AU2001284159B2 - Method of stabilizing particulates - Google Patents

Method of stabilizing particulates Download PDF

Info

Publication number
AU2001284159B2
AU2001284159B2 AU2001284159A AU2001284159A AU2001284159B2 AU 2001284159 B2 AU2001284159 B2 AU 2001284159B2 AU 2001284159 A AU2001284159 A AU 2001284159A AU 2001284159 A AU2001284159 A AU 2001284159A AU 2001284159 B2 AU2001284159 B2 AU 2001284159B2
Authority
AU
Australia
Prior art keywords
ballast
mcs
track
polymer
stabilised
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2001284159A
Other versions
AU2001284159A1 (en
Inventor
Robert Malcolm Moss
Peter Keith Woodward
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hyperlast Ltd
Heriot Watt University
Original Assignee
Hyperlast Ltd
Heriot Watt University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from GB0020399.2 external-priority
Application filed by Hyperlast Ltd, Heriot Watt University filed Critical Hyperlast Ltd
Publication of AU2001284159A1 publication Critical patent/AU2001284159A1/en
Application granted granted Critical
Publication of AU2001284159B2 publication Critical patent/AU2001284159B2/en
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B37/00Making, maintaining, renewing, or taking-up the ballastway or the track, not provided for in a single one of groups E01B27/00 - E01B35/00
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/03Injecting, mixing or spraying additives into or onto ballast or underground

