CN101277002A - Construction Method of Concrete Pole for 10kV Double Circuit Distribution Line - Google Patents
Construction Method of Concrete Pole for 10kV Double Circuit Distribution Line Download PDFInfo
- Publication number
- CN101277002A CN101277002A CNA2008100993663A CN200810099366A CN101277002A CN 101277002 A CN101277002 A CN 101277002A CN A2008100993663 A CNA2008100993663 A CN A2008100993663A CN 200810099366 A CN200810099366 A CN 200810099366A CN 101277002 A CN101277002 A CN 101277002A
- Authority
- CN
- China
- Prior art keywords
- live
- distribution line
- pole
- wires
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Electric Cable Installation (AREA)
Abstract
带电组立10kV双回配电线路砼杆施工方法,其特征是在需组立砼杆的作业点,利用绝缘升高车在每根带电的配电线路导线上安装绝缘护套,然后绝缘绳索分别固定于各绝缘护套的中部,利用配电线路导线的自身驰度,使用绝缘绳索在地面将六根带电的配电线路导线分别向线路的外侧相向牵拉,直到使两条线路导线之间的水平距离达到并保持在3.5米-4米之间;随后即可在组立砼杆的作业点上完成待组立砼杆的立杆;再由带电作业人员登杆组装导线以及各附件;最后恢复配电线路导线的位置,并完成带电接火,施工完毕。本发明方法操作安全、效率高。
The construction method for erecting concrete poles of 10kV double-circuit distribution lines with live electricity is characterized in that at the operating point where concrete poles need to be erected, an insulating sheath is installed on each live distribution line conductor by using an insulating lifting vehicle, and then the insulating ropes are installed. They are respectively fixed in the middle of each insulating sheath, and using the self-slack of the distribution line conductors, use insulating ropes to pull the six live distribution line conductors on the ground to the outside of the line, until the two line conductors are separated. The horizontal distance reaches and remains between 3.5 meters and 4 meters; then the vertical pole to be erected can be completed at the operating point where the erected concrete pole is erected; and then the wire and accessories are assembled by the live operator on the pole; Finally, the position of the wires of the distribution line is restored, and the live connection is completed, and the construction is completed. The method of the invention is safe in operation and high in efficiency.
Description
技术领域technical field
本发明涉及电力系统10kV双回配电线路中的砼杆带电组立施工方法。The invention relates to a construction method for live assembly of concrete poles in a 10kV double-circuit power distribution line of an electric power system.
背景技术Background technique
目前,在对电力系统10kV双回配电线路的砼杆带电组立作业中,对同杆架设双回导线上下排列线路,在组立砼杆时,必须保证导线对杆体、吊车起吊钢绳的绝缘,因此采用的主要方法为在杆体上部使用绝缘布包裹形成绝缘体进行组立,这种方法存在以下缺点:At present, in the live assembly operation of concrete poles for 10kV double-circuit power distribution lines in the power system, the double-circuit conductors are arranged up and down on the same pole. Insulation, so the main method used is to wrap the upper part of the rod body with insulating cloth to form an insulator for assembly. This method has the following disadvantages:
1、作业程序繁琐:根据砼杆在组立过程中需穿越双回导线的位置上,包裹上相当长度的绝缘布并固定,然后才能进行立杆;当杆塔组立好后,需要拆除绝缘布,然后才能进行安装砼杆铁附件工作。1. The operation procedure is cumbersome: according to the position where the concrete pole needs to pass through the double-circuit wire during the erection process, a considerable length of insulating cloth is wrapped and fixed before the pole can be erected; when the pole tower is erected, the insulating cloth needs to be removed , and then the work of installing concrete rod iron accessories can be carried out.
2、安全系数低:在进行砼杆组立和铁附件施工时,由于双回线路带电且距离较小,因此在安装过程中,需要根据现场情况,增设安全措施,加强地面监护,杆上作业人员还需十分小心,以免造成线路短路,因此安全隐患较大。2. Low safety factor: During the construction of concrete pole assembly and iron accessories, because the double-circuit line is charged and the distance is small, during the installation process, it is necessary to add safety measures according to the site conditions, strengthen ground monitoring, and work on poles Personnel also need to be very careful, so as not to cause a short circuit, so the potential safety hazard is relatively large.
