CN101122130B - 一种建筑物或桥梁基础用的随钻跟管桩的施工方法 - Google Patents

一种建筑物或桥梁基础用的随钻跟管桩的施工方法 Download PDF

Info

Publication number
CN101122130B
CN101122130B CN200710029023A CN200710029023A CN101122130B CN 101122130 B CN101122130 B CN 101122130B CN 200710029023 A CN200710029023 A CN 200710029023A CN 200710029023 A CN200710029023 A CN 200710029023A CN 101122130 B CN101122130 B CN 101122130B
Authority
CN
China
Prior art keywords
pipe
drilling
pipe body
drill
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN200710029023A
Other languages
English (en)
Other versions
CN101122130A (zh
Inventor
唐孟雄
陈如桂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Municipal Construction Group Co., Ltd.
Guangzhou Institute of Building Science Co Ltd
Original Assignee
GUANGZHOU MUNICIPAL CONSTRUCTION GROUP CO Ltd
Guangzhou Institute of Building Science Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU MUNICIPAL CONSTRUCTION GROUP CO Ltd, Guangzhou Institute of Building Science Co Ltd filed Critical GUANGZHOU MUNICIPAL CONSTRUCTION GROUP CO Ltd
Priority to CN200710029023A priority Critical patent/CN101122130B/zh
Publication of CN101122130A publication Critical patent/CN101122130A/zh
Application granted granted Critical
Publication of CN101122130B publication Critical patent/CN101122130B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其施工步骤是在地面先用钻杆套上高强预应力混凝土管或钢管,钻杆前端安装冲击器和扩孔可收缩钻头,随钻跟管,跟管护壁,钻进至设计标高,终止钻进,退出扩孔可收缩钻头,用泥浆泵抽干净泥浆和沉渣,向管内灌注混凝土,同时向管壁外压力注浆,当混凝土和浆液达到地面时停止;本发明目的是提出一种施工速度快、质量可靠、材料消耗少、桩的承载力高、机械化作业、并保护环境的施工方法,本发明克服了现有钻孔灌注桩施工方法中采用泥浆护壁污染环境、钻进过程中易塌孔、混凝土浇灌质量不稳定、以及预应力管桩易引起土体降起等缺点,采用本发明施工的桩身强度高、桩底无沉渣、桩端全嵌岩,能达到同直径钻孔灌注桩2倍以上的承载力。