Description

WO 02/16695 PCT/GB01/03679 1 METHOD OF STABILIZING PARTICULATES This invention relates to a method of stabilizing particulates It is known from a number of prior proposals to attempt to modify the properties of particulate engineering structures, such as railway ballast, for example to improve stability, by effectively 'holding' the stones together.
Examples are EP-A- 0, 502, 920, EP-A-0, 641, 407 and DE-A-394142 wherein multi-component systems, (MCS) such as epoxy or polyurethane resins are used to bind the particulates together.
The engineering behaviour of particulate supported structures is modified when MCS are applied. In particular, the engineering strength and stiffness characteristics are increased. Addition of MCS also modifies the dynamic characteristics, modifying properties such as the damping ratio and the speed of the stress shock waves (for example, compressive, shear and surface waves).
When applying a multi-component system to particulates it is desirable to ensure that the reinforced and stabilised structure performs to an acceptable level during its life cycle. The MCS is preferably applied in the correct spatial position and down to the correct depth to ensure that the desired engineering behavioural improvements are obtained. The MCS is also preferably designed chemically to ensure that its desired properties are correct for the particular application under consideration, for example stiffness, strength, viscosity, fatigue limits, acoustic damping, temperature CONFIRMATION COPY WO 02/16695 PCT/GB01/03679 2 range, biocidal and hydroscopic properties and curing time. Each particular application of the MCS is likely to be different, since each site application will be different with respect to geometry, surface/subsurface structural conditions and engineering characteristics. Additional additives for the MCS may be required to achieve the desired behaviour and predictability, for example, cement or asphalt based fillers.
Incorrect application of MCS may lead to premature failure of the modified structure. In very severe cases, this may lead to unplanned responses and/or catastrophic failure.
It is an object of the invention to provide a method for the treatment of particulate based structures which enables these desirable objectives to be attained.
According to the invention therefore, there is provided a method of stabilising particulates comprising the steps of:a) surveying the surface and substructure of a site using sensing apparatus and combining with any available existing site data; b) analysing the results so obtained to determine; I) where a multi-component system (MCS) is to be applied; ii) the quantities of MCS to be used; iii) properties of the MCS; and c) carrying out selective application of MCS to the structure as WO 02/16695 PCT/GB01/03679 3 determined by the analysis.
Additionally, the method preferably also includes the steps of:analysing the load characteristics required, and analysing the structure of in-situ particulates.
The invention also provides a 9 stabilised ballast structure in a railway track made by this method.
The method may include the additional step of selecting or formulating a suitable, for example polyurethane based, MCS coating material. The method makes possible the adaption of offsite and/or modular creation of components to achieve stabiliblisation of particulates and surrounding structures.
MCS may preferably be used to increase the vertical and/or lateral structural stability (eg. stiffness and strength) and needs to be carefully controlled to ensure that the stresses and forces dynamically, transiently or statically are within the fatigue or strength limits of the MCS reinforced structure with a given factor of safety for the desired life cycles under consideration. Using an inappropriate MCS may lead to premature and/or unpredictable failure or undesirable performance deterioration of the reinforced structure.
Addition of MCS modifies the static and dynamic behaviour of the particulate structure and therefore the whole or partial structural response.
WO 02/16695 PCT/GB01/03679 4 The change in the static and dynamic behaviour is related to the particular variant of MCS being applied and to the spatial location and properties of the structure (eg in a railway track application, the rails, sleepers, cutting, embankment, or in a roadway, the pavement, sidewalk, drainage, road surface and subsurface), ballast, subballast, subgrade etc.). This change needs to be assessed to ensure that it is not detrimental with respect to the static and dynamic behaviour of the applied static and transient loads.
The development of an MCS membrane or barrier, through inappropriate MCS application, may prevent dissipation of surface and substructure excess pore pressures leading to failure or undesirable performance of the structure. Therefore further design considerations need to be taken into account before MCS is applied, particularly if a desired design objective is the creation of an impermeable interlayer to ensure the desired properties of performance (eg. drainage etc.) are achieved.
Using MCS to stabilise and reinforce the 'wet-spot' areas (ie. areas prone to mud-pumping under load) also needs to be carefully controlled. Addition of MCS creates a change in the static and dynamic interaction behaviour and may create further problems and therefore needs to be assessed.
Using MCS as a tailored 'lead-in' to dynamically differently performing natural or manmade structures such as geological features or bridge decks needs to be assessed to ensure that the modified dynamic characteristics are appropriate. This is to prevent for example additional vibrations being WO 02/16695 PCT/GB01/03679 induced, leading to 'load-bounce' or return shockwaves.
Particulates Reinforced and Stabilised by the Treatment Method of the Invention may be used for:- Short/long term stabilisation of overstressed structures (eg. mudpumping and 'wet-spots' in railway track); Vertical, lateral and longitudinal stabilisation (in railway track for example, of transition curves, super-elevations, junctions/points/crossings and main lines, including high speed lines) for example, to reduce maintenance.
Stabilisation of particulate structures in tunnels; Stabilisation of retaining walls, inclines, taxiways and landing areas; Reinforcement of bridge decks including increasing particulate stiffness before and after bridges to prevent loads bouncing.
Reinforcement and stabilisation to ensure tight tolerances are maintained eg. (in rail systems for normal, double-decker and high speed tilting trains and other types of trains.
Reduce subgrade stresses through increased MCS stiffness and strength properties.
Reduce subgrade stresses by increasing particulate stiffness to help prevent local pocketing of subgrades.
Reduce induced particulates plastic strains and attrition, particulate WO 02/16695 PCT/GB01/03679 6 segregation, (eg. through chipping), by reducing particulate movement, reducing the incidence of fouled particulates. Application of MCS membrane (for example at interfaces of different structural materials) to prevent subballast/subgrade infiltration.
Help prevent hydraulic erosion of the surface and substructures.
Allow for increases in applied loads and speed of transient loads without significantly increasing structural maintenance, and for reducing structurally induced damage due to applied loads.
Prevent surface movement of the particulates through transient wind forces and through surface waves due to imposed loading.
Reduction of ambient noise generation and transmission. Allow power washing of the reinforced structures to retain cleanliness at reduced cost.
Improve the static and dynamic performance of the structure.
Some examples of procedures for stabilising ballast, and of the resulting stabilised ballast structures in accordance with the invention will now be described by way of example with reference to the accompanying drawings, wherein:- Figure 1 is a diagram of a track assembly including ballast and subgrade, to illustrate the terms and general track features used in the following description; WO 02/16695 PCT/GB01/03679 Figures 2 and 2b Figures 3a and 3b Figure 11 Figure 13 are respectively transverse and longitudinal (in the running direction) and cross sectional views of a first embodiment of track structure according to the invention; to Figures 10a and 10b are similar respective transverse and longitudinal cross-sectional views of further embodiments of track structures according to the invention; is a view showing applications of ballast with MCS to a rail bed, Figure 12 is a longitudinal section of a bridge deck installation; and is a flow diagram of the evaluation method used in particular case.
A diagram of a simplified track structure as shown in Figure 1. This comprises spaced apart rails 10 extending parallel in the running direction of the track, supported on sleepers 11 which rest on a ballast layer 12.
This in turn is carried by a layer 13 of sub ballast which rests upon subgrade 14. Subgrade 14 may comprise any natural or engineered terrain such as an embankment, the floor of a cutting, or a bridge or viaduct deck.
In the following figures, sections are taken transversely across the track structure on the line X-X of Figure 1 and longitudinally in the running directions on the line Y-Y of Figure 1.
