CN101463804B - 风力发电机主轴与齿轮箱的装配方法 - Google Patents

风力发电机主轴与齿轮箱的装配方法 Download PDF

Info

Publication number
CN101463804B
CN101463804B CN200710032716XA CN200710032716A CN101463804B CN 101463804 B CN101463804 B CN 101463804B CN 200710032716X A CN200710032716X A CN 200710032716XA CN 200710032716 A CN200710032716 A CN 200710032716A CN 101463804 B CN101463804 B CN 101463804B
Authority
CN
China
Prior art keywords
gear
box
main shaft
jack
pull bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200710032716XA
Other languages
English (en)
Other versions
CN101463804A (zh
Inventor
陈平华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MingYang Smart Energy Group Co Ltd
Original Assignee
GUANGDONG MINGYANG WIND ELECTRICAL TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG MINGYANG WIND ELECTRICAL TECHNOLOGY Co Ltd filed Critical GUANGDONG MINGYANG WIND ELECTRICAL TECHNOLOGY Co Ltd
Priority to CN200710032716XA priority Critical patent/CN101463804B/zh
Publication of CN101463804A publication Critical patent/CN101463804A/zh
Application granted granted Critical
Publication of CN101463804B publication Critical patent/CN101463804B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction

Abstract

风力发电机主轴与齿轮箱的装配方法,其装配步骤如下:a、先将齿轮箱水平放置在放置架,使齿轮箱主轴轴孔水平,齿轮箱上设有一与主轴轴孔相对穿透的孔;b、将主轴水平起吊,对准齿轮箱安装位;c、调整天车使主轴与齿轮箱轴轴孔同轴;d、用一根拉杆穿过主轴和齿轮箱轴心的孔,在拉杆伸出主轴的一端垫上固定挡件;e、所述拉杆伸出齿轮箱的另一端套有千斤顶,并加固定件;f、驱动千斤顶使千斤顶伸长,在拉杆两端都被固定的情况下,千斤顶的伸长可将主轴拉进齿轮箱;g、将主轴拉进齿轮箱后,将主轴用锁紧环固定在齿轮箱上;h、将主轴用支架支撑好,去掉吊带;i、拆下固定件和千斤顶,将拉杆拉出主轴和齿轮箱,完成整个装配过程。