3、工作效率低:由于上述方法作业程序繁琐,安全系数低,而且立杆后的导线横担、熔断器横担的组装都非常困难和危险,因此工作效率难以提高。3. Low work efficiency: due to the cumbersome operation procedures of the above-mentioned method, the safety factor is low, and the assembly of the wire cross arm and the fuse cross arm behind the vertical pole is very difficult and dangerous, so the work efficiency is difficult to improve.
发明内容Contents of the invention
本发明是为避免上述现有技术所存在的不足之处,提供一种带电组立10kV双回配电线路砼杆施工方法,通过借鉴输电线路带电作业方法,加大线间安全距离,以提高操作安全性、提高工作效率、简化双回配电线路垂直排列导线的带电组立砼杆工作。In order to avoid the shortcomings of the above-mentioned prior art, the present invention provides a construction method for concrete poles of live assembled 10kV double-circuit power distribution lines. By referring to the live working method of power transmission lines, the safety distance between lines is increased to improve Operation safety, improve work efficiency, and simplify the live assembly of concrete poles with vertically arranged conductors in double-circuit power distribution lines.
本发明解决技术问题采用如下技术方案:The present invention solves technical problem and adopts following technical scheme:
本发明带电组立10kV双回配电线路砼杆施工方法的特点是按如下步骤操作:The characteristics of the construction method of the concrete pole of the live assembled 10kV double-circuit power distribution line of the present invention are to operate according to the following steps:
a、在需组立砼杆的作业点,由带电作业人员利用绝缘升高车在每根带电的配电线路导线上安装绝缘护套,然后将六根绝缘绳索分别固定于各绝缘护套的中部,再由地面人员利用配电线路导线的自身驰度,使用绝缘绳索将六根带电的配电线路导线分别向线路的外侧相向牵拉,直到使两条线路导线之间的水平距离达到并保持在3.5米-4米之间;a. At the operating point where concrete poles need to be erected, the live workers use the insulating lifting vehicle to install insulating sheaths on each live distribution line conductor, and then fix six insulating ropes to the middle of each insulating sheath , and then the ground personnel use the self-slack of the distribution line conductors to use insulated ropes to pull the six live distribution line conductors to the outside of the line, until the horizontal distance between the two line conductors reaches and maintains Between 3.5 meters and 4 meters;
b、在所述组立砼杆的作业点上利用吊车完成待组立砼杆的立杆;b. Utilize a crane to complete the vertical pole of the concrete pole to be assembled on the operating point of the erected concrete pole;
c、由带电作业人员登杆组装导线以及包括熔断器横担、支柱瓷瓶、避雷器在内的各附件,结束操作后,带电作业人员下杆至安全地带;c. Assemble wires and accessories including fuse crossarms, pillar porcelain bottles, and lightning arresters by live workers on poles. After the operation is completed, live workers get off the poles to a safe zone;
d、由地面作业人员恢复所述六根配电线路导线的位置,再由带电作业人员利用绝缘升高车带电固定导线,并完成带电接火,施工完毕。d. The ground workers restore the position of the six distribution line wires, and then the live workers use the insulation lifting vehicle to fix the wires live, and complete the live fire connection, and the construction is completed.
本发明中绝缘护套的长度为3米。The length of the insulating sheath in the present invention is 3 meters.
与已有技术相比,本发明的有益效果体现在:Compared with the prior art, the beneficial effects of the present invention are reflected in:
1、本发明采用带电拉开带电导线的方法,使两条线路导线之间的水平距离保持在3.5米-4米之间,能有效避免导线短路的现象,保证了作业人员的人身安全,极大地提高了工作安全性。1. The present invention adopts the method of pulling apart the charged wires with electricity, so that the horizontal distance between the two line wires is kept between 3.5 meters and 4 meters, which can effectively avoid the phenomenon of short circuit of the wires, and ensure the personal safety of the operators. Greatly increased job security.