WO 02/16695 PCT/GB01O/03679 8 Figures 2a and 2b relate to stabilisation of points, crossing and other similar types of structures which are often subjected to lateral loading due to train inertia forces. Conventional stabilisation methods include the addition of plates at the end of the sleeper and/or the formation of a running beam adjacent to the sleepers. Both of these methods rely on increases in passive resistance, but often do not perform satisfactory due to progressive plastic movement of the shoulder ballast. The technique used to overcome this problem (in this design example) is the Crib Tie-back Method (CTbM).
In this technique, a polymer ballast composite beam (15) is constructed adjacent to the sleepers to help prevent the sleepers 11 from moving laterally as before. However, the beam (15) is now tied-back into the cribs using the polymer ballast composite anchors (1 6) which extend across the track generally between and below sleepers The force required to restrain the crib anchors (16) is provided by the weight of the train.
Therefore the technique makes use of the train's own weight to restrain the beam (15) against permanent lateral movement (in addition to the frictional resistance under the sleepers). The width of the anchors may or may-not cover the full width and/or depth of the crib area depending on the level of anchoring force required.
The composition of the polymer is selected based on the required stiffness and strength properties required of the composite. In particular, the tensile strength and shear strength properties of the polymer are WO 02/16695 PCT/GB01/03679 9 determined as part of the design process.
Figures 3a and 3b show a structure to stabilise the vertical movement of sleepers to problems involving poor formations, or in switch areas prone to high vertical rail forces, a conventional 'ladder type' of design Is used.
In this design only the ballast below the sleeper bottom is stabilised as shown in Figures 3a and 3b. The ladder comprises a beam 17, 18 extending along the sides of the ballast, and a plurality of cross-beams 19 extending across the track between the beams 17, 18, and between the sleepers 11. All the beams 17, 18 and cross-beams 19 are below the level of the sleepers and utilize the full depth of the ballast layer, and are formed of polymer stabilised the ladder design (Type 1 stabilisation) can only be used when the depth of the ballast 12 is sufficient to allow frictional locking of the unstabilised ballast under the sleeper the frictional properties of the unstabilised ballast are used to 'lock' the unstabilised ballast into the adjacent crib stabilised/reinforced ballast). In poor formation areas the polymer properties (for example polymer stiffness) are designed to ensure that an efficient 'pad' type of ballast stabilised foundation is constructed over the weak area. If the polymer stiffness is high enough, then a more even distribution of stress at the subgrade interface is produced. For high maintenance switches the polymer properties are selected to ensure that the large vertical forces are more efficiently distributed under the switch, but still retaining good composite damping properties.
WO 02/16695 PCT/GB01/03679 Figures 4a and 4b show a type 2 design for poor formations and high maintenance switches wherein the ballast depth is not sufficient to ensure that the unstabilised ballast under the sleeper is locked into the stabilised crib ballast (or vertical track forces are too large). Movement and penetration of the ballast under the sleeper into the formation is therefore possible. Lifting of the sleeper to stabilise the ballast directly under the sleeper is possible (this would require a separate design), but often undesired as it has a detrimental affect on the track alignment. In this design holes 20 are drilled into the sleepers 11 at various locations to allow polymer to be poured/injected into the underlying ballast and fully/partially stabilise it as shown in Figure 4a and 4b producing in addition to the 'ladder' construction of Figures 3a, 3b comprising parallel side beams 17, 18 and cross beams 19 below and between the sleepers 11, a plurality of anchoring pillars 21 below the sleepers.
In the design of Figures 5a and 5b for wet-spot stabilisation it is assumed that the ballast 13 is heavily fouled due to subgrade infiltration (mud-pumping) and must be replaced prior to polymer treatment. The replaced ballast 12 is then stabilised using the polymer producing a stabilised layer 22. The polymer is also designed to enable it to 'pool' at the ballast/subballast interface forming an integral polymer membrane 23.
The membrane stops subgrade infiltration, but should only be applied if confidence in the capability of the drainage layer is high. The depth of WO 02/16695 PCT/GB01/03679 11 stabilised ballast (from the ballast/subballast interface) may extend up to the base of the sleeper if considered appropriate but is shown with a layer of unstabilised ballast 12.
Figures 6a and 6b show a design wherein the polymer is used to ensure that track lateral tolerances are within specified limits. For example, this design would be used to ensure that track clearances in tunnels and at track platforms are within the correct limits. The depth of polymer application is generally set from the surface of the sleeper top level to below the sleeper bottom, as shown in Figure 6a and 6b. It is generally not necessary to stabilise all of the crib areas, however this depends upon the level of loading and longevity required. The polymer stiffness is usually set high to ensure that the composite stiffness remains high (ensuring low composite displacements). As shown, this produces side beams 24 of stabilised ballast up to the upper surface of the sleepers and cross beams 25 between alternate pairs of sleepers 11.
As shown in Figures 7a and 7b, polymer is used to provide a continuous stabilised blanket 26 on the ballast surface around the sleepers 11 as shown in Figure 7. The purpose of this blanket 26 is to stabilise the ballast surface only (although the blanket depth may extend below the sleepers if a high degree of stabilisation is required).
The blanket 26 is used to provide ballast stability against train generated wind forces, loss of compaction due to ballast vibration and other WO 02/16695 PCT/GB01/03679 12 detrimental problems like vandalism. For the vibration problems, the polymer stiffness is generally set low to increase the damping properties of the polymer. The vibration may originate from many sources including ground waves generated by high-speed .trains (these can become high on embankment structures or railway track over weak foundations) or by excessive vibration of other track structures, such as bridge decks vibrating at their characteristic frequencies.
Figures 8a and 8b show an embodiment for stabilisation of cyclic-top.
Cyclic-top problems generally originate from track misalignment problems or from dynamic motion of the locomotive and/or carriages. For example, a wet-spot site may generate oscillations in the train suspension system causing a sinusoidal type of motion, giving rise to changes in the dynamic forces on the rail with track length. This sinusoidal motion gives rise to permanent movement of the ballast at given wavelengths. Cyclic top can also originate from problems like an uneven subgrade. The design for this type of problem is based on the formation of two polymer/ballast composite 'running beams' 27, 28 that encompass the area of concern. The beams can be continuous (as shown in Figure 8) or may make use of the ballast locking mechanism comprising cross beams 29 under the sleepers as described in Examples 2 3 above. On straight track lateral movement may not be significant and hence stabilising the crib ballast is only necessary at certain crib locations (for example, every third of fourth crib).
WO 02/16695 PCT/GB01/03679 13 The purpose of these crib stabilisations is to ensure that the beams 27, 28 remain laterally connected. Since this type of stabilisation is generally for long track lengths, the polymer properties are selected based on the varying formation properties. For example, a uniform track modulus value may be selected as the design criteria in the determination of polymer stiffness.
Finally Figures 9a and 9b show an arrangement of stabilised ballast for stabilisation of curves on embankments. The design proposed in Figures 2a and 2b for increasing the lateral stability of railway track may not be sufficient (generally the shoulder passive resistance is lower than for track not situated on embankments). In these situations a 'ballast key' 30 may be required to increase the lateral stability. This ballast key 30 (or keys) extends beyond the normal depth of stabilisation and is used to increase the passive resistance of the stabilised track as shown in Figures 9a and 9b.
The ballast keys maybe formed from stabilised ballast as shown in Figure 9a.and 9b, or they maybe formed from another type of material that can be used to provide an additional anchor force (such as steel soil nails). The polymer properties are selected based on the criteria discussed in Example 1. The entire upper part of the ballast 31 defining the camber of the curve is stabilised by adding polymer. The ballast keys 30 extend longitudinally of the track below the rails.
Stabilised beams 31 may be applied at both sides of the sleepers 11 to WO 02/16695 PCT/GB01/03679 14 resist trains that are both faster and slower than the design track curve speed. Complete embankment stabilisation can be achieved (perhaps for 'weak embankments') by using a soil nailing technique to increase embankment strength and stiffness in combination with the polymer stabilisation technique to increase lateral (and vertical if necessary) track stability.