Description

风力发电机主轴与齿轮箱的装配方法
【技术领域】
本发明涉及一种风力发电机主轴与齿轮箱装配的方法,主要适用于非直驱结构的风力发电机主轴与齿轮箱装配。
【背景技术】
现有的风力发电机在进行主轴与齿轮箱的装配时,都是采用竖立装配的方式,即先将主轴翻转竖立起来,之后将齿轮箱连接部位向上放置在平台之上,再将齿轮箱翻转,使齿轮箱的连接部位与主轴连接的部位垂直对应,将齿轮箱吊起置并置于主轴之上并保证与主轴同心,之后慢慢落下使齿轮箱的连接部位与主轴连接孔套入主轴。装配到位后将锁紧环上螺钉用液压板手紧固。完成装配后再进行整体的翻转使其水平放置。这种装配方法的缺点是:1.齿轮箱体积大,重量有十几吨,翻转难度大,而且翻转危险性大。2.主轴与齿轮箱连接后锁紧环螺钉头向下,用液压力矩扳手紧固时,操作人员需要手向上托液压板手操作。液压板手重十几斤,这样操作人员很容易疲劳,大大降低装配的工作效率,并容易发生意外事故。3.由于装配完成后的总成高度有5到6米,重量高达近30吨。进行翻转难度太大,效率太低,危险性大。4.由于装配部件高度高,对装配车间的起吊高度要求也高。5.由于需要多次翻转部件,对天车的占用时间相对较长不利于批量生产。6,由于装配点在2米高以上,需要安装平台,并且工人需要高空作业,增加了工作的危险性。
为了解决上述存在的问题,本发明进行了突出的工艺流程改进。
【发明内容】
本发明针对上述所存在的问题,从而提供一种装配方便、工艺简单的风力发电机主轴与齿轮箱的装配方法。
为了解决上述存在的技术问题,本发明采用下列技术方案:
一种风力发电机主轴与齿轮箱的装配方法,其特征在于其装配的步骤如下:
a、先将齿轮箱水平放置在齿轮箱放置架上,保证齿轮箱主轴轴孔基本水平,该齿轮箱上设置有一与主轴轴孔相对穿透齿轮箱的孔;b、将中空的主轴用吊带水平起吊,与齿轮箱连接处对准齿轮箱安装位;c、调整天车的高低和左右位置使主轴与齿轮箱轴轴孔同轴;d、用一根拉杆穿过主轴和齿轮箱轴心的孔,使拉杆的两端露出外面,在拉杆伸出主轴的一端垫上足够强度的固定挡件使之固定;e、所述拉杆伸出齿轮箱的另一端套有一可在水平方向伸缩的中空的千斤顶,并加一足够强度的固定件使千斤顶一端固定在拉杆上;f、驱动千斤顶,使千斤顶伸长,使拉杆在两端都被固定的情况下,千斤顶的伸长可将主轴拉进齿轮箱;g、将主轴拉进到齿轮箱后,使其装配到位,之后将主轴用锁紧环固定在齿轮箱上;h、将主轴用支架支撑好,去掉吊带;i、拆下固定件和千斤顶,将拉杆拉出主轴和齿轮箱,完成整个装配过程。
如上所述的风力发电机主轴与齿轮箱的装配方法,其特征在于在装上千斤顶并固定之后和驱动千斤顶将主轴拉进齿轮箱之前需再次调整主轴与齿轮箱的同轴度。
如上所述的风力发电机主轴与齿轮箱的装配方法,其特征在于所述将主轴去掉吊带后再度加紧锁紧环使之更牢固。
如上所述的风力发电机主轴与齿轮箱的装配方法,其特征在于所述固定挡件包括有第一平垫片、拉杆挡块和第一螺母,其依次设置在拉杆上。
如上所述的风力发电机主轴与齿轮箱的装配方法,其特征在于所述固定件包括有第二平垫片和第二螺母,其依次设置在拉杆上。
如上所述的风力发电机主轴与齿轮箱的装配方法,其特征在于拉杆的长度大于主轴、齿轮箱、千斤顶和固定挡件以及固定件的长度之和。
本发明为风力发电机主轴与齿轮箱装配的方法,它采用了平行装配的方法,其带来的积极效果如下:其一、装配过程减少了齿轮箱的翻转步骤,并减少了装配完成后的翻转,大大提高了工作效率。其次是减少了翻转也就增加了工作的安全性。其二、此方法还降低了工作高度,因此不需要工作平台,操作人员不需高空作业,对厂房的高度也相应降低。其三、操作人员在紧固锁紧环螺钉时也相对轻松,提高了操作人员的工作效率。其四、由于装配的主轴在装配端有倒角,主轴在装配时采用吊带起吊具有一定的弹性,并且采用了千斤顶来驱动,因此对主轴与齿轮箱的同轴度要求相对要低。其五、装配过程相对简单,操作人员很容易上手。其六、天车的使用时间上大大缩短,更有利于产品的批量生产。
【附图说明】
下面结合附图对本发明作详细的说明:
图1为本发明的装配示意图;
图2为本发明的除去主轴和齿轮箱的示意图;
图3为图2的A部放大图;
图4为图2的B部放大图。
【具体实施方式】
下面结合附图与具体实施方式对本发明作进一步详细描述:
一种风力发电机主轴与齿轮箱的装配方法,如图1、2所示,其装配的步骤如下:
a、先将齿轮箱1水平放置在齿轮箱放置架上,保证齿轮箱主轴轴孔基本水平,该齿轮箱1上设置有一与主轴轴孔相对穿透齿轮箱的孔,使后面的拉杆3可以穿过齿轮箱1的两端;b、将中空的主轴2用吊带水平起吊,与齿轮箱1连接处对准齿轮箱安装位;c、调整天车的高低和左右位置使主轴2与齿轮箱主轴轴孔的达到同轴;d、用一根拉杆3穿过主轴2和齿轮箱轴心的孔,由于主轴2与齿轮箱主轴的达到同轴,故拉杆3很容易穿过主轴2和齿轮箱轴心的孔,使拉杆3的两端露出外面,之后在拉杆3伸出主轴的一端c垫上足够强度的固定挡件4使之固定;e、所述拉杆3伸出齿轮箱1的另一端d套有一可在水平方面伸缩的中空的千斤顶5,并在千斤顶5的末端加一足够强度的固定件6使千斤顶5末端固定在拉杆3上,再次调整主轴2与齿轮箱1的同轴度,使其同轴度保证在1mm之内即可;f、之后驱动千斤顶5,使千斤顶5的本身长度增加,使拉杆3在两端都被固定的情况下,千斤顶5本身长度的增加可将主轴2缓慢拉进齿轮箱1;g、将主轴2拉进到齿轮箱1后,之后将主轴2用锁紧环固定在齿轮箱1上,即用扳手将锁紧环上的螺钉用其规定值一半的力矩上紧;h、将主轴2用支架支撑好,去掉吊带,再度加紧锁紧环上的螺钉使主轴2更牢固地固定在齿轮箱1上;i、拆下固定件4和中空千斤顶5,将拉杆3拉出主轴2和齿轮箱1,完成整个装配过程。
如图3、4所示,所述固定挡件4包括有第一平垫片41、拉杆挡块42和第一螺母43,本实施例中用¢30平垫片、M30的螺母依次设置在拉杆3上,并由螺母旋上固定。所述固定件6包括有第二平垫片61和第二螺母62,用¢30的平垫片、M30的螺母依次设置在拉杆3上并由螺母旋上固定。在齿轮箱1与千斤顶5之间设有一千斤顶隔套7,避免损坏千斤顶5。
所述拉杆3的长度大于主轴2、齿轮箱1、中空千斤顶5和固定挡件4以及固定件6的长度之和,使拉杆3能很好地实现操作。

