CN101215836B - Construction machinery used for large diameter hollow pile and its construction method and use - Google Patents
Construction machinery used for large diameter hollow pile and its construction method and use Download PDFInfo
- Publication number
- CN101215836B CN101215836B CN2007100605589A CN200710060558A CN101215836B CN 101215836 B CN101215836 B CN 101215836B CN 2007100605589 A CN2007100605589 A CN 2007100605589A CN 200710060558 A CN200710060558 A CN 200710060558A CN 101215836 B CN101215836 B CN 101215836B
- Authority
- CN
- China
- Prior art keywords
- pile
- drill bit
- piling
- injection stream
- hollow pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 38
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 64
- 239000002689 soil Substances 0.000 claims abstract description 47
- 238000005553 drilling Methods 0.000 claims abstract description 42
- 239000004567 concrete Substances 0.000 claims abstract description 37
- 239000007921 spray Substances 0.000 claims abstract description 20
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 16
- 239000010959 steel Substances 0.000 claims abstract description 16
- 238000002347 injection Methods 0.000 claims description 71
- 239000007924 injection Substances 0.000 claims description 71
- 239000004568 cement Substances 0.000 claims description 22
- 230000003014 reinforcing effect Effects 0.000 claims description 11
- 239000011435 rock Substances 0.000 claims description 10
- 238000005520 cutting process Methods 0.000 claims description 8
- 230000002093 peripheral effect Effects 0.000 claims description 8
- 238000004537 pulping Methods 0.000 claims description 8
- 230000001360 synchronised effect Effects 0.000 claims description 8
- 230000015572 biosynthetic process Effects 0.000 claims description 6
- 150000001875 compounds Chemical class 0.000 claims description 6
- 238000007569 slipcasting Methods 0.000 claims description 6
- 238000005507 spraying Methods 0.000 claims description 6
- 241001074085 Scophthalmus aquosus Species 0.000 claims description 4
- 238000007789 sealing Methods 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 13
- 230000008569 process Effects 0.000 abstract description 2
- 238000005266 casting Methods 0.000 abstract 1
- 230000002787 reinforcement Effects 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 9
- 230000008901 benefit Effects 0.000 description 4
- 230000006378 damage Effects 0.000 description 4
- KQTVWCSONPJJPE-UHFFFAOYSA-N etridiazole Chemical compound CCOC1=NC(C(Cl)(Cl)Cl)=NS1 KQTVWCSONPJJPE-UHFFFAOYSA-N 0.000 description 3
- 239000004576 sand Substances 0.000 description 3
- 238000005056 compaction Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 238000005183 dynamical system Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 235000013312 flour Nutrition 0.000 description 2
- 239000011229 interlayer Substances 0.000 description 2
- 230000035515 penetration Effects 0.000 description 2
- 239000011148 porous material Substances 0.000 description 2
- 239000011378 shotcrete Substances 0.000 description 2
- 239000000243 solution Substances 0.000 description 2
- 208000028804 PERCHING syndrome Diseases 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000002498 deadly effect Effects 0.000 description 1
- 230000006837 decompression Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 230000010412 perfusion Effects 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 238000009738 saturating Methods 0.000 description 1
- 239000013049 sediment Substances 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Images
Landscapes
- Piles And Underground Anchors (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The invention discloses a construction machine for hollow piles with large diameter and the construction method and usage, which comprises a drilling system, a pile pounding system, a drainage system which are integrated into one part. The pile forming method comprises: a high-spray drilling bit is arranged on a steel tube (a protection cylinder) or on the bottom of an inner hole of a pre-made tube pile for hole drilling and mud making; the mud is drained from a water joint or a drainage pipe; the protection cylinder or tube pile is pressed asynchronously or synchronously along with the drilling bit; during pile-sinking process, water mud is sprayed to the outer soil of the hole to solidify the surrounding soil of the pile and fill the gaps between the pile and surrounding soil of the pile; after the drilling bit reaches certain depth, the water mud is again sprayed to solidify surrounding soil of the pile; lifting the drilling bit; putting down reinforcement cage; casting concrete for piling. The invention is a construction method for foundation piles and drilling with large diameter, super long and high load, which especially provides convenient, labor-saving, rapid and economical equipment and method for marine pile driving.
Description
Technical field
The present invention relates to a kind of construction machine and job practices thereof, especially heavy caliber foundation pile or push pipe pass through the construction machinery that is used for large diameter hollow pile and the job practices and the purposes of engineering.
Background technology
The type of the big load foundation pile of existing heavy caliber mainly contains bored pile, preformed pile etc.; The hole forming method of bored pile has positive reverse circulation drilling, rotary digging drilling hole and auger boring, gyro to be drilled to hole forming methods such as hole.It is slow that said method has speed of fulfiling hole respectively, the deficiency of retaining wall (especially liquefied sand) difficulty, and stake footpath, the stake of squeezing into preformed pile are long all very limited, and meet silt, the equal pile sinking difficulty of flour sand or stratum such as cobble, decomposed rock, cause the loading force of stake very restricted thereby easily the stake point is exploded or pile body swarmed in.This is the common problem that present domestic and international market runs in the construction of high-bearing capacity stake type, needs solution badly.