Figures 10a. and 10b show an arrangement for mainline ballast maintenance reductivity. It is generally accepted that when constructing new railway track the maintenance of the track can be reduced by ensuring that the subgrade surface is shaped so that it is parallel to the rail. This helps to prevent problems like ballast memory; in which the ballast surface (ie. at sleeper level) takes the same shape as the uneven subgrade surface.
When constructing the new line, at the point of ballast placement on the track, the polymer can be applied to ensure that a given ballast layer 32 remains parallel to the rail. This ballast layer 32 is applied at a specified level and extent within the ballast, depending on the design and longevity required as shown in Figures 10a and 10b. This type of approach helps to prevent ballast pocketing and hence reduces the likelihood of track irregularities.
When upgrading existing track the same technique can also be applied to increase upgraded track longevity for uneven/even subgrades. During the ballast cleaning/renewal process the polymer can be applied in a similar WO 02/16695 PCT/GB01/03679 way to that described for the new track. The polymer is again used to form a lower composite ballast layer that is parallel to the rail. The design would be based on (for example) stabilising the ballast from its mid-point down to the uneven subballast/subgrade interface. Not stabilising the upper ballast layer allows for normal tamping operations. As with the new track design, the polymer properties and loading would be matched to the subgrade and to the level of loading required, through design based criterion like the track modulus value. Figure 11 shows a typical application of the polymer to form a composite lower surface ballast layer 32 during a ballast cleaning operation with an uneven subballast and/or subgrade layer. Since this technique would be applied to long lengths of track the polymer properties would need to change to match the changing track properties. It is therefore likely that techniques such as ground penetrating radar would be required to examine the subsurface profile along the track. A divided chute ballast placer 33 is used to place a first layer of ballast in front of an application nozzle 34, and then a further layer of untreated ballast 12 above the stabilised ballast layer 32.
The designed polymer stabilisation technique can be used to form transition zones to allow a more uniform change in track modulus at sudden changes in track stiffness. For example, the polymer/ballast composite maybe used to form a transition zone from a relatively weak embankment structure to a stiff concrete bridge deck. The design would encompass the WO 02/16695 PCT/GB01/03679 16 spatial location of the polymer, for example a tailored lower level stabilisation leading up to the bridge, in combination with desired changes in polymer properties. By varying the overall stabilised ballast properties changes in ballast shear wave and track velocities can be achieved to modify track dynamics. The purpose of the transition zone is to help reduce problems like 'train-bounce', which arise from sudden changes in track stiffness. The complex interference patterns generated when train approach solid structures, due to track ground waves, can increase ballast maintenance. A designed based ballast stabilisation treatment can reduce maintenance requirements in these areas. An example of a tailored lead-in and lead-off ballast stabilised concrete bridge deck is shown in Figure 12.
In this design example the polymer stiffness and spatial location increase as the railway track approaches the bridge deck (and vise versa off the bridge) to allow a smoother transition from the embankment to the bridge. On the bridge deck the polymer stiffness is reduced and its damping properties increased to reduce vibration problems (and ballast attrition). In these designs it maybe desirable to introduce rubber pads, or other types of energy absorbing systems, below the sleeper to allow a more flexible sleeper foundation base if considered appropriate. The bridge deck 35 is covered by a full depth layer of stabilised ballast 36, which is sloped at each side of the deck, whilst a partial layer of stabilised ballast 37 is provided to either side of the bridge leading to and from the sloped end of layers 36.
WO 02/16695 PCT/GB01/03679 17 The transition zones maybe formed by either increasing the slope of stabilised ballast, as in Figure 12, or by using a stepped arrangement.
An example of the application of the method illustrated by the flowchart of Figure 10 is the stabilisation of a set of points over which axle loads of at 110mph regularly pass. This section of the line is rated at 35 Million Gross Tonnes (MGT) and the points are used to divert freight trains onto a turn-out to a marshalling yard. Lateral movement of the rail at the points (situated on ballasted track), measured by on-line train instrumentation, is in the order of 15-25mm depending on the actual axle weight and speed at the instant of loading. Maintenance of the points is usually performed at 6- 8 monthly intervals (often the points are re-aligned). Site investigations reveal that the ballast is of a dolerite basalt type with a type Dso of 28mm.
The ballast depth is between 300-400mm, with a subballast layer between 120-150mm overlying a silty-clay subgrade, within a slight depression. CBR readings and cone-penetrometer readings of the subgrade indicate stiffness values of 100-120MPa. Poisson's ratio for this type of material is 0.4 with shear strength coefficients of c'=4kPa and 290. In situ density readings indicated bulk unit weights around 18kN/m 3 The surface subsurface layering is known and so ground penetrating radar is not considered necessary.
The subgrade shear-wave velocity is calculated to be around 150m/s.
At 110mph the maximum train speed is 49m/s. The development of a WO 02/16695 PCT/GB01/03679 18 transeismic state is therefore not expected at current train speeds (the train speed is less than 60% of the ground shearwave velocity). Track critical velocities are also outside current train speed limits. Therefore, this example primarily concentrates on the static analysis of the track.
The ballast and subballast stiffness values are around 200MPa and 120MPa, with purely frictional strengths of f'+46° and 380 respectively.
The void ratio of the ballast is around 0.72 with a unit weight of 16kN/m 3 The rail (E=210 Gpa, p=7850kg/m 3 and rail pads (E=200 MN/m) are standard UK main line with bolt plate fasteners onto wooden sleepers of 2.6m in length, 0.14m in depth and 0.26m in width. The average distance between the sleepers is 0.38M. No signs of mud-pumping is evident, wetspot formation at this particular site is not considered to be significant. This is confirmed by observed well maintenance track drainage. Ballast contamination, due to overstressed ballast, is evident. This has resulted from the development of large lateral forces as freight trains are diverted onto the turn-out. Calculation of the expected vertical and lateral train forces (using standard procedures, for example the procedures laid out in UK and American Railway Engineering Association (AREA) guidelines) suggest dynamic amplification factors of 1.5-2x the static axle loads vertically at 100-110mph and 1.2x the static axle loads horizontally at the turn-out at 15mph. These values are used in combination with the site investigation material parameters as input to a static mathematical, model, WO 02/16695 PCT/GB01/03679 19 based on the finite element method.
The static mathematical model used is the DIANA finite element program, which is generally available and represents the current state of the art in terms of commercially available and represents the current state of the art in terms of commercially available finite element programs. The 3dimensional finite element mesh used comprises 2100 elements of the following types, 3-noded Class III Beam elements and isoparameteric brick element. A full integration scheme is used and boundary conditions are smooth in the appropriate vertical directions and fixed at the base. The mesh is spilt into several layers to simulate the different ballast, subballast and subgrade depths. Modifying the ballast material properties as appropriate to their spatial location simulates variations in the ballast densities. The rails, fasteners and sleepers are assumed to behave elastically. The ballast, suballast and subgrade are assumed to behave non-linearly and are modelled using an elasto-plastics Mohr-Coulomb constitutive soil model using a non associative plastic flow rule. Material dilation for the ballast and subballast are assumed, based on the critical state friction angles for the two materials.
Locomotive configurations for the determination of train loading cases include, CLASS 87 (for example, wheel diameter 1.150m, wheel to wheel centres 3.28m, bogie distance =9.97m, axle weight-202T+2T unsprung), CLASS 86/4 and CLASS 253/254 HST. Freight loading cases include 100 WO 02/16695 PCT/GB01/03679 tonne GLW Tank Wagon Class B (for example, wheel diameter=0.95m, wheel to wheel centres 2.0m, bogie distance 13m, axle weight An additional multiplication factor of 1.5 is used to simulate increases in the dynamic load factor for wheel flats.