Claims (6)

1.一种风力发电机主轴与齿轮箱的装配方法,其特征在于其装配的步骤如下:
a、先将齿轮箱(1)水平放置在齿轮箱放置架上,保证齿轮箱主轴轴孔基本水平,该齿轮箱(1)上设置有一与主轴轴孔相对穿透齿轮箱的孔;b、将中空的主轴(2)用吊带水平起吊,与齿轮箱(1)连接处对准齿轮箱安装位;c、调整天车的高低和左右位置使主轴(2)与齿轮箱轴轴孔同轴;d、用一根拉杆(3)穿过主轴(2)和齿轮箱轴心的孔,使拉杆(3)的两端露出外面,在拉杆(3)伸出主轴的一端(c)垫上足够强度的固定挡件(4)使之固定;e、所述拉杆(3)伸出齿轮箱(1)的另一端(d)套有一可在水平方向伸缩的中空的千斤顶(5),并加一足够强度的固定件(6)使千斤顶(5)一端固定在拉杆(3)上;f、驱动千斤顶(5),使千斤顶(5)伸长,使拉杆(3)在两端都被固定的情况下,千斤顶(5)的伸长可将主轴(2)拉进齿轮箱(1);g、将主轴(2)拉进到齿轮箱(1)后,使其装配到位,之后将主轴(2)用锁紧环固定在齿轮箱(1)上;h、将主轴(2)用支架支撑好,去掉吊带;i、拆下固定件(4)和千斤顶(5),将拉杆(3)拉出主轴(2)和齿轮箱(1),完成整个装配过程。
2.根据权利要求1所述的风力发电机主轴与齿轮箱的装配方法,其特征在于在装上千斤顶(5)并固定之后和驱动千斤顶(5)将主轴(2)拉进齿轮箱(1)之前需再次调整主轴(2)与齿轮箱(1)的同轴度。
3.根据权利要求2所述的风力发电机主轴与齿轮箱的装配方法,其特征在于所述将主轴(2)去掉吊带后再度加紧锁紧环使之更牢固。
4.根据权利要求1或2或3所述的风力发电机主轴与齿轮箱的装配方法,其特征在于所述固定挡件(4)包括有第一平垫片(41)、拉杆挡块(42)和第一螺母(43),其依次设置在拉杆(3)上。
5.根据权利要求1或2或3所述的风力发电机主轴与齿轮箱的装配方法,其特征在于所述固定件(6)包括有第二平垫片(61)和第二螺母(62),其依次设置在拉杆(3)上。
6.根据权利要求1或2或3所述的风力发电机主轴与齿轮箱的装配方法,其特征在于拉杆(3)的长度大于主轴(2)、齿轮箱(1)、千斤顶(5)和固定挡件(4)以及固定件(6)的长度之和。
CN200710032716XA 2007-12-21 2007-12-21 风力发电机主轴与齿轮箱的装配方法 Active CN101463804B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710032716XA CN101463804B (zh) 2007-12-21 2007-12-21 风力发电机主轴与齿轮箱的装配方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710032716XA CN101463804B (zh) 2007-12-21 2007-12-21 风力发电机主轴与齿轮箱的装配方法

