CN101195989A - Construction technology of prefabricated bridge based on three steel pipe truss segments - Google Patents

Construction technology of prefabricated bridge based on three steel pipe truss segments Download PDF

Info

Publication number
CN101195989A
CN101195989A CNA2008100172591A CN200810017259A CN101195989A CN 101195989 A CN101195989 A CN 101195989A CN A2008100172591 A CNA2008100172591 A CN A2008100172591A CN 200810017259 A CN200810017259 A CN 200810017259A CN 101195989 A CN101195989 A CN 101195989A
Authority
CN
China
Prior art keywords
steel pipe
bridge
truss
pipe truss
segments
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2008100172591A
Other languages
Chinese (zh)
Other versions
CN100585082C (en
Inventor
刘永健
刘君平
吝红育
刘剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN200810017259A priority Critical patent/CN100585082C/en
Publication of CN101195989A publication Critical patent/CN101195989A/en
Application granted granted Critical
Publication of CN100585082C publication Critical patent/CN100585082C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种基于三种钢管桁架节段的装配式桥梁建造工艺,首先建造桥梁下部结构,其次建造上部结构,先将预制的多段桁架节段依次架设在下部结构之上并拼装组成桥梁承重结构,最终铺设桥面完成桥梁建造,桁架节段的上下弦杆通过腹杆连为一体,预制组成所述承重结构的多段桁架节段前,应先分析各个桁架节段的受力情况,根据受力将其分为三种类型,即上弦杆与下弦杆均不填充混凝土的空钢管桁架节段、受压的上弦杆或下弦杆单独填充混凝土的钢管桁架节段与上弦杆与下弦杆全部填充混凝土的钢管桁架节段。本发明建造工艺简单、所建造桥梁结构受力合理且适用范围广,能有效解决桥梁建造中的施工、造价以及工程质量问题,具有良好的经济效益。

Figure 200810017259

The invention discloses a prefabricated bridge construction process based on three types of steel tube truss segments. First, the substructure of the bridge is constructed, and then the superstructure is constructed. First, prefabricated multiple truss segments are sequentially erected on the substructure and assembled to form a bridge load-bearing structure. Finally, the bridge deck is laid to complete the bridge construction. The upper and lower chords of the truss segments are connected as a whole through a web member. Before prefabricating multiple truss segments that form the load-bearing structure, the stress conditions of each truss segment should be analyzed first, and they are divided into three types according to the stress, namely, empty steel tube truss segments in which both the upper chord and the lower chord are not filled with concrete, steel tube truss segments in which the compressed upper chord or the lower chord is filled with concrete alone, and steel tube truss segments in which both the upper chord and the lower chord are filled with concrete. The invention has a simple construction process, reasonable stress on the constructed bridge structure, and a wide range of applications. It can effectively solve the construction, cost, and engineering quality problems in bridge construction, and has good economic benefits.

Figure 200810017259

Description

基于三种钢管桁架节段的装配式桥梁建造工艺 Construction technology of prefabricated bridge based on three steel pipe truss segments

技术领域technical field

本发明涉及桥梁建造技术领域,尤其是涉及一种基于三种钢管桁架节段的装配式桥梁建造工艺。The invention relates to the technical field of bridge construction, in particular to an assembled bridge construction process based on three steel pipe truss segments.

背景技术Background technique

目前,国内的桥梁建造形式主要是预应力混凝土结构和钢桁架、钢箱梁结构,而钢管混凝土结构和钢管桁架结构在现有桥梁建造工程中的应用也较多。上述桥梁结构形式虽各自具备诸多优点,适用于不同的桥梁建造环境,但同时这些结构也存在一些较大的缺陷。如预应力混凝土箱梁由于其结构材料比强度(材料强度/材料容重)较小,恒载在总荷载中所占比例很大,承受力利用效率低,以致无法适应大跨径桥梁需求;因而实践中为减轻自重,桥梁的腹板通常需设置大量的预应力钢筋,使得施工需要大量的、复杂的机械设备,而且现场施工场地大,施工周期较长。而钢桁架梁用钢量大,结构整体刚度小、节点构造复杂,再加上其节点性能也不好保证,安全系数较低、需定期实施加固等维修措施,使用年限有限制且完全利用钢材承受压力也不经济。对于钢箱梁结构来说,同样用钢量大,焊接要求高,不便于现场制作、拼装和架设,不适宜在山区峡谷地带建造。At present, the domestic bridge construction forms are mainly prestressed concrete structures, steel trusses, and steel box girder structures, and steel pipe concrete structures and steel pipe truss structures are also widely used in existing bridge construction projects. Although the above-mentioned bridge structures have many advantages and are suitable for different bridge construction environments, these structures also have some relatively large defects. For example, the specific strength of prestressed concrete box girders is small due to the specific strength of structural materials (material strength/material bulk density), the dead load accounts for a large proportion of the total load, and the utilization efficiency of bearing capacity is low, so that it cannot meet the needs of long-span bridges; therefore In practice, in order to reduce the self-weight, the web of the bridge usually needs to be equipped with a large number of prestressed steel bars, so that the construction requires a large number of complex mechanical equipment, and the construction site is large and the construction period is long. However, the steel truss girder uses a large amount of steel, the overall structure rigidity is small, and the joint structure is complex. In addition, the performance of its joints is not guaranteed, the safety factor is low, and maintenance measures such as reinforcement are required on a regular basis. The service life is limited and the steel is completely used to withstand pressure. Not economical either. For the steel box girder structure, the steel consumption is also large and the welding requirements are high, which is not convenient for on-site fabrication, assembly and erection, and is not suitable for construction in mountainous and canyon areas.

发明内容Contents of the invention

本发明所要解决的技术问题在于针对上述现有技术中的不足,提供一种基于三种钢管桁架节段的装配式桥梁建造工艺,其建造工艺简单、所建造强梁结构受力合理且适用范围广,能有效解决桥梁建造中的施工、造价以及工程质量问题。The technical problem to be solved by the present invention is to provide a prefabricated bridge construction process based on three steel pipe truss segments in view of the above-mentioned deficiencies in the prior art. , can effectively solve the construction, cost and project quality problems in bridge construction.

