CN100528731C - Wharf crane and construction method - Google Patents

Wharf crane and construction method Download PDF

Info

Publication number
CN100528731C
CN100528731C CNB200810105493XA CN200810105493A CN100528731C CN 100528731 C CN100528731 C CN 100528731C CN B200810105493X A CNB200810105493X A CN B200810105493XA CN 200810105493 A CN200810105493 A CN 200810105493A CN 100528731 C CN100528731 C CN 100528731C
Authority
CN
China
Prior art keywords
cantilever
wharf crane
column
crane
wharf
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB200810105493XA
Other languages
Chinese (zh)
Other versions
CN101269782A (en
Inventor
刘辉
陈永宏
张启桥
刘建廷
杜官民
邓刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
China Railway Group Ltd CREC
Original Assignee
China Railway Major Bridge Engineering Co Ltd
China Railway Group Ltd CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd, China Railway Group Ltd CREC filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CNB200810105493XA priority Critical patent/CN100528731C/en
Publication of CN101269782A publication Critical patent/CN101269782A/en
Application granted granted Critical
Publication of CN100528731C publication Critical patent/CN100528731C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

本发明的目的是提供一种新型结构的码头吊机及其构建方法,满足了现代大跨度公路、铁路特大桥梁体节段转运需要。本发明一种码头吊机,包括多组立柱以及对应立柱基础、主桁架、起吊桁架、卷扬机起吊系统、滑轮组组成的固定吊点、天车走行系统,还包括有悬臂,该悬臂为主桁架前端与一个立柱、钢管三角支撑构成,其下端与立柱基础铰接,其他立柱与立柱基础固定连接。靠近悬臂的立柱至少一个与主桁架活动连接。在钢管三角支撑内侧设有配重。在立柱处设有配重。主桁架设纵坡,该坡度可设置为0.5%。上述的一种码头吊机的构建方法为:该码头吊机跨越公路、河堤、悬臂延伸至河道上,该码头吊机架设在用于构建新的铁路桥的桥墩处,且该码头吊机主桁架中心线与河道中心线存在一夹角,起吊桁架与公路中线平行。

Figure 200810105493

The object of the present invention is to provide a wharf crane with a new structure and its construction method, which meet the segmental transfer needs of modern long-span highways and railway super-large bridges. The invention relates to a wharf crane, comprising a plurality of sets of columns and corresponding column foundations, a main truss, a lifting truss, a winch hoisting system, a fixed lifting point composed of pulley blocks, a crane running system, and a cantilever, the cantilever is the front end of the main truss It is composed of a column and a steel pipe triangular support, the lower end of which is hinged to the column foundation, and the other columns are fixedly connected to the column foundation. At least one column near the cantilever is movably connected with the main truss. A counterweight is arranged on the inner side of the steel pipe triangular support. There is a counterweight at the column. The main truss is provided with longitudinal slope, which can be set to 0.5%. The construction method of the above-mentioned wharf crane is as follows: the wharf crane spans the road, the embankment, and the cantilever extends to the river, the wharf crane is erected at the pier for building a new railway bridge, and the wharf crane There is an included angle between the centerline of the main truss and the centerline of the river, and the lifting truss is parallel to the centerline of the road.

Figure 200810105493

Description

一种码头吊机及其构建方法 A dock crane and its construction method

技术领域: Technical field:

本发明涉及现代大跨度公路、铁路特大桥梁体节段转运技术领域,具体是在不影响水路及陆路运输的条件下,实现梁体从水道上岸并横移就位的一种码头吊机及其构建方法。The invention relates to the technical field of segmental transshipment of modern long-span highways and railway super-large bridges, in particular to a wharf crane and a wharf crane that realizes the beam body from the waterway to the shore and laterally moves into place without affecting the waterway and land transportation. build method.

背景技术: Background technique:

一般预制梁由水路转运,设置的码头常规采用栈桥法,须占用河道,影响通航;而且栈桥高度有限,对于转运预制梁穿越公路的需要无法满足。更加没有办法满足大跨度公路、铁路特大桥梁体节要求转运要求。Generally, prefabricated girders are transported by water, and the wharf is usually set up by trestle bridge method, which must occupy the river and affect navigation; and the height of trestle bridges is limited, which cannot meet the needs of transshipment of prefabricated beams across the road. There is no way to meet the transshipment requirements of long-span highways and railway super-large bridge body sections.