2、本发明由于双回导线之间安全距离能够保证,因此水泥电杆无需进行绝缘的包裹和拆除工作,程序简单。2. In the present invention, since the safety distance between the double-circuit wires can be guaranteed, the cement pole does not need to be wrapped and removed for insulation, and the procedure is simple.
3、本发明由于双回导线之间安全距离较大,可以方便快捷的组立砼杆、安装杆上铁附件和固定导线,极大的提高了工作效率。3. Due to the large safety distance between the double-circuit conductors, the present invention can conveniently and quickly assemble concrete poles, install iron accessories on poles and fix conductors, greatly improving work efficiency.
附图说明Description of drawings
图1为本发明施工方法示意图。Fig. 1 is the schematic diagram of construction method of the present invention.
图2为图1俯视示意图。FIG. 2 is a schematic top view of FIG. 1 .
图中标号:1绝缘绳索、2配电线路导线、3待组立砼杆、4绝缘护套。Labels in the figure: 1 insulating rope, 2 distribution line wire, 3 concrete pole to be assembled, 4 insulating sheath.
以下通过具体实施方式,并结合附图对本发明作进一步说明。The present invention will be further described below through specific embodiments and in conjunction with the accompanying drawings.
具体实施方式Detailed ways
本实施例是以10千伏双回线路导线垂直排列、杆间距45米、横担长度2.1米、原线路电杆和新立砼杆为15米:In this embodiment, the conductors of the 10 kV double-circuit line are vertically arranged, the distance between the poles is 45 meters, the length of the cross arm is 2.1 meters, and the poles of the original line and the new concrete poles are 15 meters:
参见图1、图2,具体施工按如下步骤进行:Referring to Figure 1 and Figure 2, the specific construction is carried out as follows:
1、确定新立砼杆位置,建议设置在两杆之间位置即22.5米处,此处导线驰度最大,便于施工,提前将15米长的砼杆运输到位,并挖好杆洞。1. Determine the position of the new vertical concrete pole. It is recommended to set it at the position between the two poles, that is, 22.5 meters, where the conductor has the largest slack, which is convenient for construction. Transport the 15-meter-long concrete pole in place in advance, and dig the pole hole.
2、立杆前,在现场工作负责人的指挥下,绝缘斗臂车摆放于一侧线路适合带电作业的位置。绝缘斗臂车在作业时必须保持1米的绝缘有效长度,金属部分在抬起、回转运动中,与带电体间的安全距离不得小于1米。带电升起、下落、左右移动导线时,对被跨越物、建筑物的交叉、平行的最小距离不得小于1米。斗臂车应良好接地,作业时斗臂车发动机不得熄火,工作斗内严禁超载。工作斗的起升、下降速度不应大于0.5m/s,斗臂车回转机构回转时,作业斗外缘的速度不应大于0.5m/s。2. In front of the pole, under the command of the person in charge of the on-site work, the insulated bucket arm truck is placed in a position suitable for live work on one side of the line. The insulated arm truck must maintain an effective insulation length of 1 meter during operation, and the safe distance between the metal part and the charged body during lifting and turning motions shall not be less than 1 meter. When electrified lifting, falling, and moving wires left and right, the minimum distance to crossed objects, buildings, and parallels shall not be less than 1 meter. The arm truck should be well grounded, the engine of the bucket arm truck must not be turned off during operation, and overloading is strictly prohibited in the working bucket. The lifting and lowering speed of the working bucket should not be greater than 0.5m/s, and the speed of the outer edge of the working bucket should not be greater than 0.5m/s when the slewing mechanism of the bucket arm truck is rotating.
3、绝缘工作斗内操作人员进入工作斗前必须穿戴好绝缘安全帽、绝缘靴、绝缘服、绝缘手套及外层保护手套,由现场监护人进行检查,作业人员进入工作斗后应系好安全带并将扣环扣在工作斗专用固定点上,并将遮蔽用具及拉开导线的绝缘绳,放入工作斗内。3. Before entering the working bucket, the operators in the insulating working bucket must wear insulating safety helmets, insulating boots, insulating clothing, insulating gloves and outer protective gloves. The on-site guardians will check, and the operators should fasten their safety belts after entering the working bucket. And buckle the buckle on the special fixed point of the working bucket, and put the shielding appliance and the insulating rope for pulling the wire into the working bucket.