Summary of the invention
Technical problem to be solved by this invention is, a kind of construction machinery and job practices and purposes that is used for large diameter hollow pile is provided, and satisfies that major diameter, timber pile are long, the construction of high load foundation pile.
In order to solve the problems of the technologies described above, the technical solution used in the present invention is: a kind of construction machinery that is used for large diameter hollow pile, comprise hole-drilling system, row injection system, piling system, described hole-drilling system comprises the drill bit, drill bit power set, the drill bit stride drilling apparatus that have high injection stream water filling device, is positioned at drill bit top and the integrally formed cylindric retaining wall circle of drill bit; Described piling system comprises hanging apparatus, stake machine mobile device, piling device; Described row's injection system comprises high injection stream water filling device, annotates concrete device and discharge pipe; In the inner chamber that creeps into end of hollow pile, be fixed with fixed case, the upper end of fixed case links to each other with hanging apparatus, the lower chassis of fixed case removably is fixed on the flange that creeps into end of hollow pile, the fixed case internal fixation has drill bit stride drilling apparatus, the drill bit power set are positioned at the outside of the lower chassis of fixed case, be connected on the drill bit stride drilling apparatus, drill bit is connected on the drill bit power set by water swivel; The notes concrete pipe that is connected with notes concrete device passes fixed case and is fixed on the lower chassis, discharge pipe passes fixed case and is fixed on the lower chassis, the high jet pipe that is connected with high injection stream water filling device passes fixed case and is fixed on the water swivel entrance point, be connected with high spraying nozzle at the water swivel port of export, high spraying nozzle is positioned at the middle part of bit drills tooth.
Described row's injection system also comprises high injection stream grouting device, the high injection stream Grouting Pipe that is connected with high injection stream grouting device is passed fixed case and is fixed on the water swivel entrance point, be connected with high injection stream slip casting nozzle at the water swivel port of export, high injection stream slip casting nozzle is arranged on the top of drill bit retaining wall circle.
Described drill bit is one or more.
Described hollow pile is a kind of in casing, steel pipe pile or the prefabricated tubular pile.
A kind of job practices that is used for the construction machinery of large diameter hollow pile may further comprise the steps:
A, startup are contained in the drill bit that hollow pile creeps into end, start high injection stream water filling device, cutting soil, and the boring pulping makes mud discharge by the plasma discharge system;
B, when soil layer is not too hard, creep in the time of keeping synchronous with piling, synchronously hollow pile is pressed into;
C, when running into hard formation or decomposed rock, start the stride drilling apparatus, boring certain depth earlier, the piling certain depth circulates like this and creeps into piling, promptly asynchronous piling again;
After d, boring reached projected depth, high injection stream water filling device stopped water filling, holds native mesohigh spray cement paste with high injection stream water filling device to stake, and stake end soil is reinforced, and controlled pressure enlarges the churning diameter to form enlarged footing;
E, carry and bore to annotate concrete, pile.
The present invention is used for the job practices of the construction machinery of large diameter hollow pile, also can be may further comprise the steps:
A, startup are contained in the drill bit that hollow pile creeps into end, start high injection stream water filling device, cutting soil, the boring pulping, mud is discharged by the plasma discharge system, start high injection stream grouting device simultaneously, spray cement paste in pile peripheral earth makes all soil of stake become cement earth pile and forms compound pile with hollow pile;
B, when soil layer is not too hard, creep in the time of keeping synchronous with piling, synchronously hollow pile is pressed into;
C, when running into hard formation or decomposed rock, start the stride drilling apparatus, boring certain depth earlier, the piling certain depth circulates like this and creeps into piling, promptly asynchronous piling again;
After d, boring reached projected depth, high injection stream water filling device stopped water filling, holds native mesohigh spray cement paste with high injection stream water filling device to stake, and stake end soil is reinforced, and controlled pressure enlarges the churning diameter to form enlarged footing;
E, carry and bore to annotate concrete, pile.
Described step e is: be a mouth at the bottom of sealing, annotate concrete simultaneously carrying when boring, to certain depth, stop to annotate concrete, propose drilling tool and power set, put into reinforcing cage, annotate concrete, pile once more.
Described step e is: brill is carried on marginal not concrete limit, until reaching absolute altitude, proposes drilling tool.
Also comprise, insert reinforcing cage behind the pile again.
The construction machinery that is used for large diameter hollow pile passes through application in engineering at the foundation pile and the push pipe of heavy caliber, overlength, big load.