为解决上述技术问题,本发明的技术方案是:一种基于三种钢管桁架节段的装配式桥梁建造工艺,首先施工建造桥梁的下部结构,包括用于支撑桥梁上部结构的桥台7、桥墩8以及用于承载二者下传压力的基础;其次施工建造桥梁的上部结构,包括承重结构以及桥面16,先预制组成桥梁承重结构的多段桁架节段,再将其依次架设在下部结构之上并连接拼装组成桥梁承重结构,最终铺设桥面16完成整个桥梁的建造施工,其桁架节段的上弦杆1与下弦杆2通过腹杆3固定连接为一体,预制组成所述承重结构的多段钢管桁架节段之前,应首先分析各个桁架节段在整个桥梁承重结构中所处位置的受力情况,根据受力分析将多段钢管桁架节段分为三种类型,即对上弦杆1与下弦杆2均不受压力或均受压力较小的桁架节段采用上弦杆1与下弦杆2均不填充混凝土的空钢管桁架节段,对上弦杆1或下弦杆2单独受较大压力的桁架节段采用受压的上弦杆1或下弦杆2单独填充混凝土的钢管桁架节段,对于上弦杆1与下弦杆2均受较大压力的桁架节段采用上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段;预制完成后,在工厂或施工现场依受力情况将预制的多段钢管桁架节段固定连接并拼装组成整个桁架结构即桥梁的承重结构。In order to solve the above-mentioned technical problems, the technical solution of the present invention is: a kind of prefabricated bridge construction technology based on three kinds of steel pipe truss segments, first construct the substructure of the bridge, including the abutment 7 and pier for supporting the superstructure of the bridge. 8 and the foundation used to bear the downward pressure of the two; secondly, construct the superstructure of the bridge, including the load-bearing structure and the bridge deck 16. The upper and lower chords 1 and 2 of the truss segments are fixed and connected as a whole through the webs 3, and the multi-sections of the load-bearing structure are prefabricated. Before the steel pipe truss segments, the stress of each truss segment in the entire bridge load-bearing structure should be analyzed first. According to the force analysis, the multi-segment steel pipe truss segments are divided into three types, that is, for the For truss segments with no pressure on rod 2 or less pressure, the empty steel pipe truss segment with no concrete filling in upper chord 1 and lower chord 2 shall be used. The segment adopts the steel pipe truss segment with the upper chord 1 or the lower chord 2 under pressure filled with concrete alone, and the upper chord 1 and the lower chord 2 are all filled with concrete for the truss segment with both the upper chord 1 and the lower chord 2 under greater pressure After the prefabrication is completed, the prefabricated multi-segment steel pipe truss segments are fixedly connected and assembled to form the entire truss structure, that is, the load-bearing structure of the bridge, according to the force conditions at the factory or construction site.

作为本发明的一种优选方案,所述三种类型的钢管桁架节段的上弦杆1与下弦杆2通过腹杆3焊接成一体,腹杆3为空钢管。As a preferred solution of the present invention, the upper chord 1 and the lower chord 2 of the three types of steel pipe truss segments are welded into one body through the web 3, and the web 3 is an empty steel pipe.

作为本发明的另一种优选方案,所述上弦杆1、下弦杆2与腹杆3为矩形、方形或圆形钢管。As another preferred solution of the present invention, the upper chord 1 , the lower chord 2 and the web 3 are rectangular, square or circular steel pipes.

作为本发明的又一种优选方案,所述三种类型的钢管桁架节段之间以法兰盘4或者焊接方式连接构成整体桁架结构。As yet another preferred solution of the present invention, the three types of steel pipe truss segments are connected by means of flanges 4 or welded to form an integral truss structure.

作为本发明的进一步优选方案,所述三种类型钢管桁架节段组成的桁架结构为二榀、三榀或多榀,各榀桁架结构之间通过横连杆5进行连接。As a further preferred solution of the present invention, the truss structure composed of the three types of steel pipe truss segments is two, three or multiple trusses, and the truss structures of each truss are connected by transverse connecting rods 5 .

作为本发明的更进一步优选方案,所述三种类型钢管桁架节段组成的每两榀桁架结构横连杆5组成一个组合榀架,由一个、两个或多个组合榀架构成整体桁架结构。As a further preferred solution of the present invention, every two truss structure transverse links 5 formed by the three types of steel pipe truss segments form a combined truss, and one, two or more combined trusses form an overall truss structure .

作为本发明的再一种优选方案,所述三种钢管桁架节段整体为直线形状或弧线形状。As yet another preferred solution of the present invention, the three steel pipe truss segments are generally in the shape of a straight line or an arc.

综上,采用本发明一种基于三种钢管桁架节段的装配式桥梁建造工艺,具有以下优点:1、建造工艺简单、加工制作及施工方便,受外界建造环境限制少,适合于各种桥梁建造环境;2、适用范围范围广,适用于各种结构形式桥梁的建造;3、所建造桥梁工程质量好且造价低,其桥梁结构自重轻、跨越能力强,与传统钢桁架相比,该结构构造简单、用钢量低,结构整体刚度大、节点性能好,且便于施加预应力;4、采用的三种钢管桁架节段便于工厂标准化制作,而且现场拼装和架设方便,尤其在山区峡谷地带建造特大跨桥梁具有明显优势;5、采用三种钢管桁架节段建造的桥梁结构性能稳固,该结构的拱桥在拱顶区域可采用空钢管节段,有利于提高桥梁结构的稳定性,与传统钢管混凝土拱桥相比,其构造简单,施工方便,混凝土的填充质量好;6、应用于斜拉桥、自锚式悬索桥等体外预应力桥梁结构体系中,通过充分利用钢管混凝土的抗压性能,从而大大减少用钢量。To sum up, the adoption of a prefabricated bridge construction process based on three steel pipe truss segments of the present invention has the following advantages: 1. The construction process is simple, the processing and construction are convenient, and there are few restrictions on the external construction environment, so it is suitable for various bridges The construction environment; 2. The scope of application is wide, and it is suitable for the construction of bridges with various structural forms; 3. The bridges built are of good quality and low cost. The bridge structure has light weight and strong spanning ability. Compared with traditional steel trusses, this The structure is simple, the steel consumption is low, the overall structure rigidity is large, the joint performance is good, and it is easy to apply prestress; 4. The three steel pipe truss segments used are easy to standardize in the factory, and it is easy to assemble and erect on site, especially in mountainous canyons 5. The structural performance of the bridge constructed with three steel pipe truss sections is stable. The arch bridge of this structure can use empty steel pipe sections in the vault area, which is beneficial to improve the stability of the bridge structure. Compared with the traditional CFST arch bridge, its structure is simple, the construction is convenient, and the concrete filling quality is good; 6. It is applied to external prestressed bridge structure systems such as cable-stayed bridges and self-anchored suspension bridges. By making full use of the compressive properties of CFST , thereby greatly reducing the amount of steel used.

下面通过附图和实施例,对本发明的技术方案做进一步的详细描述。The technical solutions of the present invention will be described in further detail below with reference to the accompanying drawings and embodiments.

附图说明Description of drawings

图1是本发明第一优选实施方式基于三种直线型钢管桁架节段的梁桥结构示意图。Fig. 1 is a schematic diagram of a girder bridge structure based on three straight steel pipe truss segments according to the first preferred embodiment of the present invention.

图2是本发明第二优选实施方式基于三种弧线型钢管桁架节段的拱桥结构示意图。Fig. 2 is a schematic diagram of the structure of an arch bridge based on three arc-shaped steel pipe truss segments according to the second preferred embodiment of the present invention.

图3是图1或图2中钢管桁架节段组合连接处P处经放大后的结构示意图。Fig. 3 is an enlarged structural schematic diagram of the combined joint P of steel pipe truss segments in Fig. 1 or Fig. 2 .

图4是图1或图2中钢管桁架节段组合连接处Q处经放大后的结构示意图。Fig. 4 is an enlarged structural schematic diagram of the combined joint Q of steel pipe truss segments in Fig. 1 or Fig. 2 .

