CH152681A - Steam generator. - Google Patents

Steam generator.

Info

Publication number
CH152681A
CH152681A CH152681DA CH152681A CH 152681 A CH152681 A CH 152681A CH 152681D A CH152681D A CH 152681DA CH 152681 A CH152681 A CH 152681A
Authority
CH
Switzerland
Prior art keywords
boiler
water content
steam generator
auxiliary
steam
Prior art date
Application number
Other languages
German (de)
Inventor
Cie Aktiengesellschaft Boveri
Original Assignee
Bbc Brown Boveri & Cie
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Bbc Brown Boveri & Cie filed Critical Bbc Brown Boveri & Cie
Publication of CH152681A publication Critical patent/CH152681A/en

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22BMETHODS OF STEAM GENERATION; STEAM BOILERS
    • F22B31/00Modifications of boiler construction, or of tube systems, dependent on installation of combustion apparatus; Arrangements or dispositions of combustion apparatus
    • F22B31/04Heat supply by installation of two or more combustion apparatus, e.g. of separate combustion apparatus for the boiler and the superheater respectively

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Control Of Steam Boilers And Waste-Gas Boilers (AREA)

Description

  

  Dampferzeuger.    Den Gegenstand der Erfindung bildet ein  Dampferzeuger mit schnellster Anpassungs  fähigkeit und grossem Speicherungsvermögen.  



  Oft ist man gezwungen, eine thermische  Zentrale als Momentanreserve zu errichten,  die während des grössten Teils des Jahres  keinen elektrischen Strom abzugeben hat. Sie  muss aber in der Lage sein, jeden     Augen-          blich    sofort Leistung abzugeben, wenn bei  spielsweise eine Störung auf dem Überland  netz erfolgt. Da sich ferner eine solche Zen  trale meistens in der Nähe der Stromvertei  lung befindet, wünscht man die elektrischen  Generatoren während des lastlosen Betriebes  als Phasenschieber zu benützen. Insofern es  sich um Turbogeneratoren handelt, lässt man  die Turbine mit dem Generator gekuppelt  im Vakuum mitlaufen, um die Verluste der  Ventilation und Reibung auf ein Minimum  zu beschränken.

   Das Vakuum wird vom Kon  densator erzeugt; doch ist es nötig, dass die  Turbine, respektive deren Stopfbüchse dabei  stets mit einer gewissen Dampfmenge ge  speist wird, welche auch dazu dienen muss,    die Turbine warm zu halten, respektive zu  kühlen, so dass sie wirklich in der Lage ist,  augenblicklich     Leistung    abzugeben. Es wer  den heute Kessel mit sehr grosser Anpas  sungsfähigkeit gebaut, so dass der Kessel,  wenn er     warm    gehalten wird, in     wenigen     Minuten von der     Verdampfungsmenge    Null  auf die maximale     Verdampfungsmenge    ge  steigert werden kann.

   Das Prinzip dieser  Kessel besteht darin, eine möglichst kleine  Wassermenge zu haben, aber eine sehr grosse,       unmittelbar    durch Strahlung geheizte Heiz  fläche. Da aber der Kessel einen kleinen  Wasserinhalt hat, ist er anderseits nicht in  der Lage, unmittelbar beim Auftreten der  Belastung Dampf abzugeben, und es ist des  halb schon versucht worden, ihn mit einem  Dampfspeicher, beispielsweise einem     Ruth's-          Speicher,    zu kuppeln. Eine Zentrale, wie die  oben     beschriebene,    benötigt aber auch im  lastlosen Betrieb,     wie    gesagt, stets eine ge  wisse Dampfmenge.  



       Vm.    allen diesen Anforderungen gerecht  zu werden, soll der Dampferzeuger gemäss      der Erfindung zwei miteinander verbundene  Teile verschiedener Wirkungsweise aufwei  sen, von denen der eine Teil einen kleinen  Wasserinhalt und eine grosse, wassergekühlte       Strahlungsfläche    besitzt, die der Wirkung  der Hauptfeuerung ausgesetzt ist, und der  andere Teil einen grossen Wasserinhalt auf  weist, der der Wirkung einer Hilfsfeuerung  ausgesetzt ist, wobei die Hilfsfeuerung so  bemessen ist und geregelt wird, dass im last  losen Betrieb die Hilfsfeuerung genügt, um  den gesamten Kessel warm zu halten und  eine kleine, von der Turbine benötigte  Dampfmenge, abzugeben.  