The invention has the beneficial effects as follows:
1, equipment of the present invention and worker's method integrate drilling and forming hole and piling (or jacking), make the soil compaction pile of preformed pile become the boring pile sinking, and this reduces the side friction of pile driving process king-pile greatly, and end resistance almost becomes zero.Because the reduction greatly of penetrating resistance, during construction pile body can be not again because of passing the pan soil interlayer, or for to enter the bearing stratum flour sand layer or the decomposed rock of design, and pile crown is exploded, press from both sides pile body quick-fried or when the folder stake because of the too big destruction of causing pile strength of armful folder power; It is bigger that the diameter of pile for prestressed pipe, steel pipe pile just can design, and the hardpan that passes just no longer becomes problem.
2, present device is furnished with high injection stream grouting device, when pile sinking (or push pipe), can constantly reinforce pile peripheral earth to stake Zhou Tuzhong gunite.Pile peripheral earth becomes cement-soil, and the diameter of reinforcing scope is greater than pile tube diameter (20%~30%), and pile tube forms compound pile with all cement-soil engagements of stake, and its total side friction can make the vertical bearing capacity of single pile of stake improve 1.5~1.8 times; High injection stream water filling device is held native mesohigh gunite to make by the soil body of drill bit disturbance to stake and is replaced as cement-soil before pile sinking reaches projected depth, and drill bit is extracted; Further pressurization (more than the 30MPa) can be held the enlarged footing that forms a cement-soil in the soil in stake, and this method has not only overcome at the bottom of the conventional borehole stake hole sediment and has been difficult to remove and causes holding the often minimum deadly defect of load, and has improved the end load of stake greatly.
3, the 3rd of high injection stream water filling device the advantage is, at super large caliber (during the construction of the stake of 1.5m~5.0m) creeps into, utilize the high-pressure rotary-spray jet can be with intact soil body cutting damage pulping in the blind area between a plurality of drill bits, avoided the blind area undisturbed soil when being subjected to upper tube sunk pile pressure pressurized and will around or adjacent drill bit squeeze off normal or squeeze bad.
4, on the equipment of the present invention hydraulic feed device is housed, the benefit of this device is to run into the pan soil interlayer, when hard soil layer (mark passes through and hits several N>40) or decomposed rock, can make pile sinking and creep into that walking is asynchronous to carry out, promptly pile sinking (or push pipe) stops, and promotes drill bit by hydraulic pusher and creeps into the pulping pore-forming and reach certain depth (such as 1m), stop to creep into piling then until reaching projected depth, move in circles like this and creep into, pile sinking continues, and the propeller descending drill bit that reduces pressure shrinks relatively.
5, first benefit of machinery of the present invention is large-caliber pile construction or heavy caliber pipe when passing through, and uses drill bit to creep into, and this method reduces drill bit level torsion by stages, creeps into easilier thereby make, and drilling speed can be faster.It is littler, lighter and handier that the power set of drill bit also can become.
Description of drawings
Fig. 1 is the composition schematic diagram of the present invention's construction machinery of being used for large diameter hollow pile.
Fig. 2 is the structure chart that the present invention has a bit system and row's injection system.
Fig. 3 is the structural representation that the present invention has two bit systems and row's injection system.
Fig. 4 is the one-tenth pile work method schematic diagram of the present invention's construction machinery of being used for large diameter hollow pile.
Among the figure, 1, pile press; 2, chassis; 3, mobile device; 4, power set; 5, hollow pile; 6, high injection stream water filling device; 7, annotate the concrete device; 8 have the drill bit of high injection stream water filling device; 9, drill bit; 10, high jet pipe; 11, drill bit dynamical system; 12, hydraulic pusher; 13, hydro-power pump; 14, hydraulic power transmitting device; 15, discharge pipe; 16, annotate the concrete pipe; 17, hanging apparatus.
The specific embodiment
Below in conjunction with accompanying drawing the specific embodiment of equipment of the present invention and worker's method being done one describes in detail:
As shown in Figure 1, 2, the present invention is used for the construction machinery of large diameter hollow pile, comprise hole-drilling system, row injection system, piling system, described hole-drilling system comprises the drill bit 9, drill bit power set 11, the drill bit stride drilling apparatus 30 that have high injection stream water filling device, is positioned at drill bit top and the integrally formed cylindric retaining wall circle 27 of drill bit; Described piling system comprises hanging apparatus 17, stake machine mobile device 3, piling device; Described row's injection system comprises high injection stream water filling device 6, annotates concrete device 25 and discharge pipe 15; In the inner chamber that creeps into end of hollow pile 5, be fixed with fixed case 20, the upper end of fixed case 20 links to each other with hanging apparatus 17, the lower chassis 23 of fixed case 20 removably is fixed on the flange that creeps into end of hollow pile 5, fixed case 20 internal fixation have drill bit stride drilling apparatus 30, drill bit power set 11 are positioned at the outside of the lower chassis 23 of fixed case 20, be connected on the drill bit stride drilling apparatus 30, drill bit 9 is connected on the drill bit power set 11 by water swivel 21; The notes concrete pipe 16 that is connected with notes concrete device 7 passes fixed case 20 and is fixed on the lower chassis 23, discharge pipe 15 passes fixed case 20 and is fixed on the lower chassis 23, the high jet pipe 10 that is connected with high injection stream water filling device 6 passes fixed case 20 and is fixed on water swivel 21 entrance points, be connected with high spraying nozzle 24 at water swivel 21 ports of export, high spraying nozzle 24 is positioned at the middle part that drill bit 9 bores tooth.