4、工作斗内的带电作业人员操作斗臂车的工作斗到达作业点上方,调整好位置后以杆洞为中心点,分别用绝缘护套4对一侧三相配电线路导线2进行绝缘遮蔽,设置绝缘护套4时,应从离身体最近的带电体或接地体依次设置,即按照从近到远的原则,对多层分布的设备,应从下层开始依次向上层设置,每相配电线路导线2的遮蔽长度不小于3米。同时在绝缘护套4上系牢用于拉开配电线路导线2用的绝缘绳索1,另一头放至地面。然后带电作业人员返回地面将斗臂车调到另条线路的一侧,按同样方法对另一侧三相配电线路导线2进行绝缘遮蔽并系好绝缘绳索,带电作业人员返回地面。通过对六根带电的配电线路导线2的绝缘屏蔽,达到防止工作过程中导线的相互碰触造成短路,以及与人员碰触造成触电。4. The live working personnel in the working bucket operate the working bucket of the bucket arm truck to reach the top of the working point. After adjusting the position, take the rod hole as the center point and insulate the
5、在工作负责人的统一指挥下,地面操作人员集中在一侧线路,由下至上分别用绝缘绳索1将该侧三相配电线路导线2向线路外侧拉出并固定在地面的临时固定桩上。然后移至另一侧线路按同样方法将该侧导线拉开并固定牢固。拉开导线过程中,必须始终在线路下方观察导线拉开的距离、导线的受力情况及对交叉跨越物的安全距离。通过上述工作,保证新立砼杆上方的导线之间水平距离达到并保持在3.5米-4米之间,以利下一步砼杆起立、杆上附件安装时安全工作空间。5. Under the unified command of the person in charge of the work, the ground operators concentrate on one side of the line, and use the insulating
6、在工作负责人的统一指挥下,用于起吊待组立砼杆3的吊车就位于作业点位置,然后吊车将吊钩由拉开的带电配电线路导线2的中间放下,将杆头吊起杆根顺入杆洞,然后缓慢地将杆体立起、竖直,施工人员回填杆洞。6. Under the unified command of the person in charge of the work, the crane used to lift the concrete pole 3 to be assembled is located at the operation point, and then the crane puts down the hook from the middle of the drawn live
7、杆上作业人员登杆安装导线和熔断器横担,以及瓷瓶、避雷器等附件,在连接好附件之间的引线后下杆至安全地带。7. The workers on the pole should mount the pole to install wires and fuse crossarms, as well as accessories such as porcelain bottles and lightning arresters, and then lower the pole to a safe zone after connecting the lead wires between the accessories.
8、杆上作业人员工作结束并全部撤离后,带电作业人员操作绝缘斗臂车的工作斗升高至横担位置,并对绝缘子金属部分及横担进行绝缘遮蔽,以防止工作过程中导线间通过金属部件发生短路。8. After the workers on the pole have finished their work and all evacuate, the working bucket of the insulated bucket arm truck operated by the live workers is raised to the position of the cross arm, and the metal part of the insulator and the cross arm are insulated and shielded to prevent the wires from being damaged during the work process. Short circuit through metal parts.
9、在工作负责人的指挥下,地面人员首先将两条线路上相导线慢慢放松至新安装的横担前,工作斗内带电作业人员通过戴好绝缘手套的手托起导线,放入绝缘子固定槽内绑扎牢固,然后拆除绝缘绳及不需接火侧线路导线上的绝缘护套;其后,中相、下相导线和另一侧线路的固定工作按同样方式顺序完成。9. Under the command of the person in charge of the work, the ground personnel first slowly loosen the upper phase wires of the two lines to the front of the newly installed cross-arm, and the live workers in the work bucket hold up the wires with their hands wearing insulating gloves and put them into the Bind firmly in the insulator fixing groove, and then remove the insulating rope and the insulating sheath on the wires on the side that does not need to be connected to the fire; after that, the fixing work of the middle phase, lower phase wires and the other side of the line is completed in the same manner.
