 dischargings were finished, under the effect of power hydraulic pressure push rod 45, hook 44 was thrown off with lance 16.Swing type mechanism is made up of swing bearing 46 and device for revolving and driving, the effect of swing type mechanism be support and drive head unloader 9 on cantilever girder 37 and leaning device mounted thereto in horizontal surface, rotate, make head unloader 9 reach various discharging scope; Swing bearing 46 Internal and external cycles link with the flange of cantilever girder 37 and support cylinder base 38 respectively with bolt, with vertical power, horizontal force and the capsizing moment of bearing head unloader 9 rotating parts; Device for revolving and driving drives external toothing on reducing motor 47, miniature gears 48, the swing bearing 46 etc. by revolution to be formed, and the engagement by the external toothing on miniature gears 48 and the swing bearing 46 drives cantilever girder 37 and leaning device mounted thereto rotates in horizontal surface relative to support cylinder base 38.Support cylinder base 38 tops link to each other with swing bearing 46, and bottom and flat truck 2 are fixed.
Integral support 7: referring to Fig. 2, Fig. 3, it is a frame-type double-level-metal framing member, lower floor is used to install two cover trunkful conveyers 5, the upper strata is used to install 6, two integral supports 7 of a cover empty van conveyer and is placed on the flat truck 2 together with mounted two cover trunkful conveyers 5, empty van conveyer 6.
Railway bed laying emergency stone self-discharging train provided by the invention, its purposes is: railroad bed landslide is speedily carried out rescue work or normal roadbed is built required building stones and is loaded on the hopper of this train by the stone pit, be transported to from the stone pit by this train again and close on landslide ground or lay ground, and can automatically building stones be unloaded to the landslide point or lay point.
This train adopts the method that may further comprise the steps in application process:
1. vanning process:
(1) hopper 3 loads building stones;
(2) will be fully loaded with hopper 3 is placed on the head lifting table 27 successively;
(3) head lifting table 27 drops to delivery conduit;
(4) will be fully loaded with hopper 3 successively by trunkful conveyer 5 carries backward;
(5) repeat above-mentioned four steps, until filling the permutation train;
(6) transport landslide ground to or lay ground by the fully loaded train of engine 1 traction.
2. unload the case process:
(1) starts trunkful conveyer 5, the fully loaded hopper 3 case position that moves forward successively;
(2) head lifter 8 will be fully loaded with hopper and rise to the identical height of head unloader 9 from following delivery conduit;
(3) the trunkful conveyer 5 on startup head lifter 8 and the head unloader 9 makes hopper 3 move on the head unloader 9 and hook;
(4) head unloader 9 operation hoppers 3 dischargings comprise that rotation, rack-and-gear drive, the inclination discharging;
(5) head unloader 9 transports unloaded hopper to head lifting table 27 back;
(6) head lifter 8 with unloaded Skip hoisting to last delivery conduit;
(7) start empty van conveyer 6, unloaded hopper moves after on the last delivery conduit and is back to afterbody;
(8) afterbody elevator 10 is admitted unloaded hopper;
(9) afterbody elevator 10 carries unloaded hopper and descends and dock with following delivery conduit;
(10) successively unloaded hopper is moved forward by trunkful conveyer 5.
(11) repeat the described action of above-mentioned steps, unsnatch until car load.
Wherein:, can carry out step (7) simultaneously to step (10) carrying out the above-mentioned case step (1) of unloading to the process of step (6).

Claims (10)