图5是本发明第三优选实施方式基于三种钢管桁架节段的中承式拱桥结构示意图。Fig. 5 is a structural schematic diagram of a mid-through arch bridge based on three steel pipe truss segments according to the third preferred embodiment of the present invention.

图6是本发明第三优选实施方式基于三种钢管桁架节段的斜拉桥结构示意图。Fig. 6 is a schematic structural diagram of a cable-stayed bridge based on three steel pipe truss segments according to a third preferred embodiment of the present invention.

图7是本发明第三优选实施方式基于三种钢管桁架节段的悬索桥结构示意图。Fig. 7 is a schematic structural diagram of a suspension bridge based on three steel pipe truss segments according to the third preferred embodiment of the present invention.

图8是本发明基于三种钢管桁架节段的八榀梁桥纵向结构示意图。Fig. 8 is a schematic diagram of the longitudinal structure of the eight-girder bridge based on three steel pipe truss segments according to the present invention.

附图标记说明:Explanation of reference signs:

1-上弦杆;    2-下弦杆;   3-腹杆;1-top chord; 2-bottom chord; 3-web bar;

4-法兰盘;    5-横连杆;   6-支座;4-flange; 5-horizontal connecting rod; 6-support;

7-桥台;      8-桥墩;     9-主拱;7-Abutment; 8-Pier; 9-Main arch;

10-立柱;     11-吊杆;    12-主梁;10-column; 11-suspension rod; 12-main beam;

13-缆索;     14-塔架;    15-锚碇;13-cable; 14-tower; 15-anchor;

16-桥面;     17-地基;    18-螺栓。16-deck; 17-foundation; 18-bolt.

具体实施方式Detailed ways

第一优选实施方式,如图1所示,所述基于三种直线型钢管桁架节段的梁桥建造中,首先施工建造桥梁的下部结构,即用于支撑桥梁上部结构的3个支座6;其次施工建造桥梁的上部结构,包括承重结构以及桥面16,先预制组成桥梁承重结构的多段桁架节段,再将其依次架设在下部结构之上并连接拼装组成桥梁承重结构,最终铺设桥面16完成整个桥梁建造施工。其桁架节段的上弦杆1与下弦杆2通过腹杆3焊接成一体,且三者均为矩形钢管。预制组成所述承重结构的多段钢管桁架节段之前,应首先分析各个桁架节段在整个桥梁承重结构中所处位置的受力情况,根据受力分析将多段钢管桁架节段分为三种类型,即对上弦杆1与下弦杆2均不受压力或受压力较小的桁架节段采用上弦杆1与下弦杆2均不填充混凝土的空钢管桁架节段,对上弦杆1或下弦杆2单独受较大压力的桁架节段采用上弦杆1或下弦杆2单独填充混凝土的钢管桁架节段,对于上弦杆1与下弦杆2均受较大压力的桁架节段采用上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段;预制完成后,在工厂或现场施工过程中依受力情况将预制的多段钢管桁架节段固定连接并拼装组成桥梁的承重结构。The first preferred embodiment, as shown in Figure 1, in the construction of the girder bridge based on three straight steel pipe truss sections, first construct the substructure of the bridge, that is, three supports 6 for supporting the superstructure of the bridge Secondly, construct the upper structure of the bridge, including load-bearing structure and bridge deck 16, prefabricate the multi-section truss segments that form the bridge load-bearing structure earlier, then erect it on the lower structure in turn and connect and assemble to form the bridge load-bearing structure, and finally lay the bridge Surface 16 completes the construction of the entire bridge. The upper chord 1 and the lower chord 2 of the truss segment are welded together through the web 3, and all three are rectangular steel pipes. Before prefabricating the multi-segment steel pipe truss segments that make up the load-bearing structure, the stress situation of each truss segment in the entire bridge load-bearing structure should be analyzed first, and the multi-segment steel pipe truss segments are divided into three types according to the force analysis , that is, for the truss segments with no pressure on the upper chord 1 and the lower chord 2 or with less pressure, the empty steel pipe truss segments with no concrete filling in the upper chord 1 and the lower chord 2 are used. For the truss segment under high pressure alone, the steel pipe truss segment with the upper chord 1 or the lower chord 2 filled with concrete alone is used. 2 Steel pipe truss segments filled with concrete; after prefabrication is completed, the prefabricated multi-segment steel pipe truss segments are fixedly connected and assembled to form the load-bearing structure of the bridge according to the force conditions during the factory or on-site construction.

在图1所示的整个梁桥的承重结构中,各部分受力情况为上弦杆1单独受较大压力或下弦杆2单独受较大压力,因而只单纯地选择一种类型的钢管桁架节段,即受压上弦杆1或下弦杆2单独填充混凝土的钢管桁架节段,腹杆3为空钢管。结合图3、图4,在相邻的钢管桁架节段上弦杆1或下弦杆2中交错填充混凝土,之后将预制好的多段钢管桁架节段以法兰盘4连接构成整体桁架结构即承重结构,最终架设在梁桥两端及中心处的三个支座6上,最终再在整个承重结构上铺设桥面16完成后续工作即可。此种方式装配成的梁桥既能保证良好的承受性能,而且制造工艺简单、省时省料。In the load-bearing structure of the entire girder bridge shown in Figure 1, the stress of each part is that the upper chord 1 is under a greater pressure alone or the lower chord 2 is under a greater pressure alone, so only one type of steel pipe truss section is simply selected. Section, that is, the steel pipe truss segment in which the upper chord 1 or the lower chord 2 under compression is filled with concrete alone, and the web 3 is an empty steel pipe. Combined with Fig. 3 and Fig. 4, the upper chord 1 or the lower chord 2 of the adjacent steel pipe truss segments are filled with concrete alternately, and then the prefabricated multi-section steel pipe truss segments are connected by flanges 4 to form an overall truss structure, that is, a load-bearing structure , finally erected on the three supports 6 at the two ends and the center of the beam bridge, and finally lay the bridge deck 16 on the entire load-bearing structure to complete the follow-up work. The girder bridge assembled in this way can not only ensure good bearing performance, but also has a simple manufacturing process, saving time and materials.

第二优选实施方式,如图2所示,所述基于三种弧线型钢管桁架节段的拱桥建造工艺同第一优选实施方式,其桥梁的承重结构即主拱部分也由多段预制的三种类型钢管桁架节段依桥梁结构受力情况相应进行装配而成,其中钢管桁架节段由上弦杆1、下弦杆2与腹杆3组成,其上弦杆1与下弦杆2通过腹杆3焊接成一体且三者均为矩形钢管。拱桥与梁桥相比,其不仅要承受竖直方向的荷载,而且还要承受水平方向的力。In the second preferred embodiment, as shown in Figure 2, the construction process of the arch bridge based on three arc-shaped steel pipe truss segments is the same as that in the first preferred embodiment, and the load-bearing structure of the bridge, that is, the main arch part, is also made of multi-section prefabricated three Two types of steel pipe truss segments are assembled according to the stress of the bridge structure. The steel pipe truss segments are composed of upper chord 1, lower chord 2 and web 3, and the upper chord 1 and lower chord 2 are welded by web 3. Integrate and all three are rectangular steel pipes. Compared with beam bridges, arch bridges not only bear the load in the vertical direction, but also bear the force in the horizontal direction.