10、工作负责人检查新安装的熔断器处于打开状态后,即可下令进行带电接火,工作斗内带电作业人员测量引线长度并将多余的开断,然后将3根引线分相用并沟线夹与主线连接起来。若有避雷器需要连接,也按上述方法进行带电接火。10. After the person in charge of the work checks that the newly installed fuse is in the open state, he can order the live fire connection. The live operator in the work bucket measures the length of the lead wires and cuts off the excess, and then separates the 3 lead wires and uses them in parallel. The clamp is connected to the main line. If there is a lightning arrester that needs to be connected, also carry out live fire connection according to the above method.
11、工作斗内操作人员检查所有的连接线夹、绝缘子绑扎线确无问题后,先拆除导线绝缘套管,然后拆除横担绝缘子遮蔽用具,拆除遮蔽用具时,应从离作业人员最远处开始依次向近处拆除,多层分布的设备,应从上层开始依次向下拆除,全部工作结束后作业人员返回地面。11. After the operator in the working bucket checks that all the connecting wire clips and insulator binding wires are correct, first remove the wire insulation sleeve, and then remove the shielding device for the cross-arm insulator. When removing the shielding device, it should start from the farthest away from the operator Dismantling towards the nearest one by one, multi-layer distributed equipment should be dismantled from the upper layer downwards, and the operators return to the ground after all the work is completed.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2008100993663A CN101277002B (en) | 2008-05-06 | 2008-05-06 | Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2008100993663A CN101277002B (en) | 2008-05-06 | 2008-05-06 | Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101277002A true CN101277002A (en) | 2008-10-01 |
| CN101277002B CN101277002B (en) | 2011-07-27 |
Family
ID=39996116
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2008100993663A Expired - Fee Related CN101277002B (en) | 2008-05-06 | 2008-05-06 | Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101277002B (en) |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101752805A (en) * | 2008-12-17 | 2010-06-23 | 北京市电力公司 | Insulator bracket for ground potential upright post and operating method thereof |
| CN101847843A (en) * | 2010-04-30 | 2010-09-29 | 辽宁省电力有限公司锦州供电公司 | Method for installing sectional switches on multiloop swallow-wing-array 10kV circuit |
| CN102157907A (en) * | 2010-12-06 | 2011-08-17 | 山东电力集团公司威海供电公司 | Safe fire welding device of overhead line |
| CN103806740A (en) * | 2013-12-12 | 2014-05-21 | 国家电网公司 | Insertion type erection method for electrified pole |
| CN105932605A (en) * | 2016-06-13 | 2016-09-07 | 国家电网公司 | Electrified cross line insulating packaged sheath and construction method therefor |
| CN106437280A (en) * | 2016-11-14 | 2017-02-22 | 国网湖北省电力公司咸宁供电公司 | Live pole erecting method for 10 kV common-tower double-circuit and vertically arranged power distribution line |
| CN106786157A (en) * | 2016-12-31 | 2017-05-31 | 浙江省送变电工程公司 | Transmission line of electricity Great span above the navigation water surface tears aging method open |
| CN108683122A (en) * | 2018-06-08 | 2018-10-19 | 国网山东省电力公司青岛供电公司 | The auxiliary device and method of corridor straight line pole are shared with electromigration |
-
2008
- 2008-05-06 CN CN2008100993663A patent/CN101277002B/en not_active Expired - Fee Related
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101752805A (en) * | 2008-12-17 | 2010-06-23 | 北京市电力公司 | Insulator bracket for ground potential upright post and operating method thereof |
| CN101752805B (en) * | 2008-12-17 | 2013-06-19 | 国家电网公司 | Insulator bracket for ground potential upright post and operating method thereof |
| CN101847843A (en) * | 2010-04-30 | 2010-09-29 | 辽宁省电力有限公司锦州供电公司 | Method for installing sectional switches on multiloop swallow-wing-array 10kV circuit |
| CN102157907A (en) * | 2010-12-06 | 2011-08-17 | 山东电力集团公司威海供电公司 | Safe fire welding device of overhead line |
| CN103806740A (en) * | 2013-12-12 | 2014-05-21 | 国家电网公司 | Insertion type erection method for electrified pole |
| CN103806740B (en) * | 2013-12-12 | 2015-01-14 | 国家电网公司 | Insertion type erection method for electrified pole |
| CN105932605A (en) * | 2016-06-13 | 2016-09-07 | 国家电网公司 | Electrified cross line insulating packaged sheath and construction method therefor |