The mathematical model is first used to verify the current lateral displacement values (between 10-25mm lateral deflection depending on applied lateral force). Once the measured displacement values are simulated the finite element model is considered calibrated and various designs are investigated and analysed to determine the optimum design for the added polymer composite. To determine properties of the required designed polymer an iterative process is used in combination with the new engineered track design. The required performance is set at 5mm lateral deflection under lateral train loading.
The actual design used for this site stabilisation is a tie back design (several designs are investigated and their performance assessed with respect to the performance assessed with respect to the performance target set). In this particular case, a composite edge beam is tied-back into the cribs using the polymer composite (the tie-backs are below the sleeper base). The polymer stiffness used was E= 500MPa and the ballast loading was 10% by ballast mass. This design shows that a significant increase in lateral stability is achieved, when compared to an ordinary edge beam type stabilisation. The simulated modelling shows increases in lateral stability, WO 02/16695 PCT/GB01/03679 21 for this case particular case, of approximately 6 times greater than the ordinary unstabilised ballast and 4 times greater than edge beam only type of stabilisation under train loading conditions imposed. The results of the mathematical model are closely studied in terms of stresses, strains, displacements etc. to ensure that these quantities are within the acceptable fatigue limits for the composite/polymer chosen. The mathematical model is also used to investigate areas of possible plastic deformation, giving raise to permanent plastic movement, and to enable the design to be modified if necessary and factors of safety calculated.
To obtain the optimum polymer loading for the designed stiffness and cyclic properties of the composite laboratory tests were performed. The results of these laboratory tests are used to estimate the designed life span of the treated site by applying a similar deviatoric stress state as computed by the mathematical model. The tests include, direct shear box testing, triaxial compression testing (monotonic and cyclic) and cyclic boundary value tests, ie. three-dimensional box tests. The results of the direct-shear testing (dimensions of 300mm x 300mm) indicated that the unreinforced (unstablished) ballast for particular case of polymer loading has shear strength coefficients of c 3 okPa and f'=460. Addition of the polymer at loading (by ballast mass) to the ballast increases the shear strength coefficients to c 3 =okPa and I'=460, showing a considerable increase in strength. These values were confirmed by the unconfirmed triaxial WO 02/16695 PCT/GB01/03679 22 compression tests. The cyclic properties of the reinforced ballast were also tested. In the first of these tests a reinforced unconfirmed cyclic triaxial compression test at the simulated peak computer simulated deviatoric stress state was tested. The results showed an accumulated plastic strain of 0.4% at a peak cyclic deviatoric stress state of 384KPa (as computed by the mathematical program) after 20,000 load cycles. A second sample was cycled at a peak load of 768kPa (factor of safety of 2x on internal stressstate). Again around 0.4% accumulated plastic strains were recorded.
In a simulated boundary value test (traditional three dimensional box-type of test for railway ballast) 2.66 million load cycles at design loading conditions were applied to the surface of stabilised ballast (through loading cap) to obtain the required MGT value for 10 years loading on the WCML.
The stabilised ballast experienced around 1.0mm plastic deformation.
Typical results for unreinforced cyclic ballast tests atthis level of loading are generally available in the literature and indicate values of accumulated displacement between 30-40mm. The behaviour of the designed reinforced ballast is therefore far superior to the unreinforced ballast in both strength and cyclic properties. No evidence of ballast attrition was observed.
Based on the results of the laboratory tests and the mathematical modelling a modification to the design is made to reduce stress concentrations at the sleeper ends. The design is therefore an iterative process, taking into account the results of the of the mathematical WO 02/16695 PCT/GB01/03679 23 modelling and laboratory tests, in combination with the expected loading conditions and required performance criteria, to arrive at an optimum design for this set of points to ensure all the design criteria (displacements, strains and stresses etc.)are within tolerable limits. The final composite design therefore satisfies the overall designed life-span performance criteria for lateral displacements limit of 5mm for 10 years on the West Coast Main Line. This process therefore gives a complete design procedure and predictive capability for modified polymer stabilised railway track. To date, post-treatment performance monitoring by the local maintenance contractor has shown that the treated site has performed as per the design.
In this example a complete dynamic analysis is not necessary as subgrade and track critical velocities are significantly higher than the current train speeds. However, if the subgrade stiffness is lower (or any other special track circumstances/conditions are observed, for example significant track irregularities leading to large dynamic track forces) an additional design step to the above example is necessary. To enable a full dynamic design and analysis of railway track, and subsequently treated polymer railway track, a three-dimensional dynamic finite element program is used.
The program allows the user to examine the change in the track behaviour with polymer application and represents a sophisticated design tool for track engineers. Examples of suitable MCS compositions are set out below. The exact proportions of ingredients, and even the diisocyanates and polyols in WO 02/16695 PCT/GB01/03679 24 polyurethane used may be varied along with the physical properties such as viscosity, as determined by the results of the analysis process set out above.
Example 1 [Application to Railway Track] A ballast layer comprises an aggregate of crushed limestone of mean dimension 40mm, and this is bound to a depth of 300mm between the sleepers and rails of the track.
The MCS comprises for example a polyurethane having the following composition mixed using a Graco Hyrocat (Trade Mark) based machine, and is poured onto the ballast which is pre-laid to a depth of 300mm. The foundation for this 300mm layer of ballast is a sand carpet. The design may require an excess of polymer seeping through the ballast to create a barrier against upward movement of the sand or subgrade layer.
The polyurethane comprises the following two components, which are maintained separate prior to pouring, then mixed and poured together.
Component A (Polyoll Castor oil 49.25% parts by weight Sorbitol based polyether 28% parts by weight Polyether Diol 4% parts by weight Methyl Naphthalene (VYCEL U (TM) 12% parts by weight Tris (2-Chloropropyl) phosphate 5% parts by weight WO 02/16695 PCT/GB01/03679 Sodium Aluminum silicate (Zeolith (TM) powder) 1% parts by weight Phenyl mercuric fatty acid ester (Thorcat 535 0.5% parts by weight Dialkyl tin mercaptide (Fomrez UL22 0.3% parts by weight Component B (Isocyanate) Polymeric dimethylene diphenyl diisocyanate (MDI) 100% parts by weight The mix ratio of the two components is:- Component A 100 parts Component B 56 parts The composition, including ballast at 5% level gives the following mechanical properties:- Bulk density 1.55 y/cc Compressive modulus 100 800 Example 2 [Application to a Railway Track] A 10%, loaded rail ballast is prepared using a polyurethane/bitumen composition. The isocyanate terminated pre-polymer is added to a cationic bitumen in the following preparations:- WO 02/16695 PCT/GB01/03679 26 Polyether based FR emulsifiable pre-polymer Cationic bitumen emulsion 100ppw The pre-polymer is based on the following:- PPG diol 2000 m.w. 100ppw EID 9086 Amgard TMCP (TM) Vycel-U The pre-polymer/bitumen composition is sprayed onto the ballast at a rate to ensure 10% loading.
The composition cures in two hours, and provides an elastic solid whose compressive strength at 10% yield is 50MPa at 150C.
Other curing systems for polyurethane prepolymer include the use of alkaline agents such as sodium silicate solution, calcium hydroxide and magnesium hydroxide and magnesium hydroxide and magnesium hydroxide slurries as well as other organic polymer emulsions. These mixtures can be used similarly to bind a particulate material such as ballast to produce a strong supporting composite. The pressure, composition and amount and location to be sprayed or otherwise applied to the ballast layer is determined by mathematical modelling of the stress effects from different trains speeds and loading to determine the polymer/ballast composite required to yield a predicted lifetime of acceptable performance. Clearly, traffic comprising a WO 02/16695 PCT/GB01/03679 27 high incidence of heavy locomotives with loaded mineral trains will exert different stresses to relatively light but fast HST units, or infrequent slower and lighter multiple passenger units.
The polymer formulation enables the ballast to be wetted out and subsequently allowed to set a tough composite in place on the track bed, which provides long term load and vibration management of the track.