Publications (2)

Publication Number Publication Date
CN101463804A CN101463804A (zh) 2009-06-24
CN101463804B true CN101463804B (zh) 2011-07-06

Family

ID=40804537

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710032716XA Active CN101463804B (zh) 2007-12-21 2007-12-21 风力发电机主轴与齿轮箱的装配方法

Country Status (1)

Country Link
CN (1) CN101463804B (zh)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7836595B1 (en) * 2009-09-25 2010-11-23 General Electric Company Method and system for disengaging a shrink coupling on a turbine generator
CN101947726B (zh) * 2010-10-13 2011-12-28 济南轨道交通装备有限责任公司 风力发电机齿轮箱拆卸方法及装置
CN102092637B (zh) * 2011-03-07 2013-03-27 南车株洲电力机车研究所有限公司 一种风力发电机组齿轮箱吊装方法
CN102729022B (zh) * 2012-06-15 2015-05-06 国电联合动力技术(连云港)有限公司 用于大型风力发电机组传动系统装配的装置及方法
CN102689174B (zh) * 2012-06-21 2014-05-07 济南轨道交通装备有限责任公司 一种用于更换风电齿轮箱高速轴的装置
CN103769833A (zh) * 2012-10-24 2014-05-07 北京南口轨道交通机械有限责任公司 风电齿轮箱转动装置
CN103042378B (zh) * 2013-01-07 2015-02-04 国电联合动力技术有限公司 一种风力发电机传动主轴与齿轮箱的装配工装及装配方法
CN106286148B (zh) * 2016-08-26 2018-09-18 中车株洲电力机车研究所有限公司 一种风电整机装配方法
CN107676228B (zh) * 2017-10-11 2019-04-02 中国船舶重工集团海装风电股份有限公司 一种风电齿轮箱与发电机对中安装的对中方法
CN109623639B (zh) * 2019-02-01 2021-04-16 七冶建设集团有限责任公司 一种超大型无齿磨机中空轴的安装方法
CN112049760B (zh) * 2020-09-10 2021-08-24 中国船舶重工集团海装风电股份有限公司 一种风力发电机组的齿轮箱与发电机的集成结构及塔上拆装方法
CN114290047B (zh) * 2021-10-13 2024-01-26 包钢集团机械设备制造有限公司 一种破碎机主轴的装配方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1291521A1 (en) * 2001-09-06 2003-03-12 Turbowinds N.V./S.A. Wind turbine nacelle with moving crane
CN2739384Y (zh) * 2004-10-12 2005-11-09 南京高速齿轮制造有限公司 用于风力发电机的增速齿轮箱
CN2835640Y (zh) * 2005-11-16 2006-11-08 郑州机械研究所 风电立式中空轴增速齿轮箱及其装置

