CN101408028A - Steel float tank deposition plan position control method - Google Patents

Steel float tank deposition plan position control method Download PDF

Info

Publication number
CN101408028A
CN101408028A CNA2007100469480A CN200710046948A CN101408028A CN 101408028 A CN101408028 A CN 101408028A CN A2007100469480 A CNA2007100469480 A CN A2007100469480A CN 200710046948 A CN200710046948 A CN 200710046948A CN 101408028 A CN101408028 A CN 101408028A
Authority
CN
China
Prior art keywords
steel
buoyancy tank
spacing
spacing pier
position control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007100469480A
Other languages
Chinese (zh)
Other versions
CN101408028B (en
Inventor
李天恩
李建军
诸荣海
周慧杰
朱立新
汪涛
褚悍俊
徐晓航
衣旭东
周国海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No2 Engineering Co ltd Of Cccc Third Harbor Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
Original Assignee
CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd filed Critical CHINA COMMUNICATIONS THIRD NAVIGATIONAL BUREAU 2ND ENGINEERING Co Ltd
Priority to CN2007100469480A priority Critical patent/CN101408028B/en
Publication of CN101408028A publication Critical patent/CN101408028A/en
Application granted granted Critical
Publication of CN101408028B publication Critical patent/CN101408028B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a plane position control method for the sinking and setting of a steel buoyant box in a shipbuilding base so as to solve the shortcomings of low locating precision, inaccuracy, complex procedures and the consumption of a large amount of time and manpower and materials during sinking and setting the existing steel buoyant box. The method comprises the following steps: 1. a plurality of limiting piers are arranged at the sinking and setting position of the steel buoyant box; 2. the steel buoyant box is leveled; 3. the steel buoyant box is fixed by a bollard and a windlass which are arranged on the limiting piers, and the steel buoyant box is hauled to a pre-sinking posting under the hauling of a tug boat; and 4. water is irrigated to the steel buoyant box by a water inlet valve arranged on the steel buoyant box so as to position the steel buoyant box among all the limiting piers to gradually reach the sinking and setting position. In the plane position control method for the sinking and setting of the steel buoyant box, the plane positioning of the sinking and setting of the steel buoyant box is controlled by relying on the reference substance, namely, the limiting piers, and after the position of the steel buoyant box is precisely locked, the water irrigation sinking is reliably guaranteed.