  In der Zeichnung ist schematisch eine  beispielsweise Ausführung eines solchen  Doppelwirkungskessels dargestellt. Dieser  Doppelwirkungskessel besteht aus einem Teil  B mit kleinem Wasserinhalt und grosser  Strahlungsfläche, das heisst gebaut für rasche       Anpassungsfähigkeit,    und einem Teil A mit  grossem Wasserinhalt, der während des last  losen     Betriebes        unmittelbar    geheizt wird und  dessen Verbrennungsgase zugleich den Teil B  warm halten. In der Zeichnung ist angenom  men, dass der Kessel mit Rohöl gefeuert  wird. Im lastlosen     Betrieb    ist also der  Hauptbrenner H des Teils B     ausser    Betrieb,  während der Hilfsbrenner E des Teils A  brennt.

   Dieser     Brenner    kann durch einen  Thermostaten F gesteuert werden, wie an  gedeutet, so dass der Druck im Dampfsystem  stets     selbsttätig    um einige Atmosphären  höher gehalten wird, als der normale Be  triebsdruck, für den die     Turbine    gebaut ist.

    Während bei einer gewöhnlichen Speicher  anlage der Druck aber um viele Atmosphä  ren schwanken kann, so dass eine besondere  Speicherturbine benötigt wird, die teuer ist  und einen verringerten Wirkungsgrad hat,  kann hier eine normale Turbine verwendet  werden; denn in den     wenigen    Minuten der  ersten Belastung, während welchen der  Dampf vom Teil A .des Kessels geliefert  wird, soll der     Druck    nur wenig unter den  normalen Betriebsdruck sinken, ehe der Teil       B-    in Wirkung tritt und ,den Druck auf sei  nen Normalwert zurückführt und den be-    nötigten Dampf liefert.

   Der Hauptbrenner     H     tritt sofort in Wirkung, sobald der Druck im  Dampfsystem abnimmt, das heisst, sobald  eine Belastung erfolgt und der Hilfsbrenner  nicht mehr in der Lage ist, die benötigte  Dampfmenge zu erzeugen. Während des  lastlosen Betriebes wird die benötigte kleine  Speisewassermenge von der Hilfspumpe D  in den Kessel gedrückt; wird dagegen vom  Teil B Dampf entwickelt, das heisst sinkt  der Wasserspiegel in diesem Teil unter den  Normalwert, so tritt die     Hauptspeisepumpe     C mit .dem zugehörigen Speisewassermengen  regler in Betrieb.

   Da die beiden Teile A und  B des Kessels mit einem oder mehreren       W        asserausgleichrohren        !12    N in Verbindung  stehen, haben sie auch im lastlosen     Betrieb          nahezu,den    gleichen Speisewasserspiegel, und  der Teil B des Kessels benötigt gar keine  Wartung, während für .den Teil A eine ge  ringe Wartung erforderlich ist.  



  Dadurch, dass der Hilfsbrenner E (oder  die Hilfsfeuerung) in das Innere des Kessel  teils A mit grossem Wasserinhalt verlegt  wurde; ist erreicht,     dass    die Verluste an  Wärme auf ein Mindestmass     beschränkt    blei  ben, und dass das Wasser in diesem Teil des  Kessels auf     Siedetemperatur    gehalten     wird,     so dass man sicher ist, dass im Moment des  Auftretens der     Belastung    augenblicklich der  nötige Dampf     entwickelt    werden kann.

   Die  Abgase dieses Teils A des Kessels sind in  der Lage, den andern Teil B des Kessels  weiter zu     wärmen;    zudem ist auf der Zeich  nung das Verbindungsrohr<I>M N</I> so angeord  net, dass während ,des lastlosen Betriebes das  Wasser im Kesselteil A oben, das heisst an  der wärmsten Stelle entnommen und in den  Kesselteil B an der tiefsten Stelle eingeführt  wird, wodurch ein Übertragen von Wärme  aus dem Kesselteil<I>A</I> in den Kesselteil<I>B</I>  erzielt wird.



  Steam generator. The object of the invention forms a steam generator with the fastest adaptability and large storage capacity.



  Often one is forced to set up a thermal center as an instantaneous reserve that does not have to provide any electricity for most of the year. However, it must be in a position to immediately deliver service immediately if, for example, there is a fault on the overland network. Furthermore, since such a Zen center is usually located near the Stromvertei development, you want to use the electrical generators as phase shifter during no-load operation. As far as turbo generators are concerned, the turbine coupled with the generator is allowed to run in a vacuum in order to limit the losses of ventilation and friction to a minimum.