1.一种铁路路基铺设抢险石料自卸列车,包括火车机车、平板列车组和供电及控制系统,其特征是:在平板列车组上装有石料输送和装卸物流系统,所述系统以料箱(3)作为集装化输送和装卸的处理单元,由多个料箱(3)、一个头部输送单元、一个尾部输送单元和位于这两个单元之间的多个中间输送单元组成,两个中间输送单元头尾相接装在一个平板车(2)上;每个中间输送单元设有一个具有两层结构的整体支架(7),下层安装两套满箱输送机(5)形成所述系统下输送线的一段,上层安装一套空箱输送机(6)形成所述系统上输送线的一段,这两段输送线是料箱(3)在立面内的循环运行通道;各个中间输送单元中的循环运行通道连通;各个中间输送单元中的满载石料的料箱(3)通过连通的下输送线运移至头部输送单元,由该头部输送单元的头部卸料机(9)将料箱中的石料在列车头部的正前方或正前方两侧自动卸出,卸料完后的空载料箱由连通的上输送线运移至列车尾部,由尾部输送单元送回下输送线。1. a kind of railway embankment is laid emergency stone material self-unloading train, comprises train locomotive, flat train set and power supply and control system, it is characterized in that: on flat train set, stone material conveying and loading and unloading logistics system are housed, and described system uses feed box ( 3) As a processing unit for containerized conveying and loading and unloading, it consists of multiple material boxes (3), a head conveying unit, a tail conveying unit and multiple intermediate conveying units between these two units, two The intermediate conveying units are mounted end to end on a flatbed truck (2); each intermediate conveying unit is provided with an integral support (7) with a two-layer structure, and two sets of full-conveyor conveyors (5) are installed on the lower layer to form the system A section of the lower conveying line, and a set of empty container conveyors (6) are installed on the upper floor to form a section of the upper conveying line of the system. These two sections of conveying lines are the circulation passages of the material boxes (3) in the facade; each intermediate conveying The circulating passages in the unit are connected; the material bins (3) loaded with stones in each intermediate conveying unit are transported to the head conveying unit through the connected lower conveying line, and the head unloading machine (9) of the head conveying unit ) to automatically unload the stones in the material box in front of the head of the train or on both sides of the front. After unloading, the empty material box is transported to the tail of the train by the connected upper conveying line, and sent back by the tail conveying unit down the conveyor line. 2.根据权利要求1所述的铁路路基铺设抢险石料自卸列车,其特征是:2. The railway embankment laying rescue stone dump train according to claim 1 is characterized in that: 头部输送单元:设有一套头部升降机(8)及一套头部卸料机(9),它们各安装有一套满箱输送机(5);Head conveying unit: There is a set of head elevator (8) and a set of head unloader (9), each of which is equipped with a set of full container conveyor (5); 尾部输送单元:由一套尾部升降机(10)和一套空箱输送机(6)组成,空箱输送机装在尾部升降机上。Tail conveying unit: composed of a set of tail elevator (10) and a set of empty container conveyor (6), the empty container conveyor is installed on the tail elevator. 3.根据权利要求1所述的铁路路基铺设抢险石料自卸列车,其特征是:料箱(3)采用钢板焊接制成的敞口箱体结构,其底部和侧面焊有承载滚轮轨道(11)和导向滚轮轨道(12),其两端均设置有可开闭的侧向挡板(13)和撞杆(16),当料箱(3)运行至头部卸料机(9)的倾斜支架(39)上时,所述撞杆与倾斜支架(39)上的挂钩(44)自动连接,使料箱(3)随倾斜支架(39)倾斜时,不会从支架上脱落。3. The railway subgrade laying emergency stone dump train according to claim 1, characterized in that: the material box (3) adopts an open box structure made of steel plate welding, and its bottom and sides are welded with load-carrying roller tracks (11 ) and guide roller track (12), both ends of which are provided with side baffles (13) and rams (16) that can be opened and closed, when the material box (3) runs to the head unloader (9) When on the inclined support (39), the described lance is automatically connected with the hook (44) on the inclined support (39), so that when the material box (3) is inclined with the inclined support (39), it will not come off from the support. 4.根据权利要求1所述的铁路路基铺设抢险石料自卸列车,其特征是头部升降机(8)由头部升降驱动装置和头部升降平台(27)及头部固定支架(28)组成,其中:在横向导轮(29)、纵向导轮(30)的导向作用及头部升降驱动装置的牵引作用下,头部升降平台(27)在头部固定支架(28)的导轨上垂直上下移动,并且分别与上、下输送线路及头部卸料机(9)相衔接;头部升降平台(27)上安装有一套满箱输送机(5);整个头部升降机(8)通过头部固定支架(28)安装在平板车(2)上。4. The railway subgrade laying emergency stone dump train according to claim 1, characterized in that the head elevator (8) is composed of a head lifting drive device, a head lifting platform (27) and a head fixing bracket (28) , wherein: under the guiding effect of the horizontal guide wheel (29), the longitudinal guide wheel (30) and the traction of the head lifting drive device, the head lifting platform (27) is vertical on the guide rail of the head fixing bracket (28) Move up and down, and connect with the upper and lower conveying lines and head unloader (9) respectively; a set of full box conveyor (5) is installed on the head lifting platform (27); the whole head lift (8) passes through Head fixed bracket (28) is installed on the flatbed truck (2). 5.