Description

Steel float tank deposition plan position control method
Technical field
The present invention relates to specifically, relate to a kind of steel float tank deposition plan position control method opening wide waters steel float deposing technical field.
Background technology
2004, successful sinking 99m in Suzhou River river mouth sluice engineering * 14m * 6.35m weight reached 8201t steel concrete gate floor, used for reference Suzhou River river mouth sluice engineering gate floor sinking control technology, was applied to external brake Shoudu Iron and Steel Co float deposing technological development research.Developed the pile sinking engineering that " maritime works's Engineering GPS out boxing pile positioning system " is successfully applied to the Donghai Bridge engineering in 2002, developing " the mounting technique research under water of entrance of Changjiang River deepwater channel regulation the second stage of the project porous hollow square " in 2003 again succeeds, these two GPS navigation systems are applied to engineering practice, obtained ideal effect, used for reference this technical thought and develop research.
The outer lock head of ship lock adopts the type gravity mixed bed of subaqueous construction, sinking of monolithic buoyancy tank puts in place and forms the lock head structure, comprise hollow quoin, gate slot, Men Ku and ancillary service, wherein lock head cross pulling door track is established in gate slot and door reservoir area, time application of this kinds of structures domestic first also belongs to first Application in soft foundation formation pile foundation and type gravity mixed bed.Adopted cofferdam water retainings in the soft foundation similar engineering, drawing water forms dry application worker environment, monolithic reinforced concrete structure more in the past.
Construction mixes bedding owing to need under water, accurate sinking steel buoyancy tank, and draw water construction gate pier, gate slot structure, downing track of subdivision in the steel buoyancy tank then, the engineering structures novelty, technology advanced person is a brand-new problem.The monolithic buoyancy tank is applied to the lock head engineering, does not find similar engineering structure and construction technology data at present both at home and abroad as yet.
Ship lock comprises monomers such as outer lock head, pump house, interior lock head and lock chamber.Outer lock head is the ship lock key project, attitude after the sinking has determined the plane figure of whole ship lock and the installation site of steel gate, the disposable sinking of steel buoyancy tank is subdivision construction gate pier to the design altitude, the mixing bedding construction that steel float deposing is related, the haul of steel buoyancy tank, sinking technology are key technologies wherein.
And the control of steel float deposing process median-plane location is an important step, and existing steel float deposing positioning process precision is low, inaccurate, and operation is numerous and diverse, expends a large amount of time and manpower and materials.
Summary of the invention
The purpose of this invention is to provide and a kind ofly opening wide the plan-position control method of waters steel float deposing, positioning accuracy is low, inaccurate when solving existing steel float deposing, and operation is numerous and diverse, expends a large amount of time and manpower and materials.
Technical problem solved by the invention can realize by the following technical solutions:
A kind of steel float tank deposition plan position control method is characterized in that, comprises the steps:
1. a plurality of spacing piers are set in the steel float deposing position;
2. with the leveling of steel buoyancy tank;
3. by being arranged on fixedly steel buoyancy tank of mooring dolphin on the spacing pier and hoist engine, and under the traction of tugboat, the steel buoyancy tank is dragged to the preliminary sedimentation position;
4. in the steel buoyancy tank, pour water and make its carry between each spacing pier by being arranged on inlet valve on the steel buoyancy tank, progressively arrive the sinking position.
In the step 1 of the present invention, described spacing pier is four, spacing pier I is arranged on steel buoyancy tank width one side in the pump house, spacing pier II is arranged on steel buoyancy tank length one side in the lock chamber, it is outer and parallel with spacing pier II that spacing pier III is arranged on lock chamber, spacing pier IV is arranged in the hoist house and is relative with spacing pier I, all reserves spacing between each spacing pier and the steel buoyancy tank sideline.
In order to strengthen the intensity of spacing pier, spacing pier I, spacing pier II and spacing pier III all with steel pipe pile as the basis, the steel pipe pile of spacing pier I, spacing pier II and spacing pier III respectively is four, spacing pier IV is based on hoist house, its pile foundation is five steel pipe piles.
Described spacing pier I, spacing pier II and spacing pier III superstructure are by C30 concrete one-time cast-forming, and spacing pier IV is according to hoist house foundation structure needs, casting complete at twice.
Each spacing pier pier shaft end face is provided with fixed screw, to fixedly install hoist engine and equipment such as mooring dolphin thereon.
Described steel buoyancy tank can be divided into a plurality of identical or different separations according to different needs, on each cabin lattice a plurality of inlet valves can be set, preferably 14 inlet valves.
In the step 2 of the present invention, the leveling of steel buoyancy tank adopts the mode pour water and to be aided with concrete piece counterweight to realize.
In the step 3 of the present invention, the steel buoyancy tank is installed locating part at spacing pier II and the contiguous steel buoyancy tank of spacing pier III side when the position, and the 30mm allowance is reserved on the beam limit; Spacing pier I faces steel buoyancy tank side spacing crossbeam is installed, and cross beam edges and buoyancy tank limit are reserved with the allowance of 20mm.
In the step 4 of the present invention, the flow of inlet water of each inlet valve is 500m 3/ h, the water level that finishes in the steel buoyancy tank of back of pouring water is at least 3.0m.
Steel buoyancy tank carry time is preceding 2 hours of flood slack, and sinking time is after the flood slack 1 hour.
Among the present invention, after the steel buoyancy tank sinks,, need the packed sand of symmetrical backfill around the steel buoyancy tank for preventing the displacement of steel buoyancy tank.
After backfill puts in place around the steel buoyancy tank, promptly dismountable spacing pier I, spacing pier II and spacing pier III.
Steel float tank deposition plan position control method of the present invention, the plane positioning of steel float deposing rely on the spacing pier control of object of reference, pour water and sink to having obtained reliable assurance after accurately being locked in steel buoyancy tank position.The steel buoyancy tank is in place to be provided with certain size more than needed, and protection pump house pile foundation is avoided being collided in steel buoyancy tank carry process, for the adjustment of steel buoyancy tank carry provides the space.After the steel buoyancy tank is in place, the rigidity locating part is installed on spacing pier, the above position of the rigidity locating part control steel buoyancy tank water surface guarantees that the steel buoyancy tank accurately locatees.
Description of drawings
Fig. 1 is a spacing pier position view of the present invention.
Fig. 2 is the spacing pier structure schematic diagram of the present invention.
Fig. 3 is a steel buoyancy tank subdivision schematic diagram of the present invention.
Fig. 4 is the spacing pier of steel buoyancy tank of the present invention location schematic diagram.
Fig. 5 is the steel buoyancy tank of the present invention time diagram in place that sinks.
Fig. 6 fills out schematic diagram for adding around the steel buoyancy tank of the present invention back in place.
Specific implementation method
For technological means, creation characteristic that the present invention is realized, achieve the goal and effect is easy to understand, below in conjunction with concrete diagram, further set forth the present invention.
A kind of steel float tank deposition plan position control method, a plurality of spacing piers at first are set in the steel float deposing position, the layout of position limiting pile as shown in Figure 1, spacing pier is four, spacing pier I is arranged on steel buoyancy tank width one side in the pump house, spacing pier II is arranged on steel buoyancy tank length one side in the lock chamber, it is outer and parallel with spacing pier II that spacing pier III is arranged on lock chamber, spacing pier IV is arranged in the hoist house and is relative with spacing pier I, it is 15cm that steel buoyancy tank design sideline is left in spacing pier II and spacing pier III sideline, and it is 50cm that spacing pier I leaves in the sideline steel buoyancy tank.
Referring to Fig. 2, each spacing pier is divided into the steel pipe pile 3 of 4 Ф 800mm * δ 14mm, the long 35m of stake, and pier is of a size of 4.6 * 4.6 * 1.5m, and structural elevation is+3~+ 4.5m; Wherein the spacing pier in west side utilizes the hoist house basis, and pile foundation is 5 Ф 800 * δ 14mm steel pipe piles 3, and key dimension is 10 * 13 * 2m, and structural elevation is+4.3~+ 6.3m.
Spacing pier also has protection pump house pile foundation safety effect concurrently except that using for steel buoyancy tank location.The stake of spacing pier and the stake of pump house and hoist house construction simultaneously, the structure construction of spacing pier is interspersed in bedding construction period, structure C 30 concrete are by base agitator supply, and the olive car is transported on the embankment of works area, reuse suspension bucket and are transported to construction location and build for small-sized waterborne.Spacing pier adopts one-time-concreting to the top, than the needs of garage basis according to structure, divides secondary to build and can finish.Spacing pier pier shaft end face is embedded with set bolt (not signal), is used for fixing facilities such as hoist engine and mooring dolphin.
Referring to Fig. 3, the steel buoyancy tank can be divided into a plurality of identical or different separations according to different needs, and what adopt in the present embodiment is different separations, is not limitation of the present invention.The height of steel buoyancy tank from base plate to designing requirement, Cast-in-place concrete comprises gate floor 6750m 3With a spot of lock wall pier concrete 945m 3, steel work deadweight 3200t, thus whole steel buoyancy tank gross weight at 19465t, force-bearing situation such as following table before the base plate counterweigh.
Stressed dress condition before the steel buoyancy tank counterweight
Separation A B C D E Add up to
Separation length (m) 16.5 40 21 21 18 116.5
Concrete side amount (m 3) 1011 2915 1358 1120 1210 7694
Concrete weight (t) 2426 6996 3259 2880 2904 18466
Steel work heavy (t) 142 343 180 180 155 1000
Gross weight (t) 2568 7339 3439 3060 3059 19465
Average load (t/m) 156 183 164 146 170
Whole buoyancy tank gross weight is about 19500t, and this moment, Mean Draught was about 8.2m.But the steel buoyancy tank is in non-equilibrium state at this moment, thereby the steel buoyancy tank need take with irrigation method and be aided with concrete piece counterweight to realize leveling that leveling utilizes the 9# harbour in downstream, job site.
Steel buoyancy tank gross weight is about 21218t after the leveling, and sink when steel buoyancy tank draft is 8.8m steel buoyancy tank selection flood slack this moment, high water mark water level 3.5m, and the end absolute altitude before the steel buoyancy tank sinks is-5.7m; Sink to the discrepancy in elevation that bedding top-11.70m absolute altitude has 6m apart from the steel buoyancy tank, for making its sinking about 14500m of total amount that need pour water 3
Referring to Fig. 4, under the traction of tugboat, enter construction area after the leveling of steel buoyancy tank, divide fix the steel buoyancy tank at 4 by mooring dolphin on the spacing pier and hoist engine, tugboat 1 leaves then; Start hoist engine, slow carry under the escorting of tugboat 2.During near the position, spacing pier II and spacing pier III close on steel buoyancy tank side wide 12cm locating part are installed at the steel buoyancy tank, and beam limit and steel buoyancy tank limit are reserved with the allowance of 30mm; Face steel buoyancy tank side at spacing pier I spacing crossbeam is installed, the wide 47cm of crossbeam, cross beam edges and buoyancy tank limit are reserved with the allowance of 20mm.
At steel buoyancy tank outer wall, 14 inlet valves are set, valve is opened and closed by manually-operated, and each valve flow of inlet water is controlled at 500m 3About/h.After the steel buoyancy tank carry, after required precision is satisfied in check, the sinking of can pouring water.Manually start water intaking valve by the predetermined speed of pouring water, the steel buoyancy tank is steadily sunk down on the bedding.At last, closed shutter makes to keep in the steel buoyancy tank water level to+3.0m, in case steel buoyancy tank come-up.
Referring to Fig. 5, steel float deposing is chosen in the flood slack period, and beginning carry time is preceding 2 hours of flood slack, rule of thumb, in 2 hours the steel buoyancy tank accurately carry between spacing pier, utilize the sinking that begins to pour water of slack tide position then, these can guarantee steel buoyancy tank installation accuracy.
Referring to Fig. 6, after the steel buoyancy tank sinks,, need the packed sand of symmetrical backfill around the steel buoyancy tank for preventing the displacement of steel buoyancy tank.Make an appointment with extremely-the 8.8m absolute altitude in the first backfill steel buoyancy tank of the needs outside during backfill, is bank side and upstream and downstream then, and the backfill absolute altitude is-7.3m.
After backfill put in place around the steel buoyancy tank, promptly dismountable spacing pier I, spacing pier II and spacing pier III by small-sized crane ship waterborne, were equipped with special facility and remove spacing pier, were equipped with electrically operated hammer by crane ship then and extracted spacing pier steel pipe pile 3 recovery.
More than show and described basic principle of the present invention and principal character and advantage of the present invention.The technician of the industry should understand; the present invention is not restricted to the described embodiments; that describes in the foregoing description and the manual just illustrates principle of the present invention; under the prerequisite that does not break away from the principle of the invention and scope; the present invention also has various changes and modifications, and these changes and improvements all fall in the claimed scope of the invention.The claimed scope of the present invention is defined by appending claims and equivalent thereof.

Claims (17)

1. a steel float tank deposition plan position control method is characterized in that, comprises the steps:
1]. a plurality of spacing piers are set in the steel float deposing position;
2]. with the leveling of steel buoyancy tank;
3]. fix the steel buoyancy tank by the mooring dolphin and the hoist engine that are arranged on the spacing pier, and under the dragging of tugboat, the steel buoyancy tank is dragged to the preliminary sedimentation position;
4]. in the steel buoyancy tank, pour water and make its carry between each spacing pier by being arranged on inlet valve on the steel buoyancy tank, progressively arrive the sinking position.
2. steel float tank deposition plan position control method as claimed in claim 1, it is characterized in that: in the step 1, described spacing pier is four, spacing pier I is arranged on steel buoyancy tank width one side in the pump house, spacing pier II is arranged on steel buoyancy tank length one side in the lock chamber, it is outer and parallel with spacing pier II that spacing pier III is arranged on lock chamber, and spacing pier IV is arranged in the hoist house and is relative with spacing pier I, is equipped with spacing between each spacing pier and the steel buoyancy tank sideline.
3. steel float tank deposition plan position control method as claimed in claim 2 is characterized in that: described spacing pier I, spacing pier II and spacing pier III all with steel pipe pile as the basis, the steel pipe pile of spacing pier I, spacing pier II and spacing pier III is four.
4. steel float tank deposition plan position control method as claimed in claim 2 is characterized in that: spacing pier IV is based on hoist house, and its pile foundation is five steel pipe piles.
5. as claim 2 and 3 described steel float tank deposition plan position control methods, it is characterized in that: described spacing pier I, spacing pier II and spacing pier III adopt structure C 30 concrete one-time cast-formings.
6. as claim 2 and 4 described steel float tank deposition plan position control methods, it is characterized in that: described spacing pier IV is casting complete at twice.
7. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: described spacing pier pier shaft end face is provided with the fixed screw of equipment such as wire rope hoist and mooring dolphin.
8. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: described steel buoyancy tank is divided into a plurality of identical lattice cabins.
9. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: described steel buoyancy tank is divided into a plurality of different lattice cabins.
10. steel float tank deposition plan position control method as claimed in claim 8 or 9 is characterized in that: on the lattice of described cabin a plurality of inlet valves are set.
11. steel float tank deposition plan position control method is characterized in that: 14 inlet valves are set on the lattice of described cabin as claimed in claim 8 or 9.
12. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: in the step 2, the steel buoyancy tank uses the mode pour water and to be aided with the concrete piece to carry out leveling.
13. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: in the step 3, the steel buoyancy tank is installed locating part at spacing pier II and the contiguous steel buoyancy tank of spacing pier III side when the position, and the 3cm allowance is reserved on the beam limit; Spacing pier I faces steel buoyancy tank side spacing crossbeam is installed, and cross beam edges and buoyancy tank limit are reserved with the allowance of 20mm.
14. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: in the step 4, the flow of inlet water of each inlet valve is 500m 3/ h, the water level that finishes in the steel buoyancy tank of back of pouring water is at least 3.0m.
15. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: in the step 4, steel buoyancy tank carry time is preceding 2 hours of flood slack, and sinking time is after the flood slack 1 hour.
16. steel float tank deposition plan position control method as claimed in claim 1 is characterized in that: after the steel buoyancy tank sinks, the packed sand of symmetrical backfill around the steel buoyancy tank.
17. steel float tank deposition plan position control method as claimed in claim 16 is characterized in that: after backfill puts in place around the steel buoyancy tank, remove spacing pier I, spacing pier II and spacing pier III.
CN2007100469480A 2007-10-11 2007-10-11 Steel float tank deposition plan position control method Expired - Fee Related CN101408028B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007100469480A CN101408028B (en) 2007-10-11 2007-10-11 Steel float tank deposition plan position control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007100469480A CN101408028B (en) 2007-10-11 2007-10-11 Steel float tank deposition plan position control method