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1291521A1 (en) * 2001-09-06 2003-03-12 Turbowinds N.V./S.A. Wind turbine nacelle with moving crane
CN2739384Y (zh) * 2004-10-12 2005-11-09 南京高速齿轮制造有限公司 用于风力发电机的增速齿轮箱
CN2835640Y (zh) * 2005-11-16 2006-11-08 郑州机械研究所 风电立式中空轴增速齿轮箱及其装置

Also Published As

Publication number Publication date
CN101463804A (zh) 2009-06-24

Similar Documents

Publication Publication Date Title
CN101463804B (zh) 风力发电机主轴与齿轮箱的装配方法
CN1252386C (zh) 水平轴型风力涡轮机及其建造方法
CN101413291B (zh) 索穹顶塔架提升索杆累积安装方法
CN201217616Y (zh) 多功能全液压门架提升装置
EP2937561A1 (en) Support arrangement of a wind turbine tower
CN102092637B (zh) 一种风力发电机组齿轮箱吊装方法
CN201067903Y (zh) 发动机、变速箱维修翻转架
CN203128000U (zh) 用于直驱式风力发电机组的吊装设备
CN111661746B (zh) 吊具
CN219885503U (zh) 水轮发电机转子吊装自动插板装置
US20100139069A1 (en) Method For Repairing A Generator Frame
CN107500129A (zh) 一种风电轮毂用吊车
CN201312084Y (zh) 地线提升器
CN207061738U (zh) 一种防侧倒的升降辅助装置
CN216334610U (zh) 一种铝框过渡传送装置
CN109244946A (zh) 一种电力综合检修装置
CN112249874B (zh) 一种陆上风力发电机组分体式吊装方法
CN211029853U (zh) 一种用于拆装水轮机转轮联轴螺栓的装置
CN1987020B (zh) 附着爬升式高耸桅杆结构安装方法及施工装置
CN213899185U (zh) 一种风力发电机组吊绳用支撑架
CN217904310U (zh) 一种柔性光伏支架
CN219136109U (zh) 一种用于大型风力发电机组安装的吊装装置
CN215592324U (zh) 大型水轮发电机组联轴螺栓拉伸器倒装专用装置
CN218968624U (zh) 一种专用于风电阶梯型混凝土塔筒的管型母线顶部吊具
CN211569867U (zh) 风电机组变桨轴承吊具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUANGDONG MINGYANG WIND POWER GROUP CO., LTD.

Free format text: FORMER NAME: GUANGDONG MINGYANG WIND + ELECTRICITY TECHNOLOGY CO., LTD.

CP03 Change of name, title or address

Address after: 528400 five star village, Torch Development Zone, Guangdong, Zhongshan

Patentee after: Guangdong Mingyang Wind Power Group Co., Ltd.

Address before: 528400 Zhongshan Torch Development Zone, Guangdong

Patentee before: Guangdong Mingyang Wind Electrical Technology Co., Ltd.

EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20090624

Assignee: Jilin Mingyang Wind Power Technology Co., Ltd.

Assignor: Guangdong Mingyang Wind Power Group Co., Ltd.

Contract record no.: 2014220000055

Denomination of invention: Assembly method for principal shaft and gearbox of large aerogenerator

Granted publication date: 20110706

License type: Exclusive License

Record date: 20141225

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 528437 Torch Road, Torch Development Zone, Guangdong, Zhongshan, No. 22

Patentee after: Ming Yang wisdom Energy Group AG

Address before: 528400 five star village, Torch Development Zone, Guangdong, Zhongshan

Patentee before: Guangdong Mingyang Wind Power Group Co., Ltd.