Claims (9)

1. A method of stabilising particulates comprising the steps of:- a) surveying the site conditions including surface and substructure of a site using sensing apparatus; b) analysing the results so obtained to determine; I) where a multi-component system (MCS) composition is to be applied; ii) the quantities of MCS to be used; iii) properties of the MCS required; and c) carrying out selective applications of MCS to the particulates at the site as determined in step above.
2. A method according to claim 1 comprising the further steps of:- analysing the load characteristics required and analysing the structure of particulates at the site.
3. A method according to claim 2 comprising the further step of selecting or formulating a suitable MCS coating material.
4. A method according to any preceding claim wherein the MCS is selectively applied to ballast in a railway installation, to provide a structure of stabilised ballast wherein parts of the ballast are stabilised, and other parts are left untreated by the MCS. A method according to claim 4 wherein the MCS comprises polyurethane WO 02/16695 PCT/GB01/03679 29 based resin system which is used to bond and thereby stabilise stones comprising a bed of railway ballast.,
6. A structure comprising a ballast bed in a railway track wherein the ballast is selectively treated with MCS to stabilise parts of the ballast and leave other parts untreated, so that the stabilised parts of the ballast constitute reinforcing elements for the ballast bed.
7. A structure according to claim 7 wherein said stabilised parts of the ballast comprise elements extending longitudinally of the track, outside of the sleepers, and further elements extending transversely of the track, below and between the sleepers.
8. A structure according to either of claims 6 to 7 wherein the MCS comprises a single component organic polymer or polymer precursor which can be poured onto the ballast and cure by reaction with atmosphere moisture or oxygen, by evaporation, by post application of a curing agent treatment with irradiation, or application as a provider and melting onto the ballast.
9. A structure to any either of claims 6 to 7 wherein the MCS comprises two or more components which are pre-blended prior to pouring into the ballast. A structure according to any one of the claims 6 to 9 wherein the polymer is mixed with ballast before placing on the ballast bid and curing of the polymer. WO 02/16695 PCT/GB01/03679
11. A structure according to any of claims 6 to 10 wherein the structure is provided by a method according to any one of claims 1 to
AU2001284159A 2000-08-19 2001-08-17 Method of stabilizing particulates Ceased AU2001284159B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
GBGB0020399.2A GB0020399D0 (en) 2000-08-19 2000-08-19 Method of stabilizing particulates
GB0020399.2 2000-08-19
PCT/GB2001/003679 WO2002016695A1 (en) 2000-08-19 2001-08-17 Method of stabilizing particulates