首先,分析各个桁架节段在整个桥梁承重结构中所处位置的受力情况,根据受力分析将多段钢管桁架节段分为三种类型,即对上弦杆1与下弦杆2均不受压力或受压力较小的桁架节段采用上弦杆1与下弦杆2均不填充混凝土的空钢管桁架节段,对上弦杆1或下弦杆2单独受较大压力的桁架节段采用上弦杆1或下弦杆2单独填充混凝土的钢管桁架节段,对于上弦杆1与下弦杆2均受较大压力的桁架节段采用上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段;预制完成后,在工厂或现场施工过程中依受力情况将预制的多段钢管桁架节段固定连接并拼装组成桥梁的承重结构。在拱桥的建造中,根据受力特点,其拱顶中心处所受的压力较小,因而此部分选择上弦杆1与下弦杆2均不填充混凝土的空钢管桁架节段;从拱顶中心处逐渐往外各个钢管桁架节段的上弦杆1所需承受荷载的压力逐渐增大,因而选择上弦杆1单独填充混凝土的钢管桁架节段;而越靠近主拱底部,由于底部支撑作用等的影响其下弦杆2所需承受的压力也逐渐增大,因而选择上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段,腹杆3均为空钢管。结合图3、图4,将预制好的多段三种类型弧线型的钢管桁架节段以法兰盘4连接构成整体桁架结构,并采用螺栓18固定法兰盘4,之后再在整体桁架结构上铺上桥面16完成后续工作即可。First, analyze the stress of each truss segment in the entire bridge load-bearing structure, and divide the multi-segment steel pipe truss segments into three types according to the force analysis, that is, neither the upper chord 1 nor the lower chord 2 is under pressure Or the hollow steel pipe truss segment with upper chord 1 and lower chord 2 not filled with concrete is used for the truss segment with less pressure, and the upper chord 1 or lower chord 2 is used for the truss segment with higher pressure alone The lower chord 2 is a steel pipe truss segment filled with concrete alone, and the upper chord 1 and lower chord 2 are all filled with concrete for the truss segment where the upper chord 1 and lower chord 2 are under greater pressure; after prefabrication is completed, During the factory or on-site construction process, the prefabricated multi-segment steel pipe truss segments are fixedly connected and assembled to form the load-bearing structure of the bridge according to the stress situation. In the construction of arch bridges, according to the force characteristics, the pressure on the center of the vault is relatively small, so this part chooses the empty steel pipe truss segment with no concrete filling in the upper chord 1 and the lower chord 2; from the center of the vault Gradually outward, the upper chord 1 of each steel pipe truss segment needs to bear the load pressure gradually increases, so the steel pipe truss segment with the upper chord 1 filled with concrete alone is selected; the closer to the bottom of the main arch, due to the influence of the bottom support, etc. The pressure to be borne by the lower chord 2 is also gradually increasing, so the steel pipe truss segments in which the upper chord 1 and the lower chord 2 are all filled with concrete are selected, and the web members 3 are all empty steel pipes. Combined with Figure 3 and Figure 4, the prefabricated multi-segment three types of arc-shaped steel pipe truss segments are connected by flanges 4 to form an overall truss structure, and bolts 18 are used to fix the flanges 4, and then the overall truss structure Go up and put bridge deck 16 and finish follow-up work and get final product.

第三优选实施方式,如图5所示,所述基于三种弧线型钢管桁架节段的中承式拱桥建造同第一、第二优选实施方式,首先施工建造桥梁的下部结构即两端的桥台7及其支座6,再在桥台7上架设桥梁的承重结构。本桥梁的承重结构即主拱9也由多段预制的三种类型钢管桁架节段依桥梁结构受力情况相应进行装配而成,其中钢管桁架节段由上弦杆1、下弦杆2与腹杆3组成,其上弦杆1与下弦杆2通过腹杆3焊接成一体且三者均为矩形钢管。若仅供人行走,拱桥所需承受的压力力度较小,则可以把桥面16直接铺在呈弧形的主拱9上。但现代交通工具通行的拱桥桥面16必须保持一定的平直度,不能直接铺在弧线形的主拱9上。拱桥的支撑部分不但要承受竖直方向的压力,还要承受水平方向的作用力。因此拱桥对桥台7与地基17的要求比梁桥要高。而中承式拱桥桥面1 6的一部分在主拱9上方,一部分在主拱9下方,要通过立柱10或吊杆11将桥面16间接支承起来。其中主拱9架设在两端的桥台7上,桥面16的两端分别固定在两个支座6上。The third preferred embodiment, as shown in Figure 5, the construction of the intermediate-supported arch bridge based on three kinds of arc-shaped steel pipe truss segments is the same as that of the first and second preferred embodiments. Abutment 7 and its support 6, and then the load-bearing structure of the bridge is erected on the abutment 7. The load-bearing structure of the bridge, that is, the main arch 9 is also assembled from three types of prefabricated steel pipe truss segments according to the stress of the bridge structure. The upper chord 1 and the lower chord 2 are welded together through the web 3 and all three are rectangular steel pipes. If only for people to walk, the required pressure of the arch bridge is less, then the bridge deck 16 can be directly laid on the curved main arch 9 . But the arch bridge deck 16 that modern vehicles pass through must keep certain straightness, can not be directly paved on the arc-shaped main arch 9. The supporting part of the arch bridge not only bears the pressure in the vertical direction, but also bears the force in the horizontal direction. Therefore, arch bridges have higher requirements on abutment 7 and foundation 17 than girder bridges. And a part of the bridge deck 16 of the middle bearing type arch bridge is above the main arch 9, and a part is below the main arch 9, and the bridge deck 16 will be indirectly supported by the column 10 or the suspension rod 11. The main arch 9 is erected on the abutments 7 at both ends, and the two ends of the bridge deck 16 are respectively fixed on two supports 6 .

在本中承式拱桥的建造中,拱桥桥面16的一部分在主拱9上方,该部分桥面16靠连接固定在地基17与主拱9上的竖直向立柱10支承;另一部分在主拱9下方,该部分桥面16靠连接固定在主拱9上的竖直向吊杆11支承起来。同样地,首先分析各个钢管桁架节段的上弦杆1与下弦杆2所处位置的受力情况,根据受力分析,主拱9处于桥面16上方的部分中,拱顶中心处承受的荷载压力力度较小,因而选择上弦杆1与下弦杆2均不填充混凝土的空钢管桁架节段;从顶端中心处逐渐往外、接近桥面16的部分,上弦杆1与下弦杆2通过吊杆11需承受的压力逐渐增大,因而需采用上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段,腹杆3均为空钢管。对于主拱9处于桥面16下方的部分,其上弦杆1与下弦杆2通过立柱10均需承受很大的压力,因而选择上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段,腹杆3均为空钢管。结合图3、图4,将预制好的多段三种类型弧线型的钢管桁架节段以法兰盘4连接构成整体主拱9桁架结构,并采用螺栓18固定法兰盘4,再铺设桥面19完成后续工作即可。In the construction of this intermediate arch bridge, a part of the arch bridge deck 16 is above the main arch 9, and this part of the bridge deck 16 is supported by vertical columns 10 connected and fixed on the foundation 17 and the main arch 9; Below the arch 9, this part of the bridge deck 16 is supported by vertical suspension rods 11 connected and fixed on the main arch 9. Similarly, firstly analyze the stress situation of the upper chord 1 and the lower chord 2 of each steel pipe truss segment. According to the stress analysis, the main arch 9 is in the part above the bridge deck 16, and the load borne by the center of the vault The pressure is relatively small, so the empty steel pipe truss segment in which the upper chord 1 and the lower chord 2 are not filled with concrete is selected; the upper chord 1 and the lower chord 2 pass through the suspender 11 gradually outward from the center of the top and close to the bridge deck 16 The pressure to be withstood gradually increases, so it is necessary to adopt a steel pipe truss segment in which the upper chord 1 and the lower chord 2 are all filled with concrete, and the web 3 is an empty steel pipe. For the part of the main arch 9 below the bridge deck 16, the upper chord 1 and the lower chord 2 need to bear a lot of pressure through the column 10, so the steel pipe truss segment in which the upper chord 1 and the lower chord 2 are all filled with concrete is selected. Bar 3 is empty steel pipe. Combined with Figure 3 and Figure 4, the prefabricated multi-segment three types of arc-shaped steel pipe truss segments are connected by flanges 4 to form an overall main arch 9 truss structure, and bolts 18 are used to fix the flanges 4, and then the bridge is laid Face 19 to complete the follow-up work.

第四优选实施方式,如图6所示,所述基于三种直线型钢管桁架节段的斜拉桥建造工艺同上述三个优选实施方式,首先施工建造桥梁的下部结构,包括固定主梁12的两个桥墩8以及位于两端的两个支座6,之后在下部结构上架设固定桥梁的承重结构。其桥梁的承重结构即主梁12也由多段预制的三种类型钢管桁架节段依桥梁结构受力情况相应进行装配而成,其中钢管桁架节段由上弦杆1、下弦杆2与腹杆3组成,其上弦杆1与下弦杆2通过腹杆3焊接成一体且三者均为矩形钢管。The fourth preferred embodiment, as shown in Figure 6, the construction process of the cable-stayed bridge based on the three linear steel pipe truss segments is the same as the above three preferred embodiments, first constructing the substructure of the bridge, including fixing the main girder 12 Two piers 8 and two bearings 6 at both ends, and then the load-bearing structure of the fixed bridge is erected on the substructure. The load-bearing structure of the bridge, that is, the main girder 12, is also assembled from three types of prefabricated steel pipe truss segments according to the stress of the bridge structure. The upper chord 1 and the lower chord 2 are welded together through the web 3 and all three are rectangular steel pipes.

在本斜拉桥的建造中,其承重结构两端架设在固定在地基17之上的两个支座6上,中间部分由两个固定在地基17上的竖直向桥墩8支撑,在承重部分即主梁12上方相对两个桥墩8固定设置有两个竖直向的塔架14,同时分别在两个塔架14两侧与承重部分即主梁12之间对称连接设置多根缆索13。同样地,首先分析各个钢管桁架节段的上弦杆1与下弦杆2所处位置的受力情况,根据受力分析,其承重结构即主梁12的各个钢管桁架节段中,其上弦杆1均需承受来自上部荷载的较大水平压力,因而其所有钢管桁架节段的上弦杆1中均填充混凝土。具体来说,在靠近塔架14的部分,上弦杆1与下弦杆2同时需承受来自缆索13的水平压力,因而该部分采用上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段;对于承重部分即主梁12的中间部分以及两端部分,上弦杆1需承受较大的荷载压力,而下弦杆2承受的压力较小,因而选择上弦杆1单独填充混凝土的钢管桁架节段。对于塔架14部分,根据受力分析,靠近主梁12的部分其上弦杆1与下弦杆2均需承受来自缆索13和塔架14自重很大的竖向压力,因而选择上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段;对于塔架14上端部分,因为上弦杆1与下弦杆2承受来自缆索13和塔架14自重的竖向压力较小,因而选择上弦杆1与下弦杆2均不填充混凝土的空钢管桁架节段,而各个钢管桁架节段的腹杆3均为空钢管。结合图3、图4,将预制好的多段三种类型弧线型的钢管桁架节段以法兰盘4连接构成整体主梁12桁架结构,并采用螺栓18固定法兰盘4,再铺设桥面16并完成后续工作即可。In the construction of this cable-stayed bridge, the two ends of the load-bearing structure are erected on two supports 6 fixed on the foundation 17, and the middle part is supported by two vertical piers 8 fixed on the foundation 17. Two vertical towers 14 are fixed above the main girder 12 relative to the two piers 8, and a plurality of cables 13 are symmetrically connected between the two sides of the two towers 14 and the load-bearing part, that is, the main girder 12. . Similarly, firstly analyze the stress situation of the upper chord 1 and the lower chord 2 of each steel pipe truss segment. According to the force analysis, the load-bearing structure, that is, in each steel Both need to bear the large horizontal pressure from the upper load, so the top chord 1 of all its steel pipe truss segments are filled with concrete. Specifically, in the part close to the tower 14, the upper chord 1 and the lower chord 2 need to bear the horizontal pressure from the cable 13 at the same time, so this part uses a steel pipe truss segment in which the upper chord 1 and the lower chord 2 are all filled with concrete; The load-bearing part is the middle part and both ends of the main girder 12. The upper chord 1 needs to bear greater load pressure, while the lower chord 2 bears less pressure. Therefore, the steel pipe truss segment in which the upper chord 1 is filled with concrete alone is selected. For the part of the tower 14, according to the force analysis, the upper chord 1 and the lower chord 2 of the part close to the main beam 12 need to bear the heavy vertical pressure from the cable 13 and the tower 14, so the upper chord 1 and the lower chord are selected The steel pipe truss segment of the rod 2 is filled with concrete; for the upper part of the tower 14, because the upper chord 1 and the lower chord 2 bear less vertical pressure from the cable 13 and the tower 14's own weight, the upper chord 1 and the lower chord 2 are selected 2 are empty steel pipe truss segments that are not filled with concrete, and the web members 3 of each steel pipe truss segment are empty steel pipes. Combined with Figure 3 and Figure 4, the prefabricated multi-segment three types of arc-shaped steel pipe truss segments are connected by flanges 4 to form an overall main girder 12 truss structure, and bolts 18 are used to fix flanges 4, and then the bridge is laid Face 16 and complete the follow-up work.