| CN105932605B (en) * | 2016-06-13 | 2018-06-29 | 国家电网公司 | One kind lives across line insulation wrap jacket and construction method |
| CN106437280A (en) * | 2016-11-14 | 2017-02-22 | 国网湖北省电力公司咸宁供电公司 | Live pole erecting method for 10 kV common-tower double-circuit and vertically arranged power distribution line |
| CN106786157A (en) * | 2016-12-31 | 2017-05-31 | 浙江省送变电工程公司 | Transmission line of electricity Great span above the navigation water surface tears aging method open |
| CN108683122A (en) * | 2018-06-08 | 2018-10-19 | 国网山东省电力公司青岛供电公司 | The auxiliary device and method of corridor straight line pole are shared with electromigration |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101277002B (en) | 2011-07-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101277002B (en) | Method for construction of charged assembling 10kV bi-gyrus distribution line concrete lever | |
| CN102623926B (en) | Distant equipotential tackle and method for realizing charged equipotential access by using same | |
| CN102136693B (en) | Method and device for realizing long-distance equal electric potential access of winch hanging basket guide rail | |
| CN101640391B (en) | Live-wire operation method for replacing insulator for 35kV distribution circuit | |
| WO2016023141A1 (en) | Process for live replacement of tension hard-tube bus-bar jumper insulator of +/- 800kv ultra-high-voltage dc transmission line | |
| CN102931609B (en) | On-load changes the operational method of 10kV fuse switch | |
| CN108155501A (en) | 10KV outlet cables and overhead transmission line lap works rod-type arc-extinction device | |
| CN102664358B (en) | Live replacement method for static contact of 220 kV flexible busbar | |
| CN100590943C (en) | Method of overhead ground wire down-conductor connection and ground wire assembly | |
| CN101888075A (en) | 10kV wire lifting operational method for insulating tool of crane | |
| CN110120643A (en) | A kind of ground potential distribution power circuit uninterrupted operation method | |
| CN107482535A (en) | The Method of Installing Segment Switch on Straight Rod of 10KV Line with Load Breaking | |
| CN103806740B (en) | Insertion type erection method for electrified pole | |
| CN222029555U (en) | Bench variable structure for transformer substation overhead line | |
| CN104143783B (en) | 10 kV electrified rod erecting insulation lifting appliance and working method with lifting appliance | |
| CN103500966B (en) | 66kv disconnecting switch is to pipe bus charged disconnecting lead-in wire method | |
| CN202611568U (en) | Insulation trestle ladder | |
| CN209948529U (en) | Live lifting mechanism for three-phase lead of straight-line section of 10kV distribution network line | |
| CN207200127U (en) | A kind of insulation climbing device for the maintenance of compound cross-arm | |
| CN205882560U (en) | Special circulation cord rack device of distribution live working earth potential | |
| CN202503194U (en) | Suspension type lightning arrester applicable to power transmission lines | |
| CN201234089Y (en) | Protective interval for live operation on 1000kV AC very high voltage line | |
| CN201584691U (en) | Special tool for 220KV double-circuit common-tower line accessing tension-resistance high-pressure high-electric field | |
| CN201466565U (en) | Wire lifting device of vehicle with insulating boom | |
| CN108979102B (en) | Safe construction method for high-voltage line |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| ASS | Succession or assignment of patent right |
Owner name: STATE GRID CORPORATION OF CHINA Effective date: 20121211 |
|
| C41 | Transfer of patent application or patent right or utility model | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20121211 Address after: 239000 No. 510 Fenghuang Road, Anhui, Chuzhou Patentee after: Anhui Power Company Chuzhou Power Supply Company Patentee after: State Grid Corporation of China Address before: 239000 No. 510 Fenghuang Road, Anhui, Chuzhou Patentee before: Anhui Power Company Chuzhou Power Supply Company |
|
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20110727 Termination date: 20200506 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |