CN101394106A - Method for implementing network five defending locking system of transforming plant without person on duty - Google Patents
Method for implementing network five defending locking system of transforming plant without person on duty Download PDFInfo
- Publication number
- CN101394106A CN101394106A CNA2008100797795A CN200810079779A CN101394106A CN 101394106 A CN101394106 A CN 101394106A CN A2008100797795 A CNA2008100797795 A CN A2008100797795A CN 200810079779 A CN200810079779 A CN 200810079779A CN 101394106 A CN101394106 A CN 101394106A
- Authority
- CN
- China
- Prior art keywords
- data
- substation
- block system
- file
- defence block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 24
- 230000001131 transforming effect Effects 0.000 title claims description 14
- 230000006854 communication Effects 0.000 claims abstract description 71
- 238000004891 communication Methods 0.000 claims abstract description 58
- 230000005540 biological transmission Effects 0.000 claims abstract description 21
- 238000004519 manufacturing process Methods 0.000 claims description 34
- 238000007726 management method Methods 0.000 claims description 14
- 230000011664 signaling Effects 0.000 claims description 11
- 230000001360 synchronised effect Effects 0.000 claims description 10
- 238000005516 engineering process Methods 0.000 claims description 7
- 238000003860 storage Methods 0.000 claims description 6
- 230000008859 change Effects 0.000 claims description 5
- 238000011161 development Methods 0.000 claims description 5
- 241001269238 Data Species 0.000 claims description 4
- 230000008520 organization Effects 0.000 claims description 4
- 230000015572 biosynthetic process Effects 0.000 claims description 3
- 230000000694 effects Effects 0.000 claims description 3
- 238000004321 preservation Methods 0.000 claims description 3
- 238000010586 diagram Methods 0.000 abstract description 7
- 230000009466 transformation Effects 0.000 abstract description 5
- 230000006855 networking Effects 0.000 abstract description 3
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 238000004088 simulation Methods 0.000 description 13
- 230000008569 process Effects 0.000 description 5
- 238000012423 maintenance Methods 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 230000001105 regulatory effect Effects 0.000 description 3
- 238000012549 training Methods 0.000 description 3
- 238000004804 winding Methods 0.000 description 3
- 238000012550 audit Methods 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000012384 transportation and delivery Methods 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 1
- 230000002457 bidirectional effect Effects 0.000 description 1
- 238000013500 data storage Methods 0.000 description 1
- 238000012217 deletion Methods 0.000 description 1
- 230000037430 deletion Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 230000003278 mimic effect Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 238000003825 pressing Methods 0.000 description 1
- 238000011112 process operation Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000009897 systematic effect Effects 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
Abstract
Description
Sequence number | File content | File format | File size | The transmission cycle |
? 1 | Transformer substation switch, disconnecting link remote signalling state | Text formatting | About 20k | When there is work in transformer station, transmit switch, disconnecting link remote signalling state |
? 2 | Transformer station's information of making out an invoice | Text formatting | About 10k | During transformer station ON operation ticket, transmit the information of making out an invoice |
? 3 | The substation secondary device state information | Text formatting | About 10k | When there is work in transformer station, transmit the secondary device state information |
? 4 ? | Transforming plant primary figure graph data | Compressed file | About 500k | After transforming plant primary figure upgrades, transmit once figure graph data |
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100797795A CN101394106B (en) | 2008-11-18 | 2008-11-18 | Method for implementing network five defending locking system of transforming plant without person on duty |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2008100797795A CN101394106B (en) | 2008-11-18 | 2008-11-18 | Method for implementing network five defending locking system of transforming plant without person on duty |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101394106A true CN101394106A (en) | 2009-03-25 |
CN101394106B CN101394106B (en) | 2010-10-06 |
Family
ID=40494244
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2008100797795A Expired - Fee Related CN101394106B (en) | 2008-11-18 | 2008-11-18 | Method for implementing network five defending locking system of transforming plant without person on duty |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101394106B (en) |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101692585B (en) * | 2009-10-16 | 2011-08-31 | 国电南京自动化股份有限公司 | Anti-operation locking system of transformation substation automatic system |
CN102508084A (en) * | 2011-11-29 | 2012-06-20 | 广东电网公司电力科学研究院 | Power system monitoring method and system thereof |