   The vacuum is created by the capacitor; However, it is necessary that the turbine or its stuffing box is always fed with a certain amount of steam, which must also be used to keep the turbine warm or to cool it, so that it is really able to deliver power instantaneously . Today the boiler is built with a very high level of adaptability, so that the boiler, if it is kept warm, can be increased from zero to the maximum amount of evaporation in a few minutes.

   The principle of this boiler is to have the smallest possible amount of water, but a very large heating surface that is directly heated by radiation. On the other hand, since the boiler has a small water content, it is not able to emit steam immediately when the load occurs, and attempts have therefore already been made to couple it with a steam store, for example a Ruth's store. A control center like the one described above, however, always requires a certain amount of steam even in no-load operation, as I said.



       Vm. To meet all of these requirements, the steam generator according to the invention should have two interconnected parts of different modes of operation, one part of which has a small water content and a large, water-cooled radiation surface that is exposed to the effect of the main combustion, and the other part has a large water content that is exposed to the effect of an auxiliary heating system, whereby the auxiliary heating system is dimensioned and regulated in such a way that in unloaded operation the auxiliary heating system is sufficient to keep the entire boiler warm and a small amount of steam required by the turbine, submit.



  In the drawing, an example of an embodiment of such a double-action boiler is shown schematically. This double-action boiler consists of part B with a small water content and a large radiant surface, i.e. built for quick adaptability, and part A with a large water content, which is heated immediately during unloaded operation and whose combustion gases also keep part B warm. In the drawing it is assumed that the boiler is fired with crude oil. In no-load operation, the main burner H of part B is out of operation, while the auxiliary burner E of part A is burning.

   This burner can be controlled by a thermostat F, as indicated, so that the pressure in the steam system is always automatically kept a few atmospheres higher than the normal operating pressure for which the turbine is built.

    While in a normal storage system the pressure can fluctuate by many atmospheres, so that a special storage turbine is required, which is expensive and has a reduced efficiency, a normal turbine can be used here; because in the few minutes of the first load, during which the steam is supplied by part A of the boiler, the pressure should drop only a little below the normal operating pressure before part B takes effect and returns the pressure to its normal value and supplies the necessary steam.

   The main burner H takes effect immediately as soon as the pressure in the steam system decreases, that is, as soon as a load occurs and the auxiliary burner is no longer able to generate the required amount of steam. During the no-load operation, the required small amount of feed water is pressed into the boiler by the auxiliary pump D; if, on the other hand, steam develops from part B, i.e. if the water level in this part falls below the normal value, the main feed pump C comes into operation with the associated feed water volume regulator.

   Since the two parts A and B of the boiler are connected to one or more water equalization pipes! 12 N, they have almost the same feed water level even in no-load operation, and part B of the boiler does not require any maintenance, while for the part A little maintenance is required.



  Because the auxiliary burner E (or the auxiliary firing) was relocated to the interior of the boiler part A with a large amount of water; it is achieved that the loss of heat is kept to a minimum, and that the water in this part of the boiler is kept at boiling temperature, so that one can be sure that the necessary steam can be developed immediately when the load occurs.

   The exhaust gases from this part A of the boiler are able to further heat the other part B of the boiler; In addition, the connection pipe <I> MN </I> is arranged on the drawing so that, during no-load operation, the water in boiler part A is taken from the top, i.e. at the warmest point, and introduced into boiler part B at the lowest point is achieved, whereby a transfer of heat from the boiler part <I> A </I> in the boiler part <I> B </I> is achieved.

 

Claims (1)