发明内容: Invention content:

本发明的目的是提供一种新型结构的码头吊机及其构建方法,满足现代大跨度公路、铁路特大桥梁体节段转运需要。The object of the present invention is to provide a new type of wharf crane and its construction method, which can meet the segmental transfer needs of modern long-span highways and railway super-large bridges.

为实现本发明目的采用的技术方案是:一种码头吊机,包括多组立柱以及对应立柱基础、主桁架、起吊桁架、卷扬机起吊系统、滑轮组组成的固定吊点、天车走行系统,还包括有悬臂,该悬臂为主桁架前端与一个立柱、钢管三角支撑构成,其下端与立柱基础铰接,其他立柱与立柱基础固定连接。The technical solution adopted to realize the object of the present invention is: a wharf crane, including multiple groups of columns and corresponding column foundations, main trusses, lifting trusses, hoisting systems, fixed lifting points composed of pulley blocks, and a crane traveling system. There is a cantilever. The cantilever is composed of the front end of the main truss and a column and a steel pipe triangular support. The lower end of the cantilever is hinged to the column foundation, and the other columns are fixedly connected to the column foundation.

靠近悬臂的立柱至少一个与主桁架活动连接。At least one column near the cantilever is movably connected with the main truss.

在钢管三角支撑内侧设有配重。A counterweight is arranged on the inner side of the steel pipe triangular support.

在相邻悬臂的立柱处设有配重。A counterweight is provided at the column of the adjacent cantilever.

主桁架设置纵坡,该坡度可设置为0.5%。The main truss sets the longitudinal slope, which can be set to 0.5%.

上述的一种码头吊机的构建方法为:该码头吊机跨越公路、河堤、悬臂延伸至河道上,该码头吊机架设在用于构建新的铁路桥的桥墩处,且该码头吊机主桁架中心线与河道中心线存在一夹角,起吊桁架与公路中线平行。The construction method of the above-mentioned wharf crane is as follows: the wharf crane spans the road, the embankment, and the cantilever extends to the river, the wharf crane is erected at the pier for building a new railway bridge, and the wharf crane There is an included angle between the centerline of the main truss and the centerline of the river, and the lifting truss is parallel to the centerline of the road.

本发明的积极效果在于:本发明针对现代大跨度公路、铁路特大桥梁体节段由水运上岸并横移就位,开发出的一种新型码头吊机。该码头吊机不但解决了梁体上岸横移就位,又少占河道,并保持水路、陆路通畅;该吊机具体使用时候起吊桁架与主桁架可形成一定夹角,主桁架与桥梁纵向中心线也可成一定夹角;保证转运起吊钢箱梁不受地势的影响。同时,在设计上还采用了三角支撑单向铰接及配重手段,改善结构受力特性。整个结构沿纵向设置了0.5%的纵坡,减小悬臂端在起吊时的挠度;悬臂为主桁架前端与一个立柱、钢管三角支撑构成,其下端与立柱基础铰接,其他立柱与立柱基础固定连接,以及配重,也是为了平衡起吊钢箱梁时的不平衡弯矩;为了不限制在钢箱梁起吊时桁架的上挠,在桁架和第二靠近悬臂的立柱间设置为活动结构,即立柱为只受压结构,在桁架上挠时不参与受力。多点设置配重,一是为了减小单点设置配重的难度;二是在三角斜撑内侧设置配重减小了由于起吊时产生的负弯矩所引起的弦杆内力,改善了结构的受力状态。码头跨越河堤、公路直接将梁体吊运至公路路面,通过台车运至桥位处,组拼平台,大大节省了时间,提高了工作效率。不但解决了梁体上岸横移就位,又少占河道,并保持水路、陆路通畅。The positive effect of the present invention is that: the present invention is a new type of wharf crane developed for the modern long-span highway and railway extra-large bridge body segments to be transported ashore by water and moved laterally into place. The wharf crane not only solves the problem of the horizontal movement of the beam body on the shore, but also occupies less water, and keeps the waterway and land unobstructed; when the crane is actually used, the lifting truss and the main truss can form a certain angle, and the main truss and the longitudinal center of the bridge The line can also form a certain angle; to ensure that the transfer and lifting of the steel box girder will not be affected by the terrain. At the same time, the triangular support one-way hinge and counterweight are also used in the design to improve the mechanical characteristics of the structure. The entire structure is longitudinally set with a 0.5% longitudinal slope to reduce the deflection of the cantilever end during hoisting; the cantilever main truss front end is composed of a column and a steel pipe triangular support, its lower end is hinged to the column foundation, and other columns are fixedly connected to the column foundation , and the counterweight are also to balance the unbalanced bending moment when lifting the steel box girder; in order not to limit the upward deflection of the truss when the steel box girder is hoisted, a movable structure is set between the truss and the second column close to the cantilever, that is, the column As a compression-only structure, it does not participate in the force when the truss is deflected. The counterweight is set at multiple points, one is to reduce the difficulty of setting the counterweight at a single point; the other is to set the counterweight inside the triangular brace to reduce the internal force of the chord caused by the negative bending moment generated during lifting, and improve the structure. stress state. The wharf crosses the embankment and the highway to directly hoist the beam body to the road surface, transport it to the bridge position by trolley, and assemble the platform, which greatly saves time and improves work efficiency. It not only solves the problem of the horizontal movement of the beam body on the bank, but also occupies less river channels, and keeps the water and land routes unobstructed.

附图说明: Description of drawings:

图1本发明码头吊机结构示意图。Fig. 1 is a structural schematic diagram of a wharf crane of the present invention.

图2本发明码头吊机悬臂下端与立柱基础铰接示意图。Fig. 2 is a schematic diagram of the hinged connection between the lower end of the cantilever of the wharf crane of the present invention and the foundation of the column.

图3本发明码头吊机立柱与主桁架活动连接结构示意图。Fig. 3 is a schematic diagram of the movable connection structure between the upright column of the wharf crane and the main truss of the present invention.

图4本发明码头吊机构建示意图。Fig. 4 is a schematic diagram of the construction of the wharf crane of the present invention.

图5-图8本发明码头吊机四阶工况示意图。Figures 5-8 are schematic diagrams of the fourth-order working conditions of the wharf crane of the present invention.

具体实施方式: Detailed ways:

结合附图描述本发明的实施方式,仅仅便于理解发明内容具体实施例子,并非对保护范围的限制。The embodiments of the present invention are described in conjunction with the drawings, which are only for understanding the specific implementation examples of the content of the invention, and are not intended to limit the scope of protection.

一种码头吊机,包括多组立柱1以及对应立柱基础2、主桁架3、起吊桁架4、卷扬机起吊系统、滑轮组组成的固定吊点、天车走行系统,还包括有悬臂5,该悬臂5为主桁架前端与一个立柱、钢管三角支撑52构成,其下端与立柱基础铰接,其他立柱与立柱基础固定连接。第二靠近悬臂的立柱与主桁架活动连接。在钢管三角支撑内侧设有配重6。同时在第二靠近悬臂的立柱处也设有配重。主桁架设纵坡,该坡度可设置为0.5%。上述的一种码头吊机的构建方法为:该码头吊机跨越公路、河堤、悬臂延伸至河道上,该码头吊机架设在用于构建新的铁路桥的桥墩处,且该码头吊机主桁架中心线与河道中心线存在一夹角α,起吊桁架与公路中线平行。A wharf crane, comprising a plurality of sets of columns 1 and corresponding column foundations 2, a main truss 3, a lifting truss 4, a hoisting system, a fixed lifting point composed of pulley blocks, a crane running system, and a cantilever 5, the cantilever 5 The front end of the main truss is composed of a column and a steel pipe triangular support 52, the lower end of which is hinged to the column foundation, and the other columns are fixedly connected to the column foundation. The second column near the cantilever is flexibly connected with the main truss. A counterweight 6 is provided on the inner side of the steel pipe triangular support. Simultaneously, a counterweight is also provided at the second column near the cantilever. The longitudinal slope of the main truss can be set to 0.5%. The construction method of the above-mentioned wharf crane is as follows: the wharf crane spans the road, the embankment, and the cantilever extends to the river, the wharf crane is erected at the pier for building a new railway bridge, and the wharf crane There is an included angle α between the centerline of the main truss and the centerline of the river, and the lifting truss is parallel to the centerline of the road.

结合图5-图8所示四阶工况,以下具体描述荷载计算和码头工况内力计算分析。Combined with the fourth-order working conditions shown in Figures 5-8, the following describes the load calculation and the calculation and analysis of the internal force of the wharf condition in detail.

1、计算荷载:1. Calculate the load:

码头主桁架的主要荷载包括钢箱梁重量、起吊桁架及起吊系统重量、起吊桁架走行机构重量和主桁架自重。The main load of the main truss of the wharf includes the weight of the steel box girder, the weight of the lifting truss and the lifting system, the weight of the running mechanism of the lifting truss and the self-weight of the main truss.

全桥钢箱梁共分62个节段,其中标准梁段长12m,共46段,标准梁段顶、底板加厚8段,特殊制作梁段4段,钢混结合段4段。吊装重量分段统计如下表所示:The steel box girder of the whole bridge is divided into 62 sections, of which the standard beam section is 12m long, 46 sections in total, 8 sections are thickened on the top and bottom of the standard beam section, 4 sections are specially made, and 4 sections are combined with steel and concrete. The statistics of hoisting weight by segment are shown in the table below:

钢箱梁吊装数量统计表Statistical table of steel box girder hoisting quantity

  分类 Classification   A类梁段 Class A beam segment   B类梁段 Class B beam segment   C类梁段 Class C beam segment   D类梁段 Class D beam segment   E类梁段 Class E beam segment   钢混结合段 Steel-concrete joint section   编号 serial number   1# 1#   2#、28# 2#, 28#   3#、27# 3#, 27#   4#~26# 4#~26#   29# 29#   —— ——   数量 quantity   2 2   4 4   4 4   46 46   2 2   4 4 吊装重量Lifting weight 75.4t75.4t 204.7t204.7t 182.5t182.5t 174.9t174.9t 145.5t145.5t 142.3t142.3t

码头计算荷载取钢箱梁最大吊重(考虑1.2的冲击系数):The calculation load of the wharf is taken from the maximum hoisting weight of the steel box girder (considering the impact coefficient of 1.2):

G1=205tG 1 =205t

吊车桁架及附属结构:G2=86.4tCrane truss and auxiliary structures: G 2 =86.4t

走行机构重:G3=39.4tWeight of traveling mechanism: G 3 =39.4t

∑G=1.2G1+G2+G3=1.2×205+86.4+39.4=371.8t∑G=1.2G 1 +G 2 +G 3 =1.2×205+86.4+39.4=371.8t

码头主桁架自重由系统自动计入。The self-weight of the main truss of the wharf is automatically calculated by the system.

2、码头计算2. Wharf calculation

码头计算采用algor93有限元分析软件,建立空间桁架模型。The wharf calculation uses algor93 finite element analysis software to establish a space truss model.

如下表列出了几个主要控制工况。为了平衡悬臂最大时的倾覆力矩,在三角斜撑内侧和第三靠近悬臂的立柱处增加了60t配重。The following table lists several main control conditions. In order to balance the overturning moment when the cantilever is at its maximum, a 60t counterweight is added to the inner side of the triangular brace and the third column near the cantilever.

工况一:起吊钢箱梁的最不利工况,荷载中心悬臂长度14m。此时三角斜撑(受压)和第一靠近悬臂的立柱内侧桁架上弦杆(受拉)受力最大。此时倾覆力矩 Mq = ΣG 2 L = 371.8 2 × 14 = 2602.6 t · m . Working condition 1: the most unfavorable working condition for lifting the steel box girder, the cantilever length of the load center is 14m. At this time, the triangular brace (under compression) and the upper chord (under tension) of the inner truss of the first column close to the cantilever bear the maximum force. overturning moment Q = ΣG 2 L = 371.8 2 × 14 = 2602.6 t · m .

主要工况内力表Main working condition internal force table

  编号 serial number   R1 R1   R2 R2   R3 R3   R4 R4   R5 R5   R6 R6   R7 R7   R8 R8   R9 R9   斜撑 Diagonal brace   标识杆件 Identification bar   工况一 Working condition one   382t 382t   8.9t 8.9t   11.2t 11.2t   220.6t 220.6t   117.7t 117.7t   工况二 Working condition two   124t 124t   157t 157t  68t 68t   45.2t 45.2t   22.1t 22.1t   42t 42t   工况三 Working condition three   96t 96t   122.2t 122.2t  61t 61t   37t 37t   58t 58t   工况四 Working condition four  76t 76t   105t 105t   56.6t 56.6t  14t 14t   58.3t 58.3t

由配重产生的平衡力矩:Mp1=P(L1+L2)=60×(13+33)=2760t·mBalance moment generated by counterweight: M p1 =P(L 1 +L 2 )=60×(13+33)=2760t·m

由桁架产生的平衡力矩:Mp2=GhL3=25×27=675t·mThe balance moment generated by the truss: M p2 = G h L 3 = 25×27=675t·m

安全系数:K=(Mp1+Mp2)/Mq=(2760+675)/2602.6=1.32Safety factor: K=(M p1 +M p2 )/M q =(2760+675)/2602.6=1.32

工况二:起吊桁架运行到第二靠近悬臂的立柱附近,第二靠近悬臂的立柱受压。此时由于配重的关系主桁架的部分立杆和斜杆受力比较大。Working condition 2: The hoisting truss moves to the vicinity of the second column close to the cantilever, and the second column close to the cantilever is under pressure. At this time, due to the relationship between the counterweight, some of the vertical rods and oblique rods of the main truss are relatively stressed.

工况三:起吊桁架运行到第三靠近悬臂的立柱和第四靠近悬臂的立柱之间,上下弦杆受力不作控制,主要为立柱附近的斜杆受力较大。Working condition 3: The hoisting truss runs between the third column close to the cantilever and the fourth column close to the cantilever. The force on the upper and lower chords is not controlled, mainly because the force on the inclined bar near the column is relatively large.

工况四:起吊桁架运行到第四靠近悬臂的立柱和第五靠近悬臂的立柱之间,上下弦杆和立柱附近的斜杆受力均较大。Working condition 4: The hoisting truss runs between the fourth column close to the cantilever and the fifth column close to the cantilever, and the upper and lower chords and the oblique bars near the column are stressed.

Claims (5)

1, a kind of wharf crane, comprise fixedly suspension centre, overhead traveling crane walking system that many group columns and corresponding upright post basic, main couple, a hanging truss, winch tackling system, assembly pulley are formed, it is characterized in that: also include cantilever, this cantilever is that main couple front end and column, a steel pipe gusseted constitute, the column of adjacent cantilever and main couple flexibly connect, and multiple spot is provided with counterweight, and its lower end and upright post basic are hinged, and other columns are captiveed joint with upright post basic; Play hanging truss and main couple and can form certain angle, main couple and bridge longitudinal centerline also can form an angle.
2, a kind of wharf crane of stating as claim 1 is characterized in that: be provided with counterweight in steel pipe gusseted inboard.
3, a kind of wharf crane of stating as claim 1 is characterized in that: the column place in adjacent cantilever is provided with counterweight.
4, a kind of wharf crane of stating as claim 1 or 2 or 3, it is characterized in that: main couple is provided with longitudinal gradient, and this gradient can be set to 0.5%.
5, the construction method as the described a kind of wharf crane of each claim of claim 1-4 is: this wharf crane crossing highway, river levee, cantilever extend on the river course, this wharf crane is erected at the bridge pier place that is used to make up new railway bridge, and there are an angle in this wharf crane main couple line of centers and river course line of centers, play line parallel in hanging truss and the highway.
CNB200810105493XA 2008-04-29 2008-04-29 Wharf crane and construction method Active CN100528731C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB200810105493XA CN100528731C (en) 2008-04-29 2008-04-29 Wharf crane and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB200810105493XA CN100528731C (en) 2008-04-29 2008-04-29 Wharf crane and construction method

Publications (2)