根据权利要求1所述的铁路路基铺设抢险石料自卸列车,其特征是尾部升降机(10)由尾部升降驱动装置(34)、尾部升降平台(35)及尾部固定支架(36)组成,其中:尾部升降平台(35)上安装有一套空箱输送机(6),在横向、纵向导轮的导向作用及尾部升降驱动装置的牵引作用下,尾部升降平台(35)可在尾部固定支架(36)的导轨上垂直上下移动,并且分别与上、下输送线路相衔接;整个尾部升降机(10)通过尾部固定支架(36)安装在平板车(2)上。5. The railway embankment laying rescue stone dump train according to claim 1, characterized in that the tail elevator (10) is composed of a tail lifting drive device (34), a tail lifting platform (35) and a tail fixing bracket (36), Among them: a set of empty container conveyor (6) is installed on the tail lifting platform (35), under the guiding effect of the horizontal and vertical guide wheels and the traction of the tail lifting drive device, the tail lifting platform (35) can be fixed on the tail (36) vertically moves up and down on the guide rail, and is connected with upper and lower conveying lines respectively; Whole tail elevator (10) is installed on the flat car (2) by tail fixed support (36). 6.根据权利要求1或4或5所述的铁路路基铺设抢险石料自卸列车,其特征是:6. according to claim 1 or 4 or 5 described railway embankment laying rescue stone dump train, it is characterized in that: 满箱输送机(5)由满箱承载滚轮组、满箱导向滚轮组和满箱链式驱动装置组成,其中:满箱承载滚轮组包括两组平行的满箱承载滚轮(17),每个满箱承载滚轮(17)上均装有链轮(18),满箱链式驱动装置通过链传动驱动每个满箱承载滚轮(17)转动,当料箱(3)放置在满箱承载滚轮(17)上时,实现料箱(3)在满箱承载滚轮(17)上的水平移动;满箱导向滚轮组包括两组平行的满箱导向滚轮(19),分别安装在整体支架(7)或头部升降平台(27)或尾部升降平台(35)的两侧面;满箱承载滚轮组在每节平板车(2)两端部的滚轮高度设计为由低到高;满箱导向滚轮组在每节平板车(2)两端部的两侧滚轮间距设计为由大到小;The full-conveyor conveyor (5) is composed of a full-container bearing roller set, a full-container guide roller set and a full-container chain drive, wherein: the full-container load-bearing roller set includes two sets of parallel full-container load-bearing rollers (17), each The full container load rollers (17) are equipped with sprockets (18), and the full container chain drive drives each full container load roller (17) to rotate through chain transmission. When the material box (3) is placed on the full container load roller When (17) goes up, realize the horizontal movement of material bin (3) on the load-carrying roller (17) of full container; Full container guide roller group comprises two groups of parallel full container guide rollers (19), is respectively installed on integral support (7) ) or the two sides of the head lifting platform (27) or the tail lifting platform (35); The distance between the rollers on both sides at the two ends of each flatbed car (2) is designed from large to small; 空箱输送机(6)由空箱承载滚轮组(24)、空箱导向滚轮组(25)和空箱链式驱动装置(26)组成,它们的组成及布置与上述满箱输送机(5)相同,只是相应的参数较小。Empty case conveyor (6) is made up of empty case bearing roller group (24), empty case guide roller group (25) and empty case chain type driving device (26), and their composition and arrangement and above-mentioned full case conveyor (5 ) is the same, but the corresponding parameters are smaller. 7.根据权利要求1所述的铁路路基铺设抢险石料自卸列车,其特征是头部卸料机(9)为全回转、悬臂式卸料机,由倾斜机构、回转机构、悬臂主梁(37)及支撑圆筒底座(38)组成;倾斜机构包括倾斜驱动装置、倾斜支架(39)及料箱挂钩装置,倾斜机构安装在悬臂主梁(37)上;倾斜支架(39)上布置有一套满箱输送机(5),倾斜支架(39)的一端与悬臂主梁(37)铰接,另一端与倾斜驱动装置的齿条(42)端部铰接;倾斜驱动装置采用齿轮齿条传动,主要由倾斜驱动减速电机(40)、齿轮(41)、齿条(42)和摇架(43)组成,齿条(42)在倾斜驱动减速电机(40)的驱动下作直线往复运动,驱使倾斜支架(39)绕悬臂主梁(37)上的铰点转动,从而实现使固定在倾斜支架(39)上的料箱(3)倾斜卸料;料箱挂钩装置包括挂钩(44)及电力液压推杆(45),当料箱(3)移动至倾斜支架(39)上时,料箱(3)上的撞杆(16)撞进挂钩(44)的钩头,使料箱(3)随倾斜支架(39)倾斜时,挂钩(44)钩住料箱(3)使其不会从支架上脱落,当料箱(3)卸料完成后,在电力液压推杆(45)的作用下,挂钩(44)与撞杆(16)脱开。回转机构由回转轴承(46)和回转驱动装置组成,回转轴承(46)内外圈分别与悬臂主梁(37)和支撑圆筒底座(38)相联,在回转驱动装置的作用下,悬臂主梁(37)及安装在其上的倾斜机构相对支撑圆筒底座(38)在水平面内转动,以达到各种不同的卸料范围的目的;支撑圆筒底座(38)下部与平板车(2)固结。7. The railway subgrade laying emergency stone self-unloading train according to claim 1, characterized in that the head unloader (9) is a full-rotation, cantilever type unloader, composed of a tilting mechanism, a rotary mechanism, a cantilever main beam ( 37) and a support cylinder base (38); the tilting mechanism includes a tilting drive device, a tilting bracket (39) and a material box hook device, and the tilting mechanism is installed on the cantilever main beam (37); a tilting bracket (39) is arranged on a For the full box conveyor (5), one end of the inclined bracket (39) is hinged with the cantilever main beam (37), and the other end is hinged with the end of the rack (42) of the inclined drive device; the inclined drive device adopts rack and pinion transmission, It is mainly composed of a tilting drive reduction motor (40), a gear (41), a rack (42) and a cradle (43). The rack (42) makes a linear reciprocating motion driven by the tilting drive reduction motor (40), driving The inclined support (39) rotates around the hinge point on the cantilever main beam (37), thereby realizing the inclined discharge of the material box (3) fixed on the inclined support (39); the material box hook device includes a hook (44) and