Described row's injection system can also comprise high injection stream grouting device 25, the high injection stream Grouting Pipe 22 that is connected with high injection stream grouting device 25 is passed fixed case 20 and is fixed on water swivel 21 entrance points, be connected with high injection stream slip casting nozzle 26 at water swivel 21 ports of export, high injection stream slip casting nozzle 26 is arranged on the top of drill bit retaining wall circle 27.
Described drill bit is one or more.As shown in Figure 3, for having the structure of two bit systems and row's injection system.
Described hollow pile is a kind of in casing, steel pipe pile or the prefabricated tubular pile.
The present invention is used for the job practices of the construction machinery of large diameter hollow pile, may further comprise the steps:
A, startup are contained in the drill bit that hollow pile creeps into end, start high injection stream water filling device, cutting soil, and the boring pulping makes mud discharge by the plasma discharge system;
B, when soil layer is not too hard, creep in the time of keeping synchronous with piling, synchronously hollow pile is pressed into;
C, when running into hard formation or decomposed rock, start the stride drilling apparatus, boring certain depth earlier, the piling certain depth circulates like this and creeps into piling, promptly asynchronous piling again;
After d, boring reached projected depth, high injection stream water filling device stopped water filling, holds native mesohigh spray cement paste with high injection stream water filling device to stake, and stake end soil is reinforced, and controlled pressure enlarges the churning diameter to form enlarged footing;
E, carry and bore to annotate concrete, pile.
The present invention is used for the job practices of the construction machinery of large diameter hollow pile, also can be may further comprise the steps:
A, startup are contained in the drill bit that hollow pile creeps into end, start high injection stream water filling device, cutting soil, the boring pulping, mud is discharged by the plasma discharge system, start high injection stream grouting device simultaneously, spray cement paste in pile peripheral earth makes all soil of stake become cement earth pile and forms compound pile with hollow pile;
B, when soil layer is not too hard, creep in the time of keeping synchronous with piling, synchronously hollow pile is pressed into;
C, when running into hard formation or decomposed rock, start the stride drilling apparatus, boring certain depth earlier, the piling certain depth circulates like this and creeps into piling, promptly asynchronous piling again;
After d, boring reached projected depth, high injection stream water filling device stopped water filling, holds native mesohigh spray cement paste with high injection stream water filling device to stake, and stake end soil is reinforced, and controlled pressure enlarges the churning diameter to form enlarged footing;
E, carry and bore to annotate concrete, pile.
Described step e is: be a mouth at the bottom of sealing, annotate concrete simultaneously carrying when boring, to certain depth, stop to annotate concrete, propose drilling tool and power set, put into reinforcing cage, annotate concrete, pile once more.
Described step e is: brill is carried on marginal not concrete limit, until reaching absolute altitude, proposes drilling tool.Can also select to insert reinforcing cage again behind the pile.
The construction machinery that the present invention is used for large diameter hollow pile passes through application in engineering at the foundation pile and the push pipe of heavy caliber, overlength, big load.
Drill bit stride drilling apparatus 30 comprises hydraulic pusher 12, hydro-power pump 13 that links to each other with hydraulic pusher 12 and hydraulic power transmitting device 14.
The lower chassis 23 of fixed case 20 is connected bayonet socket 19 by the jig 18 that tightens up or unload from steel pipe or pile tube and is fixed on steel pipe or the pile for prestressed pipe flange inner wall with pile tube.
Below in conjunction with accompanying drawing, forming compound piles with two drill bits is example, and the construction of foregoing invention machinery is elaborated:
Shown in Fig. 4 (a), pile-forming machine perching, the align piles position, with steel pipe (stake) or cement pile for prestressed pipe, and all penetrate drill bit 9, dynamical system 11 etc. in the pore and fix, start drill bit with high injection stream water filling device 6 and begin water spray and creep into, and start high injection stream grouting device 25 simultaneously, spray cement paste in pile peripheral earth.
Shown in Fig. 4 (b), along with creeping into,, start piling mechanism 1 simultaneously in mud pipe 15 holes because the pressure of water is discharged to mud the mud sump of ground, synchronously steel pipe (stake) or pile tube are compressed into (or jacking); Note observing the force value of pile press upward pressure table, too high as force value, then stop synchronous piling.
Shown in Fig. 4 (c), first segment steel pipe (stake) or pile tube are pressed onto after the position, start hanging apparatus 17, the second pipe joint stake of slinging, with whole dynamic transfer systems, discharge pipe 15, high injection stream water filling device 10, high injection stream grouting device 25 etc. pass and connect from the second pipe joint stake.With the second pipe joint stake and first segment pile tube contraposition welding, continue step shown in the earlier figures 4 (b).
Shown in Fig. 4 (d), Fig. 4 (e), when (creeping into) pile sinking, when running into hard interbedded layer or entering bearing stratum, force value shows too high, at this moment, stops piling immediately, changing synchronous piling is asynchronous piling, promptly start hydraulic pusher 12 and promote drill bits and creep into, when creep into finish one stroke after, push rod is shunk in propeller 12 decompressions, begin piling (Fig. 4 (e)) simultaneously, when treating that piling reaches drilling depth, stop piling again, open propeller and creep into the spoil disposal pore-forming once more, move in circles.Asynchronous piling can be avoided drill bit is damaged by pressure.The control of force value should be determined with reference to geologic report and piling practical experience.
Shown in Fig. 4 (f), the boring piling is to the absolute altitude of designing requirement.
Shown in Fig. 4 (g), after piling puts in place, stop piling and water spray, high spray water is converted to soil body mesohigh churning cement paste to the disturbance of stake bottom, and is forced into that 30MPa is above to be sprayed, make the stake end form a cement-soil major part that enlarges, and make cement paste under high drive, upwards pierce, in the crack of pile tube outer wall and inter-pile soil, the slit squeeze note is closely knit with water under high pressure mud.Reach with this and both to improve the end load, improve the effect of side friction again, surpassed the soil compaction stake and change the side friction and end load that drilled pile loses into even remedy.
Shown in Fig. 4 (h), after finishing last high spray cement paste, drill bit 9, jig 18 are connected bayonet socket 19 to be disconnected with pile tube, carry whole apparatuses in drill bit 9 pores such as grade on the pressure injection concrete limit, concrete pipe 16 limit by annotating, when mentioning the reinforcing cage bottom when following, can stop to annotate concrete, whole operation drilling tools and each system are proposed outside the pile tube.
Shown in Fig. 4 (i), in pile tube, insert reinforcing cage.(as design no-reinforcing-bar cage, then Fig. 4 (h) but shown in step marginal not concrete limit carry drilling tool and stop up to the stake top.)
Shown in Fig. 4 (j), perfusion concrete, pile.
If do not start high injection stream grouting device 25 spray cement paste in pile peripheral earth, so just only form single pile.Described hollow pile is a kind of in casing, steel pipe pile or the prefabricated tubular pile.If use casing, casing need be extracted.
For the purpose of explanation, the detailed icon and the explanation of pile sinking have only been listed, as long as the construction sequence that the large diameter pipeline limit is passed through cuts the step of irritating cage and pile bottom reinforcing under the concrete.
The present invention satisfies the construction of high load (more than the 4000KN-6000KN) foundation pile more than major diameter (generally more than the 1m) timber pile long (generally at 50m) and the requirement of equipment, make the bored pile piling of high load, major diameter, timber pile length more guaranteed, speed is faster, thoroughly solves the middle borehole wall-protection of abominable soil layer (as quicksand) and does not become, wears the not difficult problem of saturating hard soil layer.Have the advantage, the especially marine guidance piling that reduce cost, alleviate equipment self-weight, solve a series of problems such as construction difficult problem convenient, laborsaving, quick, economic worker's method is provided.
In sum, thinking of the present invention is:
1, adds one or several high spray drill bits in the lower end of steel pipe or pile tube etc., form mud by the rotation destruction soil body of drill bit and by pile tube or steel casing (pile tube) mesopore; When many drill bits, start high-pressure injection water filling device jetting undisturbed soil body and function jet water column cutting damage between each system's drill bit is formed mud; If be provided with high injection stream grouting device, start high injection stream grouting device simultaneously, spray cement paste in pile peripheral earth makes all soil of stake become cement earth pile and forms compound pile with hollow pile;
2, mud is discharged from the plasma discharge passage, to reach the purpose in hole clearly;
3, along with the progressively intensification in hole, steel pipe (casing) or pile for prestressed pipe are pressed into; Can satisfy the speed of piling or jacking as rate of penetration in weak soil, can be pressed into synchronously,, then utilize the walking propeller to creep into certain depth earlier, and then piling or push pipe promptly adopt asynchronous being pressed into or jacking to this degree of depth as pan soil or decomposed rock etc.
4, treat that steel pipe (casing) or pile for prestressed pipe are pressed onto projected depth after, stop boring and high-pressure spray and inject cement paste, stake end disturbed soil is reinforced and cement paste is pressed in the crack between pile lining and the inter-pile soil to guarantee side friction;
5, drill bit and churning device power set etc. is proposed from casing or pile for prestressed pipe;
6, reinforcing cage is put into steel pipe or pile for prestressed pipe;
7, penetration concrete, pile is finished.
Among the embodiment that content of the present invention is not confined to, the knowledgeable people in the same area can propose other embodiment easily within technological guidance's thought of the present invention, but this embodiment comprises within the scope of the present invention.
Claims (10)
1. construction machinery that is used for large diameter hollow pile, it is characterized in that, comprise hole-drilling system, row injection system, piling system, described hole-drilling system comprises the drill bit (9), drill bit power set (11), the drill bit stride drilling apparatus (30) that have high injection stream water filling device, is positioned at drill bit top and the integrally formed cylindric retaining wall circle (27) of drill bit; Described piling system comprises hanging apparatus (17), stake machine mobile device (3), piling device; Described row's injection system comprises high injection stream water filling device (6), annotates concrete device (7) and discharge pipe (15); In the inner chamber that creeps into end of hollow pile (5), be fixed with fixed case (20), the upper end of fixed case (20) links to each other with hanging apparatus (17), the lower chassis (23) of fixed case (20) removably is fixed on the flange that creeps into end of hollow pile (5), fixed case (20) internal fixation has drill bit stride drilling apparatus (30), drill bit power set (11) are positioned at the outside of the lower chassis (23) of fixed case (20), be connected on the drill bit stride drilling apparatus (30), drill bit (9) is connected on the drill bit power set (11) by water swivel (21); The notes concrete pipe (16) that is connected with notes concrete devices (7) passes fixed case (20) and is fixed on the lower chassis (23), discharge pipe (15) passes fixed case (20) and is fixed on the lower chassis (23), the high jet pipe (10) that is connected with high injection stream water filling device (6) passes fixed case (20) and is fixed on water swivel (21) entrance point, be connected with high spraying nozzle (24) at water swivel (21) port of export, high spraying nozzle (24) is positioned at the middle part that drill bit (9) bores tooth.
2. the construction machinery that is used for large diameter hollow pile according to claim 1, it is characterized in that, described row's injection system also comprises high injection stream grouting device (25), the high injection stream Grouting Pipe (22) that is connected with high injection stream grouting device (25) is passed fixed case (20) and is fixed on water swivel (21) entrance point, be connected with high injection stream slip casting nozzle (26) at water swivel (21) port of export, high injection stream slip casting nozzle (26) is arranged on the top of drill bit retaining wall circle (27).
3. the construction machinery that is used for large diameter hollow pile according to claim 1 and 2 is characterized in that, described drill bit is one or more.
4. the construction machinery that is used for large diameter hollow pile according to claim 1 and 2 is characterized in that, described hollow pile is a kind of in casing, steel pipe pile or the prefabricated tubular pile.
5. described job practices that is used for the construction machinery of large diameter hollow pile of claim 1 may further comprise the steps:
A, startup are contained in the drill bit that hollow pile creeps into end, start high injection stream water filling device, cutting soil, and the boring pulping makes mud discharge by the plasma discharge system;
B, when soil layer is not too hard, creep in the time of keeping synchronous with piling, synchronously hollow pile is pressed into;
C, when running into hard formation or decomposed rock, start the stride drilling apparatus, boring certain depth earlier, the piling certain depth circulates like this and creeps into piling, promptly asynchronous piling again;
After d, boring reached projected depth, high injection stream water filling device stopped water filling, holds native mesohigh spray cement paste with high injection stream water filling device to stake, and stake end soil is reinforced, and controlled pressure enlarges the churning diameter to form enlarged footing;
E, carry and bore to annotate concrete, pile.
6. described job practices that is used for the construction machinery of large diameter hollow pile of claim 2 may further comprise the steps:
A, startup are contained in the drill bit that hollow pile creeps into end, start high injection stream water filling device, cutting soil, the boring pulping, mud is discharged by the plasma discharge system, start high injection stream grouting device simultaneously, spray cement paste in pile peripheral earth makes all soil of stake become cement earth pile and forms compound pile with hollow pile;
B, when soil layer is not too hard, creep in the time of keeping synchronous with piling, synchronously hollow pile is pressed into;
C, when running into hard formation or decomposed rock, start the stride drilling apparatus, boring certain depth earlier, the piling certain depth circulates like this and creeps into piling, promptly asynchronous piling again;
After d, boring reached projected depth, high injection stream water filling device stopped water filling, holds native mesohigh spray cement paste with high injection stream water filling device to stake, and stake end soil is reinforced, and controlled pressure enlarges the churning diameter to form enlarged footing;
E, carry and bore to annotate concrete, pile.
7. according to claim 5 or the 6 described job practicess that are used for the construction machinery of large diameter hollow pile, it is characterized in that, described step e is: be a mouth at the bottom of sealing, when carrying brill, annotate concrete simultaneously,, stop to annotate concrete to certain depth, drilling tool and power set are proposed, put into reinforcing cage, annotate concrete, pile once more.
8. according to claim 5 or the 6 described job practicess that are used for the construction machinery of large diameter hollow pile, it is characterized in that described step e is: brill is carried on marginal not concrete limit, until reaching absolute altitude, proposes drilling tool.
9. the job practices that is used for the construction machinery of large diameter hollow pile according to claim 8 is characterized in that, also comprises, inserts reinforcing cage behind the pile again.
10. claim 1 or the 2 described construction machineries that are used for large diameter hollow pile pass through application in engineering at the foundation pile and the push pipe of heavy caliber, overlength, big load.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2007100605589A CN101215836B (en) | 2007-12-29 | 2007-12-29 | Construction machinery used for large diameter hollow pile and its construction method and use |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2007100605589A CN101215836B (en) | 2007-12-29 | 2007-12-29 | Construction machinery used for large diameter hollow pile and its construction method and use |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN101215836A CN101215836A (en) | 2008-07-09 |
| CN101215836B true CN101215836B (en) | 2010-07-21 |
Family
ID=39622340
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2007100605589A Expired - Fee Related CN101215836B (en) | 2007-12-29 | 2007-12-29 | Construction machinery used for large diameter hollow pile and its construction method and use |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101215836B (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667266A (en) * | 2018-10-18 | 2019-04-23 | 中国海洋大学 | From construction method, device and its matched dedicated tubular pole for boring large-diameter tubular pile |
Families Citing this family (23)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101634146B (en) * | 2008-07-24 | 2011-01-26 | 邢利奥 | Construction device and construction method of artificially digging all-steel casing and retaining wall for building pile foundation |
| CN101737012B (en) * | 2009-12-15 | 2012-08-01 | 北京首尔工程技术有限公司 | Drilling bit for guiding horizontal roatatably-jetting construction and construction method thereof |
| CN102383749A (en) * | 2011-10-09 | 2012-03-21 | 中信重工机械股份有限公司 | Slurry discharging device of power head drill |
| CN102493769A (en) * | 2011-12-16 | 2012-06-13 | 朱宝顺 | Swallow-tailed sliding-type wing-profile drill |
| CN103628480A (en) * | 2012-08-27 | 2014-03-12 | 上海中技桩业股份有限公司 | Construction method and device for guide displacement pressure precast pile |
| CN104727323A (en) * | 2015-03-25 | 2015-06-24 | 张继红 | Self-drilling steel pipe pile continuous wall construction method and steel pipe pile continuous wall used in self-drilling steel pipe pile continuous wall construction method |
| CN104929520A (en) * | 2015-06-05 | 2015-09-23 | 宋姝娴 | Hole protecting drilling machine with circular pipe |
| CN107217985B (en) * | 2017-07-07 | 2023-09-29 | 山东盛唐电气有限公司 | Sector type hollow drilling device |
| CN107386295A (en) * | 2017-07-24 | 2017-11-24 | 能诚集团有限公司 | A kind of sedimentation constructing device of underground structure |
| CN107460869A (en) * | 2017-07-26 | 2017-12-12 | 大成科创基础建设股份有限公司 | Extra high load bearing capacity large-diameter tubular pile and quick pile sinking secondary grouting method |
| CN107574816B (en) * | 2017-09-14 | 2021-03-26 | 广西大学 | Detachable self-rotating bored pipe pile and construction method |
| CN109183827A (en) * | 2018-09-18 | 2019-01-11 | 何文峰 | Underwater reinforced concrete foundation construction operation engineering method |
| CN110607883B (en) * | 2019-02-19 | 2021-08-13 | 宁夏浩鑫塑钢科技有限公司 | A bamboo and wood fiber integrated wall panel |
| CN110821411B (en) * | 2019-11-14 | 2025-01-14 | 河南理工大学 | A kind of expansion stirrer for drilling holes in underwater thick fine sand layer and drilling method using the expansion stirrer |
| CN111622217A (en) * | 2020-05-08 | 2020-09-04 | 浙江大学 | Grouting precast tubular pile after rotary spraying construction and construction process thereof |
| CN111779307B (en) * | 2020-07-10 | 2021-11-02 | 武汉大学 | A non-destructive repair method for reinforced concrete walls based on jet erosion |
| CN112281828A (en) * | 2020-09-16 | 2021-01-29 | 江苏开放大学(江苏城市职业学院) | Novel composite pile structure and construction method |
| CN112695742B (en) * | 2020-11-09 | 2022-07-08 | 垣宝建设工程集团有限公司 | Precast pile and grouting method |