Publications (2)

Publication Number Publication Date
AU2001284159A1 AU2001284159A1 (en) 2002-05-30
AU2001284159B2 true AU2001284159B2 (en) 2005-11-24

Family

ID=9897881

Family Applications (2)

Application Number Title Priority Date Filing Date
AU8415901A Pending AU8415901A (en) 2000-08-19 2001-08-17 Method of stabilizing particulates
AU2001284159A Ceased AU2001284159B2 (en) 2000-08-19 2001-08-17 Method of stabilizing particulates

Family Applications Before (1)

Application Number Title Priority Date Filing Date
AU8415901A Pending AU8415901A (en) 2000-08-19 2001-08-17 Method of stabilizing particulates

Country Status (12)

Country Link
US (1) US20040109730A1 (en)
EP (1) EP1309759A1 (en)
AU (2) AU8415901A (en)
CA (1) CA2420047A1 (en)
CZ (1) CZ2003790A3 (en)
EA (1) EA004335B1 (en)
GB (1) GB0020399D0 (en)
HU (1) HU0300774A2 (en)
NO (1) NO20030768L (en)
PL (1) PL361311A1 (en)
WO (1) WO2002016695A1 (en)
ZA (1) ZA200302034B (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030223826A1 (en) * 2002-03-21 2003-12-04 Ianniello Peter J. Synthetic alternatives to uniform and non-uniform gradations of structural fill
ES2678422T3 (en) * 2008-05-23 2018-08-10 Lubrizol Advanced Materials, Inc. Fiber reinforced TPU composite materials
EP2446087B1 (en) 2009-06-24 2019-03-13 Basf Se Method of producing a composite material using a mixing system
CA2784986C (en) 2009-12-21 2017-06-06 Reynolds Presto Products, Inc. Composite pavement structure
CN102191730B (en) * 2010-03-09 2015-08-26 拜耳材料科技(中国)有限公司 Polyurethane elastomer railway ballast pad and preparation method thereof
EP2561138B1 (en) * 2010-04-21 2016-10-05 Covestro Deutschland AG A polyurethane ballast layer, the method for preparing the same and the use thereof
CN103380094A (en) 2010-12-29 2013-10-30 巴斯夫欧洲公司 Colored composite pavement structure
PL2728069T3 (en) * 2011-06-29 2016-10-31 Transition structure and construction method
CN104109989A (en) * 2013-04-18 2014-10-22 中铁十一局集团第一工程有限公司 Method for curing double-block ballastless tracks in extreme environments
US9045865B2 (en) * 2013-04-19 2015-06-02 SAFEKEY Engineering Technology(Zhengzhou), Ltd. Polymer grouting method for uplifting ballastless track of high-speed rail
JP6217291B2 (en) * 2013-10-03 2017-10-25 新日鐵住金株式会社 Repair method of structure with change of support height
CN107132160A (en) * 2017-06-13 2017-09-05 同济大学 One kind visualization high ferro roadbed granule, which shakes to fall into, recurs model assay systems
JP2019148116A (en) * 2018-02-27 2019-09-05 公益財団法人鉄道総合技術研究所 Estimation method for ballast settlement amount at ballast track
CN110219212A (en) * 2019-06-20 2019-09-10 中铁四院集团岩土工程有限责任公司 Non-fragment orbit sleeper hangs empty regulation method
CN111395075A (en) * 2020-03-09 2020-07-10 朔黄铁路发展有限责任公司 Maintenance method of ballast track bed
CN111912758B (en) * 2020-06-30 2022-07-01 太原理工大学 Test device and method for measuring drainage capacity of ballast track bed in different dirty states
CN114236536B (en) * 2022-02-23 2022-05-27 铁科检测有限公司 Railway roadbed ground penetrating radar data processing system and method thereof