Description

一种建筑物或桥梁基础用的随钻跟管桩的施工方法
技术领域
本发明涉及建筑物和桥梁基础用的管桩施工方法,特别涉及一种建筑物或桥梁基础用的随钻跟管桩的施工方法。
背景技术
目前建筑基础常用桩型的施工方法主要有以下几种:
1、人工挖孔桩:由于其成本较低、施工简单、成桩质量较好,单桩的承载力高,建筑工程和桥梁工程常采用该方法,但其缺点是:施工中易发生塌陷和毒气中毒事故,挖桩降水过程破坏周边环境,容易带来安全隐患和产生安全事故,目前已严格限制使用。
2、钻(冲)孔灌注桩:其优点是:机械化程度较高、桩径大小变化灵活、桩的承载力较高,其缺点是:施工泥浆污染环境且造价较高。
3、锤击式沉管灌注桩:其优点是:机械化施工、成本低,其缺点是:桩的承载力低、容易产生断桩和缩颈现象,施工质量难以保证,市区限制使用该桩型。
4、锤击(振动)打入预应力管桩:其优点是:施工质量较好,缺点:桩的承载力不高,施工时噪音较大,桩径大小有限,存在明显的挤土效应,难以满足单柱单桩要求,常用于多层和小高层建筑基础中,在城市中心区因噪音和振动问题,使用受到限制。
5、静压桩:其施工速度快,质量保证,环境影响小,现建筑工程用得较多,但缺点是:桩的承载力不高,最大压桩力不能满足高承载力的要求,单桩承载力一般难以满足单桩单柱要求,存在明显的挤土效应。
发明内容
针对上述桩型施工方法存在的技术问题,本发明提出一种施工速度快、质量可靠、材料消耗少、管桩的承载力高、机械化作业、并保护环境的适于建筑物或桥梁基础用随钻跟管桩的施工方法。
本发明采用以下步骤实现:
a)钻孔定位,钻机就位,第1节管体套上钻杆,用钻机上的夹具夹紧管体,钻杆前端安装潜孔锤冲击器及扩孔可收缩钻头,调整好位置和钻杆的垂直度后开钻,为保护地面孔壁不坍塌,可在地面埋设护筒;
b)潜孔锤冲击器推动扩孔可收缩钻头向下作钻进运动,钻杆带动管体下沉,当第1节管体下沉至距地面20~50cm时,停止钻进,连接第2节管体,钻杆带动管体继续下沉;
c)扩孔可收缩钻头钻进至所需设计标高,停止钻进运动;
d)潜孔锤冲击器及扩孔可收缩钻头从管体内退出,通过钻杆提升至脱离管体;
e)用法兰盘接头连接近孔口最末端的管体、软管及泥浆泵,将管体内泥浆及沉渣抽干净,使管体内成为干孔或充满清水;
f)通过灌注混凝士料斗向管体内灌注混凝土,同时用注浆管向管体外壁与桩孔之间的间隙注浆;
g)当混凝土灌注至管体孔口端,停止灌注混凝土;水泥浆返出地面达到一定浓度时,停止注浆,桩体完成。
上述所述的钻杆前端安装有潜孔锤冲击器及扩孔可收缩钻头,并可钻进地面成孔,空压机通过钻杆向潜孔锤冲击器提供动力,而形成的桩孔用管体进行护壁,提高了桩身的强度。
本发明所述的桩孔顶端设有1.0m~1.5m的护筒,可保护地面孔壁因力度变化引起的坍塌。
所述的管体采用高强预应力混凝土管或钢管,其外径为φ400mm以上,最大可达φ2000mm以上,使管桩可适应设计要求而变化。
本发明所述的管体之间采用焊接或机械式快速接头接合,可达到管体间无缝连接或快速连接,提高了施工速度、施工质量。
本发明所述的施工步骤,是在地面先用钻杆套上高强预应力混凝土管或钢管,钻杆前端安装冲击器和扩孔可收缩钻头,在动力驱动下,钻头向地面进行施工,随钻跟管,跟管护壁,钻进至所需设计标高,即终止钻进,可收缩钻头退出扩孔至地面,用泥浆泵抽干净泥浆和沉渣,向管内灌注混凝土,同时向管壁外压力注浆,当混凝土和浆液达到地面时停止。
本发明克服了钻孔灌注桩施工方法中采用泥浆护壁污染环境、钻进过程中易塌孔、混凝土浇灌质量不稳定的缺点,以及预应力管桩易引起土体降起等缺点,采用本发明施工的桩身强度高、桩底无沉渣、桩端全嵌岩,能达到同直径钻孔灌注桩2倍以上的承载力。
附图说明
下面结合附图对本发明作进一步详细说明:
图1是本发明结构示意图(初始钻进时);
图2是本发明结构示意图(管体连接时);
图3是本发明结构示意图(钻进至设计标高停止钻进时);
图4是本发明结构示意图(扩孔可收缩钻头退出孔口时);
图5是本发明结构示意图(清管时);
图6是本发明结构示意图(灌注混凝土及注浆时);
图7是本发明结构示意图(形成桩体)。
具体实施方式
如图1所示:钻孔定位,钻机就位,第1节管体4套上钻杆7上,所述管体为高强预应力混凝土管或钢管,然后用钻机5上的夹具6夹紧管体4,钻杆7前端安装潜孔锤冲击器3及扩孔可收缩钻头2,调整好位置和钻杆7的垂直度后开钻;为保护钻挖时地面孔口不坍塌,在地面埋设1.0m~1.5m的护筒1。
如图2所示:在潜孔锤冲击器3的作用下,扩孔可收缩钻头2向下钻进,钻杆7带动管体4下沉。当第1节管体4’下沉到距地面20~50cm时,停止钻进,安装第2节管体4”,两节管体之间采用机械式快速接头8连接,随钻进依次接驳多节管体4至所需设计标高。
如图3所示:扩孔可收缩钻头2钻进至设计标高,停止钻进,这时形成桩孔9。
如图4所示:潜孔锤冲击器3及扩孔可收缩钻头2通过钻杆7的向上驱动从管体4内退出,并提升至地面。
如图5所示:用法兰盘接头10连接高强预应力混凝土管或钢管4、软管11及泥浆泵12,将管体4内泥浆及沉渣通过软管11排出、抽干净,使管体4内成为干孔或充满清水,然后拆下泥浆管11。
如图6所示:通过灌注混凝士料斗13向高强预应力混凝土管或钢管4内灌注混凝土15,同时用注浆管14向管体4外壁与桩孔9间隙内通过注入注浆体16,所述的泥浆管14的管径为φ10mm~φ80mm。
如图7所示:当混凝土灌注至地面管孔口,停止灌注混凝土15;当水泥浆体16返出地面达到一定浓度时,停止注浆,完成一条桩的施工。
上述所述第一节管体与第二节管体间的多节管体连接也可采用焊接等方式实现。