an electric power Hydraulic push rod (45), when material box (3) moved on the inclined support (39), the ram (16) on the material box (3) bumped into the gib head of hook (44), made material box (3) ) when tilting with the tilting support (39), the hook (44) hooks the material box (3) so that it will not fall off from the support. Under the effect, hook (44) and lance (16) throw off. The slewing mechanism is composed of a slewing bearing (46) and a slewing drive device. The inner and outer rings of the slewing bearing (46) are respectively connected with the cantilever main beam (37) and the support cylinder base (38). Under the action of the slewing drive device, the cantilever main The beam (37) and the tilting mechanism mounted on it rotate in the horizontal plane relative to the support cylinder base (38) to achieve the purpose of various discharge ranges; Consolidation. 8.根据权利要求1所述的铁路路基铺设抢险石料自卸列车,其特征是整体支架(7)为框架型双层金属结构件,配有连接头与平板车(2)相连。8. The railway subgrade laying emergency stone dump train according to claim 1, characterized in that the integral support (7) is a frame-type double-layer metal structure, equipped with a connector to connect with the flatbed truck (2). 9.一种根据权利要求1至8中任一权利要求所述铁路路基铺设抢险石料自卸列车的用途,其特征是:将铁路路基塌方抢险或正常路基建设所需的石料由采石场进行装载到该列车的料箱(3)上,再由该列车从采石场运输到临近塌方地或铺设地,并能自动将石料卸载到塌方点或铺设点。9. A use of the railway subgrade laying emergency stone dump train according to any one of claims 1 to 8, characterized in that: the railway subgrade collapse emergency or the stone required for normal subgrade construction are carried out from the quarry Loaded on the material box (3) of the train, the train is transported from the quarry to the land near the landslide or the laying ground, and the stone can be automatically unloaded to the landslide point or the laying point. 10.根据权利要求9所述的用途,其特征是在应用过程中采用包括以下步骤的方法:10. purposes according to claim 9, it is characterized in that adopting the method that comprises the following steps in application process: a.装箱过程:a. Packing process: 1)料箱(3)装载石料,1) The material box (3) is loaded with stones, 2)将满载料箱(3)依次放置在头部升降平台(27)上,2) Place the fully loaded material boxes (3) on the head lifting platform (27) in sequence, 3)头部升降平台(27)下降到下输送线路,3) the head lifting platform (27) descends to the lower conveying line, 4)由满箱输送机(5)依次将满载料箱(3)向后输送,4) The full container conveyor (5) sequentially transports the full container (3) backwards, 5)重复上述四个步骤,直至装满整列列车,5) Repeat the above four steps until the entire train is filled, 6)然后由火车机车(1)牵引满载列车运往塌方地或铺设地;6) then the train locomotive (1) pulls the fully loaded train and transports it to landslide ground or laying ground; b.卸箱过程:b. Unpacking process: 1)启动满箱输送机(5),满载料箱(3)依次前移一个箱位,1) Start the full container conveyor (5), and the full container (3) moves forward one by one, 2)头部升降机(8)将满载料箱从下输送线路提升到头部卸料机(9)相同的高度,2) The head elevator (8) lifts the full load box from the lower conveying line to the same height as the head unloader (9), 3)启动头部升降机(8)及头部卸料机(9)上的满箱输送机(5),使料箱(3)移动到头部卸料机(9)上并挂钩,3) Start the full container conveyor (5) on the head elevator (8) and the head unloader (9), so that the material box (3) is moved to the head unloader (9) and hooked, 4)操作头部卸料机(9)使料箱(3)卸料,包括旋转、齿轮齿条驱动、倾斜卸料,4) Operate the head unloader (9) to unload the material box (3), including rotation, rack and pinion drive, and inclined unloading, 5)头部卸料机(9)将空载料箱运回至头部升降平台(27),5) The head unloader (9) transports the empty material box back to the head lifting platform (27), 6)头部升降机(8)将空载料箱提升到上输送线路,6) The head elevator (8) lifts the empty material box to the upper conveying line, 7)启动空箱输送机(6),空载料箱在上输送线路上后移返回至尾部,7) Start the empty container conveyor (6), and the empty container will move back to the tail on the upper conveying line, 8)尾部升降机(10)接纳空载料箱,8) the tail lifter (10) accepts an empty feed box, 9)尾部升降机(10)携带空载料箱下降与下输送线路对接,9) The tail elevator (10) carries the empty material box down and docks with the lower conveying line, 10)由满箱输送机(5)依次将空载料箱向前移动,10) The empty-loaded material boxes are moved forward sequentially by the full-box conveyor (5), 11)重复上述步骤所述动作,直至整车卸完,11) Repeat the actions described in the above steps until the whole vehicle is unloaded, 其中:进行上述卸箱步骤1)至步骤6)的过程中,可同时进行步骤7)至步骤10)。Wherein: in the process of carrying out the above-mentioned unpacking step 1) to step 6), step 7) to step 10) can be carried out simultaneously.
CN2009100605677A 2009-01-19 2009-01-19 Railway bed laying emergency stone self-discharging train Expired - Fee Related CN101475003B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100605677A CN101475003B (en) 2009-01-19 2009-01-19 Railway bed laying emergency stone self-discharging train