Publication Number Publication Date
CN101269782A CN101269782A (en) 2008-09-24
CN100528731C true CN100528731C (en) 2009-08-19

Family

ID=40004049

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB200810105493XA Active CN100528731C (en) 2008-04-29 2008-04-29 Wharf crane and construction method

Country Status (1)

Country Link
CN (1) CN100528731C (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103508324B (en) * 2013-03-12 2015-07-01 中国有色金属工业第六冶金建设有限公司 Method for hoisting main large components of KP125MN hot die forging press
CN103787203B (en) * 2013-12-16 2016-06-08 重庆岩安科技有限公司 For installing the bracing frame of precast beam jack
CN108423565B (en) * 2018-04-18 2019-06-14 中铁十九局集团轨道交通工程有限公司 Erection and dismantling construction method of U-shaped double girder hook gantry crane
CN109763426A (en) * 2018-12-18 2019-05-17 中铁广州工程局集团有限公司 A ship loading method for long-span steel tube arch segments
CN111980049A (en) * 2020-09-09 2020-11-24 中铁六局集团有限公司 Foundation device and construction method of deep riverbed mast-type quay crane
CN112301869A (en) * 2020-11-24 2021-02-02 广东水利电力职业技术学院(广东省水利电力技工学校) A kind of wharf steel trestle and method for crossing embankment
CN114108811B (en) * 2021-11-30 2023-07-11 中建钢构工程有限公司 Unsupported installation method of super high-rise conversion truss
CN119306117B (en) * 2024-12-19 2025-04-25 山西韵通机械设备制造有限公司 Positioning hanging device for box girder installation

Also Published As

Publication number Publication date
CN101269782A (en) 2008-09-24

Similar Documents

Publication Publication Date Title
CN100528731C (en) Wharf crane and construction method
CN102953342B (en) Assembling and lifting method of half-span skeleton of tied arch bridge
CN101215819B (en) Separated double-layer bridge-floor cable stayed bridge
CN206538672U (en) Novel fabricated truss steel trestle
CN110130203B (en) Upper-bearing arch-rigid frame continuous beam combined bridge and construction method
CN105484163B (en) Pier construction method after a kind of cable-stayed bridge auxiliary pier pier top sections elder generation beam
CN114263114A (en) Construction system and construction method of large-section steel box girder
CN111608086A (en) A kind of steel composite beam lateral flat roof construction structure and method
CN101481903B (en) The method of erecting the main truss of the suspension bridge in mountainous area by reversing the cable-span crane
CN110468743B (en) A mobile hanger and construction method for the renovation of old bridge pier caps
CN114790693B (en) Construction method of large-span river-crossing steel truss bridge structure
CN209652741U (en) A long-span viaduct across railway stations
CN105133484A (en) Cable-stayed bridge structure with high and low towers for partial ground anchors
CN111254837A (en) Construction method for building bridge by bridge crane fishing method
CN206800178U (en) A kind of steel reinforced concrete combines gate-type pier structure
CN202644410U (en) Protection canopy frame of triangle-shaped trusswork
CN209906222U (en) A loop wheel machine that descends river for large-span steel pipe encircles segment lift shipment
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN111851307A (en) Construction method of large-span prefabricated corrugated web composite box girder transport frame
CN204703068U (en) A kind of up suspention section assembling traversing carriage bridge fabrication machine
CN201943006U (en) Main tower zone movable bracket for assisting non-variable amplitude girder erecting crane to erect steel box girders
CN210216110U (en) Box girder bridge is assembled to split type prefabricated segment of pier top crossbeam of encorbelmenting greatly
CN111705682A (en) A construction method and equipment for demolition and reconstruction of superstructure of widened bridge across electrified railway
CN204919348U (en) Supplementary head tower of using of self anchored suspension bridge installation
CN109592569B (en) A river crane used for lifting and loading large-span steel pipe arch segments

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150324

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150324

Address after: Chinese Railway Building No. 26 Beijing 100021 Fengtai District Lianhuachi South Lane

Patentee after: China Railway Group Co., Ltd.

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: Chinese Railway Building No. 26 Beijing 100021 Fengtai District Lianhuachi South Lane

Patentee before: China Railway Group Co., Ltd.

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.