PATENTANSPRUCH: Dampferzeuger für eine als Momentan reserve dienende Zentrale, dadurch gekenn zeichnet, dass er einen Teil mit kleinem Was- serinhalt und grosser wassergekühlter Strah lungsfläche besitzt, die der Wirkung der Hauptfeuerung ausgesetzt ist und einen zweiten, mit dem ersten verbundenen Teil mit grossem Wasserinhalt, der der Wirkung einer Hilfsfeuerung ausgesetzt ist, deren Heizgase auch zum ersten Teil gelangen, wo bei die Hilfsfeuerung so bemessen ist und geregelt wird, dass im lastlosen Betrieb die Hilfsfeuerung genügt, um den gesamten Kes sel warm zu halten und eine kleine Dampf menge, die von der Turbine benötigt wird, abzugeben. <B>UNTERANSPRÜCHE:</B> 1. PATENT CLAIM: Steam generator for a control center serving as a momentary reserve, characterized in that it has a part with a small water content and a large water-cooled radiant surface that is exposed to the effect of the main combustion and a second part with a large water content, which is connected to the first that is exposed to the effect of an auxiliary heating system, the heating gases of which also reach the first part, where the auxiliary heating system is dimensioned and regulated so that in no-load operation the auxiliary heating system is sufficient to keep the entire boiler warm and a small amount of steam, which is required by the turbine to be delivered. <B> SUBClaims: </B> 1. Dampferzeuger nach Patentanspruch, da durch gekennzeichnet, dass .die Hilfsfeue rung durch einen Thermostaten gesteuert wird, derart, .dass der Druck während des lastlosen Betriebes im System einige Atmosphären über dem Normaldruck ge- halten wird, dass ferner dabei die Speisung durch eine Hilfspumpe erfolgt, während beim Eintreten der Belastung, das heisst bei sinkendem Druck, selbsttätig die Hauptfeuerung und die Hauptspeisepumpe in Wirksamkeit treten. 2. Steam generator according to patent claim, characterized in that the auxiliary fire is controlled by a thermostat in such a way that the pressure in the system during no-load operation is kept a few atmospheres above normal pressure, and that the supply is also carried out by an auxiliary pump , while when the load occurs, that is to say when the pressure drops, the main combustion and the main feed pump automatically come into effect. 2. Dampferzeuger nach Patentanspruch, da durch gekennzeichnet, dass ein oder meh rere Verbindungsrohre zwischen dem Kes- selteil mit grossem Wasserinhalt und dem jenigen mit grosser Strahlungsfläche so angeordnet sind, dass im lastlosen Betrieb das Wasser an der wärmsten Stelle des Kesselteils mit grossem Wasserinhalt ent nommen und der tiefsten Stelle des Kes selteils mit grosser Strahlungsfläche zuge führt wird, um einen guten Wärmeaus gleich zu erzielen. Steam generator according to claim, characterized in that one or more connecting pipes between the boiler part with a large water content and the one with a large radiation surface are arranged so that in no-load operation the water is drawn from and at the warmest point of the boiler part with a large water content the deepest point of the Kes selteils with a large radiant surface is supplied to achieve a good heat exchange.
CH152681D 1930-10-07 1930-10-07 Steam generator. CH152681A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH152681T 1930-10-07

Publications (1)

Publication Number Publication Date
CH152681A true CH152681A (en) 1932-02-15

Family

ID=4407725

Family Applications (1)

Application Number Title Priority Date Filing Date
CH152681D CH152681A (en) 1930-10-07 1930-10-07 Steam generator.

Country Status (1)

Country Link
CH (1) CH152681A (en)

Similar Documents

Publication Publication Date Title
EP0526816B1 (en) Power plant with gas and steam turbines with solar steam generator
DE19545668A1 (en) Method for operating a gas turbine group combined with a waste heat steam generator and a steam consumer
DE4132315C2 (en) Supercritical pressure boiler with separation device and return pump for cycle operation
DE2620023A1 (en) METHOD AND DEVICE FOR STORAGE OF ENERGY IN POWER PLANTS
EP0410111B1 (en) Heat recovery boiler for a gas and steam turbine plant
DE755525C (en) Steam power plant with the release of steam for heating and cooking purposes
DE2740883B2 (en) Forced steam generator
DE2544799A1 (en) GAS HEATED STEAM GENERATOR
EP0872788A1 (en) System control for a heating or cooling plant with a buffer memory
DE558052C (en) Steam generator for a thermal power plant serving as an instantaneous reserve
DE1551018A1 (en) Steam power plant for driving electrical power generators
DE1003363B (en) Boiler reactor
DE723860C (en) Method and device for the operation of forced running pipe steam generators
CH301118A (en) Cogeneration system.
AT229336B (en) Converter waste heat boiler
CH226747A (en) Procedure for expanding an existing steam plant.
DE602480C (en) High temperature heating system
DE478543C (en) Device to compensate for pressure fluctuations when generating steam from high-temperature water
DE593674C (en) Device for supporting power generators with turbine drives on the condenser
AT377576B (en) STEAM POWER PLANT WITH STEAM FAILURE RESERVE
DE1196668B (en) Steam power plant with forced flow boiler and reheater for operation with steep load cycles
DE1296654B (en) Process for starting up a forced-flow steam generator and forced-flow steam generation for carrying out the process
DE657281C (en) Steam power plant with fluctuating power and heat requirements
DE1626224B1 (en) Steam power plant
DE415031C (en) Steam generating plant with storage device