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100605677A CN101475003B (en) 2009-01-19 2009-01-19 Railway bed laying emergency stone self-discharging train

Publications (2)

Publication Number Publication Date
CN101475003A true CN101475003A (en) 2009-07-08
CN101475003B CN101475003B (en) 2010-11-10

Family

ID=40835800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100605677A Expired - Fee Related CN101475003B (en) 2009-01-19 2009-01-19 Railway bed laying emergency stone self-discharging train

Country Status (1)

Country Link
CN (1) CN101475003B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014075960A1 (en) * 2012-11-15 2014-05-22 K & K Maschinenentwicklungs Gmbh & Co. Kg System for track-bound transportation of objects
WO2014075959A1 (en) * 2012-11-15 2014-05-22 K & K Maschinenentwicklungs Gmbh & Co. Kg System for rail-bound transport of objects
CN104828100A (en) * 2015-04-29 2015-08-12 安徽兴宇轨道装备有限公司 Rail type flat transporting vehicle for rail construction
CN105452084A (en) * 2013-06-04 2016-03-30 哈斯科公司 Reciprocation system and method for rail vehicle
CN106460346A (en) * 2014-07-01 2017-02-22 普拉塞-陶依尔铁路出口股份有限公司 Carrier with independently controllable unloading device
CN110055828A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of embankment heavy grade cogwheel railway structure and construction method
CN110817980A (en) * 2018-08-07 2020-02-21 江苏佳佩环保机械设备有限公司 Steel wire rope traction type grating cleaner
CN112340485A (en) * 2020-12-15 2021-02-09 北京国电龙源环保工程有限公司 Movable automobile discharging platform and discharging method based on same
CN113494030A (en) * 2021-07-27 2021-10-12 武汉理工大学 Multi-channel ballast blowing device and method
CN115402285A (en) * 2022-09-13 2022-11-29 成都威奥轨道科技有限公司 A Method of Accelerating the Mitigation of Vehicles in the Rear of a Long Train