Claims (7)

1.一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其特征在于:采用以下步骤:
a)钻孔定位,钻机就位,第1节管体(4’)套上钻杆(7),用钻机(5)上的夹具(6)夹紧管体(4),钻杆(7)前端安装潜孔锤冲击器(3)及扩孔可收缩钻头(2),调整好位置和钻杆(7)的垂直度后开钻,地面孔壁不坍塌,在地面埋设护筒(1);
b)潜孔锤冲击器(3)推动扩孔可收缩钻头(2)向下作钻进运动,钻杆(7)带动管体下沉,当第1节管体(4’)下沉到距地面20~50cm时,停止钻进,连接第2节管体(4”),钻杆(7)带动管体继续下沉;
c)扩孔可收缩钻头(2)钻进至所需设计标高,停止钻进运动;
d)潜孔锤冲击器(3)及扩孔可收缩钻头(2)从管体(4)内退出,通过钻杆(7)提升至脱离管体(4);
e)用法兰盘接头(10)连接近孔口最末端的管体(4)、软管(11)及泥浆泵(12),将管体(4)内泥浆及沉渣抽干净,使管体(4)内成为干孔或充满清水;
f)通过灌注混凝士料斗(13)向管体(4)内灌注混凝土(15),同时用注浆管(14)向管体(4)外壁与桩孔(9)之间的间隙注浆(16);
g)当混凝土灌注至管体(4)孔口端,停止灌注混凝土;水泥浆体返出地面达到一定浓度时,停止注浆。
2.根据权利要求1所述的一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其特征在于:钻杆(7)前端安装潜孔锤冲击器(3)及扩孔可收缩钻头(2)钻进成孔,空压机通过钻杆(7)向潜孔锤冲击器(3)提供动力,形成的桩孔(9)用管体(4)护壁。
3.根据权利要求2所述的一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其特征在于:所述的桩孔(9)顶端设有1.0m~1.5m的护筒(1)。
4.根据权利要求1所述的一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其特征在于:所述的管体(4)为高强预应力混凝土管或钢管,其外径为φ400mm以上。
5.根据权利要求1所述的一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其特征在于:注浆管(14)的管径为φ10mm~φ80mm。
6.根据权利要求1所述的一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其特征在于:所述b)中管体(4’)与管体(4”)之间的连接采用焊接或机械式快速接头(8)接合。
7.根据权利要求1所述的一种建筑物或桥梁基础用的随钻跟管桩的施工方法,其特征在于:所述潜孔锤冲击器(3)在钻机(5)作用下驱动扩孔可收缩钻头(2)向下钻进,钻杆(7)带动管体(4)下沉,同时潜孔锤冲击器(3)及扩孔可收缩钻头(2)可从管体(4)内退出,通过钻杆(7)提升至地面。
CN200710029023A 2007-07-04 2007-07-04 一种建筑物或桥梁基础用的随钻跟管桩的施工方法 Active CN101122130B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710029023A CN101122130B (zh) 2007-07-04 2007-07-04 一种建筑物或桥梁基础用的随钻跟管桩的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710029023A CN101122130B (zh) 2007-07-04 2007-07-04 一种建筑物或桥梁基础用的随钻跟管桩的施工方法

Publications (2)

Publication Number Publication Date
CN101122130A CN101122130A (zh) 2008-02-13
CN101122130B true CN101122130B (zh) 2010-05-19

Family

ID=39084613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710029023A Active CN101122130B (zh) 2007-07-04 2007-07-04 一种建筑物或桥梁基础用的随钻跟管桩的施工方法

Country Status (1)

