CN101412489A - 一种大吨位缆索起重机索鞍横移方法 - Google Patents

一种大吨位缆索起重机索鞍横移方法 Download PDF

Info

Publication number
CN101412489A
CN101412489A CNA2008101476217A CN200810147621A CN101412489A CN 101412489 A CN101412489 A CN 101412489A CN A2008101476217 A CNA2008101476217 A CN A2008101476217A CN 200810147621 A CN200810147621 A CN 200810147621A CN 101412489 A CN101412489 A CN 101412489A
Authority
CN
China
Prior art keywords
cable saddle
cable
traversing
saddle
large tonnage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CNA2008101476217A
Other languages
English (en)
Inventor
林用祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Erju Co Ltd
China Railway Erju 5th Engineering Co Ltd
Original Assignee
China Railway Erju Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CNA2008101476217A priority Critical patent/CN101412489A/zh
Publication of CN101412489A publication Critical patent/CN101412489A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明适用于桥梁施工领域,提供了一种大吨位缆索起重机索鞍横移方法,具体为采用液压系统控制油缸步进顶推索鞍的方式实现索鞍横移。本发明通过采用液压顶推的方式使索鞍步进横移,最终可以实现索鞍长/短距离的横移,相比于现有的横移方法,这种方式可以使索鞍横移的距离更长、过程更高效、到位更精确,且操作简单。

Description

一种大吨位缆索起重机索鞍横移方法
技术领域
本发明属于桥梁施工领域,尤其涉及一种大吨位缆索起重机索鞍横移方法。
背景技术
固定缆索起重机在建筑施工,尤其是桥梁施工中,应用十分广泛,目前,桥梁施工中,固定式缆索起重机吊装重量均较小,仅部分项目需进行横移施工,且横移距离均较小。传统施工中,缆索横移大多是采用卷扬机牵引索鞍小距离横移,其次是采用索塔整体横移。
但对于起重构件,尤其是横向距离随高度变化较大的起重构件,在纵桥向和横桥向都需要长距离移动吊装作业下,现有的索鞍横移方法无论在横移距离上还是在横移效率上都无法满足施工的需要。
发明内容
本发明的目的在于:提供一种大吨位缆索起重机索鞍横移方法,旨在解决现有的索鞍横移技术横移距离较短且横移操作效率低的问题。
本发明的目的是这样实现的:
一种大吨位缆索起重机索鞍横移方法,采用液压系统控制油缸步进顶推索鞍的方式实现索鞍横移。
所述方法具体包括下述步骤:
将液压油缸的顶推支座通过固定连接装置固定安装在塔顶横梁上的轨道上,并拆除索鞍底座与轨道间的固定连接装置;
操作液压系统的操作阀,控制所述轨道上的液压油缸的活塞杆顶推索鞍前移预定距离,再将索鞍底部通过固定连接装置固定安装在轨道上;
拆除顶推支座与轨道间的固定连接装置,操作液压系统的操作阀将液压油缸的缸体收回;
循环操作以上步骤至索鞍横移至目标距离。
所述预定距离小于或等于一米。
所述液压油缸共有两支,分别沿轨道方向安装在前后轨道上,并在所述液压系统的控制下同步顶推或收回。
所述固定连接装置为高强螺栓。
所述索鞍最大顶推位移量为34.6米。
本发明的突出优点是:本发明通过采用液压顶推的方式使索鞍步进横移,最终可以实现索鞍长/短距离的横移,相比于现有的横移方法,这种方式可以使索鞍横移的距离更长、过程更高效、到位更精确,且操作简单。
附图说明
图1是本发明实施例提供的大吨位缆索起重机索鞍横移第一行程的步骤图。
具体实施方式
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
塔顶索鞍采用横向移动式,以满足钢箱拱、钢箱梁节段安装位置的变化需要。索道在吊装下一节段前,将索鞍与塔顶横梁连接的螺栓拆除,然后采用轨道上安装的两支液压油缸同步顶推实现索鞍移动到位后,用螺栓将索鞍底座横梁与塔顶横梁连接。
索鞍安装在索塔顶部轨道梁上,索鞍底部的分配梁直接与塔架顶部的工字形滑移横梁连接。每个索鞍均能在双油缸同步顶推的作用下沿塔顶轨道横桥向移动,索鞍移动带动主承重索移动实现吊装位置的变化,索鞍横移就位后安装锁定螺栓固定。横移极限位置时的钢丝绳偏角最大为4.7°,索鞍最大顶推位移量为34.6米。
图1a、1b、1c分别示出了本发明实施例提供的大吨位缆索起重机索鞍横移第一行程的各步骤,详述如下:
步骤一(见图1a):将液压系统6及两支液压油缸3安装就位,然后安装油缸顶推支座4,并安装顶推支座4与塔顶横梁上的轨道1的连接高强螺栓5,再拆除索鞍2底座与轨道1的连接高强螺栓8;
步骤二(见图1b):通过操作液压系统6的操作阀,使前后轨道上1的两支油缸活塞杆7同步顶推索鞍2前移预定距离(一般是一米),索鞍2第一行程顶推就位后,安装索鞍2底座与轨道1的连接高强螺栓8;
步骤三(见图1c):索鞍螺栓8安装好后,拆除顶推支座4与轨道1的连接高强螺栓5,然后操作液压系统6的操作阀,将油缸缸体3收回,再安装顶推支座4与轨道1的连接高强螺栓5,准备进行索鞍2下一推移行程的循环操作,通过油缸顶推支座4沿轨道1方向的不断移进,即可以实现索鞍2的步进横移。
在本发明实施例中,索鞍2的每次行程最多只能步进一米。例如,当要使索鞍2横移20米时,则只需将上述几个步骤循环操作20次即可。
本发明实施例通过采用液压顶推的方式使索鞍步进横移,最终可以实现索鞍长/短距离的横移,相比于现有的横移方法,这种方式可以使索鞍横移的距离更长、过程更高效、到位更精确,且操作简单。
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。

Claims (6)

1、一种大吨位缆索起重机索鞍横移方法,其特征在于,采用液压系统控制油缸步进顶推索鞍的方式实现索鞍横移。
2、如权利要求1所述的大吨位缆索起重机索鞍横移方法,其特征在于,所述方法具体包括下述步骤:
将液压油缸的顶推支座通过固定连接装置固定安装在塔顶横梁上的轨道上,并拆除索鞍底座与轨道间的固定连接装置;
操作液压系统的操作阀,控制所述轨道上的液压油缸的活塞杆顶推索鞍前移预定距离,再将索鞍底部通过固定连接装置固定安装在轨道上;
拆除顶推支座与轨道间的固定连接装置,操作液压系统的操作阀将液压油缸的缸体收回;
循环操作以上步骤至索鞍横移至目标距离。
3、如权利要求1所述的大吨位缆索起重机索鞍横移方法,其特征在于,所述预定距离小于或等于一米。
4、如权利要求1所述的大吨位缆索起重机索鞍横移方法,其特征在于,所述液压油缸共有两支,分别沿轨道方向安装在前后轨道上,并在所述液压系统的控制下同步顶推或收回。
5、如权利要求1所述的大吨位缆索起重机索鞍横移方法,其特征在于,所述固定连接装置为高强螺栓。
6、如权利要求1所述的大吨位缆索起重机索鞍横移方法,其特征在于,所述索鞍最大顶推位移量为34.6米。
CNA2008101476217A 2008-11-20 2008-11-20 一种大吨位缆索起重机索鞍横移方法 Pending CN101412489A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNA2008101476217A CN101412489A (zh) 2008-11-20 2008-11-20 一种大吨位缆索起重机索鞍横移方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNA2008101476217A CN101412489A (zh) 2008-11-20 2008-11-20 一种大吨位缆索起重机索鞍横移方法

Publications (1)

Publication Number Publication Date
CN101412489A true CN101412489A (zh) 2009-04-22

Family

ID=40593266

Family Applications (1)

Application Number Title Priority Date Filing Date
CNA2008101476217A Pending CN101412489A (zh) 2008-11-20 2008-11-20 一种大吨位缆索起重机索鞍横移方法

Country Status (1)

Country Link
CN (1) CN101412489A (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243649A (zh) * 2013-05-21 2013-08-14 中交四航局第一工程有限公司 一种索鞍快速安装、定位的系统及方法
CN103276671A (zh) * 2013-06-17 2013-09-04 湖南省建筑工程集团总公司 大吨位缆索起重机转向索鞍
CN106283964A (zh) * 2016-08-31 2017-01-04 武汉冶钢结构有限责任公司 一种大型构件平移装置及方法
CN107311048A (zh) * 2017-08-30 2017-11-03 广西路桥工程集团有限公司 缆索吊机
CN107344697A (zh) * 2017-08-30 2017-11-14 广西路桥工程集团有限公司 缆索起吊装置
CN110182682A (zh) * 2019-06-03 2019-08-30 中铁大桥局集团有限公司 一种用于大节段钢桁梁吊装的吊具
CN111101447A (zh) * 2020-01-02 2020-05-05 中交第二航务工程局有限公司 用于索股入鞍设备的精度控制系统
CN112609578A (zh) * 2020-11-24 2021-04-06 中铁二局集团有限公司 一种斜拉桥桥塔墩顶段钢桁梁的安装方法

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103243649A (zh) * 2013-05-21 2013-08-14 中交四航局第一工程有限公司 一种索鞍快速安装、定位的系统及方法
CN103276671A (zh) * 2013-06-17 2013-09-04 湖南省建筑工程集团总公司 大吨位缆索起重机转向索鞍
CN103276671B (zh) * 2013-06-17 2014-08-06 湖南省建筑工程集团总公司 大吨位缆索起重机转向索鞍
CN106283964A (zh) * 2016-08-31 2017-01-04 武汉冶钢结构有限责任公司 一种大型构件平移装置及方法
CN106283964B (zh) * 2016-08-31 2018-03-02 武汉一冶钢结构有限责任公司 一种大型构件平移装置及方法
CN107311048A (zh) * 2017-08-30 2017-11-03 广西路桥工程集团有限公司 缆索吊机
CN107344697A (zh) * 2017-08-30 2017-11-14 广西路桥工程集团有限公司 缆索起吊装置
CN110182682A (zh) * 2019-06-03 2019-08-30 中铁大桥局集团有限公司 一种用于大节段钢桁梁吊装的吊具
CN111101447A (zh) * 2020-01-02 2020-05-05 中交第二航务工程局有限公司 用于索股入鞍设备的精度控制系统
CN112609578A (zh) * 2020-11-24 2021-04-06 中铁二局集团有限公司 一种斜拉桥桥塔墩顶段钢桁梁的安装方法

Similar Documents

Publication Publication Date Title
CN101412489A (zh) 一种大吨位缆索起重机索鞍横移方法
CN210507167U (zh) 一种过混凝土连续梁免拆装移动模架
CN109653105B (zh) 箱梁桥悬臂施工挂篮主桁系统及其使用方法
CN201943007U (zh) 活动支架不变幅架梁吊机
CN201634330U (zh) 轻型双梁桥式起重机
CN202945003U (zh) 一种安装大型设备的门式起重机
CN201367241Y (zh) 钢卷步进梁输送机
CN101602469B (zh) 曲张式单轨吊
CN115818472A (zh) 一种起重机用配重块安装固定装置
CN107244534A (zh) 预制箱涵运输车
CN212251443U (zh) 旧厂房除尘管道改造安装专用管道移动吊装装置
CN210366808U (zh) 一种用于轨道行走的升降拆除装置
CN201002930Y (zh) 电动履带起重机
CN102372228B (zh) 大跨度吊车梁平移安装方法
CN201473253U (zh) 移动式轻型液压吊车
CN208183540U (zh) 钢箱梁安装用桥面吊机
CN212954051U (zh) 一种斜拉桥桥面吊机液压提升及调位机构
CN201849911U (zh) 重型设备运输装置
CN108821127A (zh) 一种洞内拆卸起吊敞开式tbm的装置及其方法
CN102865086A (zh) 全液压针梁钢模台车
CN211470149U (zh) 顶升式客滚桥驱动装置
CN102153017A (zh) 一种矿井用桥式起重机小车
CN208120639U (zh) 盾构机双梁管片连接提升装置
CN201292510Y (zh) 分段顶推法架设悬索桥主桁所采用的重物滚移装置
CN114148222A (zh) 大型货场集装箱柔性移动接触网及操作方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090626

Address after: Postal code 10, Ma Jia Huayuan Road, Sichuan, Chengdu: 610032

Applicant after: China Railway two Bureau Co., Ltd.

Co-applicant after: China Railway Erju 5th Engineering Co., Ltd.

Address before: Postal code 10, Ma Jia Huayuan Road, Sichuan, Chengdu: 610032

Applicant before: China Railway Erju Co., Ltd.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20090422