第五优选实施方式,如图7所示,所述基于三种直线型钢管桁架节段的悬索桥建造工艺同上述四种优选实施方式,首先施工建造桥梁的下部结构,包括固定主梁12的两个桥墩8以及位于两端的两个支座6,之后在下部结构上架设固定桥梁的承重结构。其桥梁的承重结构即主梁12也由多段预制的三种类型钢管桁架节段依桥梁结构受力情况相应进行装配而成,其中钢管桁架节段由上弦杆1、下弦杆2与腹杆3组成,其上弦杆1与下弦杆2通过腹杆3焊接成一体且三者均为矩形钢管。In the fifth preferred embodiment, as shown in Figure 7, the construction process of the suspension bridge based on the three linear steel pipe truss segments is the same as the above four preferred embodiments. There are two piers 8 and two supports 6 at both ends, and then the load-bearing structure of the fixed bridge is erected on the substructure. The load-bearing structure of the bridge, that is, the main girder 12, is also assembled from three types of prefabricated steel pipe truss segments according to the stress of the bridge structure. The upper chord 1 and the lower chord 2 are welded together through the web 3 and all three are rectangular steel pipes.

本悬索桥的建造与斜拉桥大体相同,其承重部分两端架设在固定在地基17之上的两个支座6上,中间部分由两个固定在地基17上的竖直向桥墩8支撑,在承重部分即主梁12上方相对两个桥墩8固定设置有两个竖直向的塔架14。同时在两个塔架14顶端之间搭设一根缆索13,另外从每个塔架14的顶端向外引出一根缆索13并锚固在主梁12两端的锚碇15上。这样便在整个主梁12上方搭设了缆索13,同时在缆索13与主梁12之间均匀连接固定有多根吊杆11。The construction of the suspension bridge is generally the same as that of the cable-stayed bridge. The two ends of the load-bearing part are erected on two supports 6 fixed on the foundation 17, and the middle part is supported by two vertical piers 8 fixed on the foundation 17. Two vertical towers 14 are fixedly arranged above the load-bearing part, that is, the main girder 12 , relative to the two bridge piers 8 . Simultaneously, a cable 13 is set up between the tops of the two towers 14 , and a cable 13 is drawn outwards from the top of each tower 14 and anchored on the anchorage 15 at the two ends of the main beam 12 . In this way, cables 13 are set up above the entire main girder 12, and a plurality of suspenders 11 are evenly connected and fixed between the cables 13 and the main girder 12.

同样地,首先分析各个钢管桁架节段的上弦杆1与下弦杆2所处位置的受力情况,根据受力分析,其承重结构即主梁12的各个钢管桁架节段中,其上弦杆1均需承受来自上部荷载的较大水平压力,因而其所有钢管桁架节段的上弦杆1中均需填充混凝土。具体来说,对于靠近塔架14的部分,其各个钢管桁架节段的下弦杆需承受水平很大的压力,即此部分中上弦杆1与下弦杆2同时均需承受很大的压力,因而该部分采用上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段;对于承重部分即主梁12的中间部分以及两端部分,相对来说需承受的作用力较小,只是上弦杆1需承受较大的压力,而下弦杆2承受的压力较小,因而选择上弦杆1单独填充混凝土的钢管桁架节段。对于塔架14部分,靠近主梁12的部分其上弦杆1与下弦杆2通过吊杆11均需承受来自缆索13和塔架自重很大的竖向压力,因而选择上弦杆1与下弦杆2全部填充混凝土的钢管桁架节段;对于塔架14上端部分,因为上弦杆1与下弦杆2通过吊杆11承受来自缆索13和塔架自重的竖向压力较小,因而选择上弦杆1与下弦杆2均不填充混凝土的空钢管桁架节段,而各个钢管桁架节段的腹杆3均为空钢管。结合图3、图4,将预制好的多段三种类型弧线型的钢管桁架节段以法兰盘4连接构成整体主梁12桁架结构,并采用螺栓18固定法兰盘4,再铺设桥面16并完成后续工作即可。Similarly, firstly analyze the stress situation of the upper chord 1 and the lower chord 2 of each steel pipe truss segment. According to the force analysis, the load-bearing structure, that is, in each steel They all need to bear the large horizontal pressure from the upper load, so the top chord 1 of all steel pipe truss segments needs to be filled with concrete. Specifically, for the part close to the tower 14, the lower chords of each steel pipe truss segment need to bear a large level of pressure, that is, both the upper chord 1 and the lower chord 2 in this part need to bear a lot of pressure at the same time, so This part adopts steel pipe truss segments in which the upper chord 1 and the lower chord 2 are all filled with concrete; for the load-bearing part, that is, the middle part and both ends of the main girder 12, the force to be borne is relatively small, and only the upper chord 1 needs The lower chord 2 bears less pressure, so the steel pipe truss segment in which the upper chord 1 is filled with concrete alone is selected. For the part of the tower 14, the upper chord 1 and the lower chord 2 of the part close to the main beam 12 need to bear the large vertical pressure from the cable 13 and the tower’s own weight through the suspender 11, so the upper chord 1 and the lower chord 2 are selected. A steel pipe truss segment filled with concrete; for the upper part of the tower 14, because the upper chord 1 and the lower chord 2 bear less vertical pressure from the cables 13 and the tower’s own weight through the suspender 11, the upper chord 1 and the lower chord 2 are selected The rods 2 are empty steel pipe truss segments that are not filled with concrete, and the web members 3 of each steel pipe truss segment are empty steel pipes. Combined with Figure 3 and Figure 4, the prefabricated multi-segment three types of arc-shaped steel pipe truss segments are connected by flanges 4 to form an overall main girder 12 truss structure, and bolts 18 are used to fix flanges 4, and then the bridge is laid Face 16 and complete the follow-up work.

综上五种本发明的优选实施方式中,不论是拱桥、斜拉桥,还是悬索桥,均可以根据实际需要建造成二榀、三榀或多榀,以增大所建桥梁的稳固性,增大桥梁的承受能力。如图8所示,所述八榀梁桥由四个组合榀架构成整体桁架结构,各个组合榀架的各榀桁架结构之间通过横连杆5进行连接,通过横连杆5将各个钢管桁架节段的上弦杆1之间、下弦杆2之间连接固定起来。最终在整体桁架结构上铺设桥面16并完成后续工作即可。In summary, in the above five preferred embodiments of the present invention, no matter it is an arch bridge, a cable-stayed bridge, or a suspension bridge, it can be built into two, three or more bridges according to actual needs, so as to increase the stability of the built bridge and increase the stability of the bridge. Bearing capacity of large bridges. As shown in Figure 8, the eight truss girder bridge is composed of four combined trusses to form an overall truss structure, and each truss structure of each combined truss is connected by a horizontal connecting rod 5, and each steel pipe is connected by a horizontal connecting rod 5 The upper chords 1 and the lower chords 2 of the truss segments are connected and fixed. Finally, lay the bridge deck 16 on the overall truss structure and complete the follow-up work.

以上所述,仅是本发明的较佳实施例,并非对本发明作任何限制,凡是根据本发明技术实质对以上实施例所作的任何简单修改、变更以及等效结构变化,均仍属于本发明技术方案的保护范围内。The above are only preferred embodiments of the present invention, and do not limit the present invention in any way. All simple modifications, changes and equivalent structural changes made to the above embodiments according to the technical essence of the present invention still belong to the technical aspects of the present invention. within the scope of protection of the scheme.

Claims (7)

1.一种基于三种钢管桁架节段的装配式桥梁建造工艺,首先施工建造桥梁的下部结构,包括用于支撑桥梁上部结构的桥台(7)、桥墩(8)以及用于承载二者下传压力的基础;其次施工建造桥梁的上部结构,包括承重结构以及桥面(16),先预制组成桥梁承重结构的多段桁架节段,再将其依次架设在下部结构之上并连接拼装组成桥梁承重结构,最终铺设桥面(16)完成整个桥梁的建造施工,其桁架节段的上弦杆(1)与下弦杆(2)通过腹杆(3)固定连接为一体,其特征在于:预制组成所述承重结构的多段钢管桁架节段之前,应首先分析各个桁架节段在整个桥梁承重结构中所处位置的受力情况,根据受力分析将多段钢管桁架节段分为三种类型,即对上弦杆(1)与下弦杆(2)均不受压力或均受压力较小的桁架节段采用上弦杆(1)与下弦杆(2)均不填充混凝土的空钢管桁架节段,对上弦杆(1)或下弦杆(2)单独受较大压力的桁架节段采用受压的上弦杆(1)或下弦杆(2)单独填充混凝土的钢管桁架节段,对于上弦杆(1)与下弦杆(2)均受较大压力的桁架节段采用上弦杆(1)与下弦杆(2)全部填充混凝土的钢管桁架节段;预制完成后,在工厂或施工现场依受力情况将预制的多段钢管桁架节段固定连接并拼装组成整个桁架结构即桥梁的承重结构。1. A prefabricated bridge construction process based on three steel pipe truss segments, first constructing the substructure of the bridge, including an abutment (7) for supporting the superstructure of the bridge, piers (8) and for carrying both The foundation of the downward pressure; secondly, construct the upper structure of the bridge, including the load-bearing structure and the bridge deck (16). For the load-bearing structure of the bridge, the bridge deck (16) is finally laid to complete the construction of the entire bridge. The upper chord (1) and the lower chord (2) of the truss segment are fixedly connected as one through the web (3), and it is characterized in that: prefabricated Before forming the multi-segment steel pipe truss segments of the load-bearing structure, the stress situation of each truss segment in the entire bridge load-bearing structure should be analyzed first, and the multi-segment steel pipe truss segments are divided into three types according to the force analysis. That is, for the truss segments with no pressure on the upper chord (1) and lower chord (2) or less pressure, the empty steel pipe truss segments in which the upper chord (1) and the lower chord (2) are not filled with concrete are used. For the truss segment of the upper chord (1) or the lower chord (2) that is under relatively large pressure alone, the steel pipe truss segment that is filled with concrete by the upper chord (1) or the lower chord (2) under compression, for the upper chord (1 ) and the lower chord (2) are subjected to relatively high pressure, the steel pipe truss segment with the upper chord (1) and the lower chord (2) being filled with concrete; The prefabricated multi-segment steel pipe truss segments are fixedly connected and assembled to form the entire truss structure, which is the load-bearing structure of the bridge. 2.按照权利要求1所述的基于三种钢管桁架节段的装配式桥梁建造工艺,其特征在于:所述三种类型的钢管桁架节段的上弦杆(1)与下弦杆(2)通过腹杆(3)焊接成一体,腹杆(3)为空钢管。2. according to claim 1, based on the prefabricated bridge construction process of three kinds of steel pipe truss segments, it is characterized in that: the upper chord (1) and the lower chord (2) of the three types of steel pipe truss segments pass The web bar (3) is welded into one, and the web bar (3) is an empty steel pipe. 3.按照权利要求1或2所述的基于三种钢管桁架节段的装配式桥梁建造工艺,其特征在于:所述上弦杆(1)、下弦杆(2)与腹杆(3)为矩形、方形或圆形钢管。3. According to claim 1 or 2, the fabricated bridge construction process based on three steel pipe truss segments is characterized in that: the upper chord (1), the lower chord (2) and the web (3) are rectangular , square or round steel pipes. 4.按照权利要求1或2所述的基于三种钢管桁架节段的装配式桥梁建造工艺,其特征在于:所述三种类型的钢管桁架节段之间以法兰盘(4)或者焊接方式连接构成整体桁架结构。4. according to claim 1 or 2 described based on three kinds of steel pipe truss section prefabricated bridge construction technology, it is characterized in that: said three types of steel pipe truss sections are flanged (4) or welded connected to form an overall truss structure. 5.按照权利要求1或2所述的基于三种钢管桁架节段的装配式桥梁建造工艺,其特征在于:所述三种类型钢管桁架节段组成的桁架结构为二榀、三榀或多榀,各榀桁架结构之间通过横连杆(5)进行连接。5. According to claim 1 or 2, the fabricated bridge construction process based on three types of steel pipe truss segments is characterized in that: the truss structure composed of the three types of steel pipe truss segments is two, three or more Each truss structure is connected by a transverse connecting rod (5). 6.按照权利要求5所述的基于三种钢管桁架节段的装配式桥梁建造工艺,其特征在于:所述三种类型钢管桁架节段组成的每两榀桁架结构横连杆(5)组成一个组合榀架,由一个、两个或多个组合榀架构成整体桁架结构。6. according to claim 5 based on the fabricated bridge construction technique of three kinds of steel pipe truss segments, it is characterized in that: every two truss structure transverse connecting rods (5) formed by the three types of steel pipe truss segments A composite truss is composed of one, two or more composite trusses to form an overall truss structure. 7.按照权利要求1或2所述的基于三种钢管桁架节段的装配式桥梁建造工艺,其特征在于:所述三种钢管桁架节段整体为直线形状或弧线形状。7. The fabrication process of bridge construction based on three steel pipe truss sections according to claim 1 or 2, characterized in that: the three steel pipe truss sections are generally in the shape of a straight line or an arc.
CN200810017259A 2008-01-08 2008-01-08 Construction technology of prefabricated bridge based on three steel pipe truss segments Expired - Fee Related CN100585082C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810017259A CN100585082C (en) 2008-01-08 2008-01-08 Construction technology of prefabricated bridge based on three steel pipe truss segments

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810017259A CN100585082C (en) 2008-01-08 2008-01-08 Construction technology of prefabricated bridge based on three steel pipe truss segments

Publications (2)

Publication Number Publication Date
CN101195989A true CN101195989A (en) 2008-06-11
CN100585082C CN100585082C (en) 2010-01-27

Family

ID=39546597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810017259A Expired - Fee Related CN100585082C (en) 2008-01-08 2008-01-08 Construction technology of prefabricated bridge based on three steel pipe truss segments

Country Status (1)

Country Link
CN (1) CN100585082C (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101967793A (en) * 2010-10-28 2011-02-09 南京工业大学 Rapidly Assembled Segmented Composite Truss Bridge
CN102409603A (en) * 2011-07-29 2012-04-11 中铁大桥勘测设计院有限公司 Double-layer steel truss concrete superposed arch structure and construction method thereof
CN102418315A (en) * 2011-09-30 2012-04-18 长沙理工大学 Construction method for concrete-filled steel tube arched bridge with large low-buckle tower erection bridge width
CN104562936A (en) * 2014-12-08 2015-04-29 中铁六局集团有限公司 Construction method for continuous tie bar steel tube arch bridge
CN105568840A (en) * 2014-10-17 2016-05-11 任丘市永基建筑安装工程有限公司 Application of steel bow bridge in municipal road
CN105625175A (en) * 2014-10-27 2016-06-01 任丘市永基建筑安装工程有限公司 Steel arch bridge service life guarantee technology
CN105862593A (en) * 2015-01-20 2016-08-17 任丘市永基建筑安装工程有限公司 Rapid construction method of steel arch bridge
CN105926462A (en) * 2016-06-20 2016-09-07 中山市公路钢结构制造有限公司 A method for erecting a split steel bridge
CN107542032A (en) * 2017-04-25 2018-01-05 江苏沪宁钢机股份有限公司 A kind of safety-type bolt steel girder bridge and its construction technology
CN109056496A (en) * 2018-09-13 2018-12-21 中铁第四勘察设计院集团有限公司 A kind of super-span steel truss continuous bridge having initial curvature and construction method
CN109972491A (en) * 2019-04-30 2019-07-05 泉州理工职业学院 A kind of method of construction of arch bridge structure and arch bridge
CN111364362A (en) * 2020-03-16 2020-07-03 长安大学 Bridge construction process adopting all-welded integral node steel pipe truss chord member prefabricated unit
CN111894053A (en) * 2020-09-08 2020-11-06 江西诚规检测咨询有限公司 A benchmark beam structure for self-balancing load box detection of foundation piles

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85102731B (en) * 1985-04-16 1988-12-21 布亚格斯特 Method for building bridge span and truss type bridge span
CN1081486A (en) * 1993-06-26 1994-02-02 汤国栋 Integrated glass-fibre reinforced plastics, steel pipe concrete cable-carried arch bridge and job practices
CN1730825A (en) * 2004-08-08 2006-02-08 李勇 Steel pipe concrete double Y-type rigid frame bridge

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101967793A (en) * 2010-10-28 2011-02-09 南京工业大学 Rapidly Assembled Segmented Composite Truss Bridge
CN102409603A (en) * 2011-07-29 2012-04-11 中铁大桥勘测设计院有限公司 Double-layer steel truss concrete superposed arch structure and construction method thereof
CN102418315A (en) * 2011-09-30 2012-04-18 长沙理工大学 Construction method for concrete-filled steel tube arched bridge with large low-buckle tower erection bridge width
CN105568840A (en) * 2014-10-17 2016-05-11 任丘市永基建筑安装工程有限公司 Application of steel bow bridge in municipal road
CN105625175A (en) * 2014-10-27 2016-06-01 任丘市永基建筑安装工程有限公司 Steel arch bridge service life guarantee technology
CN104562936A (en) * 2014-12-08 2015-04-29 中铁六局集团有限公司 Construction method for continuous tie bar steel tube arch bridge
CN105862593A (en) * 2015-01-20 2016-08-17 任丘市永基建筑安装工程有限公司 Rapid construction method of steel arch bridge
CN105926462B (en) * 2016-06-20 2018-02-13 中山市公路钢结构制造有限公司 Method for erecting split steel bridge
CN105926462A (en) * 2016-06-20 2016-09-07 中山市公路钢结构制造有限公司 A method for erecting a split steel bridge
CN107542032A (en) * 2017-04-25 2018-01-05 江苏沪宁钢机股份有限公司 A kind of safety-type bolt steel girder bridge and its construction technology
CN109056496A (en) * 2018-09-13 2018-12-21 中铁第四勘察设计院集团有限公司 A kind of super-span steel truss continuous bridge having initial curvature and construction method
CN109056496B (en) * 2018-09-13 2023-12-15 中铁第四勘察设计院集团有限公司 Ultra-large span steel truss continuous beam bridge with initial curvature and construction method
CN109972491A (en) * 2019-04-30 2019-07-05 泉州理工职业学院 A kind of method of construction of arch bridge structure and arch bridge
CN109972491B (en) * 2019-04-30 2024-04-12 泉州职业技术大学 Arch bridge structure and arch bridge construction method
CN111364362A (en) * 2020-03-16 2020-07-03 长安大学 Bridge construction process adopting all-welded integral node steel pipe truss chord member prefabricated unit
CN111894053A (en) * 2020-09-08 2020-11-06 江西诚规检测咨询有限公司 A benchmark beam structure for self-balancing load box detection of foundation piles

Also Published As

Publication number Publication date
CN100585082C (en) 2010-01-27

Similar Documents

Publication Publication Date Title
CN101195989A (en) Construction technology of prefabricated bridge based on three steel pipe truss segments
CN201148590Y (en) A simply supported to continuous beam bridge composed of rectangular steel pipe trusses
Shao et al. Conceptual design of 1000 m scale steel-UHPFRC composite truss arch bridge
CN110777643A (en) A large-span steel truss composite continuous beam structure and its construction method
CN103061243B (en) Prestressed steel tube concrete combination trussed beam and construction method thereof
CN103669194B (en) Based on the continuous rigid frame bridge of steel truss-concrete slab composite beam
CN102140850B (en) Frame with floors of composite grid structure and construction method thereof
CN206328669U (en) The narrow composite beam of steel box of new concrete
CN111979891A (en) A kind of semi-penetrating rectangular steel tube concrete composite truss bridge and construction method
CN212335738U (en) Double-combination continuous truss girder of combined steel web member for highway and railway construction
CN214573257U (en) Truss-suspension cable composite pedestrian bridge structure using cold-formed thin-wall steel
CN107724227A (en) A kind of continuous rigid frame deck type plate arch combined bridge
CN108978432A (en) A medium-span assembled steel hollow sandwich slab bridge and its manufacturing method
CN209816632U (en) Arch foot structure for special-shaped space arch bridge
CN112049078A (en) Truss-like steel aqueduct of wave web
CN111749114A (en) Steel truss-UHPC combined beam bridge hogging moment area structure and construction method
CN207933866U (en) Duplexing font ultra-high performance concrete-normal concrete composite beam bridge girder construction
CN216040610U (en) Large-span deck cable-auxiliary beam arch combined rigid frame bridge
CN216947799U (en) A steel hollow sandwich slab concrete composite channel girder bridge
CN218951933U (en) Large-span upper-bearing type perforated web girder arch combined rigid frame bridge
CN114457667B (en) Large-span top-decker open-hole web-beam-arch composite rigid frame bridge and its construction method
CN211689854U (en) Large-span steel truss combined continuous beam structure
CN214831844U (en) Assembled lacing wire steel pipe concrete composite beam
CN214328474U (en) A prestressed V-truss steel-concrete composite structure bridge
CN216893067U (en) Assembled composite floor system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100127

Termination date: 20110108