Family Cites Families (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE394142C (en) 1924-04-23 Schicketanz & Co Device for the production of spherical bodies from plastic masses
US2357769A (en) * 1942-12-31 1944-09-05 Rushmer John Robbins Stabilizing material introducing device
JPS521161B2 (en) * 1972-02-10 1977-01-12
US4084381A (en) * 1977-01-19 1978-04-18 Woodbine Corporation Stabilization of earth subsurface layers
US4451180A (en) * 1978-05-09 1984-05-29 Duval Henry H Method for restructuring railway roadbeds
US4494694A (en) * 1982-09-28 1985-01-22 Iowa State University Research Foundation, Inc. Support system for a railroad track
AT105741T (en) 1989-12-02 1994-06-15 Koch Marmorit Gmbh METHOD AND DEVICE FOR APPLYING MULTI-COMPONENT RESINS AND APPLICATIONS THEREOF.
DE4014529A1 (en) * 1990-05-07 1991-11-14 Koch Marmorit Gmbh Thermosetting resin mixer and applicator and use of mixed resins
US5372844A (en) * 1989-12-02 1994-12-13 Koch Marmorit Gmbh Process and device of applying multi-component resins and use of same
DE4214890C2 (en) * 1992-05-07 1998-07-09 Koch Marmorit Gmbh Use of a process for the temporary consolidation of a ballast bed
DE4313880A1 (en) * 1993-04-28 1994-11-03 Koch Marmorit Gmbh Method and device for the controlled application of adhesives
JP3340795B2 (en) * 1993-05-11 2002-11-05 三洋化成工業株式会社 Ballast consolidation method and consolidation material
ES2109657T3 (en) * 1993-08-31 1998-01-16 Plasser Bahnbaumasch Franz PROCEDURE FOR THE STABILIZATION OF A LAND LEVEL.

Also Published As

Publication number Publication date
CA2420047A1 (en) 2002-02-28
EA200300280A1 (en) 2003-08-28
EA004335B1 (en) 2004-04-29
US20040109730A1 (en) 2004-06-10
PL361311A1 (en) 2004-10-04
AU8415901A (en) 2002-03-04
ZA200302034B (en) 2004-04-20
GB0020399D0 (en) 2000-10-04
NO20030768L (en) 2003-03-28
HU0300774A2 (en) 2003-10-28
WO2002016695A1 (en) 2002-02-28
NO20030768D0 (en) 2003-02-18
EP1309759A1 (en) 2003-05-14
CZ2003790A3 (en) 2003-12-17

Similar Documents

Publication Publication Date Title
AU2001284159B2 (en) Method of stabilizing particulates
Li et al. Railway geotechnics
Sol-Sánchez et al. Review of the design and maintenance technologies used to decelerate the deterioration of ballasted railway tracks
Lazorenko et al. Dynamic behavior and stability of soil foundation in heavy haul railway tracks: A review
Michas Slab track systems for high-speed railways.
Woodward et al. Application of polyurethane geocomposites to help maintain track geometry for high-speed ballasted railway tracks
Gundavaram et al. Polyurethane-based stabilization of railroad ballast–a critical review
US9045865B2 (en) Polymer grouting method for uplifting ballastless track of high-speed rail
Holm et al. Mitigation of track and ground vibrations by high speed trains at Ledsgard, Sweden
Likitlersuang et al. Numerical modelling of railway embankments for high-speed train constructed on soft soil
Bian et al. Track settlement restoration of ballastless high-speed railway using polyurethane grouting: Full-scale model testing
Li 25 years of heavy axle load railway subgrade research at the Facility for Accelerated Service Testing (FAST)
Tayabji et al. Concrete slab track state of the practice
EP1608812A2 (en) Civil engineering support structures
JP2604476B2 (en) How to build a slab track
Setiawan Subgrade service life and construction cost of ballasted, asphaltic underlayment, and combination rail track design
RU97382U1 (en) THE BASIS OF THE UNBALLAST WAY
Esveld Innovations in railway track
RU97379U1 (en) BASIS FOR A UNBALLASTED RAILWAY
Le et al. Evaluation on the full-scale testbed performance of lightweight foamed soil using railroad loading system
RU2583112C2 (en) Method of reinforcing railway track ballast section
RU97378U1 (en) BASIS OF A UNBALLASTED RAILWAY
Tzanakakis The effect of track stiffness on track performance
Qatamin et al. Asphalt layers within railway tracks’ substructure
RU97380U1 (en) BASIS OF A UNBALLASTED RAILWAY

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)
MK14 Patent ceased section 143(a) (annual fees not paid) or expired