Country Link
CN (1) CN101122130B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071645A (zh) * 2010-12-31 2011-05-25 中铁大桥局集团有限公司 一种桥梁钻孔桩孔壁口防护方法

Families Citing this family (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102251521A (zh) * 2011-04-26 2011-11-23 东南大学 加固预应力管桩及其施工方法
CN102286976B (zh) * 2011-06-29 2013-03-06 中铁四局集团第一工程有限公司 岩溶地区桩基施工跟进长钢护筒施工的方法
CN102359128A (zh) * 2011-11-01 2012-02-22 中国建筑第八工程局有限公司 桩基入岩判定方法
CN102561946B (zh) * 2012-02-01 2014-07-23 山河智能装备股份有限公司 一种随钻跟管钻机及随钻跟管桩施工方法
CN103835647A (zh) * 2012-11-23 2014-06-04 四川省地质工程勘察院 一种漂卵石层的钻进方法
CN103103985B (zh) * 2013-01-25 2015-09-23 黄吉永 一种基于植桩过程的地源热泵管埋置方法
CN103132908B (zh) * 2013-02-07 2015-06-17 宁波市中乾建筑工程有限公司 潜孔锤凿岩植入嵌岩预应力管桩设备及其施工方法
CN103161164B (zh) * 2013-03-27 2015-04-15 孔超 一种旋压凿岩植入桩底后注浆的嵌岩预应力管桩
CN103527087B (zh) * 2013-09-26 2017-01-11 浙江钱塘江水利建筑工程公司 灌注桩施工工法中冲击成孔方法
CN103526747B (zh) * 2013-09-26 2016-05-18 浙江钱塘江水利建筑工程公司 潮汐环境冲击成孔灌注桩施工工法
CN104563951A (zh) * 2014-12-25 2015-04-29 贵州省交通规划勘察设计研究院股份有限公司 一种冲击成孔钻孔泥浆隔离装置
CN104632100A (zh) * 2014-12-25 2015-05-20 贵州省交通规划勘察设计研究院股份有限公司 一种基于多条出渣管和注浆管的冲击成孔钻孔泥浆隔离装置
CN105735252A (zh) * 2016-03-31 2016-07-06 海南大学 多孔管无砂透水混凝土桩及其安装结构、施工方法
CN107938666B (zh) * 2017-12-26 2023-06-02 浙江大学 带桩靴管桩桩端内锤击沉桩及同步端测注浆结构及工艺
CN108316911B (zh) * 2018-04-04 2023-05-23 广州市建筑科学研究院有限公司 一种用于随钻跟管桩机的自动控制系统
CN108661576B (zh) * 2018-05-10 2019-11-08 中建八局轨道交通建设有限公司 软土地层钻孔灌注桩的成孔装置及其施工方法
CN108868665B (zh) * 2018-06-29 2019-12-31 张家口市宣化正远钻采机械有限公司 一种水井钻机用套管定位推进装置
CN109537669B (zh) * 2018-12-06 2023-08-11 陶德明 连续墙组合矩形锤
WO2021047095A1 (zh) * 2019-09-09 2021-03-18 江西基业科技有限公司 一种连续成桩的施工方法
CN111335312A (zh) * 2020-03-06 2020-06-26 中交第三航务工程局有限公司 大直径锁扣钢管桩入岩施工工艺
CN112324322B (zh) * 2020-09-17 2024-08-06 广州市市政工程试验检测有限公司 一种岩土钻进方法
CN112983258A (zh) * 2021-01-28 2021-06-18 中铁上海工程局集团有限公司 一种用于松散岩层地质的潜孔锤快速成孔施工方法
CN113431490B (zh) * 2021-06-25 2022-11-25 广州市建筑科学研究院集团有限公司 一种用于岩溶地区的大直径管桩施工设备及方法
CN114673452B (zh) * 2022-03-17 2025-10-14 湖南磐石机械有限公司 推压式自护壁成孔灌注桩钻头及钻孔方法
CN115030145B (zh) * 2022-06-24 2023-06-30 广东众安建筑工程有限公司 一种扩翼式钻进跟管桩桩侧注浆施工方法
CN116446466B (zh) * 2023-05-30 2026-03-24 广东工业大学 一种随钻跟管排水抗浮桩及其施工方法
CN116556852B (zh) * 2023-06-14 2026-02-06 江西省勘察设计研究院有限公司 一种适用气动潜孔锤跟管钻进的止水套管及其施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0376923A (ja) 1989-08-19 1991-04-02 Shinwa Kiso Kogyo Kk アースドリル工法におけるケーシングの建込み方法及びその連動連結構造
CN2346837Y (zh) * 1998-09-18 1999-11-03 孔清华 干取土灌注桩钢管护壁装置
CN1544764A (zh) * 2003-11-27 2004-11-10 强 黄 沉管灌注桩施工工艺及其桩端承载力加强器