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104903516A (en) * 2012-11-15 2015-09-09 K&K机械开发两合公司 Systems for rail transport of objects
WO2014075959A1 (en) * 2012-11-15 2014-05-22 K & K Maschinenentwicklungs Gmbh & Co. Kg System for rail-bound transport of objects
WO2014075960A1 (en) * 2012-11-15 2014-05-22 K & K Maschinenentwicklungs Gmbh & Co. Kg System for track-bound transportation of objects
CN105452084B (en) * 2013-06-04 2017-10-13 哈斯科公司 Repeat system and method for railcar
CN105452084A (en) * 2013-06-04 2016-03-30 哈斯科公司 Reciprocation system and method for rail vehicle
CN106460346A (en) * 2014-07-01 2017-02-22 普拉塞-陶依尔铁路出口股份有限公司 Carrier with independently controllable unloading device
CN106460346B (en) * 2014-07-01 2018-08-03 普拉塞-陶依尔铁路出口股份有限公司 Carrier with independently controllable unloading device
CN104828100A (en) * 2015-04-29 2015-08-12 安徽兴宇轨道装备有限公司 Rail type flat transporting vehicle for rail construction
CN110817980A (en) * 2018-08-07 2020-02-21 江苏佳佩环保机械设备有限公司 Steel wire rope traction type grating cleaner
CN110055828A (en) * 2019-04-28 2019-07-26 中铁二院工程集团有限责任公司 A kind of embankment heavy grade cogwheel railway structure and construction method
CN110055828B (en) * 2019-04-28 2023-09-26 中铁二院工程集团有限责任公司 Construction method of embankment large-gradient toothed rail railway structure
CN112340485A (en) * 2020-12-15 2021-02-09 北京国电龙源环保工程有限公司 Movable automobile discharging platform and discharging method based on same
CN113494030A (en) * 2021-07-27 2021-10-12 武汉理工大学 Multi-channel ballast blowing device and method
CN115402285A (en) * 2022-09-13 2022-11-29 成都威奥轨道科技有限公司 A Method of Accelerating the Mitigation of Vehicles in the Rear of a Long Train

Also Published As

Publication number Publication date
CN101475003B (en) 2010-11-10

Similar Documents

Publication Publication Date Title
CN101475003B (en) Railway bed laying emergency stone self-discharging train
CN105083867B (en) Free-discharging rotary displacement conveyor for tailing discharge and use method thereof
CN103303692B (en) A kind of automation both arms frame mixed-windrowed locomotive efficiently
CN103318663B (en) Automatically loading, easing gear
CN107650761B (en) Automatic discharging equipment for vehicle-mounted telescopic conveyor belt
CN109625880B (en) Bucket-type belt conveyor gallery blanking recovery vehicle
CN113200374B (en) A bulk material direct unloading loader
CN204872930U (en) Take gate -type scraper blade reclaimer of windrow arm
CN107304006A (en) A kind of Transmission system for automotive seat automatic loading and unloading
JP2014508696A (en) Reclaimer equipment
CN109823810A (en) A kind of novel energy-storing vanadium cell pile production conveying device
CN110697436B (en) A horizontally rotating folding arm conveyor
CN116495501A (en) A kind of train container unloading system and unloading method
CN204802677U (en) Material carloader is got to gate -type nucket -wheel
CN214827440U (en) Full-moving earth surface shipment distributing machine
CN201390257Y (en) Laying of railway embankment to rescue stone dump train
CN203033294U (en) Container wood floor automatic material trimming and feeding conveying device
US20070297883A1 (en) Bulk material unloading system and method
CN108263865A (en) A kind of cantilevered windrow machine equipment
CN203975800U (en) A kind of rotation material casting load-transfer device
CN115743187B (en) Distributed driving type mining track transportation system and method thereof
CN215827906U (en) Bulk material direct-unloading type car loader
CN205739513U (en) A kind of crawler type rehandling facilities
CN104176450A (en) Automatic conveying and storing equipment of cement prefabricated slab for housing project
CN211109395U (en) Double-bin intelligent sand conveying device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20101110

Termination date: 20140119