| CN113529725A (en) * | 2021-08-27 | 2021-10-22 | 重庆大学 | Construction system and method of high-pressure water jet rock-breaking cement-soil pile in hard soil foundation |
| CN115748792A (en) * | 2022-12-05 | 2023-03-07 | 浙大城市学院 | Barrel-shaped foundation with resistance reduction system and hinged suction type penetration installation method |
| WO2024119331A1 (en) * | 2022-12-05 | 2024-06-13 | 浙大城市学院 | Bucket foundation with resistance reduction system, and cutter suction penetration installation method |
| CN115977100A (en) * | 2022-12-05 | 2023-04-18 | 浙大城市学院 | A bucket base negative pressure sinking system and method based on a self-drilling flushing water device |
| CN115772899A (en) * | 2022-12-12 | 2023-03-10 | 陕西华山路桥集团有限公司 | A device and method for drilling and cleaning the collapsed hole of cast-in-situ pile reinforcement cage |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3410830C2 (en) * | 1984-03-23 | 1989-05-24 | Stump Bohr Gmbh, 8045 Ismaning, De | |
| CN1710213A (en) * | 2005-07-04 | 2005-12-21 | 雷玉华 | Construction method of synchronous combined pile with high-pressure rotary-spraying pile tip |
| CN201165663Y (en) * | 2007-12-29 | 2008-12-17 | 雷玉华 | Construction machinery of large caliber hollow pile |
-
2007
- 2007-12-29 CN CN2007100605589A patent/CN101215836B/en not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3410830C2 (en) * | 1984-03-23 | 1989-05-24 | Stump Bohr Gmbh, 8045 Ismaning, De | |
| CN1710213A (en) * | 2005-07-04 | 2005-12-21 | 雷玉华 | Construction method of synchronous combined pile with high-pressure rotary-spraying pile tip |
| CN201165663Y (en) * | 2007-12-29 | 2008-12-17 | 雷玉华 | Construction machinery of large caliber hollow pile |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109667266A (en) * | 2018-10-18 | 2019-04-23 | 中国海洋大学 | From construction method, device and its matched dedicated tubular pole for boring large-diameter tubular pile |
Also Published As
| Publication number | Publication date |
|---|---|
| CN101215836A (en) | 2008-07-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101215836B (en) | Construction machinery used for large diameter hollow pile and its construction method and use | |
| CN105735251B (en) | Cutting type full-casing follow-up pile-forming construction method and system of bridge pile foundation rotary drilling rig | |
| CN203452083U (en) | Rotary expanding pile construction equipment and grout feeding device | |
| CN101173517A (en) | Pile-pulling construction method | |
| EP2500473B1 (en) | Method of creating a foundation for a offshore structure | |
| CN104047542B (en) | Embedding rock taper pile impacts drilling pipe hammer system and embedding rock taper pile impacts construction method | |
| CN110273413A (en) | A kind of efficient construction method of prefabricated pile | |
| CN107489158A (en) | A kind of spiral-digging pore stirs the construction method of water spray soil occlusion curtain pile | |
| EP2700750B1 (en) | Foundation pile for offshore structures and method for constructing a foundation pile for offshore structures | |
| CN109025816A (en) | Ultra-deep super thick dense sand stratum pile for prestressed pipe long spire drawing hole construction method | |
| CN109057716A (en) | One kind having water jetting at high pressure stream pore-forming rotary digging drill bit and its construction method | |
| CN106677166A (en) | Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode | |
| CN102808407B (en) | Construction method of soft-foundation reinforced concrete cast-in-place pile | |
| CN205100879U (en) | Crowded counterboring machine is dug soon to sickleleaf style | |
| CN1587544A (en) | Multipurpose controllable slip casting device after cleaving and utilizing process | |
| EP2650446B1 (en) | Method of creating a foundation for a offshore structure | |
| CN104947664A (en) | Thick stone sea-filling layer prestressing force high-strength concrete square pile construction method | |
| CN201165663Y (en) | Construction machinery of large caliber hollow pile | |
| CN106837343A (en) | Push pipe goes out the construction method of hole second consolidation | |
| CN108625388B (en) | Sleeve combined type large-diameter single pile foundation suitable for shallow bedrock geological conditions and construction method thereof | |
| CN103821137B (en) | The construction method of guncreting pile at the bottom of the embedding rock of a kind of long auger, expansion | |
| CN213653445U (en) | Self-tapping type protective cylinder | |
| CN111549782B (en) | Equipment for enlarging grouting reinforcement range | |
| CN210530745U (en) | Combined drilling bottom-expanding pile-planting system | |
| CN209339143U (en) | A kind of concrete pipe pile construction equipment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C17 | Cessation of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100721 Termination date: 20111229 |