Publications (2)

Publication Number Publication Date
CN101408028A true CN101408028A (en) 2009-04-15
CN101408028B CN101408028B (en) 2010-06-16

Family

ID=40571218

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007100469480A Expired - Fee Related CN101408028B (en) 2007-10-11 2007-10-11 Steel float tank deposition plan position control method

Country Status (1)

Country Link
CN (1) CN101408028B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106609506A (en) * 2015-10-23 2017-05-03 天津市北斗海洋信息科技有限公司 Method for sea reclamation by using caissons
CN110331701A (en) * 2019-06-13 2019-10-15 中交第三航务工程勘察设计院有限公司 Integral prefabricated type sluice chamber structure and its construction method on a kind of soft soil foundation

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5439321A (en) * 1993-03-11 1995-08-08 Conoco Inc. Interruptive mobile production system
CN1173572A (en) * 1996-08-12 1998-02-18 姚慧根 Construction method of caisson cut-off dam

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106609506A (en) * 2015-10-23 2017-05-03 天津市北斗海洋信息科技有限公司 Method for sea reclamation by using caissons
CN110331701A (en) * 2019-06-13 2019-10-15 中交第三航务工程勘察设计院有限公司 Integral prefabricated type sluice chamber structure and its construction method on a kind of soft soil foundation

Also Published As

Publication number Publication date
CN101408028B (en) 2010-06-16

Similar Documents

Publication Publication Date Title
Lunniss et al. Immersed tunnels
CN100419164C (en) Method for moving large-scale heavy member to launch and float on water, and member mounting method
CN101408027B (en) Construction method of large-scale steel float tank on soft soil foundation
CN102561371B (en) Steel caisson enclosure structure at island-tunnel combination part and construction method thereof
CN102979039A (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN105780750B (en) Cross three-dimensional ship lock and water transport interchange
CN101408028B (en) Steel float tank deposition plan position control method
CN102383442B (en) Water inlet pump chamber construction method
CN102561454B (en) Water intake method utilizing pipe jacking vertically
CN105672213A (en) Floating transportation type integral steel gate dam for coastal region
CN205475122U (en) A whole steel gate dam of transportation by driving formula for coastal area
CN113585345B (en) Offshore inland river junction area immersed tunnel construction process
CN104047276B (en) The on-the-spot joining method of a kind of lattice steel sheet pile large cylinder nominative sheet pile 1/4 cylinder
CN101182706A (en) Suspension conveying submergence method of sluice bottom board
CN205776066U (en) Reservoir water level fluctuation zone tread structure
Mower Locks and Dam No. 17, Black Warrior River, Alabama
Hall et al. Deas island tunnel
Xu et al. Review of Construction Technology of Typical Immersed Tube Engineering
CORPS OF ENGINEERS WASHINGTON DC Planning and Design of Navigation Locks
Wooley et al. Navigation Conditions at Point Marion Lock and Dam, Monongahela River: Hydraulic Model Investigation
Niederhoff et al. Discussion of “Neiderhoff on Chicago River Control Works”
Lewis et al. Mississippi River—Gulf Outlet
Shafer Jr et al. Baltimore’s New Berth
Brown Erie Overhaul: The New York State Barge Canal
IRWIN CHILDS et al. DISCUSSION. THE ROYAL PORTBURY DOCK, BRISTOL.

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090403

Address after: No. 132 Pu circuit, Shanghai, Pudong New Area

Applicant after: NO.2 ENGINEERING CO.,LTD. OF CCCC THIRD HARBOR ENGINEERING CO.,LTD.

Co-applicant after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Address before: No. 132 Pu circuit, Shanghai, Pudong New Area

Applicant before: NO.2 ENGINEERING CO.,LTD. OF CCCC THIRD HARBOR ENGINEERING CO.,LTD.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100616

CF01 Termination of patent right due to non-payment of annual fee