CN102570606A (en) * | 2011-12-30 | 2012-07-11 | 长园深瑞继保自动化有限公司 | Method for operating bay level cross measuring and controlling device for sequential control of intelligent transformer substation |
CN102594910A (en) * | 2012-03-15 | 2012-07-18 | 天津市电力公司 | Method adopting data service bus to realize single-instance transformer station programmed processing |
CN102955454A (en) * | 2011-08-22 | 2013-03-06 | 鸡西电业局 | Interconnection method for large combined screen and novel geological survey main station system |
CN103336857A (en) * | 2012-12-24 | 2013-10-02 | 国家电网公司 | Electric-system-oriented anti-misoperation microcomputer simulation system and implementation method thereof |
CN103645716A (en) * | 2013-12-16 | 2014-03-19 | 国家电网公司 | Method and device for data processing in transformer station switching system |
CN104266641A (en) * | 2014-10-10 | 2015-01-07 | 国家电网公司 | Intelligent navigation control method for five-prevention lock of transformer substation |
CN104281136A (en) * | 2014-10-10 | 2015-01-14 | 国家电网公司 | Five-prevention lock intelligent navigation control system for transformer substation |
CN104300679A (en) * | 2014-09-28 | 2015-01-21 | 国网浙江余姚市供电公司 | Error prevention system of centralized control station |
CN104579463A (en) * | 2014-12-29 | 2015-04-29 | 云南电网公司电力科学研究院 | System for communicating with OTDR by RJ45 port and user-defined protocol |
CN105429289A (en) * | 2014-08-26 | 2016-03-23 | 国家电网公司 | Remote control method and remote control system for reclosing |
CN106710051A (en) * | 2017-01-19 | 2017-05-24 | 珠海优特电力科技股份有限公司 | Management control system and method for preventing error operations of electrical secondary equipment |
CN107368004A (en) * | 2017-09-04 | 2017-11-21 | 安徽科盟电子科技有限公司 | A kind of power system Anti-false action device based on GPRS wireless telecommunications |
CN107623381A (en) * | 2017-09-12 | 2018-01-23 | 国家电网公司 | Substation secondary pressing plate check system and method |
CN107992019A (en) * | 2017-10-31 | 2018-05-04 | 中国电力科学研究院有限公司 | A kind of boss station integration anti-error system closed loop test method and system |
CN109634173A (en) * | 2018-12-12 | 2019-04-16 | 广东电网有限责任公司 | A kind of spare anti-misoperation locking operating method |
CN110350662A (en) * | 2019-07-16 | 2019-10-18 | 广东电网有限责任公司 | A kind of transformer substation grounding wire real-time monitoring system |
-
2008
- 2008-11-18 CN CN2008100797795A patent/CN101394106B/en not_active Expired - Fee Related
Cited By (27)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101692585B (en) * | 2009-10-16 | 2011-08-31 | 国电南京自动化股份有限公司 | Anti-operation locking system of transformation substation automatic system |
CN102955454A (en) * | 2011-08-22 | 2013-03-06 | 鸡西电业局 | Interconnection method for large combined screen and novel geological survey main station system |
CN102955454B (en) * | 2011-08-22 | 2014-10-22 | 鸡西电业局 | Interconnection method for large combined screen and novel geological survey main station system |
CN102508084A (en) * | 2011-11-29 | 2012-06-20 | 广东电网公司电力科学研究院 | Power system monitoring method and system thereof |
CN102570606B (en) * | 2011-12-30 | 2014-06-18 | 长园深瑞继保自动化有限公司 | Method for operating bay level cross measuring and controlling device for sequential control of intelligent transformer substation |
CN102570606A (en) * | 2011-12-30 | 2012-07-11 | 长园深瑞继保自动化有限公司 | Method for operating bay level cross measuring and controlling device for sequential control of intelligent transformer substation |
CN102594910A (en) * | 2012-03-15 | 2012-07-18 | 天津市电力公司 | Method adopting data service bus to realize single-instance transformer station programmed processing |
CN103336857B (en) * | 2012-12-24 | 2016-11-23 | 国家电网公司 | Microcomputer anti-error Simulation system of lunar rover and its implementation towards power system |
CN103336857A (en) * | 2012-12-24 | 2013-10-02 | 国家电网公司 | Electric-system-oriented anti-misoperation microcomputer simulation system and implementation method thereof |
CN103645716A (en) * | 2013-12-16 | 2014-03-19 | 国家电网公司 | Method and device for data processing in transformer station switching system |
CN103645716B (en) * | 2013-12-16 | 2017-01-04 | 国家电网公司 | Data processing method in a kind of transformer station back brake system and device |
CN105429289B (en) * | 2014-08-26 | 2018-02-23 | 国家电网公司 | The long-distance remote-control method and system of reclosing |
CN105429289A (en) * | 2014-08-26 | 2016-03-23 | 国家电网公司 | Remote control method and remote control system for reclosing |
CN104300679A (en) * | 2014-09-28 | 2015-01-21 | 国网浙江余姚市供电公司 | Error prevention system of centralized control station |
CN104281136A (en) * | 2014-10-10 | 2015-01-14 | 国家电网公司 | Five-prevention lock intelligent navigation control system for transformer substation |
CN104266641A (en) * | 2014-10-10 | 2015-01-07 | 国家电网公司 | Intelligent navigation control method for five-prevention lock of transformer substation |
CN104281136B (en) * | 2014-10-10 | 2017-01-18 | 国家电网公司 | Five-prevention lock intelligent navigation control system for transformer substation |
CN104266641B (en) * | 2014-10-10 | 2017-02-01 | 国家电网公司 | Intelligent navigation control method for five-prevention lock of transformer substation |
CN104579463A (en) * | 2014-12-29 | 2015-04-29 | 云南电网公司电力科学研究院 | System for communicating with OTDR by RJ45 port and user-defined protocol |