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0376923A (ja) 1989-08-19 1991-04-02 Shinwa Kiso Kogyo Kk アースドリル工法におけるケーシングの建込み方法及びその連動連結構造
CN2346837Y (zh) * 1998-09-18 1999-11-03 孔清华 干取土灌注桩钢管护壁装置
CN1544764A (zh) * 2003-11-27 2004-11-10 强 黄 沉管灌注桩施工工艺及其桩端承载力加强器

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102071645A (zh) * 2010-12-31 2011-05-25 中铁大桥局集团有限公司 一种桥梁钻孔桩孔壁口防护方法
CN102071645B (zh) * 2010-12-31 2012-10-17 中铁大桥局集团有限公司 一种桥梁钻孔桩孔壁口防护方法

Also Published As

Publication number Publication date
CN101122130A (zh) 2008-02-13

Similar Documents

Publication Publication Date Title
CN101122130B (zh) 一种建筑物或桥梁基础用的随钻跟管桩的施工方法
US11214938B2 (en) Construction method for pouring concrete in karst cave
CN105780763B (zh) 中孔振动套管护壁长螺旋钻孔压灌桩的施工方法
CN101831906B (zh) 一种干式气动凿岩钻孔桩机及其工法
CN100572683C (zh) 大直径超深入岩钻孔扩底灌注桩施工方法
CN100497843C (zh) 全套管大直径振动取土灌注桩施工方法
CN112761076A (zh) 一种应用于水位变化条件下的锁扣钢管桩围堰及施工方法
CN105569560A (zh) 全套管式长螺旋钻孔桩机及利用该桩机施工的方法
CN112746615B (zh) 一种卤水地层淤泥质土灌注桩施工用护筒装置
CN106761474A (zh) 一种可主动运渣土的全套管工法用钢套管及其施工方法
CN113969581A (zh) 一种入岩植桩的施工方法
CN114592795A (zh) 大直径灌注桩硬岩旋挖导向分级扩孔施工方法
CN103485344A (zh) 一种拔除建筑工程桩基的方法
CN110409433B (zh) 利用带钢套筒的灌注桩进行地基处理的施工系统及方法
CN111236233B (zh) 灌注桩清除桩头浮浆的方法
CN105649010A (zh) 一种灌注桩施工工艺
CN112324322A (zh) 一种岩土钻进装置、随钻跟管桩、岩土钻进方法
CN216920297U (zh) 一种长螺旋钻孔压灌混凝土桩的施工装置
CN101503878B (zh) 用薄壁筒桩作围护桩的建筑物基坑围护结构的施工方法
CN112647495A (zh) 一种预制端承管桩的施工方法
CN106930274A (zh) 一种钢筋笼位置固定的全套筒回转钻孔灌注桩施工方法
CN115710903A (zh) 既有工程结构改造钢管桩深入岩施工方法
CN101245597A (zh) 护壁式钻孔灌注桩施工方法及其桩机
CN103498567B (zh) 砌筑墙体内后增暗圈梁抗震加固方法及其加固结构
CN112343045B (zh) 桩尖可回收的静压沉管桩装置及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUANGZHOU INSTITUTE OF BUILDING SCIENCE CO., LTD.

Free format text: FORMER NAME: GUANGZHOU INSTITUTE OF BUILDING SCIENCE

CP01 Change in the name or title of a patent holder

Address after: 510440, No. 833, Baiyun Avenue, Guangzhou, Guangdong

Co-patentee after: Guangzhou Municipal Construction Group Co., Ltd.

Patentee after: Guangzhou Institute of Building Science Co., Ltd.

Address before: 510440, No. 833, Baiyun Avenue, Guangzhou, Guangdong

Co-patentee before: Guangzhou Municipal Construction Group Co., Ltd.

Patentee before: Guangzhou Institute Of Building Science