CN104579463B (en) * | 2014-12-29 | 2017-05-17 | 云南电网公司电力科学研究院 | System for communicating with OTDR by RJ45 port and user-defined protocol |
CN106710051A (en) * | 2017-01-19 | 2017-05-24 | 珠海优特电力科技股份有限公司 | Management control system and method for preventing error operations of electrical secondary equipment |
CN107368004A (en) * | 2017-09-04 | 2017-11-21 | 安徽科盟电子科技有限公司 | A kind of power system Anti-false action device based on GPRS wireless telecommunications |
CN107623381A (en) * | 2017-09-12 | 2018-01-23 | 国家电网公司 | Substation secondary pressing plate check system and method |
CN107992019A (en) * | 2017-10-31 | 2018-05-04 | 中国电力科学研究院有限公司 | A kind of boss station integration anti-error system closed loop test method and system |
CN107992019B (en) * | 2017-10-31 | 2023-07-18 | 中国电力科学研究院有限公司 | Main station and sub station integrated error-prevention system closed loop test method and system |
CN109634173A (en) * | 2018-12-12 | 2019-04-16 | 广东电网有限责任公司 | A kind of spare anti-misoperation locking operating method |
CN110350662A (en) * | 2019-07-16 | 2019-10-18 | 广东电网有限责任公司 | A kind of transformer substation grounding wire real-time monitoring system |
Also Published As
Publication number | Publication date |
---|---|
CN101394106B (en) | 2010-10-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101394106B (en) | Method for implementing network five defending locking system of transforming plant without person on duty | |
CN102929911B (en) | Substation and scheduling station method of integrated modeling | |
CN101546472B (en) | Implement method of integrated universal simulation test system for electric network scheduling and electric quantity collection | |
CN108400908A (en) | Supervisory control of substation information checks and accepts device and method automatically | |
CN102832703B (en) | Transformer station and scheduling station model fast conversion method based on model conversion machine | |
CN107069950A (en) | Automatic identifying method and system of a kind of distribution main website to terminal device | |
CN102025195B (en) | Distribution network simulation dispatching and management system | |
CN105225566B (en) | A kind of electric network emergency drills visual simulating deduction system | |
CN103888291A (en) | Power distribution terminal plug-and-play communication method based on IEC 61850 standard | |
CN103532744A (en) | Information-communication integrated supporting platform of intelligent power grid | |
CN201490764U (en) | General simulation test system with integrated power grid dispatching and electric quantity acquisition | |
CN101329564A (en) | Computer room management system | |
CN103441570A (en) | One-button type sequential control operation control method based on integrated information platform | |
CN104348254A (en) | Transformer substation monitoring system framework facing services | |
CN103023147A (en) | Remote vision linkage method for electric power master station and substation based on computer integrated manufacturing (CIM) data model | |
CN104504483B (en) | Method for realizing province and local integration of anti-misoperation tickets | |
CN106779508A (en) | Secondary system of intelligent substation safety measure analogue simulation and O&M control platform | |
CN110276516A (en) | Distribution monitoring analysis and repairing command methods based on power grid GIS | |
CN102064602A (en) | Operating method of B/S framework networked electronic simulation drawing board system | |
CN104915794A (en) | Multi-time-state full-service unified modeling method based on model center | |
CN102916489A (en) | Virtual terminal automatic wiring method based on primary system structure of regional power grid | |
CN108764409A (en) | Secondary device machine account management system | |
Shuang et al. | Intelligent mobile operation and maintenance technology and its application of for relay protection based on power wireless virtual private network | |
CN107992019A (en) | A kind of boss station integration anti-error system closed loop test method and system | |
CN202870564U (en) | Digital mine safety production local area network system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
ASS | Succession or assignment of patent right |
Owner name: HEBEI ELECTRIC POWER CORPORATION SHIJIAZHUANG POWE Effective date: 20121129 Owner name: STATE GRID CORPORATION OF CHINA Free format text: FORMER OWNER: SHIJIAZHUANG POWER SUPPLY COMPANY Effective date: 20121129 |
|
C41 | Transfer of patent application or patent right or utility model | ||
COR | Change of bibliographic data |
Free format text: CORRECT: ADDRESS; FROM: 050051 SHIJIAZHUANG, HEBEI PROVINCE TO: 100761 DONGCHENG, BEIJING |
|
TR01 | Transfer of patent right |
Effective date of registration: 20121129 Address after: 100761 West Chang'an Avenue, Beijing, No. 86 Patentee after: State Grid Corporation of China Patentee after: Hebei Electric Power Corporation Patentee after: Shijiazhuang Power Supply Co.,Ltd. Address before: 050051, 66 Hongqi Avenue, Hebei, Shijiazhuang Patentee before: Shijiazhuang Power Supply Co.,Ltd. |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20101006 Termination date: 20201118 |
|
CF01 | Termination of patent right due to non-payment of annual fee |